You are on page 1of 6

TECHNICAL FEATURE

ASHRAE www.ashrae.org. Used with permission from ASHRAE Journal, February 2014 at www.atkinsglobal.com. This article may not be
copied nor distributed in either paper or digital form without ASHRAEs permission. For more information about ASHRAE, visit www.ashrae.org.

Technical vs. Process Commissioning


Design Phase Commissioning
BY DAVE MCFARLANE, MEMBER ASHRAE; AND THOMAS FARMER, P.E., MEMBER ASHRAE

New building commissioning is a process with naval origins. A commis-


sioned ship is one that has been fully tested, adjusted, and proven under the
hands of a trained crew; its a thorough process carried out primarily after a
vessel has been constructed, christened, and launched.
In contrastand as noted in the first article of this ensures that every element of the Owners Project
series (Technical Commissioning in the June 2013 Requirement (OPR) document is accounted for in the
issue)an effective technical commissioning process buildings schematic design, which is the first stage of
must be integrated into the entire life cycle of a construc- the design process.
tion project, which for commissioning purposes can be Future articles will deal with construction phase and
divided into four phases: post-occupancy phase commissioning. As we move for-
1. Planning; ward, youll notice that the differences between techni-
2. Design; cal commissioning and process commissioning become
3. Construction; and more pronounced in the later steps of the Cx process.
4. Post-occupancy.
The second, third, and fourth articles in this series cov- Understanding Design Phase Commissioning
ered technical commissioning activities that take place ASHRAE Guideline 0-2005, The Commissioning Process,
during the planning phase of the project. states, During the Design Phase the Owners Project
With this article, we move into the design phase of the Requirements are translated into construction docu-
projecttherefore, this portion of the technical com- ments . [The CxA verifies] the Basis of Design docu-
missioning process can be referred to as design phase ment with the OPR document [and performs a] commis-
commissioning (DPC). During DPC, the CxA carefully sioning-focused design review.
This is the fifth in a series of bimonthly articles that explain the technical commissioning process The National Environmental Balancing Bureau (NEBB)
for new buildings. Some of these articles content is based on ASHRAE Guideline 0-2005, The has also published a technical commissioning manual,
Commissioning Process (published 2005) and the National Environmental Balancing Bureau (NEBB)
publication Procedural Standards for Whole Building Systems Technical Commissioning for New Procedural Standards for Whole Building Systems: Technical
Construction (revised April 2013). In addition, some of the information in this article series has been Commissioning for New Construction (Fourth Edition, April
adapted from an unpublished NEBB standard titled NEBB Standard Owners Project Requirements
(OPR) Guideline (draft dated June 20, 2011); and from NEBBs Procedural Standards for Building 2013). NEBB describes design phase commissioning (in
Enclosure Testing (March 2013). part) as evaluating the design for conformance to the

ABOUT THE AUTHORS Dave McFarlane is principal project director, and Thomas Farmer, P.E., is senior group manager at Atkins in Fort Myers, Fla.

52 A S H R A E J O U R N A L ashrae.org FEBRUARY 2014


OPR and [verifying that] the components, systems, and CxAs best interest to review the project documents as if
assemblies in the design directly relate to the testability, he or she were the projects designer.
accessibility, maintainability, efficient operation, and The CxA needs to be confident that the building
industry-accepted best practices [italics in original text]. will operate in accordance with the OPR document.
Design phase commissioning is the process of compar- Therefore, the CxA team should be comprised of pro-
ing each element of the design to the OPR... [and help- fessionals who are experts in the design and operation
ing] the design team [ensure that] the Basis of Design of their various areas of specialization (architecture,
meets the requirements of the [OPR]. mechanical, electrical, etc.).
Both definitions are rather flexibly worded and do not Its important to stress the impact of the OPR and BOD
define the details of the CxAs many DPC functions. For documents in DPC. A well-written OPR clearly spotlights
example, DPC should include an independent review a wide range of design specific considerations, and an
of the contract documents to identify items that may effective BOD document explains how the design team
be missing or issues that may be improperly or incom- will address those considerations.
pletely documented. The goal of commissioning is to produce a building
DPC is not an engineering peer review process. that works, so its unwise to begin DPC when the con-
Instead, the goal of DPC is to review the projects design struction drawings are already 50% complete. A design
documents and identify issues during the schematic change at that point in the project can become a costly
design (SD) processwell before any actual design work proposition for both the owner and the A/E firm, and
is completed. After all, to be successful, a project doesnt can create an adversarial relationship between them.
need false starts or design rework. The ultimate objective is The commissioning process will fail if the CxA doesnt
a building that works properly, can be tested to verify cor- question apparent inconsistencies. For example, an
rect operation, and then maintained on an ongoing basis. air-handling system that generates 0.5 in. of static
DPC provides an important quality check that is miss- pressure (124 Pa) cannot deliver the airflows required
ing from too many construction projects. for a system that is designed around 1.5 in. of pres-
sure (373 Pa). Such an error in specifying static pres-
Whos Responsible? sure would prevent the HVAC system from providing
I sometimes hear a CxA say, Well review the design design mandated airflow volume throughout the entire
to ensure that the building has appropriate means and building.
devices that will enable specific tests to be performed By beginning DPC during the schematic design pro-
and conditions to be measured during commission- cess, such mistakes can be found and corrected before
ing. Well also review the drawings to ensure there are they become costly and burdensome. DPC continues
adequate spaces and clearances for performing routine through the creation of the design development (DD)
maintenance. But the engineer of record is responsible documents and is finalized during the preparation of
for the buildings design. the construction drawings (CD)but before the project
Its true that engineers are responsible for building bidding process begins.
design. But the commissioning process exists because While effective DPC should include detailed reviews
traditional design, engineering, construction, and start- of the projects architectural, mechanical, and electrical
up processes too often have delivered buildings that (A/M/E) components, technical commissioning does not
dont meet owner expectations. A properly executed typically include code, structural, or civil engineering
commissioning process provides a system of checks and reviews (although such elements may sometimes be
balances that is more likely to yield the result the owner evaluated for specific projects). Therefore, this series of
is seeking. articles deals only with the A/M/E-related portions of the
Bottom line? The CxAs job is to drive the commission- construction process.
ing process.
Architectural Design Review
Careful Document Review: Key to Success The first category of DPC considerations the CxA must
On a problem project, everyone is potentially subject to evaluate relates to the buildings architectural design
callbacks, review meetings, and litigation. So its in the elements. Based on our experience, some of the more
FEBRUARY 2014 ashrae.org A S H R A E J O U R N A L 53
TECHNICAL FEATURE

common architectural oversights TABLE 1 Sample checklist of the primary architectural elements the CxA should review during DPC.
the CxA should look for include:
Roof R values, penetrations, reflectance, exterior wall insulation, perimeter slab insulation, and vapor
Infiltration rates that exceed ac- 1 barrier designs must match the energy/mechanical model and be appropriate for the building application and
cepted industry standards; geographic location.
Improperly specified vapor/air 2
Window and door U values and shading coefficients must match the energy/mechanical model and be
appropriate for the building application and geographic location.
barriers;
Spaces that require special equipment (such as computer rooms, elevator equipment rooms, kitchens, labs,
Poorly defined thermal breaks at 3
etc.) must be properly identified.
windows, doors, walls, and rooflines; Thermal breaks at windows and door frames, roofs, and walls must be clearly defined and appropriate for the
4
and building application and geographic location.
Improperly located equipment 5
Vapor/air barriers that separate exterior conditions from conditioned interiors must be clearly defined and
(which can transmit noise or vibra- appropriate for the building application and geographic location.

tions to occupied spaces). The buildings life-safety plan must clearly define egress, wall types, and any special system requirements
6
(such as smoke exhausts, controls, or pressurization). Review all applicable drawings to cross-check
Table 1 is a sample checklist of the mechanical and electrical systems that relate to the overall life-safety plan and the buildings air-distribution
primary architectural elements the requirements across rated partitions.

CxA should review during DPC. 7


The locations specified for generators, air handlers, chillers, cooling towers, and pumps must meet all of the
owners requirements for aesthetics, noise, vibration, and maintenance.
The project specifications for entry/exit infiltration rates must reflect the correct pressure (example: ASTM
Mechanical Systems Review 8
Standard E1677-11 calls for a pressure of 0.30 inches H2O [75 Pascal]).
A modern building incorporates Wall/roof, wall/floor, window, louver, and door caulking and sealing specifications must be able to achieve the
9
a broad spectrum of unique com- specified leakage rate.
ponents and control sequences. 10 Envelope leakage testing procedures must be properly specified per appropriate NEBB or ASTM standards.
As a result, its mechanical sys- 11 Structural bracing for mechanical equipment must be clearly specified and depicted.
tems are often more technically
complex than its architecture, so theres a lot that can
TABLE 2 Sample checklist of the primary mechanical component specifications
go wrong. the CxA should review during DPC.
Some of the more common mechanical issues the CxA HVAC system specifications must be appropriate for the application and
1
should check for include: geographic location.
Incorrectly specified HVAC systems; 2
Conditioning and zoning considerations (exposure, size, use, and occupancy)
and thermostat locations must be appropriate for the application.
Improperly defined zones;
Total variable air volume (VAV) that exceeds air-han- 3 System diversity must be within acceptable ranges for actual building operations.

dling unit (AHU) capacity, does not match the sum of the Airflow volumes for supply and return air diffusers/grilles must match both
4
individual components, or is outside industry-accept- terminal devices and the central air equipment.
able limits; 5
Diffuser sizing and capacity must produce adequate throw within allowable
noise criteria.
Equipment velocities, pressure drops, or installation
System flows must match equipment and system design and rated capacities
techniques that do not meet industry standards; 6
while meeting general industry-accepted practices for size and application.
Improperly calculated energy balances (in which the Building pressurization airflows must account for exhaust and allowable leak-
7
components supplying the boilers, chillers and air han- age at designed wind velocities.
dlers do not correctly match the specified pumps, cooling Pipe and duct velocities must be consistent with the OPR, the BOD, and ap-
8
coils, reheat coils, and filters); and plicable industry standards.
Improperly specified start-up, flushing, and com- 9
Equipment, coil, terminal inlet/outlet flow velocities, and pressure drops must
be within acceptable industry ranges.
missioning procedures.
10
The inlet and outlet configurations of fans, pumps, coils, filters, and other
Table 2 is a sample checklist of the primary mechanical equipment must not cause reductions in airflow volume.
component specifications the CxA should review. 11 Ducts and piping must be consistent with industry best practices.

Control Sequence Review Sequences written in complex or confusing language;


Control sequences are normally unique to each build- Contradictory or inconsistent requirements;
ing, and must be analyzed to determine their appropri- Sequences that describe opening control require-
ateness for each application. Common control sequence ments but fail to describe shutdown requirements;
issues include: No instructions for power or equipment failure;
54 A S H R A E J O U R N A L ashrae.org FEBRUARY 2014
Advertisement formerly in this space.
TECHNICAL FEATURE

TABLE 3 Sample checklist of the primary control-sequence issues the CxA should TABLE 4 Sample checklist of the plumbing concerns the CxA should review during DPC.
check during DPC.
Plumbing pipes and equipment sizes must match the requirements neces-
Control schematics and sequences must be clearly written and specific to 1 sitated by the specified water fixture units (WFUs) and drainage fixture units
the system, equipment, application, and operations. Control sequences should (DFUs).
1
be written in step-by-step form, using simple, clear, and concise language.
Sequences must cover all foreseeable scenarios, including life-safety events. 2
Water pressure (and any pressure boosters) must be sufficient for the system
configuration, building height, and fixture types.
Sequences must specify proper control procedures for equipment start-up
2 and shut-down, as well as how to handle equipment failure during power loss 3
Verify the need for (and specification of) expansion tanks and/or recirculating
or malfunction. pumps.

Pressurization sequences and equipment components must be appropriate for 4


Verify that hot-water circulating pumps will have balance valves and pressure-
3 gauge test ports.
the application.

5
Verify that plumbing systems will be able to handle high-occupancy loads
4 Temperature and pressure reset sequences must be described in detail. during special events.

Inadequately defined building pressurization se- TABLE 5 Sample checklist of electrical-system factors the CxA should review
during DPC.
quences; and
Verify electrical/mechanical design coordination, including equipment location,
Failure to specify temperature and pressure reset se- 1
voltage, and load and control specifications.
quences. Verify all standby/emergency power requirements, including the redundancy
Table 3 is a sample checklist of the primary control 2 approach. Ensure that proper need and control strategies are in place for
backing up different levels of standby power.
sequence issues the CxA should check during DPC.
3
Ensure that proper lighting-control designs and associated control strategies
are in place.
Plumbing Design Review Verify correct fire-alarm sequences and interlocks are defined for specific life-
4
Plumbing is usually not as prone to problems as safety operations, such as standard alarming, shut-downs, smoke exhaust, etc.
other mechanical areas (perhaps due to the many code 5
Ensure that motor controls, starters, and variable frequency drives (VFDs) are
requirements plumbing systems must satisfy). But coordinated with the appropriate mechanical systems.
plumbing-related issues can prove problematic and Verify that the specifications call for full-power electrical-system quality
testing, including:
should be validated by the CxA, including: Current load balance on each leg.
6
Improperly sized fixture inlets; Current to ground measurements.
Voltage balance on each leg.
Inadequate water pressure from supply source; Current and voltage total harmonic distortion (THD).
Lack of expansion tanks on closed systems; and Ensure that project documents call for load tests of uninterruptible power
7
Failure to consider peak loads during special events. system (UPS) equipment and battery discharge rates.
Table 4 is a sample checklist of the plumbing concerns 8
Verify that the documents call for an 8- to 12-hour standby/emergency
generator performance test using an appropriate load bank.
the CxA should review during DPC.
9
Ensure that connected-lighting load-density specifications do not exceed code
or LEED limits.
Electrical System Design Review Verify that the documents specify permanent service-usage labels for all
Commissioning-related electrical issues can have 10 electrical equipment and that all panel-board schedules are to be filled out at
project completion.
a major impact on whether a building can satisfy
owner expectations. Weve seen many problems that Ensure that the specifications call for all power connections over 5 horsepower
11 be photographed with a thermal-imaging camera while operating under full
seem to surface repeatedly, including: load to identify hot spots and improper connections.
Failure to coordinate electrical panels with mechani-
cal and/or architectural components; Project Design Manual
Improperly sized emergency generators; During DPC, the CxA should collaborate with the
Incorrectly performed generator testing procedures; owner and the design team to decide which documents
Improperly performed electrical power quality test- will be included in the project design manual (PDM) (or
ing and connector adequacy testing; and systems manual within the LEED community). While
Different electrical specifications for mechanical every project will have its own unique design manual,
equipment and electrical service voltages. certain documents should be included in every PDM.
Table 5 is a sample checklist of electrical system factors In addition to the final OPR, BOD, and commissioning
the CxA should review during DPC. plan, the PDM should include:
56 A S H R A E J O U R N A L ashrae.org FEBRUARY 2014
TECHNICAL FEATURE

Final, approved submittals and shop drawings; outlines the design review, but calls for the actual review
Final contract documents; to be performed by the design team, not the CxA.
Record drawings (as-built); Completing a detailed, technical review of the design
Equipment manufacturers operation and mainte- documents during the design phase will help the build-
nance manuals; ing project move forwardwith both the owner and the
Final commissioning report; design team being confident that potential design prob-
Operator training materials; lems have been identified and corrected before actual
Recommended standard operating procedures design work begins. Its one more step toward the overall
(SOPs); and project objective: a fully satisfied building owner.
Pre-functional and functional
test reports.

Dealing With Budget Constraints


Lets face it. Sometimes a tight
budget simply does not allow for
the comprehensive commissioning
process the owner really wants. So
if budget constraints dont permit a
DPC process thats complete in every
detail, the CxA must meet with the
owner to determine exactly what
will be fully commissionedand
Advertisement formerly in this space.
what will not. During that meeting,
its vital to identify which elements
of the review process are essential to
the owner, and which are optional.
The CxA must do everything pos-
sible to ensure that the owners
essential requirements are verified
during the Cx process.
After determining which ele-
ments of the project will (and will
not) be fully commissioned, the CxA
must clearly document whatever
limitations the owner has agreed
to. Clear documentation of those
limitations helps prevent later
misunderstandings.

Technical vs. Process Commissioning


The technical commissioning
approach to the design review is
more robust than process-based
commissioning. Thats because tech-
nical commissioning calls for the CxA
(or the CxA team) to be the expert
party conducting the design review.
In contrast, process commissioning
FEBRUARY 2014 ashrae.org A S H R A E J O U R N A L 57

You might also like