Professional Documents
Culture Documents
Concept: Make sure Money putting in the project Shortens project duration!!!
At normal schedule, available activities for shortening are act20, act22, and act30.
We can shorten project duration by shorten either act22 for +100 a day or act30 for +200 a day.
Common sense, Pay less to get more. We shorten act22 for +100 a day.
1
Next question is HOW MANY DAYS???
Therefore, from normal schedule to schedule 1, we only shorten act22 to 8 days, because non-critical activity
act20 becomes a critical activity.
2
3
Example 2: Using Excel Solver
4
Setup formula for SD and FD based on Duration using NormalDuration
5
IMPORTANT: TURN ON EXCEL SOLVER by
1. Go to File->Options-> Add-Ins
2. At Manage, select Excel-Add-ins
6
Setup Solver Parameters as shown below
Note:
7
Homework
1. Use Excel Solver to find minimum direct cost at different project duration (from normal to crash)
2. Calculate project indirect cost using
3. Calculate minimum project total cost
4. Plot a graph with project indirect cost, minimum project direct cost, and project total cost
Minimum Project Total Cost = Project Indirect Cost + Minimum Project Direct Cost
Indirect Cost = 800 + (Project Duration 21) x 250
8
Solution