CANADA MORTGAGE AND HOUSING CORPORATION

Project Costing and the


Construction Process
necessary elements to take into account, of general categories and specific items
Residential development is whether you contract the work or do it that you will need to consider for your
complex and costly, whether it in-house. capital budget:
is high-end condos or affordable Land: Purchase price; taxes, fees, legal
rental housing for low income Project Costing costs related to acquisition of the
property;
households. Skilled and diligent Project costing is the process of
Servicing:The costs of bringing power,
management and coordination assembling and confirming the capital
telephone, water and sewer service,
are necessary to ensure accurate costs, from project conception to project
roads or sidewalks to the site;
completion. As the concept develops into
costing and a timely, efficient Municipal Fees: Development and
detailed plans and designs, the information
construction or renovation building permits, levies, fees,
provided by quantity surveyors and other
development cost charges; property
process. professionals becomes clearer and more taxes during construction;
specific.When municipal approval costs
Professional Fees: Architect, structural,
are defined and contractors' prices are
mechanical and electrical engineers,
When pursuing a vision of providing received, the project costing process geotechnical engineer, landscape
good quality affordable housing in your becomes more precise. It is essential to architect; quantity surveyor;
community, you may consider either new have reliable financial information to development consultant; legal counsel
construction or renovation or successfully finance the project and for land transfer, contract advice;
conversion of an existing building.There market your units.Your development Construction Financing: Interest on
is an array of specialists in costing, consultant, quantity surveyor, architect, monies borrowed during the
planning, managing, and building involved and funding agencies can help you to get construction period only, mortgage
in the many aspects of multi-unit up-to-date figures. insurance premium; lender fee;
development and it is rare to find one Organizational Expenses: Marketing;
person who can do it all. If your Capital Costs utilities to the site; liability and
organization does not have an builder's risk insurance premiums
Capital costs are directly related to
experienced staff person dedicated to during construction;
property development including 'hard'
the project, consider engaging a qualified Construction, Renovation, or
costs like land and construction and 'soft'
development consultant to guide the Conversion Costs: All construction or
costs such as consulting and legal fees,
process.This fact sheet outlines the renovation materials and labour;
permits, and financing costs. Here is a list
P ro j e c t C o s t i n g a n d t h e C o n s t r u c t i o n P ro c e s s

in-suite appliances; common laundry,


kitchen, and office equipment; amenity Suggested Activities
and dining furniture; landscaping; new
home warranty fees; Use a spreadsheet software program to calculate your budget and keep track of
Contingencies: An allowance to cover each version as the information changes.
unexpected expenditures; Before you have professional consultants on board, you can still develop a
GST: If the Goods and Services Tax preliminary budget:Talk to other groups that have recently developed housing to
applies to your project, build this find out about their costs. Research local and project-specific information, and
expense into your capital budget. then compile the results.
Have a professional quantity surveyor on your development team to track
The Construction construction costs based on the architect's design as it evolves from concept to
Process final working drawings.
Knowing what to expect during the Consult with a qualified tax accountant to determine if you are required to
construction phase will guide you and remit Goods and Services Tax on the project upon completion
your group in planning to monitor the Get in touch with local non-profit housing providers to find out about typical
process and conduct organizational operating expenses for similar buildings to your planned project.
activities so that the project is ready to
Check out the CMHC Affordable Housing Project Viability Assessment Tool for
occupy when the construction is
rental projects at www.cmhc-schl.gc.ca.
complete.The actual schedule of a
construction project will vary based upon
many factors such as size and complexity Construction Procurement Construction Stage
of the proposed development, site and Models
Construction projects work through the
weather conditions, material and
The two most common construction following steps: foundation; framing;
contractor availability, the knowledge and
contracts used to construct or renovate roofing; installation of windows and
experience of those managing the
affordable housing are stipulated price doors; siding; mechanicals including
project, and the changes made to the
contract and design-build or turnkey plumbing, electrical, heating, ventilation
original contract after construction has
contract. and air conditioning; insulation; drywall;
begun. Most construction and renovation
painting; interior trim and other finish
projects will involve the following In the stipulated price contract, the
work; flooring; cabinets, and countertops.
elements: sponsor first awards an architect/
engineer contract to design the project. The architect administers the
Design, Site Development, and After detailed project plans and drawings construction contract for their client
Municipal Approvals are completed, a contractor is selected, (either the design-build/turnkey developer
The architect will provide design usually based on competitive bidding, to or the sponsor in a stipulated price
drawings to conform to the housing and perform the construction work.The project).The contractor submits regular
service program for the future residents contractor then takes full responsibility monthly requests for payment for
and comply with building code and for completing the project on time and at approval by the architect. In most
municipal planning bylaws. Once planning the tendered price, under the terms of contracts there will be a 10% holdback
approval is secured and funding/financing the construction contract.With the on monthly payments in case the
in place, the project is ready to proceed design-build contract, the sponsor contractor fails to pay for materials or
to full working drawings, tendering and contracts with a general contractor or contracts and a lien is placed against the
the building permit process. These areas developer to both design and build the project.These funds are held in trust and
are covered in separate fact sheets. project at a fixed price. only paid to the contractor the day the
holdback period expires by provincial law.

2 Canada Mortgage and Housing Corporation


Project Costing and the Construction Process

As the owner, your group will be called


upon to make certain decisions during Suggested Activities
the course of the construction such as
changes to the design or materials, Learn more about construction procurement models and construction
sometimes related to budget issues.Your contracts at the website of the Canadian Construction Documents Committee,
architect and development consultant www.ccdc.org
should be providing progress reports on Ensure that you have adequate insurance on the property during construction,
the construction and guiding the renovation, or conversion, as well as builder's risk insurance and construction
decisions you may face. performance bonds on the contractor.
Prepare for management during the construction or renovation phase by:
Renovation/Conversion Stage
- Marketing the units and/or developing a waiting list;
Renovation may involve simple repairs or - Developing management policies, systems and structures;
extensive retrofit of structural or
- Planning amenity and recreational programs; and
mechanical systems to a building you
own or plan to purchase. An existing - Preparing for move-in.
apartment building may retain the unit Become familiar with the general scheduling path in order to work in
layouts but require an elevator or dining coordination with the construction or renovation phases.
room to meet the needs of more frail Be sure to arrange with funders and lenders for timely payment to the general
residents. Municipal and provincial contractor.
building codes and regulations may
Hold regular meetings with existing tenants in a residential renovation project,
require upgrades of electrical or
keeping them informed of the plans and the progress, and addressing their
mechanical systems to meet modern
concerns about the impacts of the changes.
standards. Making the building more
energy efficient may actually pay for the
upgrades over time with the money Always get a written contract with the deficiencies is provided to the contractor
saved on heat, light, and water. An renovation company, describing the work and a holdback value is assessed, to be
existing residential building that is to be done and what it will cost. No paid upon final project completion.When
occupied requires a plan for relocating matter how small or large the scope of the architect declares that construction is
tenants while renovations are underway the renovation or conversion project, be substantially completed, the municipality
in their individual units. sure that the renovator is licensed, hires will inspect the building to ensure it
If you are converting a non-residential skilled workers, and is properly insured. conforms to basic safety standards and
building, such as an office building or then issue an Occupancy Permit.
warehouse, there are other considerations. Building Turnover/Rent-Up Depending on the type of housing tenure
Conversion to residential from office and target population, the building rent-
As the project nears completion, the
space would entail significant revisions to up could take a few days or several
architect identifies the construction
the building layout to create dwelling months.
deficiencies and ensures that the
units with bathrooms, kitchens, and contractor has provided all of the
bedrooms as well as mechanical and necessary documentation specified in the
electrical upgrades.There may also be construction contract. A list of
environmental hazards in older industrial
buildings, requiring significant upgrades to
residential standards.

Canada Mortgage and Housing Corporation 3


Project Costing and the Construction Process

windows will have a longer warranty Conclusion


Suggested Activities period.The contractor must correct
Once you know that your project is
deficiencies during this period. At the end
Have the architect arrange for viable the wheels can be set in motion to
of one year from turnover, there will be
your group to have a tour of the build, renovate, or convert it.This is
an inspection to correct any new
project for a demonstration of perhaps the most intense time period,
deficiencies and to ensure the building
how all the systems work. with critical deadlines and decisions that
systems are still operating correctly.
will have a serious impact on the end
Develop a detailed plan for move-
result. It is important to make good use
in that takes into account the use
of the elevator(s) when scheduling Suggested Activities of the professional consultants in your
development team to ensure accurate
residents based on the floor they
Pay careful attention to the cost estimates, a cost-effective design, and
will occupy.
warranties and guarantees when a smooth building process that completes
creating your property on time.
Warranty Period/ maintenance policies, systems and
First Year Inspection procedures. Some warranties are
not valid if recommended
Most construction contracts call for a scheduled maintenance routines
one-year warranty period.The warranty are not carried out.
period is for all of the building elements.
Some elements such as the roof and

Further Resources
Affordable Housing Project Viability Assessment, and the Affordable Housing Project Viability Assessment Tool for rental
projects, CMHC: www.cmhc-schl.gc.ca

Affordable Housing Design Advisor: www.designadvisor.org

The Royal Architectural Institute of Canada: www.raic.org/index_e.htm

Canadian Institute of Quantity Surveyors: www.ciqs.org/

Alberta Urban Municipalities Association's Affordable Housing Toolkit: www.munilink.net/live/AUMA/Toolkits

Canada Revenue Agency Self supply and the GST: www.cra-arc.gc.ca/E/pub/gm/19-2-3/19-2-3-e.html#P53_1524

Canadian Construction Documents Committee: www.ccdc.org/docs/docs.html

Canadian Construction Association: www.cca-acc.com/overview/overview.html

Canadian Home Builders Association: www.chba.ca/