Site Commissioning Check List


Star Solutions - Engineering Department

BTS NAME: BTS ID: DATE:


BTS CONFIGURATION: Eng Name:

A. General ok / not ok NOTE


1. Verify site Grounding test shelter, rack, antenna
2. check that the equimnet dose't damege
3. Verify that the shelter is well cooled
B. BSS Configuration
1. Verify BSS SW version (1X/EVDO)
2. Verify ACM SW version
3. Verify BSS IP as designed
4. Verify BSS host names as designed
5. Verfiy BTS neighbor-list configuration as designed
6. Verify BSS performance jobs configuration (OMC/CEM SNMP target)
C. BSS cabling
1. Verify console cables and connectivity (ACM-BTS; ACM-BSC; BSC-ACM)
2. Verify RF connector are properly connected (top of bay, duplexer)
D. ANTENNA
1. Antenna Sweep test
ANT DIST RETERN LOSS
Main Alpha
Div Alpha
Main Beta
Div Bets Provide results in a separate file
Main Gamma
Div Gamma
5. Verify GPS antenna installed (or PP1S connectivity) - min 4 satellite
E. Alarm / Performance
1. Verify BSS alarms notifications at OMC/CEM (BSC/RNC/BTS/ACM/RFS)
2. Verify BSS performance at OMC/CEM (BSC/RNC/BTS/ACM/RFS)
F. Single Cell Functionality Test
Sector Alpha Sector Beta Sector Gamma
1. Antenna Azimuth
2. Antenna Tilt
3. TX power and spectrum measurements Provide results in a separate file
1XRTT channel 31 Sector Alpha Sector Beta Sector Gamma
4. Verify pilot offset (PN)
5. Registration (power up/down)
6. MM Call
7. ML Call
8. LM Call
9. Correct Mobile TOD display
10. Softer Handoff
11. Soft Handoff
12. 1X Connection (PPP)
13. 1X DATA (web/ftp)
EVDO Channel 157 Sector Alpha Sector Beta Sector Gamma
14. Verify pilot offset (PN)
15. Correct Mobile TOD display
16. EVDO Connection (PPP)
17. Softer Handoff
18. Soft Handoff
19. EVDO DATA (web/ftp)
20. Average RTD (ping 500)
21. Active to dorment time