PROJECT PROPOSAL

DEEP WELL WATER HAND PUMP PROJECT

I. PROJECT DESCRIPTION

Project Title: DEEP WELL WATER HAND PUMP

PROJECT
Type of Project: Water and Health Sanitation Project
This project is to acquire and install
Water Hand Pump Machine to the Local

School Board

Project Proponent/s: BAGONG SILANG NATIONAL


HIGH SCH.
Number of Beneficiaries: 169 Secondary students , 10
teachers,
Project Beneficiaries: Urban poor students
Location of Beneficiaries: P-13, San Mateo, Butuan City
Date of Implementation/Duration: October 2016
Area of Project Implementation: Bagong Silang National High School
Budget Requirement: P 32,302.00
Budget Requested: P 32,302.00

II. BACKGROUND/SITUATION ANALYSIS

Water is a vital need of a human being as one cannot survive without it.
Students, teachers, and residents of Sitio Bagong Silang, P-13 San Mateo,
Butuan City are farmers and for a long time has no access to a direct clean, and
safe potable water supply

Bagong Silang National High School is a new school established in year


2008, The majority of the students are sons and daughters of farmers and
laborers . The school and the community has suffers from a lack of water
especially in dry season, which lasts from March to September. The barangay
school previously receives from local water supply but its always out of water,
and with so many residents dependents on it resulted to the school no supply of
water where it becomes a problem for we cannot clean the comfort room, clean
the surrounding and unable to water the gardens and other plants in the school.

Since the school receives minimal funds from the Government thru
MOEE , and this cannot sustain the expenses needed in putting up our own
water supply . This project will result to request the help of the Local School
Board of the City Government to acquire and install Water Hand Pump Supply
in the school.
Water Hand Pump is the most economical and simple solutions in
providing a collective supply of water in the school. This will also help to
eliminate the risk of our students in falling of in an open wells, and in the use of
pitching of water in distant areas and of uncertain cleanliness, thereby limiting
diseases associated with contaminated water. Thus Sanitation and Hygiene of
the school will be improved.

III. PROJECT OBJECTIVES

OBJECTIVES STRATEGIES
1.The project will provide a ready flow of water for 1.Held a GPTA meeting to consult school
use by the students, and teachers . Health and Sanitation Problems.
2.Improved health and sanitation of the general 2.Consult Division Incharge in Local
populations School Board
3. Improve school attendance due to better health 3.Write a project proposal to submit for
and reduced water carrying burdens especially for the Local Board for assistance.
girls.
4. Increased knowledge of gardening and
agriculture, food security and community
development
5.Engage local governments unit to efficiently use
the special education funds to promote basic
education

IV. DESIRED IMPACT AND OUTCOME OF THE PROJECT

This project will benefit the 169 students with the ages ranging from 12
to 18 years old and 10 teachers to provide an ample supply of water .
It will solve the Health , Sanitation , and Hygiene of the students and
teaching staff.
Safe and acceptable water for human consumption is crucial prequisite
for human being.
Access to safe water is not only fundamental to good health but also to
satisfactory livelihood, dignity and prospects for economic growth and education

V. RISK MANAGEMENT PLAN

Lack of funds for the proposed projects


GPTA funds has intended projects for the school year
The significant physical exertion required for water supply and relatively
high cost in installing.
Difficulty of obtaining needed equipments, materials or spare parts
VI. PROJECT ORGANIZATION AND STAFFING

Office/Staff Designated Responsibilities Contact Person Contact Details


School Head To draft the project Mr.Peterson A. 09174913533
proposal Oropa
PTA President Consult the General Mrs. Arlene Simini
members for the crucial
problems in the school
Parents & Stakeholders Approved Resolutions Mrs, Arlene Simini
for the Proposal

VII. PROJECT WORK PLAN

PHASES OF THE ACTIVITIES OUTPUT / INDICATORS PERSON RESOURCE COST


PROJECT (DATE) TARGET IN S NEEDED
CHARGE
Sept. 30, 2016 General Members PTA Meeting PTA Voluntary None
PTA hip School
Meeting meeting Head
and Teachers
consultati Parents
on and
Stakehold
ers

Oct. 4-5, 2016 Drafting of Project Draft Proposal School Voluntary None
Project Proposal Head
Proposal Teachers
PTA
President
Oct 2016 Consult Project Consultation School Voluntary None
Division Proposal Head
Incharge PTA
on Local President
School
Board
Oct 2016 Submissio Project School Voluntary None
n of Project Proposal Head
Proposal to Submissi PTA
Local on President
School
Board

VIII. DETAILED BUDGET REQUIREMENT


Budget Line Item Description Amount Needed Proposed Source/s
1 -Water Hand Pump JETTMATIC P5,500.00 Local School Board
10-Galvanized Iron pipes Black Iron P2650.00 Local School Board
(P 265 each x 10
pcs.)
Pipes and Fittings PPR Pipes and P1140.00 Local School Board
Fittings (P190.00 x 6)
GI Coupling 050mm P608.00 Local School Board
8 pcs. 76.00
GI ISI Union P500.00 Local School Board
2 x 250.00
GI CON elbow P76.00 Local School Board
2 x 38.00
G.I.R. Tee P390.00 Local School Board
2x 195.00
2-Cement Holcim Cement P470.00 Local School Board
(P235.00 each x 2)
2-Steel Rod Rod Lid Steel P408,00 Local SchoolBoard
(P204x 2 steel rod)
Gravel and Sands 5 sacks P560.00 Local School Board
P112 x 5 sacks
Labor and Others Pakyaw System P20,000.00 PTAFunds/Solicitation
Total P32,302.00

Prepared by :

PETERSON A. OROPA ARLENE SIMINI


School Head PTA President

Noted by :

ARSENIO T. CORNITES CESO V


School Division Super9intendents

IX. ATTACHMENTS
Profile/brochure of the organization
Endorsement and recommendation letters
Other documents to support the request