SNAG LISTS

Item Description of Photos Remarks


SNAG
1 Refrigeration Panda to render the
trench under trench wall smooth finish
building D. and water proofing.

Require smooth
finish and
waterproofing.

2 Modification to Visible evidence of


Steel beam RC modification to the
column prescribed connection
connection. details especially on
building A.

Panda to provide As
Built connection details
and specifications of
welding and the welder
professional credential
We strongly request a
weld testing to be done by
an independent certified
Non-Destructive Tester.

Structural Design Engineer


was not advised on this
modification and is
considered to be a
professional negligence.
3 Block Pier Need injection of non-shrink
Building C grout around block pier and
smooth to finish

No Progress as of last
visit Panda to attend to
this immediately and
email photographic
evidence of completed
works

4 Excessive Panda to provide exit


ponding was drainage which can
observed behind potentially saturate
Building D. natural subgrade under
Panda to provide Building D and
exit drainage and subsequently lead to
leave the building differential settlement
foundation and
natural subgrade Works commenced at the
dry at all times time of this inspection
5 All concrete Provision of QA test and
works and report is the responsibility of
reinforcement contractor under this
works shall be contractor and must be
photographed provided at every stage of
and emailed concrete works.
clearing noting
date when
poured and
formwork is
stripped.
Concrete pour
schedule must
correspond with
QA testing
number and
photographic
evidences must
be provided.
6 Holding down Panda to tape and shall
bolts at building clean and sand blast
C suffer before placement of
excessive column base plate
corrosion

7 Undermining of Panda to provide sound


retaining wall splash pad for to disperse
behind Building the energy
C and B at the
location of storm
water discharge
outfall
8 Temporal welded Panda to drill the top
connection plates holes again and
(Beam-Column) shall bring it to alignment
due to miss with minimum 2mm
match of bolt clearance before
holes at Building conversion to bolted
B connection

9 Corrosion Panda to sand blast and


noticed at clean before application
locations of of anti-rust paint
splice connection
for all building.

10 RC columns at Panda to render the


Building D needs finished surface
render