You are on page 1of 149

ADR || First Batch 1

Republic of the Philippines been missing for more than seven (7) years. It was granted on
SUPREME COURT December 12, 1996. 5
Manila
SECOND DIVISION Meantime, respondent Laperal Realty subdivided the land of
Salas, Jr. and sold subdivided portions thereof to respondents
Rockway Real Estate Corporation and South Ridge Village, Inc.
G.R. No. 135362 December 13, 1999 on February 22, 1990; to respondent spouses Abrajano and
Lava and Oscar Dacillo on June 27, 1991; and to respondents
HEIRS OF AUGUSTO L. SALAS, JR., namely: TERESITA D. Eduardo Vacuna, Florante de la Cruz and Jesus Vicente
SALAS for herself and as legal guardian of the minor Capalan on June 4, 1996 (all of whom are hereinafter referred
FABRICE CYRILL D. SALAS, MA. CRISTINA S. LESACA, to as respondent lot buyers).
and KARINA TERESA D. SALAS, petitioners,
On February 3, 1998, petitioners as heirs of Salas, Jr. filed in
vs. the Regional Trial Court of Lipa City a Complaint 6 for
declaration of nullity of sale, reconveyance, cancellation of
contract, accounting and damages against herein respondents
LAPERAL REALTY CORPORATION, ROCKWAY REAL
which was docketed as Civil Case No. 98-0047.
ESTATE CORPORATION, SOUTH RIDGE VILLAGE, INC.,
MAHARAMI DEVELOPMENT CORPORATION, Spouses
THELMA D. ABRAJANO and GREGORIO ABRAJANO, On April 24, 1998, respondent Laperal Realty filed a Motion to
OSCAR DACILLO, Spouses VIRGINIA D. LAVA and RODEL
LAVA, EDUARDO A. VACUNA, FLORANTE DE LA CRUZ, Dismiss 7 on the ground that petitioners failed to submit their
JESUS VICENTE B. CAPELLAN, and the REGISTER OF grievance to arbitration as required under Article VI of the
DEEDS FOR LIPA CITY, respondents. Agreement which provides:

Art. VI. ARBITRATION.

DE LEON, JR., J.: All cases of dispute between CONTRACTOR and OWNER'S
representative shall be referred to the committee represented
Before us is a petition for review on certiorari of the Order 1 of by:
Branch 85 of the Regional Trial Court of Lipa City 2 dismissing
petitioners' complaint 3 for rescission of several sale a. One representative of the OWNER;
transactions involving land owned by Augusto L. Salas, Jr.,
their predecessor-in-interest, on the ground that they failed to b. One representative of the CONTRACTOR;
first resort to arbitration.
c. One representative acceptable to both OWNER and
Salas, Jr. was the registered owner of a vast tract of land in CONTRACTOR. 8
Lipa City, Batangas spanning 1,484,354 square meters.
On May 5, 1998, respondent spouses Abrajano and Lava and
On May 15, 1987, he entered into an Owner-Contractor respondent Dacillo filed a Joint Answer with Counterclaim and
Agreement 4 (hereinafter referred to as the Agreement) with Crossclaim 9 praying for dismissal of petitioners' Complaint for
respondent Laperal Realty Corporation (hereinafter referred to the same reason.
as Laperal Realty) to render and provide complete (horizontal)
construction services on his land.
On August 9, 1998, the trial court issued the herein assailed
Order dismissing petitioners' Complaint for non-compliance with
On September 23, 1988, Salas, Jr. executed a Special Power the foregoing arbitration clause.
of Attorney in favor of respondent Laperal Realty to exercise
general control, supervision and management of the sale of his
Hence this petition.
land, for cash or on installment basis.
Petitioners argue, thus:
On June 10, 1989, Salas, Jr. left his home in the morning for a
business trip to Nueva Ecija. He never returned.
The petitioners' causes of action did not emanate from the
Owner-Contractor Agreement.
On August 6, 1996, Teresita Diaz Salas filed with the Regional
Trial Court of Makati City a verified petition for the declaration of
presumptive death of her husband, Salas, Jr., who had then The petitioners' causes of action for cancellation of contract and
accounting are covered by the exception under the Arbitration
ADR || First Batch 2

Law. The petitioners' contention is without merit. For while


rescission, as a general rule, is an arbitrable issue, 20 they
Failure to arbitrate is not a ground for dismissal. 10 impleaded in the suit for rescission the respondent lot buyers
who are neither parties to the Agreement nor the latter's
assigns or heirs. Consequently, the right to arbitrate as
In a catena of cases 11 inspired by Justice Malcolm's
provided in Article VI of the Agreement was never vested in
provocative dissent in Vega v. San Carlos Milling Co. 12, this
respondent lot buyers.
Court has recognized arbitration agreements as valid, binding,
enforceable and not contrary to public policy so much so that
when there obtains a written provision for arbitration which is Respondent Laperal Realty, as a contracting party to the
not complied with, the trial court should suspend the Agreement, has the right to compel petitioners to first arbitrate
proceedings and order the parties to proceed to arbitration in before seeking judicial relief. However, to split the proceedings
accordance with the terms of their into arbitration for respondent Laperal Realty and trial for the
respondent lot buyers, or to hold trial in abeyance pending
arbitration between petitioners and respondent Laperal Realty,
agreement 13. Arbitration is the "wave of the future" in dispute
would in effect result in multiplicity of suits, duplicitous
resolution. 14 To brush aside a contractual agreement calling for
procedure and unnecessary delay. On the other hand, it would
arbitration in case of disagreement between parties would be a
be in the interest of justice if the trial court hears the complaint
step backward. 15
against all herein respondents and adjudicates petitioners'
rights as against theirs in a single and complete proceeding.
Nonetheless, we grant the petition.
WHEREFORE, the instant petition is hereby GRANTED. The
A submission to arbitration is a contract. 16 As such, the Order dated August 19, 1998 of Branch 85 of the Regional Trial
Agreement, containing the stipulation on arbitration, binds the Court of Lipa City is hereby NULLIFIED and SET ASIDE. Said
parties thereto, as well as their assigns and heirs. 17 But only court is hereby ordered to proceed with the hearing of Civil
they. Petitioners, as heirs of Salas, Jr., and respondent Laperal Case No. 98-0047.
Realty are certainly bound by the Agreement. If respondent
Laperal Realty had assigned its rights under the Agreement to
Costs against private respondents.
a third party, making the former, the assignor, and the latter, the
assignee, such assignee would also be bound by the arbitration
provision since assignment involves such transfer of rights as to SO ORDERED.
vest in the assignee the power to enforce them to the same
extent as the assignor could have enforced them against the Bellosillo, Mendoza, Quisumbing and Buena, JJ., concur.
debtor 18 or in this case, against the heirs of the original party to
the Agreement. However, respondents Rockway Real Estate Footnotes
Corporation, South Ridge Village, Inc., Maharami Development
Corporation, spouses Abrajano, spouses Lava, Oscar Dacillo,
Eduardo Vacuna, Florante de la Cruz and Jesus Vicente
Capellan are not assignees of the rights of respondent Laperal
Realty under the Agreement to develop Salas, Jr.'s land and 1 Annex "A" of the Petition, Rollo, pp. 19-20.
sell the same. They are, rather, buyers of the land that
respondent Laperal Realty was given the authority to develop 2 Presided by Hon. Judge Avelino G. Demetria.
and sell under the Agreement. As such, they are not "assigns"
contemplated in Art. 1311 of the New Civil Code which provides 3 Rollo, p. 32.
that "contracts take effect only between the parties, their
assigns and heirs". 4 Annex "B" of the Petition, Rollo, p. 22.

Petitioners claim that they suffered lesion of more than one- 5 Decision of Branch 59 of the Regional Trial Court of Makati
fourth (1/4) of the value of Salas, Jr.'s land when respondent City in SP. PROC. No. M-4394 marked as Annex "C" of the
Laperal Realty subdivided it and sold portions thereof to Petition, Rollo, pp. 29-31.
respondent lot buyers. Thus, they instituted action 19 against
both respondent Laperal Realty and respondent lot buyers for
6 Annex "D" of the Petition, Rollo, pp. 32-49.
rescission of the sale transactions and reconveyance to them of
the subdivided lots. They argue that rescission, being their
cause of action, falls under the exception clause in Sec. 2 of 7 Annex "E" of the Petition, Rollo, pp. 50-56.
Republic Act No. 876 which provides that "such submission [to]
or contract [of arbitration] shall be valid, enforceable and 8 Owner-Contractor Agreement, p. 6, Rollo, p. 27.
irrevocable, save upon such grounds as exist at law for the
revocation of any contract".
ADR || First Batch 3

9 Annex "F" of the Petition, Rollo, pp. 58-73. Republic of the Philippines
SUPREME COURT
10 Petition, pp. 7, 9-10, Rollo, pp. 9, 11-12. Manila
THIRD DIVISION
11 Mindanao Portland Cement Corporation v. McDonough
Construction Company of Florida, 19 SCRA 808, 815 (1967);
Bengson v. Chan, 78 SCRA 113, 119 (1977); Chung Fu G.R. No. 120105 March 27, 1998
Industries (Phils.), Inc. v. Court of Appeals, 206 SCRA 545,
549-552 (1992); Puromines, Inc. v. Court of Appeals, 220 BF CORPORATION, petitioner,
SCRA 281, 289-290 (1993); National Power Corporation v.
Court of Appeals, 254 SCRA 116, 125 (1996). vs.

12 51 Phil. 908, 916-920 (1924). COURT OF APPEALS, SHANGRI-LA PROPERTIES, INC.,


RUFO B. COLAYCO, ALFREDO C. RAMOS, MAXIMO G.
13 Bengson v. Chan, supra. LICAUCO III and BENJAMIN C. RAMOS, respondents.

14 B.F. Corporation v. Court of Appeals, et al., 288 SCRA 267,


286 (1998).
ROMERO, J.:
15 Ibid.
The basic issue in this petition for review on certiorari is
16 Manila Electric Company v. Pasay Transportation Co., 57 whether or not the contract for the construction of the EDSA
Phil. 600, 603 (1932). Plaza between petitioner BF Corporation and respondent
Shangri-la Properties, Inc. embodies an arbitration clause in
17 Art. 1311, Civil Code. case of disagreement between the parties in the
implementation of contractual provisions.
18 Tolentino, Arturo M., Commentaries and Jurisprudence on
the Civil Code of the Philippines, Vol. 5 (1992), p. 188. Petitioner and respondent Shangri-la Properties, Inc. (SPI)
entered into an agreement whereby the latter engaged the
former to construct the main structure of the "EDSA Plaza
19 Complaint dated February 2, 1998 marked as Annex "D" of
Project," a shopping mall complex in the City of Mandaluyong.
the Petition, Rollo, pp. 32-48.
The construction work was in progress when SPI decided to
expand the project by engaging the services of petitioner again.
20 Santiago v. Gonzalez, 79 SCRA 494, 500 (1977). Thus, the parties entered into an agreement for the main
contract works after which construction work began.

However, petitioner incurred delay in the construction work that


SPI considered as "serious and substantial." On the other
1

hand, according to petitioner, the construction works


"progressed in faithful compliance with the First Agreement until
a fire broke out on November 30, 1990 damaging Phase I" of
the Project. Hence, SPI proposed the re-negotiation of the
2

agreement between them.

Consequently, on May 30, 1991, petitioner and SPI entered into


a written agreement denominated as "Agreement for the
Execution of Builder's Work for the EDSA Plaza Project." Said
agreement would cover the construction work on said project as
of May 1, 1991 until its eventual completion.

According to SPI, petitioner "failed to complete the construction


works and abandoned the project." This resulted in
3

disagreements between the parties as regards their respective


liabilities under the contract. On July 12, 1993, upon SPI's
initiative, the parties' respective representatives met in
ADR || First Batch 4

conference but they failed to come to an agreement. 4 It appears from the said document that in the letter-agreement
dated May 30, 1991 (Annex C, Complaint), plaintiff BF and
Barely two days later or on July 14, 1993, petitioner filed with defendant Shangri-La Properties, Inc. agreed upon the terms
the Regional Trial Court of Pasig a complaint for collection of and conditions of the Builders Work for the EDSA Plaza Project
the balance due under the construction agreement. Named (Phases I, II and Carpark), subject to the execution by the
defendants therein were SPI and members of its board of parties of a formal trade contract. Defendants have submitted a
directors namely, Alfredo C. Ramos, Rufo B. Calayco, Antonio copy of the alleged trade contract, which is entitled "Contract
B. Olbes, Gerardo O. Lanuza, Jr., Maximo G. Licauco III and Documents For Builder's Work Trade Contractor" dated 01 May
Benjamin C. Ramos. 1991, page 2 of which is entitled "Contents of Contract
Documents" with a list of the documents therein contained, and
Section A thereof consists of the abovementioned Letter-
On August 3, 1993, SPI and its co-defendants filed a motion to
Agreement dated May 30, 1991. Section C of the said Contract
suspend proceedings instead of filing an answer. The motion
Documents is entitled "Articles of Agreement and Conditions of
was anchored on defendants' allegation that the formal trade
Contract" which, per its Index, consists of Part A (Articles of
contract for the construction of the project provided for a clause
Agreement) and B (Conditions of Contract). The said Articles of
requiring prior resort to arbitration before judicial intervention
Agreement appears to have been duly signed by President
could be invoked in any dispute arising from the contract. The
Rufo B. Colayco of Shangri-La Properties, Inc. and President
following day, SPI submitted a copy of the conditions of the
Bayani F. Fernando of BF and their witnesses, and was
contract containing the arbitration clause that it failed to append
thereafter acknowledged before Notary Public Nilberto R.
to its motion to suspend proceedings.
Briones of Makati, Metro Manila on November 15, 1991. The
said Articles of Agreement also provides that the "Contract
Petitioner opposed said motion claiming that there was no Documents" therein listed "shall be deemed an integral part of
formal contract between the parties although they entered into this Agreement", and one of the said documents is the
an agreement defining their rights and obligations in "Conditions of Contract" which contains the Arbitration Clause
undertaking the project. It emphasized that the agreement did relied upon by the defendants in their Motion to Suspend
not provide for arbitration and therefore the court could not be Proceedings.
deprived of jurisdiction conferred by law by the mere allegation
of the existence of an arbitration clause in the agreement
This Court notes, however, that the 'Conditions of Contract'
between the parties.
referred to, contains the following provisions:
In reply to said opposition, SPI insisted that there was such an
3. Contract Document.
arbitration clause in the existing contract between petitioner and
SPI. It alleged that suspension of proceedings would not
necessarily deprive the court of its jurisdiction over the case Three copies of the Contract Documents referred to in the
and that arbitration would expedite rather than delay the Articles of Agreement shall be signed by the parties to the
settlement of the parties' respective claims against each other. contract and distributed to the Owner and the Contractor for
their safe keeping." (emphasis supplied).
In a rejoinder to SPI's reply, petitioner reiterated that there was
no arbitration clause in the contract between the parties. It And it is significant to note further that the said "Conditions of
averred that granting that such a clause indeed formed part of Contract" is not duly signed by the parties on any page thereof
the contract, suspension of the proceedings was no longer although it bears the initials of BF's representatives (Bayani
proper. It added that defendants should be declared in default F. Fernando and Reynaldo M. de la Cruz) without the initials
for failure to file their answer within the reglementary period. thereon of any representative of Shangri-La Properties, Inc.

In its sur-rejoinder, SPI pointed out the significance of Considering the insistence of the plaintiff that the said
petitioner's admission of the due execution of the "Articles of Conditions of Contract was not duly executed or signed by the
Agreement." Thus, on page D/6 thereof, the signatures of Rufo parties, and the failure of the defendants to submit any signed
B. Colayco, SPI president, and Bayani Fernando, president of copy of the said document, this Court entertains serious doubt
petitioner appear, while page D/7 shows that the agreement is whether or not the arbitration clause found in the said
a public document duly notarized on November 15, 1991 by Conditions of Contract is binding upon the parties to the Articles
Notary Public Nilberto R. Briones as document No. 345, page of Agreement." (Emphasis supplied.)
70, book No. LXX, Series of 1991 of his notarial register. 5

The lower court then ruled that, assuming that the arbitration
Thereafter, upon a finding that an arbitration clause indeed clause was valid and binding, still, it was "too late in the day for
exists, the lower court denied the motion to suspend
6 defendants to invoke arbitration." It quoted the following
proceedings, thus: provision of the arbitration clause:
ADR || First Batch 5

Notice of the demand for arbitration of a dispute shall be filed in The reasons given by the respondent Court in denying
writing with the other party to the contract and a copy filed with petitioners' motion to suspend proceedings are untenable.
the Project Manager. The demand for arbitration shall be made
within a reasonable time after the dispute has arisen and 1. The notarized copy of the articles of agreement attached as
attempts to settle amicably have failed; in no case, however, Annex A to petitioners' reply dated August 26, 1993, has been
shall the demand he made be later than the time of final submitted by them to the respondent Court (Annex G, petition).
payment except as otherwise expressly stipulated in the It bears the signature of petitioner Rufo B. Colayco, president of
contract. petitioner Shangri-La Properties, Inc., and of Bayani Fernando,
president of respondent Corporation (Annex G-1, petition). At
Against the above backdrop, the lower court found that per the page D/4 of said articles of agreement it is expressly provided
May 30, 1991 agreement, the project was to be completed by that the conditions of contract are "deemed an integral part"
October 31, 1991. Thereafter, the contractor would pay thereof (page 188, rollo). And it is at pages D/42 to D/44 of the
P80,000 for each day of delay counted from November 1, 1991 conditions of contract that the provisions for arbitration are
with "liquified (sic) damages up to a maximum of 5% of the total found (Annexes G-3 to G-5, petition, pp. 227-229). Clause No.
contract price." 35 on arbitration specifically provides:

The lower court also found that after the project was completed Provided always that in case any dispute or difference shall
in accordance with the agreement that contained a provision on arise between the Owner or the Project Manager on his behalf
"progress payment billing," SPI "took possession and started and the Contractor, either during the progress or after the
operations thereof by opening the same to the public in completion or abandonment of the Works as to the construction
November, 1991." SPI, having failed to pay for the works, of this Contract or as to any matter or thing of whatsoever
petitioner billed SPI in the total amount of P110,883,101.52, nature arising thereunder or in connection therewith (including
contained in a demand letter sent by it to SPI on February 17, any matter or being left by this Contract to the discretion of the
1993. Instead of paying the amount demanded, SPI set up its Project Manager or the withholding by the Project Manager of
own claim of P220,000,000.00 and scheduled a conference on any certificate to which the Contractor may claim to be entitled
that claim for July 12, 1993. The conference took place but it or the measurement and valuation mentioned in clause 30 (5)
proved futile. (a) of these Conditions' or the rights and liabilities of the parties
under clauses 25, 26, 32 or 33 of these Conditions), the Owner
Upon the above facts, the lower court concluded: and the Contractor hereby agree to exert all efforts to settle
their differences or dispute amicably. Failing these efforts then
such dispute or difference shall be referred to Arbitration in
Considering the fact that under the supposed Arbitration Clause
accordance with the rules and procedures of the Philippine
invoked by defendants, it is required that "Notice of the demand
Arbitration Law.
for arbitration of a dispute shall be filed in writing with the other
party . . . . in no case . . . . later than the time of final payment .
. . "which apparently, had elapsed, not only because The fact that said conditions of contract containing the
defendants had taken possession of the finished works and the arbitration clause bear only the initials of respondent
plaintiff's billings for the payment thereof had remained pending Corporation's representatives, Bayani Fernando and Reynaldo
since November, 1991 up to the filing of this case on July 14, de la Cruz, without that of the representative of petitioner
1993, but also for the reason that defendants have failed to file Shangri-La Properties, Inc. does not militate against its
any written notice of any demand for arbitration during the said effectivity. Said petitioner having categorically admitted that the
long period of one year and eight months, this Court finds that it document, Annex A to its reply dated August 26, 1993 (Annex
cannot stay the proceedings in this case as required by Sec. 7 G, petition), is the agreement between the parties, the initial or
of Republic Act No. 876, because defendants are in default in signature of said petitioner's representative to signify conformity
proceeding with such arbitration. to arbitration is no longer necessary. The parties, therefore,
should be allowed to submit their dispute to arbitration in
accordance with their agreement.
The lower court denied SPI's motion for reconsideration for lack
of merit and directed it and the other defendants to file their
responsive pleading or answer within fifteen (15) days from 2. The respondent Court held that petitioners "are in default in
notice. proceeding with such arbitration." It took note of "the fact that
under the supposed Arbitration Clause invoked by defendants,
it is required that "Notice of the demand for arbitration of a
Instead of filing an answer to the complaint, SPI filed a petition
dispute shall be filed in writing with the other party . . . in no
for certiorari under Rule 65 of the Rules of Court before the
case . . . later than the time of final payment," which apparently,
Court of Appeals. Said appellate court granted the petition,
had elapsed, not only because defendants had taken
annulled and set aside the orders and stayed the proceedings
possession of the finished works and the plaintiff's billings for
in the lower court. In so ruling, the Court of Appeals held:
the payment thereof had remained pending since November,
1991 up to the filing of this case on July 14, 1993, but also for
ADR || First Batch 6

the reason that defendants have failed to file any written notice On the first assigned error, petitioner contends that the Order of
of any demand for arbitration during the said long period of one the lower court denying the motion to suspend proceedings "is
year and eight months, . . . ." a resolution of an incident on the merits." As such, upon the
continuation of the proceedings, the lower court would
Respondent Court has overlooked the fact that under the appreciate the evidence adduced in their totality and thereafter
arbitration render a decision on the merits that may or may not sustain the
existence of an arbitration clause. A decision containing a
finding that the contract has no arbitration clause can then be
clause
elevated to a higher court "in an ordinary appeal" where an
adequate remedy could be obtained. Hence, to petitioner, the
Notice of the demand for arbitration dispute shall be filed in Court of Appeals should have dismissed the petition for
writing with the other party to the contract and a copy filed with certiorari because the remedy of appeal would still be available
the Project Manager. The demand for arbitration shall be made to private respondents at the proper time. 7

within a reasonable time after the dispute has arisen and


attempts to settle amicably had failed; in no case, however,
The above contention is without merit.
shall the demand be made later than the time of final payment
except as otherwise expressly stipulated in the contract
(emphasis supplied) The rule that the special civil action of certiorari may not be
invoked as a substitute for the remedy of appeal is succinctly
reiterated in Ongsitco v. Court of Appeals as follows:
8
quoted in its order (Annex A, petition). As the respondent Court
there said, after the final demand to pay the amount of
P110,883,101.52, instead of paying, petitioners set up its own . . . . Countless times in the past, this Court has held that
claim against respondent Corporation in the amount of "where appeal is the proper remedy, certiorari will not lie." The
P220,000,000.00 and set a conference thereon on July 12, writs of certiorari and prohibition are remedies to correct lack or
1993. Said conference proved futile. The next day, July 14, excess of jurisdiction or grave abuse of discretion equivalent to
1993, respondent Corporation filed its complaint against lack of jurisdiction committed by a lower court. "Where the
petitioners. On August 13, 1993, petitioners wrote to proper remedy is appeal, the action for certiorari will not be
respondent Corporation requesting arbitration. Under the entertained. . . . Certiorari is not a remedy for errors of
circumstances, it cannot be said that petitioners' resort to judgment. Errors of judgment are correctible by appeal, errors
arbitration was made beyond reasonable time. Neither can they of jurisdiction are reviewable by certiorari."
be considered in default of their obligation to respondent
Corporation. Rule 65 is very clear. The extraordinary remedies of certiorari,
prohibition and mandamus are available only when "there is no
Hence, this petition before this Court. Petitioner assigns the appeal or any plain, speedy and adequate remedy in the
following errors: ordinary course of law . . . ." That is why they are referred to as
"extraordinary." . . . .
A
The Court has likewise ruled that "certiorari will not be issued to
cure errors in proceedings or correct erroneous conclusions of
THE COURT OF APPEALS ERRED IN ISSUING THE
law or fact. As long as a court acts within its jurisdiction, any
EXTRAORDINARY WRIT OF CERTIORARI ALTHOUGH THE
alleged errors committed in the exercise of its jurisdiction will
REMEDY OF APPEAL WAS AVAILABLE TO RESPONDENTS.
amount to nothing more than errors of judgment which are
reviewable by timely appeal and not by a special civil action of
B certiorari."
9

THE COURT OF APPEALS ERRED IN FINDING GRAVE This is not exactly so in the instant case. While this Court does
ABUSE OF DISCRETION IN THE FACTUAL FINDINGS OF not deny the eventual jurisdiction of the lower court over the
THE TRIAL COURT THAT: controversy, the issue posed basically is whether the lower
court prematurely assumed jurisdiction over it. If the lower court
(i) THE PARTIES DID NOT ENTER INTO AN AGREEMENT indeed prematurely assumed jurisdiction over the case, then it
TO ARBITRATE. becomes an error of jurisdiction which is a proper subject of a
petition for certiorari before the Court of Appeals. And if the
(ii) ASSUMING THAT THE PARTIES DID ENTER INTO THE lower court does not have jurisdiction over the controversy,
AGREEMENT TO ARBITRATE, RESPONDENTS ARE then any decision or order it may render may be annulled and
ALREADY IN DEFAULT IN INVOKING THE AGREEMENT TO set aside by the appellate court.
ARBITRATE.
However, the question of jurisdiction, which is a question of law
ADR || First Batch 7

depends on the determination of the existence of the arbitration the parties. Second, private respondents misrepresented before
clause, which is a question of fact. In the instant case, the lower the Court of Appeals that they produced in the trial court a
court found that there exists an arbitration clause. However, it notarized duplicate original copy of the construction agreement
ruled that in contemplation of law, said arbitration clause does because what were submitted were mere photocopies thereof.
not exist. The contract(s) introduced in court by private respondents were
therefore "of dubious authenticity" because: (a) the Agreement
The issue, therefore, posed before the Court of Appeals in a for the Execution of Builder's Work for the EDSA Plaza Project
petition for certiorari is whether the Arbitration Clause does not does not contain an arbitration clause, (b) private respondents
in fact exist. On its face, the the question is one of fact which is "surreptitiously attached as Annexes "G-3" to "G-5" to their
not proper in a petition for certiorari. petition before the Court of Appeals but these documents are
not parts of the Agreement of the parties as "there was no
formal trade contract executed," (c) if the entire compilation of
The Court of Appeals found that an Arbitration Clause does in
documents "is indeed a formal trade contract," then it should
fact exist. In resolving said question of fact, the Court of
have been duly notarized, (d) the certification from the Records
Appeals interpreted the construction of the subject contract
Management and Archives Office dated August 26, 1993
documents containing the Arbitration Clause in accordance with
merely states that "the notarial record of Nilberto Briones . . . is
Republic Act No. 876 (Arbitration Law) and existing
available in the files of (said) office as Notarial Registry Entry
jurisprudence which will be extensively discussed hereunder. In
only," (e) the same certification attests that the document
effect, the issue posed before the Court of Appeals was
entered in the notarial registry pertains to the Articles of
likewise a question of law. Being a question of law, the private
Agreement only without any other accompanying documents,
respondents rightfully invoked the special civil action of
and therefore, it is not a formal trade contract, and (f) the
certiorari.
compilation submitted by respondents are a "mere hodge-
podge of documents and do not constitute a single intelligible
It is that mode of appeal taken by private respondents before agreement."
the Court of Appeals that is being questioned by the petitioners
before this Court. But at the heart of said issue is the question
In other words, petitioner denies the existence of the arbitration
of whether there exists an Arbitration Clause because if an
clause primarily on the ground that the representatives of the
Arbitration Clause does not exist, then private respondents took
contracting corporations did not sign the "Conditions of
the wrong mode of appeal before the Court of Appeals.
Contract" that contained the said clause. Its other contentions,
specifically that insinuating fraud as regards the alleged
For this Court to be able to resolve the question of whether insertion of the arbitration clause, are questions of fact that
private respondents took the proper mode of appeal, which, should have been threshed out below.
incidentally, is a question of law, then it has to answer the core
issue of whether there exists an Arbitration Clause which,
This Court may as well proceed to determine whether the
admittedly, is a question of fact.
arbitration clause does exist in the parties' contract. Republic
Act No. 876 provides for the formal requisites of an arbitration
Moreover, where a rigid application of the rule that certiorari agreement as follows:
cannot be a substitute for appeal will result in a manifest failure
or miscarriage of justice, the provisions of the Rules of Court
Sec. 4. Form of arbitration agreement. A contract to arbitrate
which are technical rules may be relaxed. As we shall show
10

a controversy thereafter arising between the parties, as well as


hereunder, had the Court of Appeals dismissed the petition for
a submission to arbitrate an existing controversy, shall be in
certiorari, the issue of whether or not an arbitration clause
writing and subscribed by the party sought to be charged, or by
exists in the contract would not have been resolved in
his lawful agent.
accordance with evidence extant in the record of the case.
Consequently, this would have resulted in a judicial rejection of
a contractual provision agreed by the parties to the contract. The making of a contract or submission for arbitration described
in section two hereof, providing for arbitration of any
controversy, shall be deemed a consent of the parties of the
In the same vein, this Court holds that the question of the
province or city where any of the parties resides, to enforce
existence of the arbitration clause in the contract between
such contract of submission. (Emphasis supplied.).
petitioner and private respondents is a legal issue that must be
determined in this petition for review on certiorari.
The formal requirements of an agreement to arbitrate are
therefore the following: (a) it must be in writing and (b) it must
Petitioner, while not denying that there exists an arbitration
be subscribed by the parties or their representatives. There is
clause in the contract in question, asserts that in contemplation
no denying that the parties entered into a written contract that
of law there could not have been one considering the following
was submitted in evidence before the lower court. To
points. First, the trial court found that the "conditions of
"subscribe" means to write underneath, as one's name; to sign
contract" embodying the arbitration clause is not duly signed by
at the end of a document. That word may sometimes be
11
ADR || First Batch 8

construed to mean to give consent to or to attest. 12 fire that partially gutted the project. The almost two-year delay
in paying its liabilities may not therefore be wholly ascribed to
The Court finds that, upon a scrutiny of the records of this case, private respondent SPI.
these requisites were complied with in the contract in question.
The Articles of Agreement, which incorporates all the other Besides, private respondent SPI's initiative in calling for a
contracts and agreements between the parties, was signed by conference between the parties was a step towards the agreed
representatives of both parties and duly notarized. The failure resort to arbitration. However, petitioner posthaste filed the
of the private respondent's representative to initial the complaint before the lower court. Thus, while private
"Conditions of Contract" would therefor not affect compliance respondent SPI's request for arbitration on August 13, 1993
with the formal requirements for arbitration agreements might appear an afterthought as it was made after it had filed
because that particular portion of the covenants between the the motion to suspend proceedings, it was because petitioner
parties was included by reference in the Articles of Agreement. also appeared to act hastily in order to resolve the controversy
through the courts.
Petitioner's contention that there was no arbitration clause
because the contract incorporating said provision is part of a The arbitration clause provides for a "reasonable time" within
"hodge-podge" document, is therefore untenable. A contract which the parties may avail of the relief under that clause.
need not be contained in a single writing. It may be collected "Reasonableness" is a relative term and the question of
from several different writings which do not conflict with each whether the time within which an act has to be done is
other and which, when connected, show the parties, subject reasonable depends on attendant circumstances. This Court
15

matter, terms and consideration, as in contracts entered into by finds that under the circumstances obtaining in this case, a
correspondence. A contract may be encompassed in several
13 one-month period from the time the parties held a conference
instruments even though every instrument is not signed by the on July 12, 1993 until private respondent SPI notified petitioner
parties, since it is sufficient if the unsigned instruments are that it was invoking the arbitration clause, is a reasonable time.
clearly identified or referred to and made part of the signed Indeed, petitioner may not be faulted for resorting to the court
instrument or instruments. Similarly, a written agreement of to claim what was due it under the contract. However, we find
which there are two copies, one signed by each of the parties, its denial of the existence of the arbitration clause as an
is binding on both to the same extent as though there had been attempt to cover up its misstep in hurriedly filing the complaint
only one copy of the agreement and both had signed it. 14 before the lower court.

The flaw in petitioner's contentions therefore lies in its having In this connection, it bears stressing that the lower court has not
segmented the various components of the whole contract lost its jurisdiction over the case. Section 7 of Republic Act No.
between the parties into several parts. This notwithstanding, 876 provides that proceedings therein have only been stayed.
petitioner ironically admits the execution of the Articles of After the special proceeding of arbitration has been pursued
16

Agreement. Notably, too, the lower court found that the said and completed, then the lower court may confirm the award 17

Articles of Agreement "also provides that the 'Contract made by the arbitrator.
Documents' therein listed 'shall be deemed an integral part of
this Agreement,' and one of the said documents is the It should be noted that in this jurisdiction, arbitration has been
'Conditions of Contract' which contains the Arbitration Clause.'" held valid and constitutional. Even before the approval on June
It is this Articles of Agreement that was duly signed by Rufo B. 19, 1953 of Republic Act No. 876, this Court has countenanced
Colayco, president of private respondent SPI, and Bayani F. the settlement of disputes through arbitration. Republic Act
18

Fernando, president of petitioner corporation. The same No. 876 was adopted to supplement the New Civil Code's
agreement was duly subscribed before notary public Nilberto R. provisions on arbitration. 19 Its potentials as one of the
Briones. In other words, the subscription of the principal alternative dispute resolution methods that are now rightfully
agreement effectively covered the other documents vaunted as "the wave of the future" in international relations, is
incorporated by reference therein. recognized worldwide. To brush aside a contractual agreement
calling for arbitration in case of disagreement between the
This Court likewise does not find that the Court of Appeals parties would therefore be a step backward.
erred in ruling that private respondents were not in default in
invoking the provisions of the arbitration clause which states WHEREFORE, the questioned Decision of the Court of Appeals
that "(t)he demand for arbitration shall be made within a is hereby AFFIRMED and the petition for certiorari DENIED.
reasonable time after the dispute has arisen and attempts to This Decision is immediately executory. Costs against
settle amicably had failed." Under the factual milieu, private petitioner.
respondent SPI should have paid its liabilities tinder the
contract in accordance with its terms. However,
SO ORDERED.
misunderstandings appeared to have cropped up between the
parties ostensibly brought about by either delay in the
completion of the construction work or by force majeure or the Narvasa, C.J., Kapunan and Purisima, JJ., concur.
ADR || First Batch 9

Footnotes Republic of the Philippines


SUPREME COURT
1 Rollo, p. 75. Manila
THIRD DIVISION
2 Ibid., p. 9.

G.R. No. 110434 December 13, 1993


3 Ibid., p. 76.

HI-PRECISION STEEL CENTER, INC., petitioner,


4 Ibid.

vs.
5 Annexes G-1 and G-2 of Reply to Opposition to Motion to
Suspend Proceedings; Rollo in CA-G.R. SP No. 33412, pp.
190-191. LIM KIM STEEL BUILDERS, INC., and CONSTRUCTION
INDUSTRY ARBITRATION COMMISSION, respondents.
6 Presided by Judge Domingo R. Garcia.
Felix Q. Vinluan and Siguion Reyna, Montecillo & Ongsiako for
petitioner.
7 Rollo, pp. 16-17.

De Castro & Cagampang Law Offices for Lim Kim teel Builders,
8 325 Phil. 1069, 1076 (1996).
Inc.
9 Commissioner of Internal Revenue v. Court of Appeals, 327
RESOLUTION
Phil. 1, 41-42 (1996).

10 Sps. Mejares v. Hon. Reyes, 324 Phil. 710, 718 (1996).

FELICIANO, J.:
11 Gamido v. New Bilibid Prisons Officials, 312 Phil. 100, 104.

12 2 BOUVIER'S LAW DICTIONARY, 3rd revision, p. 3171. On 18 June 1993, a "Petition for Extension to File Petition for
Review" 1 was filed before the Court, petitioner Hi-Precision
Steel Center, Inc. ("Hi-Precision") stating that it intended to file
13 17 C.J.S. 727-728. a Petition for Review on Certiorari in respect of the 13
November 1992 Award 2 and 13 May 1993 Order 3 of public
14 Ibid., pp. 728 & 729. respondent Construction Industry Arbitration Commission
("CIAC") in Arbitration Case No. 13-90. The Petition (really a
15 MORENO, PHILIPPINE LAW DICTIONARY, 3rd ed., p. 790. Motion) prayed for an extension of thirty (30) days or until 21
July 1993 within which to file a Petition for Review.
16 Sec. 22, Rep. Act No. 876.
An opposition 4 to the Motion was filed by private respondent
17 Sec. 23 of Rep. Act No. 876 provides: "Confirmation of Lim Kim Steel Builders, Inc. ("Steel Builders") on 5 July 1993.
award. At any time within one month after the award is On the same day, however, the Court issued a Resolution 5
made, any party to the controversy which was arbitrated may granting the Motion with a warning that no further extension
apply to the court having jurisdiction, as provided in section would be given.
twenty-eight, for an order confirming the award; and thereupon
the court must grant such order unless the ward is vacated, The Opposition, the subsequent Reply 6 of petitioner filed on 20
modified or corrected, as prescribed herein. Notice of such July 1993 and the Petition for Review 7 dated 21 July 1993,
motion shall be served upon the adverse party or his attorney were noted by the Court in its Resolution 8 of 28 July 1993. The
as prescribed by law for the service of such notice upon an Court also required private respondent Steel Builders to file a
attorney in action in the same court. Comment on the Petition for Review and Steel Builders
complied.
18 Puromines, Inc. v. Court of Appeals, G.R. No. 91228, March
22, 1993, 220 SCRA 281, 289-290. The Petition prays for issuance of a temporary restraining order
9 to stay the execution of the assailed Order and Award in favor

19 Chung Fu Industries (Phils.), Inc. v. Court of Appeals, G.R. of Steel Builders, which application the Court merely noted, as
No. 96283, February 25, 1992, 206 SCRA 545, 551. it did subsequent Urgent Motions for a temporary restraining
order. 10
ADR || First Batch 10

Petitioner Hi-Precision entered into a contract with private allegedly incurred to complete the project; and (b) private
respondent Steel Builders under which the latter as Contractor respondent's claim for profit it had failed to earn because of
was to complete a P21 Million construction project owned by petitioner's take over of the project.
the former within a period of 153 days, i.e. from 8 May 1990 to
8 October 1990. The project completion date was first moved to The Tribunal then proceeded to resolve the remaining specific
4 November 1990. On that date, however, only 75.8674% of claims of the parties. In disposing of these multiple, detailed
the project was actually completed. Petitioner attributed this claims the Arbitral Tribunal, in respect of one or more of the
non-completion to Steel Builders which allegedly had frequently respective claims of the parties: (a) averaged out the conflicting
incurred delays during the amounts and percentages claimed by the parties; 13 (b) found
neither basis nor justification for a particular claim; 14 (c) found
original contract period and the extension period. Upon the the evidence submitted in support of particular claims either
other hand, Steel Builders insisted that the delays in the project weak or non-existent; 15 (d) took account of the admissions of
were either excusable or due to Hi-Precision's own fault and liability in respect of particular claims; 16 (e) relied on its own
issuance of change orders. The project was taken over on 7 expertise in resolving particular claims; 17 and (f) applied a
November 1990, and eventually completed on February 1991, "principle of equity" in requiring each party to bear its own loss
by Hi-Precision. resulting or arising from mutual fault or delay (compensation
morae). 18
Steel Builders filed a "Request for Adjudication" with public
respondent CIAC. In its Complaint filed with the CIAC, Steel Petitioner Hi-Precision now asks this Court to set aside the
Builders sought payment of its unpaid progress buildings, Award, contending basically that it was the contractor Steel
alleged unearned profits and other receivables. Hi-Precision, Builders who had defaulted on its contractual undertakings and
upon the other hand, in its Answer and Amended Answer, so could not be the injured party and should not be allowed to
claimed actual and liquidated damages, reimbursement of recover any losses it may have incurred in the project.
alleged additional costs it had incurred in order to complete the Petitioner Hi-Precision insists it is still entitled to damages, and
project and attorney's fees. claims that the Arbitral Tribunal committed grave abuse of
discretion when it allowed certain claims by Steel Builders and
The CIAC formed an Arbitral Tribunal with three (3) members, offset them against claims of Hi-Precision.
two (2) being appointed upon nomination of Hi-Precision and
Steel Builders, respectively; the third member (the Chairman) A preliminary point needs to be made. We note that the Arbitral
was appointed by the CIAC as a common nominee of the two Tribunal has not been impleaded as a respondent in the
(2) parties. On the Chairman was a lawyer. After the arbitration Petition at bar. The CIAC has indeed been impleaded;
proceeding, the Arbitral Tribunal rendered a unanimous Award however, the Arbitral Award was not rendered by the CIAC, but
dated 13 November 1992, the dispositive portion of which reads rather by the Arbitral Tribunal. Moreover, under Section 20 of
as follows: Executive Order No. 1008, dated 4 February 1985, as
amended, it is the Arbitral Tribunal, or the single Arbitrator, with
WHEREFORE, premises considered, the Owner [petitioner Hi- the concurrence of the CIAC, which issues the writ of execution
Precision] is ordered to pay the Contractor [private respondent requiring any sheriff or other proper officer to execute the
Steel Builders] the amount of P6,400,717.83 and all other award. We consider that the Arbitral Tribunal which rendered
claims of the parties against each other are deemed the Award sought to be reviewed and set aside, should be
compensated and offset. No pronouncement as to costs. impleaded even though the defense of its Award would
presumably have to be carried by the prevailing party.
The Parties are enjoined to abide by the award. 11
Petitioner Hi-Precision apparently seeks review of both under
Rule 45 and Rule 65 of the Rules of Court. 19 We do not find it
Upon motions for reconsideration filed, respectively, by Hi-
necessary to rule which of the two: a petition for review under
Precision and Steel Builders, the Arbitral Tribunal issued an
Rule 45 or a petition for certiorari under Rule 65 is necessary
Order dated 13 May 1993 which reduced the net amount due to
under Executive Order No. 1008, as amended; this issue was,
contractor Steel Builders to P6,115,285.83. 12
in any case, not squarely raised by either party and has not
been properly and adequately litigated.
In its Award, the Arbitral Tribunal stated that it was guided by
Articles 1169, 1192 and 2215 of the Civil Code. With such
In its Petition, Hi-Precision purports to raise "legal issues," and
guidance, the arbitrators concluded that (a) both parties were at
in presenting these issues, prefaced each with a creative
fault, though the Tribunal could not point out which of the
formula:
parties was the first infractor; and (b) the breaches by one party
affected the discharge of the reciprocal obligations of the other
party. With mutual fault as a principal premise, the Arbitral (1)
Tribunal denied (a) petitioner's claims for the additional costs
ADR || First Batch 11

The public respondent [should be the "Arbitral Tribunal'] People, 95 Phil. 253); (3) when the judgment is premised on a
committed serious error in law, if not grave abuse of discretion, misapprehension of facts (De la Cruz v. Sosing, 94 Phil. 26 and
when it failed to strictly apply Article 1191, New Civil Code, Castillo vs. CA, 124 SCRA 808); (4) when the findings of fact
against the are conflicting (Casica v. Villaseca, 101 Phil. 1205); (5) when
the findings are contrary to the admissions of the parties
contractor . . .; (Evangelista v. Alto Surety, 103 Phil. 401), and therefore, the
findings of facts of the public respondent in the instant case
may be reviewed by the Honorable Supreme Court. 20
(2)
(Emphasis partly applied and partly in the original)
The public respondent committee serious error in law, if not
From the foregoing, petitioner Hi-Precision may be seen to be
grave abuse of discretion, when it failed to rule in favor of the
making two (2) basic arguments:
owner, now petitioner herein, all the awards it claimed on
arbitration, and when it nonetheless persisted in its awards of
damages in favor of the (a) Petitioner asks this Court to correct legal errors committed
by the Arbitral Tribunal, which at the same time constitute grave
abuse of discretion amounting to lack of jurisdiction on the part
respondent. . . .;
of the Arbitral Tribunal; and
(3)
(b) Should the supposed errors petitioner asks us to correct be
characterized as errors of fact, such factual errors should
The public respondent committed serious error in law, if not nonetheless be reviewed because there was "grave abuse of
grave abuse of discretion, for its abject failure to apply the discretion" in the misapprehension of facts on the part of the
doctrine of waiver, estoppel against the contractor, the private Arbitral Tribunal.
respondent herein, when it agreed on November 16, 1990 to
award termination of the contract and the owner's takeover of
Executive Order No. 1008, as amended, provides, in its Section
the project . . .;
19, as follows:
(4)
Sec. 19. Finality of Awards. The arbitral award shall be
binding upon the parties. It shall be final and inappealable
The public respondent committed serious error in law, if not except on questions of law which shall be appealable to the
grave abuse of discretion, when it did not enforce the law Supreme Court.
between the parties, the "technical specification[s]" which is one
of the contract documents, particularly to par. (a), sub-part 3.01,
Section 19 makes it crystal clear that questions of fact cannot
part 3, Sec. 2b, which expressly requires that major site work
be raised in proceedings before the Supreme Court which is
activities like stripping, removal and stockpiling of top soil shall
not a trier of facts in respect of an arbitral award rendered
be done "prior to the start of regular excavation or backfiling
under the aegis of the CIAC. Consideration of the animating
work", the principal issue in arbitration being non-compliance
purpose of voluntary arbitration in general, and arbitration under
with the contract documents;
the aegis of the CIAC in particular, requires us to apply
rigorously the above principle embodied in Section 19 that the
(5) Arbitral Tribunal's findings of fact shall be final and
inappealable.
The public respondent committed serious error in law, if not
grave abuse of discretion, when it found, in the May 13, 1993 Voluntary arbitration involves the reference of a dispute to an
Order, the petitioner "guilty of estoppel" although it is claimed impartial body, the members of which are chosen by the parties
that the legal doctrine of estoppel does not apply with respect themselves, which parties freely consent in advance to abide by
to the required written formalities in the issuance of change the arbitral award issued after proceedings where both parties
order . . .; had the opportunity to be heard. The basic objective is to
provide a speedy and inexpensive method of settling disputes
(6) by allowing the parties to avoid the formalities, delay, expense
and aggravation which commonly accompany ordinary
The exceptional circumstances in Remalante vs. Tibe, 158 litigation, especially litigation which goes through the entire
SCRA 138, where the Honorable Supreme Court may review hierarchy of courts. Executive Order No. 1008 created an
findings of facts, are present in the instant case, namely; (a) arbitration facility to which the construction industry in the
when the inference made is manifestly absurd, mistaken or Philippines can have recourse. The Executive Order was
impossible (Luna vs. Linatoc, 74 Phil. 15); (2) when there is enacted to encourage the early and expeditious settlement of
grave abuse of discretion in the appreciation of facts (Buyco vs. disputes in the construction industry, a public policy the
ADR || First Batch 12

implementation of which is necessary and important for the persons who have acquired the thing, in accordance with
realization of national development goals. 21 articles 1385 and 1388 and the Mortgage Law.

Aware of the objective of voluntary arbitration in the labor field, Hi-Precision contends energetically that it is the injured party
in the construction industry, and in any other area for that and that Steel Builders was the obligor who did not comply with
matter, the Court will not assist one or the other or even both what was incumbent upon it, such that Steel Builders was the
parties in any effort to subvert or defeat that objective for their party in default and the entity guilty of negligence and delay. As
private purposes. The Court will not review the factual findings the injured party, Hi-Precision maintains that it may choose
of an arbitral tribunal upon the artful allegation that such body between the fulfillment or rescission of the obligation in
had "misapprehended the facts" and will not pass upon issues accordance with Article 1191, and is entitled to damages in
which are, at bottom, issues of fact, no matter how cleverly either case. Thus, Hi-Precision continues, when the contractor
disguised they might be as "legal questions." The parties here Steel Builders defaulted on the 153rd day of the original
had recourse to arbitration and chose the arbitrators contract period, Hi-Precision opted for specific performance and
themselves; they must have had confidence in such arbitrators. gave Steel Builders a 30-day extension period with which to
The Court will not, therefore, permit the parties to relitigate complete the project.
before it the issues of facts previously presented and argued
before the Arbitral Tribunal, save only where a very clear What petitioner Hi-Precision, in its above argument, disregards
showing is made that, in reaching its factual conclusions, the is that the determination of whether Hi-Precision or Steel
Arbitral Tribunal committed an error so egregious and hurtful to Builders was the "injured party" is not to be resolved by an
one party as to constitute a grave abuse of discretion resulting application of Article 1191. That determination is eminently a
in lack or loss of jurisdiction. 22 Prototypical examples would be question of fact, for it requires ascertainment and identification
factual conclusions of the Tribunal which resulted in deprivation of which the two (2) contending parties had first failed to comply
of one or the other party of a fair opportunity to present its with what is incumbent upon it. In other words, the supposed
position before the Arbitral Tribunal, and an award obtained misapplication of Article 1191, while ostensibly a "legal issue,"
through fraud or the corruption of arbitrators. 23 Any other, more is ultimately a question of fact, i.e., the determination of the
relaxed, rule would result in setting at naught the basic existence or non-existence of a fact or set of facts in respect of
objective of a voluntary arbitration and would reduce arbitration which Article 1191 may be properly applied. Thus, to ask this
to a largely inutile institution. Court to correct a claimed misapplication or non-application of
Article 1191 is to compel this Court to determine which of the
Examination of the Petition at bar reveals that it is essentially two (2) contending parties was the "injured party" or the "first
an attempt to re-assert and re-litigate before this Court the infractor." As noted earlier, the Arbitral Tribunal after the
detailed or itemized factual claims made before the Arbitral prolonged arbitration proceeding, was unable to make that
Tribunal under a general averment that the Arbitral Tribunal had factual determination and instead concluded that both parties
"misapprehended the facts" submitted to it. In the present had committed breaches of their respective obligations. We will
Petition, too, Hi-Precision claims that the Arbitral Tribunal had not review, and much less reverse, that basic factual finding of
committed grave abuse of discretion amounting to lack of the Arbitral Tribunal.
jurisdiction in reaching its factual and legal conclusions.
A second "legal issue" sought to be raised by petitioner Hi-
The first "legal issue" submitted by the Petition is the claimed Precision relates to the supposed failure of the Arbitral Tribunal
misapplication by the Arbitral Tribunal of the first and second to apply the doctrines of estoppel and waiver as against Steel
paragraphs of Article 1911 of the Civil Code. 24 Article 1191 Builders. 25 The Arbitral Tribunal, after declaring that the parties
reads: were mutually at fault, proceeded to enumerate the faults of
each of the parties. One of the faults attributed to petitioner Hi-
Art. 1191. The power to rescind obligations is implied in Precision is that it had failed to give the contractor Steel
reciprocal ones, in case one of the obligors should not comply Builders the required 15-day notice for termination of the
with what is incumbent upon him. contract. 26 This was clearly a finding of fact on the part of the
Tribunal, supported by the circumstance that per the record,
petitioner had offered no proof that it had complied with such
The injured party may choose between the fulfillment and the
15-day notice required under Article 28.01 of the General
rescission of the obligation, with the payment of damages in
Conditions of Contract forming part of the Contract Documents.
either case. He may also seek rescission, even after he has
Petitioner Hi-Precision's argument is that a written Agreement
chosen fulfillment, if the latter should become impossible.
dated 16 November 1990 with Steel Builders concerning the
take over of the project by Hi-Precision, constituted waiver on
The court shall decree the rescission claimed, unless there be the part of the latter of its right to a 15-day notice of contract
just cause authorizing the fixing of a period. termination. Whether or not that Agreement dated 16
November 1990 (a document not submitted to this Court) is
This is understood to be without prejudice to the rights of third properly characterized as constituting waiver on the part of
ADR || First Batch 13

Steel Builders, may be conceded to be prima facie a question 12.8. -do- 7 503,836.53
of law; but, if it is, and assuming arguendo that the Arbitral
Tribunal had erred in resolving it, that error clearly did not 12.9. -do- 8 216,138.75
constitute a grave abuse of discretion resulting in lack or loss of
jurisdiction on the part of the Tribunal.
12.10. -do- 9 101,621.40

A third "legal issue" posed by Hi-Precision relates to the


12.11. -do- 10 7,200.00
supposed failure on the part of the Arbitral Tribunal "to uphold
the supremacy of 'the
12.12. -do- 11 0.00
law between the parties' and enforce it against private
respondent [Steel Builders]." 27 The "law between that parties" 12.13. -do- 12 7,800.00
here involved is the "Technical Specifications" forming part of
the Contract Documents. Hi-Precision asserts that the Arbitral 12.14. -do- 13 49,250.00
Tribunal did not uphold the "law between the parties," but
instead substituted the same with "its [own] absurd inference 12.15. -do- 14 167,952.00
and 'opinion' on mud." Here again, petitioner is merely
disguising a factual question as a "legal issue," since petitioner 12.16. -do- 15 445,600.00
is in reality asking this Court to review the physical operations
relating, e.g., to site preparation carried out by the contractor
12.17. -do- 16 92,457.30
Steel Builders and to determine whether such operations were
in accordance with the Technical Specifications of the project.
The Arbitral Tribunal resolved Hi-Precision's claim by finding 12.18. -do- 17 1,500.00
that Steel Builders had complied substantially with the
Technical Specifications. This Court will not pretend that it has 12.19. 20,240.00
the technical and engineering capability to review the resolution
of that factual issue by the Arbitral Tribunal. 12.20. 63,518.00

Finally, the Petition asks this Court to "review serious errors in 12.21. 0.00
the findings of fact of the [Arbitral Tribunal]." 28 In this section of
its Petition, 12.22. 0.00

Hi-Precision asks us to examine each item of its own claims 12.23. 0.00
which the Arbitral Tribunal had rejected in its Award, and each
claim of the contractor Steel Builders which the Tribunal had
granted. In respect of each item of the owner's claims and each 12.24. 0.00
item of the contractor's claims, Hi-Precision sets out its
arguments, to all appearances the same arguments it had 12.25. 0.00
raised before the Tribunal. As summarized in the Arbitral
Award, Contractor's Claims were as follows: 12.26. 730,201.57

12.1. Unpaid Progress Billing 1,812,706.95 12.27. 1,130,722.70

12.2. Change Order 1 0.00 12.28. 0.00

12.3. -do- 2 10,014.00 12.29. 273,991.00

12.4. -do- 3 320,000.00 12.30. 0.00

12.5. -do- 4 112,300.70

12.6. -do- 5 398,398.00 12.31. 7,318,499.28 29

12.7. -do- 6 353,050.38 =============


ADR || First Batch 14

Upon the other hand, the petitioner's claims we are asked to (P24.1326%) 2,027,138.40
review and grant are summarized as follows:
b. Due to Huey Commercial
1. Actual Damages
used for HSCI Project 51,110.40
Advance Downpayment
IC Additional construction expenses
[at] signing of Contract
a. Increases in prices since Oct. 5,272,096.81
which is subject to 40%
b. Cost of money of (a) 873,535.49
deduction every progress
ID Installation of machinery
billing (40% of Contract Price) P8,406,000.00
a. Foreign exchange loss 11,565,048.37
Progress Billings 5,582,585.55
b. Cost of money (a) 2,871,987.01
Advances made to Lim Kim
I[E] Raw Materials
a) prior to take-over 392,781.45
a. Foreign exchange loss 4,155,982.18
b) after the take-over
b. Cost of money (a) 821,242.72
Civil Works 1,158,513.88
c. Additional import levy of 5% 886,513.33
Materials 4,213,318.72
d. Cost of money (c) 170,284.44
Labor 2,155,774.79
e. Cost of money on marginal
Equipment Rental 1,448,208.90
deposit on Letter of Credit 561,195.25

IF Cost of money on holding to CRC INTY 3,319,609.63


P8,974,816.45
Total Actual Damages 35,295,927.32
Total Amount Paid for Construction 23,650,183.00
2. Liquidated Damages 2,436,000.00
Less: Contract Price (21,000,000.00)
3. Attorney's Fees 500,000.00
IA Excess of amount paid

over contract price 2,650,163.29
P38,231,927.32 30
IB Other items due from Lim
=============
Kim Steel Builders
We consider that in asking this Court to go over each individual
a. Amount not yet deducted claim submitted by it and each individual countering claim
submitted by Steel Builders to the Arbitral Tribunal, petitioner
from Downpayment due Hi-Precision is asking this Court to pass upon claims which are
either clearly and directly factual in nature or require previous
determination of factual issues. This upon the one hand. Upon
to non-completion of Project
the other hand, the Court considers that petitioner Hi-Precision
ADR || First Batch 15

has failed to show any serious errors of law amounting to grave 16 Claims concerning Change Order No. 10; Change Order No.
abuse of discretion resulting in lack of jurisdiction on the part of 17.
the Arbitral Tribunal, in either the methods employed or the
results reached by the Arbitral Tribunal, in disposing of the 17 Claims concerning Change Order No. 7; Change Order No.
detailed claims of the respective parties. 12; Change Order

WHEREFORE, for all the foregoing, the Petition is hereby No. 13; Change Order No. 14.
DISMISSED for lack of merit. Costs against petitioner.
18 Claims concerning Contractor's Claim No. 19; Contractor's
SO ORDERED. Claim No. 20; Contractor's Claim No. 21; Contractor's Claim
No. 22; Contractor's Claim No. 23; Contractor's Claim No. 24;
Bidin, Romero, Melo and Vitug, JJ., concur Contractor's Claim No. 25; Contractor's Claim No. 27;
Contractor's Claim No. 28; Contractor's Claim No. 29;
Contractor's Claim No. 30; Owner's Claim No. 3.

# Footnotes 19 The Petition said, inter alia: "[t]he prevalence of grave abuse
of discretion in the May 13, 1993 Order on appeal in this
Petition under Rule 45 is made more manifest in the November
1 Rollo, pp. 2-9.
13, 1992 Arbitral Award, the principal resolution subject of the
motion for reconsideration denied by the May 13, 1993 Order,
2 Id., pp. 137-181. and thus, it becomes procedurally appropriate and necessary,
in the interest of truth and justice, to respectfully pray the
3 Id., pp. 11-23. Honorable Court to likewise review on certiorari under Rule 65,
the November 13, 1992 award." (Emphasis supplied)
4 Id., pp. 24-26.
20 Rollo, pp. 74-76.
5 Id., p. 23-a.
21 See first three (3) Whereas clauses and Section 2 of
6 Id., pp. 29-32. Executive Order No. 1008, as amended.

7 Id., pp. 42-136. 22 See: Asian Construction and Development Corporation v.


Construction Industry Arbitration Commission, et al., 218 SCRA
8 Id., p. 181-a. 529 (1993); Chung Fu v. Court of Appeals, 206 SCRA 545
(1992); Primary Structures Corp. v. Victor P. Lazatin, etc., et al.,
G.R. No. 101258, July 13, 1992 (unsigned resolution); A.C.
9 Id., p. 89; Rollo, p. 131.
Enterprises, Inc. v. Construction Industry Arbitration
Commission, et al., G.R. No. 101444, February 10, 1992
10 Urgent Motions for the Issuance of a Temporary Restraining (unsigned resolution); and Sime Darby Pilipinas, Inc. v.
Order dated 5 August 1993; 25 August 1993; 20 September Magsalin, 180 SCRA 177 (1989).
1993; 21 October 1993.
23 It is noteworthy that Section 24 of R.A. No. 876 known as
11 Rollo, pp. 180-181. "An Act to Authorize the Making of Arbitration and Submission
Agreements, to Provide for the Appointment of Arbitrators and
12 Id., p. 23. the Procedure for Arbitration in Civil Controversies, and for
Other Purposes" (approved on 29 June 1953) sets out the
13 Claims concerning Contractor's Claim No. 1; Owner's Claim following grounds for vacating an arbitral award:
No. 1; Unpaid Progressive Billing; Change Order No. 6; Change
Order No. 8. "Sec. 24. Grounds for vacating award. In any one of the
following cases, the court must make an order vacating award
14 Claims concerning Change Order No. 1. upon the petition of any party to the controversy when such
party proved affirmatively that in the arbitration proceedings;
15 Claims concerning Change Order No. 2; Change Order No.
3; Change Order No. 4; Change Order No. 5; Change Order (a) The award was procured by corruption, fraud or other undue
No. 11; Change Order No. 16. means; or
ADR || First Batch 16

(b) That there was evident partiality or corruption in the Republic of the Philippines
arbitrators or any of them; or SUPREME COURT
Manila
(c) That the arbitrators were guilty of misconduct in refusing to SECOND DIVISION
postpone the hearing upon sufficient cause shown, or in
refusing to hear evidence pertinent and material to the
controversy; that one or more of the arbitrators was disqualified G.R. No. 115412 November 19, 1999
to act as such under section nine hereof, and willfully refrained
from disclosing such disqualifications or of any other HOME BANKERS SAVINGS AND TRUST COMPANY,
misbehavior by which the rights of any party have been petitioner,
materially prejudiced; or
vs.
(d) That the arbitrators exceeded their powers, or so imperfectly
executed them, that a mutual, final and definite award upon the
COURT OF APPEALS and FAR EAST BANK & TRUST CO.,
subject matter submitted to them was not made.
INC. respondents.

xxx xxx xxx

24 Petition, Rollo, pp. 93-97.


BUENA, J.:

25 Id., Rollo, pp. 77-80.


This appeal by certiorari under Rule 45 of the Rules of Court
seeks to annul and set aside the decision 1 of the Court of
26 Arbitral Award, Rollo, p. 153. Appeals 2 dated January 21, 1994 in CA-G.R. SP No. 29725,
dismissing the petition for certiorari filed by petitioner to annul
27 Petition, Rollo, pp. 80-90. the two (2) orders issued by the Regional Trial Court of Makati 3
in Civil Case No. 92-145, the first, dated April 30, 1992, denying
28 Id., Rollo, p. 97 et seq. petitioner's motion to dismiss and the second, dated October 1,
1992 denying petitioner's motion for reconsideration thereof.
29 Rollo, pp. 111-112.
The pertinent facts may be briefly stated as follows: Victor
Tancuan, one of the defendants in Civil Case No. 92-145,
30 Id., pp. 131-133.
issued Home Bankers Savings and Trust Company (HBSTC)
check No. 193498 for P25,250,000.00 while Eugene
Arriesgado issued Far East Bank and Trust Company (FEBTC)
check Nos. 464264, 464272 and 464271 for P8,600,000.00,
P8,500,000.00 and P8,100,000.00, respectively, the three
checks amounting to P25,200,000.00. Tancuan and Arriesgado
exchanged each other's checks and deposited them with their
respective banks for collection. When FEBTC presented
Tancuan's HBSTC check for clearing, HBSTC dishonored it for
being "Drawn Against Insufficient Funds." On October 15, 1991,
HBSTC sent Arriesgado's three (3) FEBTC checks through the
Philippine Clearing House Corporation (PCHC) to FEBTC but
was returned on October 18, 1991 as "Drawn Against
Insufficient Funds." HBSTC received the notice of dishonor on
October 21, 1991 but refused to accept the checks and on
October 22, 1991, returned them to FEBTC through the PCHC
for the reason "Beyond Reglementary Period," implying that
HBSTC already treated the three (3) FEBTC checks as cleared
and allowed the proceeds thereof to be withdrawn. 4 FEBTC
demanded reimbursement for the returned checks and inquired
from HBSTC whether it had permitted any withdrawal of funds
against the unfunded checks and if so, on what date. HBSTC,
however, refused to make any reimbursement and to provide
FEBTC with the needed information.
ADR || First Batch 17

Thus, on December 12, 1991, FEBTC submitted the dispute for may go to court to obtain conservatory reliefs in connection with
arbitration before the PCHC Arbitration Committee, 5 under the his cause of action although the disposal of that action on the
PCHC's Supplementary Rules on Regional Clearing to which merits cannot as yet be obtained." 18 The respondent court
FEBTC and HBSTC are bound as participants in the regional discarded Puromines, Inc. vs. Court of Appeals, 19 stating that ".
clearing operations administered by the PCHC. 6 . . perhaps Puromines may have been decided on a different
factual basis." 20
On January 17, 1992, while the arbitration proceeding was still
pending, FEBTC filed an action for sum of money and damages In the instant petition, 21 petitioner contends that first, "no party
with preliminary litigant can file a non-existent complaint," 22 arguing that ". . .
one cannot file a complaint in court over a subject that is
attachment 7 against HBSTC, Robert Young, Victor Tancuan undergoing arbitration." 23 Second, petitioner submits that
and Eugene Arriesgado with the Regional Trial Court of Makati, "[s]ince arbitration is a special proceeding by a clear provision
Branch 133. A motion to dismiss was filed by HBSTC claiming of law, 24 the civil suit filed below is, without a shadow of doubt,
that the complaint stated no cause of action and accordingly ". . barred by litis pendentia and should be dismissed de plano
. should be dismissed because it seeks to enforce an arbitral insofar as HBSTC is concerned." 25 Third, petitioner insists that
award which as yet does not exist." 8 The trial court issued an "[w]hen arbitration is agreed upon and suit is filed without
omnibus order dated April 30, 1992 denying the motion to arbitration having been held and terminated, the case that is
dismiss and an order dated October 1, 1992 denying the filed should be dismissed," 26 citing Associated Bank vs. Court
motion for reconsideration. of Appeals, 27 Puromines, Inc. vs. Court of Appeals, 28 as and
Ledesma vs. Court of Appeals. 29 Petitioner demurs that the
Puromines ruling was deliberately not followed by the
On December 16, 1992, HBSTC filed a petition for certiorari
respondent court which claimed that:
with the respondent Court of Appeals contending that the trial
court acted with grave abuse of discretion amounting to lack of
jurisdiction in denying the motion to dismiss filed by HBSTC. xxx xxx xxx

In a Decision 9 dated January 21, 1994, the respondent court It would really be much easier for Us to rule to dismiss the
dismissed the petition for lack of merit and held that "FEBTC complaint as the petitioner here seeks to do, following
can reiterate its cause of action before the courts which it had Puromines. But with utmost deference to the Honorable
already raised in the arbitration case" 10 after finding that the Supreme Court, perhaps Puromines may have been decided
complaint filed by FEBTC ". . . seeks to collect a sum of money on a different factual basis.
from HBT [HBSTC] and not to enforce or confirm an arbitral
award." 11 The respondent court observed that "[i]n the xxx xxx xxx 30
Complaint, FEBTC applied for the issuance of a writ of
preliminary attachment over HBT's [HBSTC] property" 12 and Petitioner takes exception to FEBTC's contention that
citing section 14 of Republic Act No. 876, otherwise known as Puromines cannot modify or reverse the rulings in National
the Arbitration Law, maintained that "[n]ecessarily, it has to Union Fire Insurance Company of Pittsburg vs. Stolt-Nielsen
reiterate its main cause of action for sum of money against HBT Philippines, Inc., 31 and Bengson vs. Chan, 32 where this Court
[HBSTC]," 13 and that "[t]his prayer for conservatory relief [writ suspended the action filed pending arbitration, and argues that
of preliminary attachment] satisfies the requirement of a cause "[s]ound policy requires that the conclusion of whether a
of action which FEBTC may pursue in the courts." 14 Supreme Court decision has or has not reversed or modified [a]
previous doctrine, should be left to the Supreme Court itself;
Furthermore, the respondent court ruled that based on section until then, the latest pronouncement should prevail." 33 Fourth,
7 of the Arbitration Law and the cases of National Union Fire petitioner alleges that the writ of preliminary attachment issued
Insurance Company of Pittsburg vs. Stolt-Nielsen Philippines, by the trial court is void considering that the case filed before it
Inc., 15 and Bengson vs. Chan, 16 ". . . when there is a condition "is a separate action which cannot exist," 34 and ". . . there is
requiring prior submission to arbitration before the institution of even no need for the attachment as far as HBSTC is concerned
a court action, the complaint is not to be dismissed but should because such automatic debit/credit procedure 35 may be
be suspended for arbitration." 17 Finding no merit in HBSTC's regarded as a security for the transactions involved and, as
contention that section 7 of the Arbitration Law ". . . jurisprudence confirms, one requirement in the issuance of an
contemplates a situation in which a party to an arbitration attachment [writ of preliminary attachment] is that the debtor
agreement has filed a court action without first resorting to has no sufficient security." 36 Petitioner asserts further that a
arbitration, while in the case at bar, FEBTC has initiated writ of preliminary attachment is unwarranted because no
arbitration proceedings before filing a court action," the ground exists for its issuance. According to petitioner, ". . . the
respondent court held that ". . . if the absence of a prior only allegations against it [HBSTC] are that it refused to refund
arbitration may stay court action, so too and with more reason, the amounts of the checks of FEBTC and that it knew about the
should an arbitration already pending as obtains in this case fraud perpetrated by the other defendants," 37 which, at best,
stay the court action. A party to a pending arbitral proceeding constitute only "incidental fraud" and not causal fraud which
ADR || First Batch 18

justifies the issuance of the writ of preliminary attachment. to issue subpoena and subpoena duces tecum at any time
before rendering the award. The exercise of such power is
Private respondent FEBTC, on the other hand, contends that ". without prejudice to the right of a party to file a petition in court
. . the cause of action for collection [of a sum of money] can to safeguard any matter which is the subject of the dispute in
coexist in the civil suit and the arbitration [proceeding]" 38 citing arbitration. In the case at bar, private respondent filed an action
section 7 of the Arbitration Law which provides for the stay of for a sum of money with prayer for a writ of preliminary
the civil action until an arbitration has been had in accordance attachment. Undoubtedly, such action involved the same
with the terms of the agreement providing for arbitration. Private subject matter as that in arbitration, i.e., the sum of
respondent further asserts that following section 4(3), article P25,200,000.00 which was allegedly deprived from private
VIII 39 of the 1987 Constitution, the subsequent case of respondent in what is known in banking as a "kiting scheme."
Puromines does not overturn the ruling in the earlier cases of However, the civil action was not a simple case of a money
National Union Fire Insurance Company of Pittsburg vs. Stolt- claim since private respondent has included a prayer for a writ
Nielsen Philippines, Inc., 40 and Bengson vs. Chan, 41 hence, of preliminary attachment, which is sanctioned by section 14 of
private respondent concludes that the prevailing doctrine is that the Arbitration Law.
the civil action must be stayed rather than dismissed pending
arbitration. Petitioner cites the cases of Associated Bank vs. Court of
Appeals, 43 Puromines, Inc. vs. Court of Appeals, 44 and
In this petition, the lone issue presented for the consideration of Ledesma vs. Court of Appeals 45 in contending that "[w]hen
this Court is: arbitration is agreed upon and suit is filed without arbitration
having been held and terminated, the case that is filed should
be dismissed." 46 However, the said cases are not in point. In
WHETHER OR NOT PRIVATE RESPONDENT WHICH
Associated Bank, we affirmed the dismissal of the third-party
COMMENCED AN ARBITRATION PROCEEDING UNDER
complaint filed by Associated Bank against Philippine
THE AUSPICES OF THE PHILIPPINE CLEARING HOUSE
Commercial International Bank, Far East Bank & Trust
CORPORATION (PCHC) MAY SUBSEQUENTLY FILE A
Company, Security Bank and Trust Company, and Citytrust
SEPARATE CASE IN COURT OVER THE SAME SUBJECT
Banking Corporation for lack of jurisdiction, it being shown that
MATTER OF ARBITRATION DESPITE THE PENDENCY OF
the said parties were bound by the Clearing House Rules and
THAT ARBITRATION, SIMPLY TO OBTAIN THE
Regulations on Arbitration of the Philippine Clearing House
PROVISIONAL REMEDY OF ATTACHMENT AGAINST THE
Corporation. In Associated Bank, we declared that:
BANK THE ADVERSE PARTY IN THE ARBITRATION
PROCEEDING. 42
. . . . . .. Under the rules and regulations of the Philippine
Clearing House Corporation (PCHC), the mere act of
We find no merit in the petition. Section 14 of Republic Act 876,
participation of the parties concerned in its operations in effect
otherwise known as the Arbitration Law, allows any party to the
amounts to a manifestation of agreement by the parties to
arbitration proceeding to petition the court to take measures to
abide by its rules and regulations. As a consequence of such
safeguard and/or conserve any matter which is the subject of
participation, a party cannot invoke the jurisdiction of the courts
the dispute in arbitration, thus:
over disputes and controversies which fall under the PCHC
Rules and Regulations without first going through the arbitration
Sec. 14. Subpoena and subpoena duces tecum. Arbitrators processes laid out by the body. 47 (emphasis supplied)
shall have the power to require any person to attend a hearing
as a witness. They shall have the power to subpoena witnesses
And thus we concluded:
and documents when the relevancy of the testimony and the
materiality thereof has been demonstrated to the arbitrators.
Arbitrators may also require the retirement of any witness Clearly therefore, petitioner Associated Bank, by its voluntary
during the testimony of any other witness. All of the arbitrators participation and its consent to the arbitration rules cannot go
appointed in any controversy must attend all the hearings in directly to the Regional Trial Court when it finds it convenient to
that matter and hear all the allegations and proofs of the do so. The jurisdiction of the PCHC under the rules and
parties; but an award by the majority of them is valid unless the regulations is clear, undeniable and is particularly applicable to
concurrence of all of them is expressly required in the all the parties in the third party complaint under their obligation
submission or contract to arbitrate. The arbitrator or arbitrators to first seek redress of their disputes and grievances with the
shall have the power at any time, before rendering the award, PCHC before going to the trial court. 48 (emphasis supplied)
without prejudice to the rights of any party to petition the court
to take measures to safeguard and/or conserve any matter Simply put, participants in the regional clearing operations of
which is the subject of the dispute in arbitration. (emphasis the Philippine Clearing House Corporation cannot bypass the
supplied) arbitration process laid out by the body and seek relief directly
from the courts. In the case at bar, undeniably, private
Petitioner's exposition of the foregoing provision deserves scant respondent has initiated arbitration proceedings as required by
consideration. Section 14 simply grants an arbitrator the power the PCHC rules and regulations, and pending arbitration has
ADR || First Batch 19

sought relief from the trial court for measures to safeguard 8 Rollo, p. 131.
and/or conserve the subject of the dispute under arbitration, as
sanctioned by section 14 of the Arbitration Law, and otherwise 9 Ibid., at p. 127.
not shown to be contrary to the PCHC rules and regulations.
10 Ibid., at p. 135.
Likewise, in the case of Puromines, Inc. vs. Court of Appeals, 49
we have ruled that:
11 Ibid., at p. 131.

In any case, whether the liability of respondent should be based


12 Ibid., at p. 136.
on the sales contract or that of the bill of lading, the parties are
nevertheless obligated to respect the arbitration provisions on
the sales contract and/or bill of lading. Petitioner being a 13 Ibid.
signatory and party to the sales contract cannot escape from
his obligation under the arbitration clause as stated therein. 14 Ibid., at p. 138.

In Puromines, we found the arbitration clause stated in the 15 184 SCRA 682 (1990).
sales contract to be valid and applicable, thus, we ruled that the
parties, being signatories to the sales contract, are obligated to 16 78 SCRA 113 (1977).
respect the arbitration provisions on the contract and cannot
escape from such obligation by filing an action for breach of 17 Rollo, p. 139.
contract in court without resorting first to arbitration, as agreed
upon by the parties.
18 Ibid., at p. 140.
At this point, we emphasize that arbitration, as an alternative
19 220 SCRA 281 (1993).
method of dispute resolution, is encouraged by this Court.
Aside from unclogging judicial dockets, it also hastens solutions
especially of commercial disputes. 50 The Court looks with favor 20 Rollo, p. 141.
upon such amicable arrangement and will only interfere with
great reluctance to anticipate or nullify the action of the 21 Petitioner's memorandum was filed on February 17, 1995.
arbitrator. 51
22 Rollo, p. 314.
WHEREFORE, premises considered, the petition is hereby
DISMISSED and the decision of the court a quo is AFFIRMED. 23 Ibid., at p. 315.

SO ORDERED. 24 Petitioner referring to section 22 of Republic Act. No. 876.

Bellosillo, Mendoza, Quisumbing and De Leon, Jr., JJ., concur. 25 Rollo, p. 318.

Footnotes 26 Ibid.

1 Penned by Justice Cesar D. Francisco and concurred in by 27 233 SCRA 137 (1994).
Justices Manuel C. Herrera and Cancio C. Garcia.
28 220 SCRA 281 (1993).
2 Special Fifth Division.
29 211 SCRA 753 (1992).
3 Branch 133. Presided by Judge Buenaventura J. Guerrero,
now Associate Justice of the Court of Appeals. 30 Rollo, p. 141.

4 Rollo, p. 128. 31 184 SCRA 682 (1990).

5 Docketed as PCHC Arbitration Case No. 91-069. 32 78 SCRA 113 (1977).

6 Ibid., at p. 129. 33 Rollo, p. 320.

7 Docketed as Civil Case No. 92-145.


ADR || First Batch 20

34 Ibid., at p. 323. Republic of the Philippines


SUPREME COURT
35 Under the arbitration system of the PCHC, an award results Manila
in a mere automatic debit/credit procedure. THIRD DIVISION

36 Rollo, p. 324. Citation omitted. G.R. No. 141833 March 26, 2003

37 Ibid. LM POWER ENGINEERING CORPORATION, petitioner,

38 Ibid., p. 278. vs.

39 Art. VIII, section 4(3) provides: CAPITOL INDUSTRIAL CONSTRUCTION GROUPS, INC.,
respondent.
. . . . . .; Provided that no doctrine or principle of law laid down
by the court in a decision rendered en banc or in division may PANGANIBAN, J.:
be modified or reversed except by the court sitting en banc.
Alternative dispute resolution methods or ADRs -- like
40 184 SCRA 682 (1990). arbitration, mediation, negotiation and conciliation -- are
encouraged by the Supreme Court. By enabling parties to
resolve their disputes amicably, they provide solutions that are
41 78 SCRA 113 (1977).
less time-consuming, less tedious, less confrontational, and
more productive of goodwill and lasting relationships.1
42 Rollo, pp. 310-311.
The Case
43 233 SCRA 137 (1994).
Before us is a Petition for Review on Certiorari2 under Rule 45
44 220 SCRA 281 (1993). of the Rules of Court, seeking to set aside the January 28,
2000 Decision of the Court of Appeals3 (CA) in CA-GR CV No.
45 211 SCRA 753 (1992). This case involves the application of 54232. The dispositive portion of the Decision reads as follows:
the Katarungang Pambarangay Law (P.D. 1508).
"WHEREFORE, the judgment appealed from is REVERSED
46 Rollo, p. 318. and SET ASIDE. The parties are ORDERED to present their
dispute to arbitration in accordance with their Sub-contract
47 Associated Bank vs. Court of Appeals, 233 SCRA 137, 142- Agreement. The surety bond posted by [respondent] is
143 (1994). [d]ischarged."4

48 Ibid., at p. 145. The Facts

49 220 SCRA 281 (1993). On February 22, 1983, Petitioner LM Power Engineering
Corporation and Respondent Capitol Industrial Construction
50 Allied Banking Corporation vs. Court of Appeals, 294 SCRA Groups Inc. entered into a "Subcontract Agreement" involving
803, 812 (1998). electrical work at the Third Port of Zamboanga.5

51 Puromines, Inc. vs. Court of Appeals, 220 SCRA 281, 290 On April 25, 1985, respondent took over some of the work
(1993). contracted to petitioner.6 Allegedly, the latter had failed to finish
it because of its inability to procure materials.7

Upon completing its task under the Contract, petitioner billed


respondent in the amount of P6,711,813.90.8 Contesting the
accuracy of the amount of advances and billable
accomplishments listed by the former, the latter refused to pay.
Respondent also took refuge in the termination clause of the
Agreement.9 That clause allowed it to set off the cost of the
work that petitioner had failed to undertake -- due to termination
or take-over -- against the amount it owed the latter.
ADR || First Batch 21

Because of the dispute, petitioner filed with the Regional Trial Whether Dispute Is Arbitrable
Court (RTC) of Makati (Branch 141) a Complaint10 for the
collection of the amount representing the alleged balance due it Petitioner claims that there is no conflict regarding the
under the Subcontract. Instead of submitting an Answer, interpretation or the implementation of the Agreement. Thus,
respondent filed a Motion to Dismiss,11 alleging that the without having to resort to prior arbitration, it is entitled to collect
Complaint was premature, because there was no prior recourse the value of the services it rendered through an ordinary action
to arbitration. for the collection of a sum of money from respondent. On the
other hand, the latter contends that there is a need for prior
In its Order12 dated September 15, 1987, the RTC denied the arbitration as provided in the Agreement. This is because there
Motion on the ground that the dispute did not involve the are some disparities between the parties positions regarding
interpretation or the implementation of the Agreement and was, the extent of the work done, the amount of advances and
therefore, not covered by the arbitral clause.13 billable accomplishments, and the set off of expenses incurred
by respondent in its take-over of petitioners work.
After trial on the merits, the RTC14 ruled that the take-over of
some work items by respondent was not equivalent to a We side with respondent. Essentially, the dispute arose from
termination, but a mere modification, of the Subcontract. The the parties ncongruent positions on whether certain provisions
latter was ordered to give full payment for the work completed of their Agreement could be applied to the facts. The instant
by petitioner. case involves technical discrepancies that are better left to an
arbitral body that has expertise in those areas. In any event, the
Ruling of the Court of Appeals inclusion of an arbitration clause in a contract does not ipso
facto divest the courts of jurisdiction to pass upon the findings
of arbitral bodies, because the awards are still judicially
On appeal, the CA reversed the RTC and ordered the referral
reviewable under certain conditions.18
of the case to arbitration. The appellate court held as arbitrable
the issue of whether respondents take-over of some work
items had been intended to be a termination of the original In the case before us, the Subcontract has the following arbitral
contract under Letter "K" of the Subcontract. It ruled likewise on clause:
two other issues: whether petitioner was liable under the
warranty clause of the Agreement, and whether it should "6. The Parties hereto agree that any dispute or conflict as
reimburse respondent for the work the latter had taken over.15 regards to interpretation and implementation of this Agreement
which cannot be settled between [respondent] and [petitioner]
Hence, this Petition.16 amicably shall be settled by means of arbitration x x x."19

The Issues Clearly, the resolution of the dispute between the parties herein
requires a referral to the provisions of their Agreement. Within
the scope of the arbitration clause are discrepancies as to the
In its Memorandum, petitioner raises the following issues for the
amount of advances and billable accomplishments, the
Courts consideration:
application of the provision on termination, and the consequent
set-off of expenses.
"A
A review of the factual allegations of the parties reveals that
Whether or not there exist[s] a controversy/dispute between they differ on the following questions: (1) Did a take-
petitioner and respondent regarding the interpretation and over/termination occur? (2) May the expenses incurred by
implementation of the Sub-Contract Agreement dated February respondent in the take-over be set off against the amounts it
22, 1983 that requires prior recourse to voluntary arbitration; owed petitioner? (3) How much were the advances and billable
accomplishments?
"B
The resolution of the foregoing issues lies in the interpretation
In the affirmative, whether or not the requirements provided in of the provisions of the Agreement. According to respondent,
Article III 1 of CIAC Arbitration Rules regarding request for the take-over was caused by petitioners delay in completing
arbitration ha[ve] been complied with[.]"17 the work. Such delay was in violation of the provision in the
Agreement as to time schedule:
The Courts Ruling
"G. TIME SCHEDULE
The Petition is unmeritorious.
"[Petitioner] shall adhere strictly to the schedule related to the
First Issue: WORK and complete the WORK within the period set forth in
ADR || First Batch 22

Annex C hereof. NO time extension shall be granted by from the progress payments and/or retained amount. Any
[respondent] to [petitioner] unless a corresponding time excess from the retained amount after deducting [respondents]
extension is granted by [the Ministry of Public Works and claims shall be released by [respondent] to [petitioner] after the
Highways] to the CONSORTIUM."20 issuance of [the Ministry of Public Works and Highways] of the
Certificate of Completion and final acceptance of the WORK by
Because of the delay, respondent alleges that it took over some [the Ministry of Public Works and Highways].
of the work contracted to petitioner, pursuant to the following
provision in the Agreement: xxx xxx xxx

"K. TERMINATION OF AGREEMENT "D. IMPORTED MATERIALS AND EQUIPMENT

"[Respondent] has the right to terminate and/or take over this "[Respondent shall open the letters of credit for the importation
Agreement for any of the following causes: of equipment and materials listed in Annex E hereof after the
drawings, brochures, and other technical data of each items in
xxx xxx xxx the list have been formally approved by [the Ministry of Public
Works and Highways]. However, petitioner will still be fully
responsible for all imported materials and equipment.
6. If despite previous warnings by [respondent], [petitioner]
does not execute the WORK in accordance with this
Agreement, or persistently or flagrantly neglects to carry out "All expenses incurred by [respondent], both in foreign and
[its] obligations under this Agreement."21 local currencies in connection with the opening of the letters of
credit shall be deducted from the Contract Prices.
Supposedly, as a result of the "take-over," respondent incurred
expenses in excess of the contracted price. It sought to set off xxx xxx xxx
those expenses against the amount claimed by petitioner for
the work the latter accomplished, pursuant to the following "N. OTHER CONDITIONS
provision:
xxx xxx xxx
"If the total direct and indirect cost of completing the remaining
part of the WORK exceed the sum which would have been "2. All customs duties, import duties, contractors taxes, income
payable to [petitioner] had it completed the WORK, the amount taxes, and other taxes that may be required by any government
of such excess [may be] claimed by [respondent] from either of agencies in connection with this Agreement shall be for the sole
the following: account of [petitioner]."23

1. Any amount due [petitioner] from [respondent] at the time of Being an inexpensive, speedy and amicable method of settling
the termination of this Agreement."22 disputes,24 arbitration -- along with mediation, conciliation and
negotiation -- is encouraged by the Supreme Court. Aside from
The issue as to the correct amount of petitioners advances and unclogging judicial dockets, arbitration also hastens the
billable accomplishments involves an evaluation of the manner resolution of disputes, especially of the commercial kind.25 It is
in which the parties completed the work, the extent to which thus regarded as the "wave of the future" in international civil
they did it, and the expenses each of them incurred in and commercial disputes.26 Brushing aside a contractual
connection therewith. Arbitrators also need to look into the agreement calling for arbitration between the parties would be a
computation of foreign and local costs of materials, foreign and step backward.27
local advances, retention fees and letters of credit, and taxes
and duties as set forth in the Agreement. These data can be Consistent with the above-mentioned policy of encouraging
gathered from a review of the Agreement, pertinent portions of alternative dispute resolution methods, courts should liberally
which are reproduced hereunder: construe arbitration clauses. Provided such clause is
susceptible of an interpretation that covers the asserted
"C. CONTRACT PRICE AND TERMS OF PAYMENT dispute, an order to arbitrate should be granted.28 Any doubt
should be resolved in favor of arbitration.29
xxx xxx xxx
Second Issue:
"All progress payments to be made by [respondent] to
[petitioner] shall be subject to a retention sum of ten percent Prior Request for Arbitration
(10%) of the value of the approved quantities. Any claims by
[respondent] on [petitioner] may be deducted by [respondent] According to petitioner, assuming arguendo that the dispute is
ADR || First Batch 23

arbitrable, the failure to file a formal request for arbitration with acquire jurisdiction over the same. Rather, it is plain and clear
the Construction Industry Arbitration Commission (CIAC) that as long as the parties agree to submit to voluntary
precluded the latter from acquiring jurisdiction over the arbitration, regardless of what forum they may choose, their
question. To bolster its position, petitioner even cites our ruling agreement will fall within the jurisdiction of the CIAC, such that,
in Tesco Services Incorporated v. Vera.30 We are not even if they specifically choose another forum, the parties will
persuaded. not be precluded from electing to submit their dispute before
the CIAC because this right has been vested upon each party
Section 1 of Article II of the old Rules of Procedure Governing by law, i.e., E.O. No. 1008."34
Construction Arbitration indeed required the submission of a
request for arbitration, as follows: Clearly, there is no more need to file a request with the CIAC in
order to vest it with jurisdiction to decide a construction dispute.
"SECTION. 1. Submission to Arbitration -- Any party to a
construction contract wishing to have recourse to arbitration by The arbitral clause in the Agreement is a commitment on the
the Construction Industry Arbitration Commission (CIAC) shall part of the parties to submit to arbitration the disputes covered
submit its Request for Arbitration in sufficient copies to the therein. Because that clause is binding, they are expected to
Secretariat of the CIAC; PROVIDED, that in the case of abide by it in good faith.35 And because it covers the dispute
government construction contracts, all administrative remedies between the parties in the present case, either of them may
available to the parties must have been exhausted within 90 compel the other to arbitrate.36
days from the time the dispute arose."
Since petitioner has already filed a Complaint with the RTC
Tesco was promulgated by this Court, using the foregoing without prior recourse to arbitration, the proper procedure to
provision as reference. enable the CIAC to decide on the dispute is to request the stay
or suspension of such action, as provided under RA 876 [the
On the other hand, Section 1 of Article III of the new Rules of Arbitration Law].37
Procedure Governing Construction Arbitration has dispensed
with this requirement and recourse to the CIAC may now be WHEREFORE, the Petition is DENIED and the assailed
availed of whenever a contract "contains a clause for the Decision AFFIRMED. Costs against petitioner.
submission of a future controversy to arbitration," in this wise:
SO ORDERED.
"SECTION 1. Submission to CIAC Jurisdiction An arbitration
clause in a construction contract or a submission to arbitration Puno, (Chairman), Sandoval-Gutierrez, Corona and Carpio-
of a construction dispute shall be deemed an agreement to Morales, JJ., concur.
submit an existing or future controversy to CIAC jurisdiction,
notwithstanding the reference to a different arbitration institution
or arbitral body in such contract or submission. When a contract
contains a clause for the submission of a future controversy to
arbitration, it is not necessary for the parties to enter into a Footnotes
submission agreement before the claimant may invoke the
jurisdiction of CIAC." 1 See Panganiban, A Centenary of Justice, 2001 ed., p. 83.

The foregoing amendments in the Rules were formalized by 2 Rollo, pp. 7-17.
CIAC Resolution Nos. 2-91 and 3-93.31
3 Seventh Division. Written by Justice Portia Alio-
The difference in the two provisions was clearly explained in Hormachuelos and concurred in by Justices Corona Ibay-
China Chang Jiang Energy Corporation (Philippines) v. Rosal Somera (Division chairman) and Wenceslao I. Agnir Jr.
Infrastructure Builders et al.32 (an extended unsigned (member).
Resolution) and reiterated in National Irrigation Administration
v. Court of Appeals,33 from which we quote thus: 4 Assailed CA Decision, pp. 21-22; rollo, pp. 40-41.

"Under the present Rules of Procedure, for a particular 5See Pay Item Nos. 7.01 to 7.26 of the Bill of Quantities;
construction contract to fall within the jurisdiction of CIAC, it is Records, pp. 16-25.
merely required that the parties agree to submit the same to
voluntary arbitration Unlike in the original version of Section 1, 6See Letters dated March 15, 1985 and April 25, 1985, pp. 63-
as applied in the Tesco case, the law as it now stands does not 64.
provide that the parties should agree to submit disputes arising
from their agreement specifically to the CIAC for the latter to 7 See Letter dated March 7, 1985, p. 62.
ADR || First Batch 24
8 See Letter dated September 30, 1986, p. 65. 29Moses H. Cone Hospital v. Mercury Construction Co., 460
US 1, February 23, 1983; Metro Industrial Painting Corp. v.
9 Records, pp. 68-69. Terminal Construction Co., 287 F2d 382 (US Court of Appeals,
2nd Circuit), February 16, 1961.
10 Id., pp. 1-3.
30 209 SCRA 440, May 29, 1992.
11 Id., pp. 32-34.
31These were promulgated by the CIAC on June 21, 1991 and
August 25, 1993, respectively.
12 Presided by Judge Phinney C. Araquil.
32 GR No. 125706, September 30, 1996.
13 Records, p. 41.
33 318 SCRA 255, November 17, 1999.
14Transferred to Makati, Branch 64. Presided by Judge Delia H.
Panganiban.
34 Id., p. 268, per Davide Jr., CJ.
15 Assailed CA Decision, pp. 20-21; rollo, pp. 39-40.
35Toyota Motor Philippines Corporation v. Court of Appeals,
216 SCRA 236, December 7, 1992.
16This case was deemed submitted for decision on October 25,
2001, upon this Courts receipt of respondents Memorandum
signed by Atty. Henry S. Rojas. Petitioners Memorandum, filed
36 See 6 of RA 876.
on October 10, 2001, was signed by Atty. Eleazar G. Ferry.
37 "SEC. 7. Stay of Civil Action. If any suit or proceeding be
17Petitioners Memorandum, p. 5; rollo, p. 223. Original in upper brought upon an issue arising out of an agreement providing for
case. the arbitration thereof, the court in which such suit or
proceeding is pending, upon being satisfied that the issue
involved in such suit or proceeding is referable to arbitration,
18 Bengson v. Chan, 78 SCRA 113, July 29, 1977.
shall stay the action or proceeding until an arbitration has been
had in accordance with the terms of the agreement: Provided,
19 Subcontract Agreement, p. 10; rollo, p. 52. Italics supplied. That the applicant for the stay is not in default in proceeding
with such arbitration."
20 Subcontract Agreement, p. 6; rollo, p. 47.

21 Id., pp. 7-8 & 48-49. Italics supplied.

22 Id., pp. 8 & 49.

23 Id., pp. 3-10 & 44-51.

24Del Monte Corporation-USA v. Court of Appeals, 351 SCRA


373, February 7, 2001; Eastboard Navigation, Ltd. v. Juan
Ysmael and Co., Inc., 102 Phil. 1, September 10, 1957.

25Home Bankers Savings and Trust Company v. Court of


Appeals, 318 SCRA 558, November 19, 1999.

26Heirs of Augusto L. Salas Jr. v. Laperal Realty Corporation,


320 SCRA 610, December 13, 1999; BF Corporation v. Court of
Appeals, 288 SCRA 267, March 27, 1998.

27 Ibid.

28Seaboard Coastline Railroad Co. v. National Rail Passenger


Corporation, 554 F2d 657 (US Court of Appeals, 5th Circuit),
June 22, 1977.
ADR || First Batch 25

Republic of the Philippines Benito Sy as Director thereof.8 Only respondent Nelson Tiu
SUPREME COURT affixed his signature on the letter to signify his agreement to the
Manila terms and conditions of the restructuring.9
SECOND DIVISION
On 20 July 2000 the RTC of Makati City, on its own initiative,
G.R. No. 152878 May 5, 2003 issued an Order dismissing without prejudice Civil Case No. 99-
518 for failure of petitioner as plaintiff therein to "prosecute its
RIZAL COMMERCIAL BANKING CORPORATION, petitioner, action for an unreasonable length of time . . .."10 On 31 July
2000 petitioner moved for reconsideration of the Order by
informing the trial court of respondents' unremitting desire to
vs.
settle the case amicably through a loan restructuring program.11
On 22 August 2000 petitioner notified the trial court of the
MAGWIN MARKETING CORPORATION, NELSON TIU, acquiescence thereto of respondent Nelson Tiu as an officer of
BENITO SY and ANDERSON UY, respondents. Magwin Marketing Corporation and defendant in the civil
case.12
BELLOSILLO, J.:
On 8 September 2000 the court a quo issued an Order
WE ARE PERTURBED that this case should drag this Court in reconsidering the dismissal without prejudice of Civil Case No.
the banal attempts to decipher the hazy and confused intent of 99-518 -
the trial court in proceeding with what would have been a
simple, straightforward and hardly arguable collection case. Acting on plaintiff's "Motion for Reconsideration" of the Order
Whether the dismissal without prejudice for failure to prosecute dated 20 July 2000 dismissing this case for failure to prosecute,
was unconditionally reconsidered, reversed and set aside to it appearing that there was already conformity to the
reinstate the civil case and have it ready for pre-trial are matters restructuring of defendants' indebtedness with plaintiff by
which should have been clarified and resolved in the first defendant Nelson Tiu, President of defendant corporation per
instance by the court a quo. Unfortunately, this feckless "Manifestation and Motion" filed by plaintiff on 22 August 2000,
imprecision of the trial court became the soup stock of the there being probability of settlement among the parties, as
parties and their lawyers to further delay the case below when prayed for, the Order dated 20 July 2000 is hereby set aside.
they could have otherwise put things in proper order efficiently
and effectively.
Plaintiff is directed to submit the compromise agreement within
15 days from receipt hereof. Failure on the part of plaintiff to
On 4 March 1999 petitioner Rizal Commercial Banking submit the said agreement shall cause the imposition of
Corporation (RCBC) filed a complaint for recovery of a sum of payment of the required docket fees for re-filing of this case.13
money with prayer for a writ of preliminary attachment against
respondents Magwin Marketing Corporation, Nelson Tiu, Benito
On 27 July 2000 petitioner filed in Civil Case No. 99-518 a
Sy and Anderson Uy.1 On 26 April 1999, the trial court issued a
Manifestation and Motion to Set Case for Pre-Trial Conference
writ of attachment.2 On 4 June 1999 the writ was returned
alleging that "[t]o date, only defendant Nelson Tiu had affixed
partially satisfied since only a parcel of land purportedly owned
his signature on the May 10, 2000 letter which informed the
by defendant Benito Sy was attached.3 In the meantime,
defendants that plaintiff [herein petitioner] already approved
summons was served on each of the defendants, respondents
defendant Magwin Marketing Corporations request for
herein, who filed their respective answers, except for defendant
restructuring of its loan obligations to plaintiff but subject to the
Gabriel Cheng who was dropped without prejudice as party-
terms and conditions specified in said letter."14 This motion was
defendant as his whereabouts could not be located.4 On 21
followed on 5 October 2000 by petitioner's Supplemental
September 1999 petitioner moved for an alias writ of
Motion to Plaintiffs Manifestation and Motion to Set Case for
attachment which on 18 January 2000 the court a quo denied.5
Pre-Trial Conference affirming that petitioner "could not submit
a compromise agreement because only defendant Nelson Tiu
Petitioner did not cause the case to be set for pre-trial.6 For had affixed his signature on the May 10, 2000 letter . . .."15
about six (6) months thereafter, discussions between petitioner Respondent Anderson Uy opposed the foregoing submissions
and respondents Magwin Marketing Corporation, Nelson Tiu, of petitioner while respondents Magwin Marketing Corporation,
Benito Sy and Anderson Uy, as parties in Civil Case No. 99- Nelson Tiu and Benito Sy neither contested nor supported
518, were undertaken to restructure the indebtedness of them.16
respondent Magwin Marketing Corporation.7 On 9 May 2000
petitioner approved a debt payment scheme for the corporation
The trial court, in an undated Order (although a date was later
which on 15 May 2000 was communicated to the latter by
inserted in the Order), denied petitioner's motion to calendar
means of a letter dated 10 May 2000 for the conformity of its
Civil Case No. 99-518 for pre-trial stating that -
officers, i.e., respondent Nelson Tiu as President/General
Manager of Magwin Marketing Corporation and respondent
ADR || First Batch 26

Acting on plaintiff's [herein petitioner] "Manifestation and Motion cannot coerce the parties in Civil Case No. 99-518 to execute a
to Set Case for Pre-Trial Conference," the "Opposition" filed by compromise agreement and penalize their failure to do so by
defendant Uy and the subsequent "Supplemental Motion" filed refusing to go forward with the pre-trial conference. To hold
by plaintiff; defendant Uy's "Opposition," and plaintiff's "Reply;" otherwise, so petitioner avers, would violate Art. 2029 of the
for failure of the plaintiff to submit a compromise agreement Civil Code which provides that "[t]he court shall endeavor to
pursuant to the Order dated 8 September 2000 plaintiff's motion persuade the litigants in a civil case to agree upon some fair
to set case for pre-trial conference is hereby denied.17 compromise," and this Court's ruling in Goldloop Properties,
Inc. v. Court of Appeals23 where it was held that the trial court
On 15 November 2000 petitioner filed its Notice of Appeal from cannot dismiss a complaint for failure of the parties to submit a
the 8 September 2000 Order of the trial court as well as its compromise agreement.
undated Order in Civil Case No. 99-518. On 16 November 2000
the trial court issued two (2) Orders, one of which inserted the On the other hand, respondent Anderson Uy filed his comment
date "6 November 2000" in the undated Order rejecting after several extensions asserting that there are no special and
petitioner's motion for pre-trial in the civil case, and the other important reasons for undertaking this review. He also alleges
denying due course to the Notice of Appeal on the ground that that petitioner's attack is limited to the Order dated 8
the "Orders dated 8 September 2000 and 6 November 2000 September 2000 as to whether it is conditional as the Court of
are interlocutory orders and therefore, no appeal may be taken Appeals so found and the applicability to this case of the ruling
. . .."18 in Goldloop Properties, Inc. v. Court of Appeals. Respondent
Uy claims that the Order reconsidering the dismissal of Civil
On 7 December 2000 petitioner elevated the Orders dated 8 Case No. 99-518 without prejudice is on its face contingent
September 2000, 6 November 2000 and 16 November 2000 of upon the submission of the compromise agreement which in
the trial court to the Court of Appeals in a petition for certiorari the first place was the principal reason of petitioner to justify the
under Rule 65 of the Rules of Civil Procedure.19 In the main, withdrawal of the Order declaring his failure to prosecute the
petitioner argued that the court a quo had no authority to civil case. He further contends that the trial court did not force
compel the parties in Civil Case No. 99-518 to enter into an the parties in the civil case to execute a compromise
amicable settlement nor to deny the holding of a pre-trial agreement, the truth being that it dismissed the complaint
conference on the ground that no compromise agreement was therein for petitioner's dereliction.
turned over to the court a quo.20
Finally, respondent Uy contests the relevance of Goldloop
On 28 September 2001 the appellate court promulgated its Properties, Inc. v. Court of Appeals, and refers to its
Decision dismissing the petition for lack of merit and affirming incongruence with the instant case, i.e., that the complaint of
the assailed Orders of the trial court21 holding that - petitioner was dismissed for failure to prosecute and not for its
reckless disregard to present an amicable settlement as was
the situation in Goldloop Properties, Inc., and that the dismissal
. . . although the language of the September 8, 2000 Order may
was without prejudice, in contrast with the dismissal with
not be clear, yet, a careful reading of the same would clearly
prejudice ordered in the cited case. For their part, respondents
show that the setting aside of the Order dated July 20, 2000
Magwin Marketing Corporation, Nelson Tiu and Benito Sy
which dismissed petitioner's complaint . . . for failure to
waived their right to file a comment on the instant petition and
prosecute its action for an unreasonable length of time is
submitted the same for resolution of this Court.24
dependent on the following conditions, to wit: a) The
submission of the compromise agreement by petitioner within
fifteen (15) days from notice; and b) Failure of petitioner to The petition of Rizal Commercial Banking Corporation is
submit the said compromise agreement shall cause the meritorious. It directs our attention to questions of substance
imposition of the payment of the required docket fees for the re- decided by the courts a quo plainly in a way not in accord with
filing of the case; so much so that the non-compliance by applicable precedents as well as the accepted and usual
petitioner of condition no. 1 would make condition no. 2 course of judicial proceedings; it offers special and important
effective, especially that petitioner's manifestation and motion reasons that demand the exercise of our power of supervision
to set case for pre-trial conference and supplemental motion . . and review. Furthermore, petitioner's objections to the
. [were] denied by the respondent judge in his Order dated proceedings below encompass not only the Order of 8
November 6, 2000, which in effect means that the Order dated September 2000 but include the cognate Orders of the trial
July 20, 2000 was ultimately not set aside considering that a court of 6 and 16 November 2000. This is evident from the
party need not pay docket fees for the re-filing of a case if the prayer of the instant petition which seeks to reverse and set
original case has been revived and reinstated.22 aside the Decision of the appellate court and to direct the trial
court to proceed with the pre-trial conference in Civil Case No.
99-518. Evidently, the substantive issue involved herein is
On 2 April 2002 reconsideration of the Decision was denied;
whether the proceedings in the civil case should progress, a
hence, this petition.
question which at bottom embroils all the Orders affirmed by
the Court of Appeals.
In the instant case, petitioner maintains that the trial court
ADR || First Batch 27

On the task at hand, we see no reason why RTC-Br. 135 of do we read that the reconsideration is subject to two (2)
Makati City should stop short of hearing the civil case on the qualifications. Certainly far from it, for in Goldloop Properties,
merits. There is no substantial policy worth pursuing by Inc. v. Court of Appeals28 a similar directive, i.e., "[t]he parties
requiring petitioner to pay again the docket fees when it has are given a period of fifteen (15) days from today within which
already discharged this obligation simultaneously with the filing to submit a Compromise Agreement," was held to mean that
of the complaint for collection of a sum of money. The "should the parties fail in their negotiations the proceedings
procedure for dismissed cases when re-filed is the same as would continue from where they left off." Goldloop Properties,
though it was initially lodged, i.e., the filing of answer, reply, Inc. further said that its order, or a specie of it, did not constitute
answer to counter-claim, including other foot-dragging an agreement or even an expectation of the parties that should
maneuvers, except for the rigmarole of raffling cases which is they fail to settle their differences within the stipulated number
dispensed with since the re-filed complaint is automatically of days their case would be dismissed.
assigned to the branch to which the original case pertained.25 A
complaint that is re-filed leads to the re-enactment of past The addition of the second sentence in the second paragraph
proceedings with the concomitant full attention of the same trial does not change the absolute nullification of the dismissal
court exercising an immaculate slew of jurisdiction and control without prejudice decreed in the first paragraph. The sentence
over the case that was previously dismissed,26 which in the "[f]ailure on the part of plaintiff to submit the said agreement
context of the instant case is a waste of judicial time, capital shall cause the imposition of payment of the required docket
and energy. fees for re-filing of this case" is not a directive to pay docket
fees but only a statement of the event that may result in its
What judicial benefit do we derive from starting the civil case all imposition. The reason for this is that the trial court could not
over again, especially where three (3) of the four (4) have possibly made such payment obligatory in the same civil
defendants, i.e., Magwin Marketing Corporation, Nelson Tiu case, i.e., Civil Case No. 99-518, since docket fees are
and Benito Sy, have not contested petitioner's plea before this defrayed only after the dismissal becomes final and executory
Court and the courts a quo to advance to pre-trial conference? and when the civil case is re-filed.
Indeed, to continue hereafter with the resolution of petitioner's
complaint without the usual procedure for the re-filing thereof, It must be emphasized however that once the dismissal attains
we will save the court a quo invaluable time and other the attribute of finality, the trial court cannot impose legal fees
resources far outweighing the docket fees that petitioner would anew because a final and executory dismissal although without
be forfeiting should we rule otherwise. prejudice divests the trial court of jurisdiction over the civil case
as well as any residual power to order anything relative to the
Going over the specifics of this petition and the arguments of dismissed case; it would have to wait until the complaint is
respondent Anderson Uy, we rule that the Order of 8 docketed once again.29 On the other hand, if we are to concede
September 2000 did not reserve conditions on the that the trial court retains jurisdiction over Civil Case No. 99-518
reconsideration and reversal of the Order dismissing without for it to issue the assailed Orders, a continuation of the hearing
prejudice Civil Case No. 99-518. This is quite evident from its thereon would not trigger a disbursement for docket fees on the
text which does not use words to signal an intent to impose part of petitioner as this would obviously imply the setting aside
riders on the dispositive portion - of the order of dismissal and the reinstatement of the complaint.

Acting on plaintiff's "Motion for Reconsideration" of the Order Indubitably, it is speculative to reckon the effectivity of the
dated 20 July 2000 dismissing this case for failure to prosecute, Order of dismissal without prejudice to the presentation of the
it appearing that there was already conformity to the compromise agreement. If we are to admit that the efficacy of
restructuring of defendants' indebtedness with plaintiff by the invalidation of the Order of dismissal is dependent upon this
defendant Nelson Tiu, President of defendant corporation per condition, then we must inquire: from what date do we count
"Manifestation and Motion" filed by plaintiff on 22 August 2000, the fifteen (15)-day reglementary period within which the
there being probability of settlement among the parties, as alleged revival of the order of dismissal began to run? Did it
prayed for, the Order dated 20 July 2000 is hereby set aside. commence from the lapse of the fifteen (15) days provided for
in the Order of 8 September 2000? Or do we count it from the 6
Plaintiff is directed to submit the compromise agreement within November 2000 Order when the trial court denied the holding of
15 days from receipt hereof. Failure on the part of plaintiff to a pre-trial conference? Or must it be upon petitioner's receipt of
submit the said agreement shall cause the imposition of the 16 November 2000 Order denying due course to its Notice
payment of the required docket fees for re-filing of this case.27 of Appeal? The court a quo could not have instituted an Order
that marked the proceedings before it with a shadow of
instability and chaos rather than a semblance of constancy and
Contrary to respondent Uy's asseverations, the impact of the
firmness.
second paragraph upon the first is simply to illustrate what the
trial court would do after setting aside the dismissal without
prejudice: submission of the compromise agreement for the The subsequent actions of the trial court also belie an intention
consideration of the trial court. Nothing in the second paragraph to revive the Order of dismissal without prejudice in the event
ADR || First Batch 28

that petitioner fails to submit a compromise agreement. The come to terms (a) If willingness to discuss a possible
Orders of 6 and 16 November 2000 plainly manifest that it was compromise is expressed by one or both parties; or (b) If it
retaining jurisdiction over the civil case, a fact which would not appears that one of the parties, before the commencement of
have been possible had the dismissal without prejudice been the action or proceeding, offered to discuss a possible
resuscitated. Surely, the court a quo could not have denied on compromise but the other party refused the offer, pursuant to
6 November 2000 petitioner's motion to calendar Civil Case No. Art. 2030 of the Civil Code. If despite efforts exerted by the trial
99-518 for pre-trial if the dismissal had been restored to life in court and the parties the negotiations still fail, only then should
the meantime. By then the dismissal without prejudice would the action continue as if no suspension had taken place.33
have already become final and executory so as to effectively
remove the civil case from the docket of the trial court. Ostensibly, while the rules allow the trial court to suspend its
proceedings consistent with the policy to encourage the use of
The same is true with the Order of 16 November 2000 denying alternative mechanisms of dispute resolution, in the instant
due course to petitioner's Notice of Appeal. There would have case, the trial court only gave the parties fifteen (15) days to
been no basis for such exercise of discretion because the conclude a deal. This was, to say the least, a passive and
jurisdiction of the court a quo over the civil case would have paltry attempt of the court a quo in its task of persuading
been discharged and terminated by the presumed dismissal litigants to agree upon a reasonable concession.34 Hence, if
thereof. Moreover, we note the ground for denying due course only to inspire confidence in the pursuit of a middle ground
to the appeal: the "Orders dated 8 September 2000 and 6 between petitioner and respondents, we must not interpret the
November 2000 are interlocutory orders and therefore, no trial court's Orders as dismissing the action on its own motion
appeal may be taken from . . .."30 This declaration strongly because the parties, specifically petitioner, were anxious to
suggests that something more was to be accomplished in the litigate their case as exhibited in their several manifestations
civil case, thus negating the claim that the Order of dismissal and motions.
without prejudice was resurrected upon the parties' failure to
yield a compromise agreement. A "final order" issued by a court We reject respondent Uy's contention that Goldloop Properties,
has been defined as one which disposes of the subject matter Inc. v. Court of Appeals is irrelevant to the case at bar on the
in its entirety or terminates a particular proceeding or action, dubious reasoning that the complaint of petitioner was
leaving nothing else to be done but to enforce by execution dismissed for failure to prosecute and not for the non-
what has been determined by the court, while an "interlocutory submission of a compromise agreement which was the bone of
order" is one which does not dispose of a case completely but contention in that case, and that the dismissal imposed in the
leaves something more to be decided upon.31 instant case was without prejudice, in contrast to the dismissal
with prejudice decreed in the cited case. To begin with, whether
Besides the semantic and consequential improbabilities of the dismissal is with or without prejudice if grievously erroneous
respondent Uy's argument, our ruling in Goldloop Properties, is detrimental to the cause of the affected party; Goldloop
Inc., is decisive of the instant case. In Goldloop Properties, Inc., Properties, Inc. does not tolerate a wrongful dismissal just
we reversed the action of the trial court in dismissing the because it was without prejudice. More importantly, the facts in
complaint for failure of the plaintiff to prosecute its case, which Goldloop Properties, Inc. involve, as in the instant case, a
was in turn based on its inability to forge a compromise with the dismissal for failure to prosecute on the ground of the parties'
other parties within fifteen (15) days from notice of the order to inability to come up with a compromise agreement within fifteen
do so and held - (15) days from notice of the court's order therein. All told, the
parallelism between them is unmistakable.
Since there is nothing in the Rules that imposes the sanction of
dismissal for failing to submit a compromise agreement, then it Even if we are to accept on face value respondent's
is obvious that the dismissal of the complaint on the basis understanding of Goldloop Properties, Inc. as solely about the
thereof amounts no less to a gross procedural infirmity failure to submit a compromise agreement, it is apparent that
assailable by certiorari. For such submission could at most be the present case confronts a similar problem. Perhaps initially
directory and could not result in throwing out the case for failure the issue was one of failure to prosecute, as can be observed
to effect a compromise. While a compromise is encouraged, from the Order dated 20 July 2000, although later reversed and
very strongly in fact, failure to consummate one does not set aside. But thereafter, in the Order of 6 November 2000, the
warrant any procedural sanction, much less an authority to trial court refused to proceed to pre-trial owing to the "failure of
jettison a civil complaint worth P4,000,000.00 . . . Plainly, the plaintiff to submit a compromise agreement pursuant to the
submission of a compromise agreement is never mandatory, Order dated 8 September 2000." When the civil case was
nor is it required by any rule.32 stalled on account of the trial court's refusal to call the parties to
a pre-trial conference, the reason or basis therefor was the
As also explained therein, the proper course of action that absence of a negotiated settlement - a circumstance that takes
should have been taken by the court a quo, upon manifestation the case at bar within the plain ambit of Goldloop Properties,
of the parties of their willingness to discuss a settlement, was to Inc. In any event, given that the instant case merely revolves
suspend the proceedings and allow them reasonable time to around the search for a reasonable interpretation of the several
ADR || First Batch 29

Orders of the trial court, i.e., as to whether the dismissal without complaint regardless of its characterization as being without
prejudice was revived upon petitioner's helplessness to perfect prejudice.
an out-of-court arrangement, with more reason must we employ
the ruling in Goldloop Properties, Inc. to resolve the parties' In fine, petitioner cannot be said to have lost interest in fighting
differences of opinion. the civil case to the end. A court may dismiss a case on the
ground of non prosequitur but the real test of the judicious
We also find nothing in the record to support respondent Uy's exercise of such power is whether under the circumstances
conclusion that petitioner has been mercilessly delaying the plaintiff is chargeable with want of fitting assiduousness in not
prosecution of Civil Case No. 99-518 to warrant its dismissal. A acting on his complaint with reasonable promptitude. Unless a
complaint may be dismissed due to plaintiff's fault: (a) if he fails party's conduct is so indifferent, irresponsible, contumacious or
to appear during a scheduled trial, especially on the date for the slothful as to provide substantial grounds for dismissal, i.e.,
presentation of his evidence in chief, or when so required at the equivalent to default or non-appearance in the case, the courts
pre-trial; (b) if he neglects to prosecute his action for an should consider lesser sanctions which would still amount to
unreasonable length of time; or (c) if he does not comply with achieving the desired end.38 In the absence of a pattern or
the rules or any order of the court. None of these was obtaining scheme to delay the disposition of the case or of a wanton
in the civil case. failure to observe the mandatory requirement of the rules on the
part of the plaintiff, as in the case at bar, courts should decide
While there was a lull of about six (6) months in the prosecution to dispense rather than wield their authority to dismiss.39
of Civil Case No. 99-518, it must be remembered that
respondents themselves contributed largely to this delay. They Clearly, another creative remedy was available to the court a
repeatedly asked petitioner to consider re-structuring the debt quo to attain a speedy disposition of Civil Case No. 99-518
of respondent Magwin Marketing Corporation to which without sacrificing the course of justice. Since the failure of
petitioner graciously acceded. Petitioner approved a new debt petitioner to submit a compromise agreement was the refusal of
payment scheme that was sought by respondents, which it then just one of herein respondents, i.e., Benito Sy, to sign his name
communicated to respondent Corporation through a letter for on the conforme of the loan restructure documents, and the
the conformity of the latter's officers, i.e., respondent Nelson common concern of the courts a quo was dispatch in the
Tiu as President/General Manager and respondent Benito Sy proceedings, the holding of a pre-trial conference was the best-
as Director thereof. Regrettably, only respondent Nelson Tiu suited solution to the problem as this stage in a civil action is
affixed his signature on the letter to signify his concurrence with where issues are simplified and the dispute quickly and
the terms and conditions of the arrangement. The momentary genuinely reconciled. By means of pre-trial, the trial court is
lag in the civil case was aggravated when respondent Benito Sy fully empowered to sway the litigants to agree upon some fair
for unknown and unexplained reasons paid no heed to the compromise.
adjustments in the indebtedness although curiously he has not
opposed before this Court or the courts a quo petitioner's desire Dismissing the civil case and compelling petitioner to re-file its
to go ahead with the pre-trial conference. complaint is a dangerous, costly and circuitous route that may
end up aggravating, not resolving, the disagreement. This case
Admittedly, delay took place in this case but it was not an management strategy is frighteningly deceptive because it does
interruption that should have entailed the dismissal of the so at the expense of petitioner whose cause of action, perhaps,
complaint even if such was designated as without prejudice. To may have already been admitted by its adverse parties as
constitute a sufficient ground for dismissal, the inattention of shown by three (3) of four (4) defendants not willing to contest
plaintiff to pursue his cause must not only be prolonged but petitioner's allegations, and more critically, since this approach
also be unnecessary and dilatory resulting in the trifling of promotes the useless and thankless duplication of hard work
judicial processes. In the instant case, the adjournment was not already undertaken by the trial court. As we have aptly
only fleeting as it lasted less than six (6) months but was also observed, "[i]nconsiderate dismissals, even if without prejudice,
done in good faith to accommodate respondents' incessant do not constitute a panacea nor a solution to the congestion of
pleas to negotiate. Although the dismissal of a case for failure court dockets. While they lend a deceptive aura of efficiency to
to prosecute is a matter addressed to the sound discretion of records of individual judges, they merely postpone the ultimate
the court, that judgment however must not be abused. The reckoning between the parties. In the absence of clear lack of
availability of this recourse must be determined according to the merit or intention to delay, justice is better served by a brief
procedural history of each case, the situation at the time of the continuance, trial on the merits, and final disposition of the
dismissal, and the diligence of plaintiff to proceed therein.35 cases before the court."40
Stress must also be laid upon the official directive that courts
must endeavor to convince parties in a civil case to WHEREFORE, the Petition for Review is GRANTED. The
consummate a fair settlement36 and to mitigate damages to be Decision dated 28 September 2001 and Resolution dated 2
paid by the losing party who has shown a sincere desire for April 2002 of the Court of Appeals in CA-G.R. SP No. 62102
such give-and-take.37 All things considered, we see no are REVERSED and SET ASIDE.
compelling circumstances to uphold the dismissal of petitioner's
ADR || First Batch 30

The Orders dated 8 September 2000, 6 November 2000 and 16 13 Order issued by Judge Francisco B. Ibay; CA Record, p. 24.
November 2000 of the Regional Trial Court, Branch 135, of
Makati City, docketed as Civil Case No. 99-518, are also 14 Rollo, p. 8.
REVERSED and SET ASIDE insofar as these Orders are
interpreted to impose upon and collect anew from petitioner 15 Ibid.
RIZAL COMMERCIAL BANKING CORPORATION docket or
legal fees for its complaint, or to dismiss without prejudice Civil
Case No. 99-518, or to preclude the trial court from calling the
16 Id. at 9.
parties therein to pre-trial conference, or from proceeding
thereafter with dispatch to resolve the civil case. 17 Order issued by Judge Francisco B. Ibay, CA Record, p. 25.

Civil Case No. 99-518 is deemed REINSTATED in, as it was 18 CA Record, pp. 32-33.
never taken out from, the dockets of the Regional Trial Court,
Branch 135, of Makati City. The trial court is ORDERED to 19Docketed as CA-G.R. SP No. 62102, Rizal Commercial
exercise its jurisdiction over Civil Case No. 99-518, to Banking Corporation v. Hon. Judge Francisco B. Ibay, et al.
CONDUCT the pre-trial conference therein with dispatch, and
to UNDERTAKE thereafter such other proceedings as may be 20 Id. at 11-13.
relevant, without petitioner being charged anew docket or other
legal fees in connection with its reinstatement. Costs against 21Decision penned by Associate Justice Mercedes Gozo-
respondents.
Dadole and concurred in by then Presiding Justice (now
Associate Justice of this Court) Ma. Alicia Austria-Martinez and
SO ORDERED. Associate Justice Jose L. Sabio Jr.; Rollo, pp. 26-35.

Quisumbing, Austria-Martinez and Callejo, Sr., JJ ., concur. 22 Id. at 34.

23 G.R. No. 99431, 11 August 1992, 212 SCRA 498.

Footnotes 24 Resolution dated 18 September 2002; Rollo, p. 43.


1 Docketed as Civil Case No. 99-518, Rizal Commercial 25 The 2002 Revised Manual for Clerks of Courts, Vol. I, p. 223.
Banking Corporation v. Magwin Marketing Corporation, et al.,
which was raffled to RTC-Br. 135, Makati City; Rollo, p. 4.
Baares II v. Balising, G.R. No. 132624, 13 March 2000, 328
26

SCRA 36.
2 CA Record, p. 234.
27 Issued by Judge Francisco B. Ibay; CA Record, p. 24.
3 Id. at 237.
28 See Note 22 at 506.
4 Id. at 7.
29Ortigas & Company Limited Partnership v. Velasco, G.R. No.
5 Id. at 237. 109645, 25 July 1994, 234 SCRA 455; Aquizap v. Basilio, No.
L-21293, 29 December 1967, 21 SCRA 1434.
6 Id. at 234.
30 CA Record, pp. 32-33.
7 Rollo, p. 6; CA Record, p. 136.
31 See Note 26.
8 Id. at 6; id. at 42-43.
32 See Note 22 at 506.
9 Rollo, p. 7.
33 Ibid.
10 Ibid.
34Civil Code, art. 2029; see SC Adm. Order No. 21-01; see also
11 CA Record, p. 242. A.M. No. 99-6-01-SC.

12 Rollo, p. 7. 35 Calalang v. Court of Appeals, G.R. No. 103185, 22 January


ADR || First Batch 31

1993, 217 SCRA 462. Republic of the Philippines


SUPREME COURT
36 See Note 34. Manila
FIRST DIVISION
37 Civil Code, art. 2031.
G.R. No. 141897 September 24, 2001
38Bank of the Philippine Islands v. Court of Appeals, G.R. No.
117385, 11 February 1999, 303 SCRA 19. METRO CONSTRUCTION, INC., petitioner,

39 Ibid. vs.

40 Macasa v. Herrera, 101 Phil. 44, 48 (1957). CHATHAM PROPERTIES, INC., respondent.

DAVIDE, JR., C.J.:

The core issue in this case is whether under existing law and
rules the Court of Appeals can also review findings of facts of
the Construction Industry Arbitration Commission (CIAC).

Respondent Chatham Properties, Inc. (CHATHAM) and


petitioner Metro Construction, Inc. (MCI) entered into a contract
for the construction of a multi-storey building known as the
Chatham House located at the corner of Herrera and Valero
Streets, Salcedo Village, Makati City, Metro Manila. In April
1998, MCI sought to collect from CHATHAM a sum of money
for unpaid progress billings and other charges and instituted a
request for adjudication of its claims with the CIAC. The case
was docketed as CIAC Case No. 10-98. The arbitral tribunal
was composed of Joven B. Joaquin as Chairman, and Beda G.
Fajardo and Loreto C. Aquino as members.

The preliminary conference before the CIAC started in June


1998 and was concluded a month after with the signing of the
Terms of Reference (TOR) of the Case.1 The hearings
immediately started with the presentation of MCI's witnesses,
namely: Ms. Ma. Suzette S. Nucum, Chief Accountant; Ms.
Isabela Redito, Office Engineer; Mr. John Romulo, Field
Manager; and Dr. John Y. Lai, President. CHATHAM's
witnesses were: Engr. Ruperto Kapunan III, Managing Director
of RK Development and Construction Co., Inc. (RKDCCI),
which was the Construction Manager firm hired by CHATHAM
to oversee the construction work of the Chatham House; Engr.
Alex Bautista, Area Manager of RKDCCI; Mr. Avelino M.
Mercado, CHATHAM's Project Manager; and Engr. Jose T.
Infante.

In the meantime, the TOR was amended and finalized on 19


August 1998.2

The facts, as admitted by the parties before the CIAC and


incorporated in the original TOR, are as follows:

1. On 21 April 1994, the parties formally entered into a . . .


contract for the construction of the "Chatham House" . . . for the
contract price of price of P50,000,000.00 inclusive of value-
ADR || First Batch 32

added tax, subject to adjustments in accordance with Article 9 by CHATHAM in MCI's progress billing reasonable?
of the contract. Construction of the project, however,
commenced on 15 April 1994 upon the release by CHATHAM 7. Is MCI's claim of P1,646,502.00 for labor escalation valid?
of the down payment
8. Is MCI entitled to payment of attendance fee? To what extent
2. On 12 July 1994, a Supplemental Contract was executed by and how much?
and between the parties whereby CHATHAM authorized MCI to
procure in behalf of the former materials, equipment, tools,
9. Did MCI fail to complete and/or deliver the project within the
fixtures, refurbishing, furniture, and accessories necessary for
approved completion period? If so, is MCI liable for liquidated
the completion of the project.
damages and how much?

3. Under Section I.04 of the Supplemental Contract, the total


10. Whether or not CHATHAM is entitled to claim x x x actual
amount of procurement and transportation cost[s] and
damages? If so, to what extent and how much?
expenses which may be reimbursed by MCI from CHATHAM
shall not exceed the amount of P75, 000,000.00.
11. Whether or not CHATHAM is entitled to x x x additional
counterclaims as follows:
4. In the course of the construction, Change Orders No. 1, 4,
8A, 11, 12 and 13 were implemented, payment of which were
recommended by x x x RKDCCI and approved by one of 11.1. Core testing expenses and penalty for concrete strength
CHATHAM's Project Managers, Romulo F. Sugay. failure P3,630,587.38.

5. On 15 September 1995, CHATHAM through its Project 11.2. Expenses to rectify structural steel works for the
Manager, Romulo F. Sugay, agreed to give P20,000 per floor foundation P1,331,139.74.
for five (5) floors, or a total of P100,000.00 as bonus/incentive
pay to MCI's construction workers for the completion of each 11.3. Cost of additional materials (concrete & rebars) supplied
floor on schedule. CHATHAM reimbursed MCI the amount of by CPI P5,761,457.91.
P60,000.00 corresponding to bonuses advanced to its workers
by the latter for the 14th, 16th, and 17th floors. 12. Are the parties entitled to their respective claims for
attorney's fees and cost of litigation? If so, how much?3
6. CHATHAM's payments to MCI totaled P104,875,792.37,
representing payments for portions of MCI's progress billings In the resolution of these issues, the CIAC discovered
and x x x additional charges. significant data, which were not evident or explicit in the
documents and records but otherwise revealed or elicited
The parties then stipulated on the following issues, again, as during the hearings, which the CIAC deemed material and
set forth in the TOR: relevant to the complete adjudication of the case. In its decision
of 19 October 1998, 4 the CIAC made the following findings
1. Is MCI entitled to its claims for unpaid progress billings and conclusions:
amounting to P21,062,339.76?
It was established during the hearing that the contract was
2. Were the approved Change Orders 1, 4, 8a, 11, 12 and 13 awarded to MCI through negotiation as no bidding was
fully paid by CHATHAM? If not, is MCI entitled to its claim for conducted, x x x It was also revealed that two agreements were
the unpaid balance? entered into, one is labeled Construction Contract for the total
fixed amount of P50,000,000.00 and the other a Supplemental
Contract for an amount not to exceed P75,000,000.00. The
3. Is CHATHAM liable for Change Orders 7a, 7b, 10, 14, 15,
latter is supposed to cover the procurement of materials for the
16, 17, 19 and 20?
project. The Construction Contract provides for monthly
progress billings and payments based on actual
4. Were the CHB works from the 8th to the 31st floors part of accomplishments of the various phases of work. The
the original contract or in the nature of extra/additional works? Supplemental Contract provides for; reimbursement of [the]
Is CHATHAM liable for the same? If so, how much? total amount of procurement and transportation costs and
expenses, upon MCI's presentation of suppliers'
5. Is MCI entitled to an additional reimbursement of P40,000.00 invoices/receipts.
for bonuses granted to workers as an incentive for the early
completion of each floor? However, from testimonies of witnesses from both parties, it
was revealed that the two distinct manner(s) of payment to MCI
6. Were the deductions in the amount of P1,393,458.84 made was set aside. The earlier attempt by CHATHAM to prove that
ADR || First Batch 33

MCI was remiss in submitting suppliers' invoices and/or cited "special relations" between the owner of MCI (Dr. John
receipts in support of its billings against the Supplemental Lai) and the president of CHATHAM (Mr. Lamberto Ocampo)
Contract was in fact later on abandoned when CHATHAM's as the reason.
witness Mercado admitted that the matter of adherence to the
payment provision of the Supplemental Contract is a 'non- On the other hand, Dr. Lai contends that, as explained in his
issue.' This was borne out by the fact that progress billings and letter to CHATHAM dated 17 February 1995, (Exh. 4-A) MCI's
payments under both contracts were made on the basis of work was on schedule. During the hearings, Dr. Lai also
percentage of project completion. insisted that beginning 15 February 1995, MCI was relieved of
full control of the construction operations, that it was relegated
Both documentary and testimonial evidence prove that, to (be) a mere supplier of labor, materials and equipment, and
effectively, the construction contract and supplemental contract that the alleged interim takeover actually extended through the
is but one agreement for a lump sum contract amount of completion of the project. Dr. Lai cited CHATHAM's purchases
P125,000,000.00. of materials, fielding labor force and sub-contracting works
allegedly for the project without his knowledge and consent as
xxx xxx xxx proof that CHATHAM had taken full control of the project.

There was also the admitted fact that the contract was To the above allegation of MCI that CHATHAM went ahead and
negotiated and awarded in the absence of a complete procured materials, hired labor and entered into sub-contract
construction plan. In any case, in support of the total contract agreements with the intention of eventually charging the costs
amount of P125 million, is a Cost Breakdown (Exh. 17-L), thereof to MCI, witness Mercado countered, that CHATHAM
where the estimated quantities of owner furnished materials has the right to do this under the provisions of Article 27 of the
(OFM) are indicated. It is however, understood that these contract, dealing with 'Recision, Cancellation, Termination of
quantities are estimates, based on (an) incomplete set of Contract.'
construction plans. It is likewise understood that except for the
OFM, all the other costs in the Cost Breakdown form the basis By way of responding to the various counterclaims of
for the lump-sum agreement under the contract, subject to CHATHAM, MCI referred to a letter of the former addressed to
adjustment only if there are any significant changes in the MCI dated 18 January 1997 (Exhibit E-1) the first paragraph of
contract plans. which reads as follows:

RKDCCI in its letter to MCI dated 15 Feb. 1995 (Exh. 4), After evaluating all the documents issued and received from
informed MCI that it was confirming the agreement allegedly both Chatham Properties Inc. and Metro Construction, Inc., the
accepted by Dr. Lai that the Building Committee will take over Building Committee of Chatham Properties, Inc. evaluated
the management of the construction operations (of the project) them. The Building Committee finds the total receivable of
albeit under certain conditions. Specifically, the take over was Metro Construction is in the amount of EIGHT MILLION PESOS
for an interim period and will extend only after concreting of up (P8,000,000.00) only.
to basement level 5 or up to 30 May 1995 whichever is later.
The letter also stated that the Building Committee . . . will be When queried by the Tribunal if the said amount already took
responsible for management and direction including into account the costs and expenses, (Chatham) claims to have
management of MCI engineers at the site, sequencing of work, incurred for the account of MCI, Mr. Mercado answered in the
additional labor, additional equipment and management of the affirmative. When queried further how the amount was arrived
yard and staging area. The letter, however, emphasized that at, Mr. Mercado replied that it was the sum the Building
the intent is not a take over of the contract or take over of the Committee figured it was willing to pay MCI simply to close the
entire work and in fact, it was mentioned that MCI will still be issue.
responsible for earth anchoring and steel fabrication work.
Mr. Mercado even added that while MCI is not actually entitled
CHATHAM claims that the interim take-over was necessitated to this amount, it was out of a friendship" that CHATHAM
by MCI's delay in the progress of its work, due allegedly to offered this sum to MCI as final settlement under the contract.
MCI's lack of manpower and equipment. During the hearings of
this case, this claim of MCI's lack of manpower, necessary
It is with the above attendant circumstances that this Tribunal
equipment, qualified engineers and inefficient construction
will be guided in the resolution of issues brought before it for
management was testified to by both Mr. Mercado [of
adjudication. From what this Tribunal finds as peculiar
CHATHAM] and Engr. Kapunan of RKDCCI. CHATHAM's
circumstances surrounding the contracting and implementation
witnesses, however, testified that in spite of these alleged
of the CHATHAM House Project. it arrived at the following
deficiencies, MCI was nevertheless allowed to continue to take
fundamental conclusions:
full control of the operations. When asked why termination of
the contract was not resorted to if truly, MCI was not performing
its contracted obligations, witnesses Mercado and Kapunan 1. That indeed 'special friendly relations' were present between
ADR || First Batch 34

the parties in this case, although decisions by either party on MCI was in January 1996 representing payment of Progress
any particular issue were made not purely on the basis of such Billing No. 19 for the period ending 31 December 1995. The
special relations. For example, this Tribunal believes that, percentage of completion claimed then by MCI was 80.02%,
contrary to the allegation of (CHATHAM's) witnesses, the the amount evaluated and eventually paid to MCI was the
decision not to terminate the contract was not due to the equivalent of 77.15% work accomplishment. No further
admitted 'special relations' only, but also due to the greater progress payments were made thereafter, other than for
problems the project would be faced with by terminating the advances to cover MCI payrolls from April 1996 to March 1997
MCI contract and mobilizing another contractor. in the amount of P8,196,755.51 and for various advances and
payments of approved change orders in the amount of
2. That while there was no official termination of the contract, P5,474,419.67.
the manner by which CHATHAM had taken upon themselves
the procurement of materials, the fielding of labor, the control In the meantime, up to Billing No. 23 for the period ending 30
over MCI's engineers, and the subcontracting of various phases April 1996, MCI billed CHATHAM a total accomplishment of
of work on its own, is considered by this Tribunal as implied 95.29%. This billing was however, evaluated by CHATHAM,
termination of the contract. The idea of allowing MCI to remain and in its letter to MCI dated 27 May 1996 (Exhibit E) it
on the project in spite of what CHATHAM claims. (to be) MCI's confirmed that MCI's remaining balance of work stands at
shortcomings, and MCI's agreement to stay on the project P7,374,201.15 as of 23 May 1996. This amount, percentage-
under conditions set by CHATHAM, is believed a matter of wise, equals roughly 5.88% of the contract amount as testified
mutual benefit to both parties. to by Engr. Jose Infante. (Exhibit 22-B). Therefore, what was
computed as MCI's work accomplishment as of 23 May 1996
3. That CHATHAM's invoking its rights under the provisions of was 94.12% and it is this evaluation which this Tribunal
Article 27 of the construction contract is believed out of place, believes MCI is entitled to as of said date.
as it failed to observe the required antecedent acts before it can
exercise its prerogative under the said contract provision. Applying this percentage of completion of 94.12% to the
P125,000,000.00 contract amount gives a total accomplishment
4. That there is no reason to believe, either party was in any equivalent to P117,650,000.00 as of 23 May 1996. Add to this
way guilty of bad faith in acting as it did on certain relevant amount the sum of P5,353,091.08 representing the total of
matters. However, this Tribunal is of the belief that due perhaps approved Change Orders as of 31 December 1995 gives a total
to the eagerness on the part particularly of CHATHAM's MCI accomplishment of P123,003,091.08, as CHATHAM saw
representatives to take such steps it considered necessary to it. Of this amount, CHATHAM admitted having paid MCI the
insure completion of the project within the period desired by total sum of P104,752,358.42 only (Exhibit 7) up to March 15,
CHATHAM, it deviated from some generally accepted 1997, leaving a balance of P18,250,732.66. It should be noted
procedures in the construction industry in dealing with MCI. that of the total payment of P104,752,358.42, the sum of
One example was not giving MCI the opportunity to rectify P5,750,000.00 was paid after May 1996 so that as of 25 May
some of what CHATHAM considered as construction 1996, CHATHAM's total payment to MCI was P99,002,358.42.
deficiencies and instead engaging the services of other parties
to undertake the corrective works and later on charging the Effectively, therefore, the amount due MCI as of 23 May 1996
costs thereof to MCI. amounted to P24,005,732.66 computed as follows:

In addition to the above conclusions resulting from what this Total accomplishment as of 23 May 1996 at 94.12%
Tribunal considered peculiar of circumstances surrounding the Add approved change orders
implementation of the project that were revealed during the Total
proceedings of this case, this Tribunal finds the necessity of Less payments up to 23 May 1996
establishing a cut-off date with regard to the fiscal liability of Balance due MCI as of 23 May 1996
one party towards the other. Of the above balance of P24,005,732.66 as of 23 May 1996,
the only payments made by CHATHAM to MCI is the sum of
Mr. Avelino Mercado of CHATHAM presented a list of what he P5,750,000.00 from June 1996 onwards, allegedly to cover MCI
claims as its Payments to MCI (Exhibit 7) summarized as payrolls. It is of course noted that CHATHAM's suspension of
follows: further payments to MCI was because it had been undertaking
on its own, the further procurement of materials and sub-
contracting of various phases of works on the project.
a. Down payment (Paid in two equal trances P 20,000,000.00
b. Cash Advance for Mobilization 800,000.00
c. Payments of Progress Billings up to Billing No. 19 In consideration of the above facts, this Tribunal's conclusion
71,081,183.44
d. Other Payments (Mar 1994 to Apr. 1996) that there5,474,419.67
was in fact an implied take over of the project is
e. Advances on MCI Payrolls (April 1996 to March 1997) further confirmed. Furthermore, this Tribunal additionally
8,196,755.51
Total concludesP that
104,752,358.42date for purposes of delineating the
the cut-off
The records of this case show that the last progress payment to financial obligations of the parties between them should be 23
ADR || First Batch 35

May 1996, the date when CHATHAM evaluated MCI's as follows:


accomplishment at 94.10% but nevertheless suspended all
further progress payments to MCI. 1/4 x 1/3[(1/10 x P125,000,000.00) 1%] x 294 =
P3,062,498.78.6
MCI presented further documentary evidence (Exhibit E-6) the
subject of which is a PUNCHLISTING-CIVIL STRUCTURAL." The CIAC then decreed:
In this particular document which bears the signatures of
representatives of both MCI and RKDCCI, MCI tried to prove
Accordingly, as presented below, all the amounts due MCI are
that as of 30 August 1996 it had actually attained 99.16% work
first listed and added up and the total payment is deducted
accomplishment. While it may be true that as of that date the
therefrom. The admitted total payment figure as reflected in the
project had reached 99.16% completion, there is no
Terms of Reference is the amount applied instead of the total
incontrovertible evidence showing that MCI was responsible for
reflected in CHATHAM's Summary of Payments which
such accomplishment. This was in fact actually testified to by
incidentally reflected a lesser amount. From the 'Balance Due
Engr. Alex Bautista of RKDCCI, when he said that it was an
MCI' the 'Amounts CPI is Held Entitled To' is deducted and the
evaluation of the project's completion stage, not necessarily
'Net Amount Due MCI' is arrived at.
MCI's work accomplishment. This Tribunal therefore stands firm
on its conclusion that MCI's accomplishment is only up to the
extent of 94.10%.5 A. AMOUNTS HELD CPI IS ENTITLED TO:
A.1. From the original contract: P
With those findings, the CIAC disposed of the specific money
claims by either granting or reducing them. On Issue No. 9, i.e., 94.12% of P125,000,000.00
whether CHATHAM failed to complete and/or deliver the project A.2. Approved Change Orders 5
within the approved completion period and, if so, whether A.3 Pending Change Orders 1
CHATHAM is liable for liquidated damages and how much, the A.4 CHB Works 1
CIAC ruled in this wise: A.5 Workers Bonus -
A.6 Disputed Deductions 9
A.7 Labor Escalation 1
This Tribunal holds that the provision of the contract insofar as
A.8 Attendance Fee 5
the Overall Schedule is concerned cannot justifiably be applied
Total P
in the instant case in view of the implied take-over of the
Less: Total payments - Item 11-6 of TOR 1
Chatham House project by CHATHAM. Accordingly, this
Balance Due MCI P
Tribunal finds no necessity to resolve whether or not MCI
B. AMOUNTS HELD CPI IS ENTITLED TO:
complete[d] and/or deliver[ed] the project within the approved
B.1. liquidated Damages P
completion period. In fact, Mr. Mercado testified that it was
B.2. Actual Damages 3
CHATHAM who ultimately completed the project, with
B.3. Penalties 1
assistance of the construction managers.
B.4. Cash Payments in Behalf of MCI 2
Total Amount Due CPI 7
In any case, this Tribunal finds merit in RKDCCI's claim that C. NET AMOUNT DUE MCI (A minus B) P
MCI was in delay in the concreting milestone and that [it] is WHEREFORE, judgment is hereby rendered in favor of the
liable for liquidated damages therefor. This, notwithstanding Claimant [MCI] directing Respondent [CHATHAM] to pay
MCI's invoking that Chatham is estopped from claiming Claimant [MCI] the net sum of SIXTEEN MILLION ONE
liquidated damages after it failed to deduct the alleged HUNDRED TWENTY SIX THOUSAND NINE HUNDRED
liquidated damages from MCI's progress billings. This Tribunal TWENTY TWO & 91/100 (16,126,922.91) PESOS.
holds that such failure to deduct, which CHATHAM claims it did
in order not to hamper progress of work in the project, is an
SO ORDERED.7
option which [it] may or may not exercise.
Impugning the decision of the CIAC, CHATHAM instituted a
However, this Tribunal finds that CHATHAM's Exh. 11-A where
petition for review with the Court of Appeals, which was
the liquidated damages on delays in concreting milestone was
docketed as CA-G.R. SP No. 49429. In its petition, CHATHAM
applied is not consistent with [its] own Exhibit 3-I. This Tribunal
alleged that:
notes that in Exh. 11-A, CHATHAM included a projected delay
of 85 days for the Helipad Concreting works, while no such
projected delay was included in Exh. 3-I as it should be. The Arbitral Tribunal grossly erred in failing to indicate specific
reference to the evidence presented or to the transcript of
stenographic notes in arriving at its questioned Decision, in
This Tribunal holds that Exh. 3-I showing a delay of 294 days in
violation of the cardinal rule under Section 1, Rule 36 of the
concreting milestones should rightfully be used in computing
Revised Rules of Civil Procedure that a judgment must state
liquidated damages. Accordingly, this Tribunal holds that MCI is
clearly and definitely the facts and the law on which it is based.
liable for liquidated damages in the amount of P3,062,498.78
ADR || First Batch 36

The Tribunal's conclusions are grounded entirely on The Court of Appeals ascertained that the evidence
speculations, surmises and conjectures. overwhelmingly proved that there was no takeover by
CHATHAM and that MCI exercised complete control, authority
The Arbitral Tribunal grossly erred in failing to consider the and responsibility over the construction. In support of this
evidence presented by CHATHAM and the testimony of its conclusion, the appellate court pointed to the following
witnesses. evidentiary bases:10

The Arbitral Tribunal gravely abused its discretion in 1. Testimony of CHATHAM's Engr. Kapunan that the interim
considering arbitrarily that there was an implied takeover takeover for the works on the basement was triggered by lack
contrary to the facts and evidence submitted. of manpower and delays as early as February 1995, as
evidenced by their assessment11 and that the interim takeover
was only with respect to the direction or management of the
The Arbitral Tribunal committed grave error and gross
field operations and was limited only to works on the basement
misapprehension of facts in holding that CHATHAM is not
and intended to assist MCI to catch up with the schedule of
entitled to liquidated damages despite failure of MCI to meet
completion, since at that time the project was very much
the over-all schedule of completion.
delayed; thereafter, the MCI was back in full control of the
project.12
The Arbitral Tribunal manifestly erred in holding that MCI is
entitled to its claim for unpaid progress billings.
2. Testimony of Engr. Bautista that the takeover was only
partial and temporary and limited to the management portion on
The Arbitral Tribunal committed gross and reversible error in the basement only and that MCI was always in control of the
equating the percentage of MCI's work accomplishment with project.13
the entire work in place, despite evidence to the contrary.
3. Testimony of Engr. Infante that MCI personnel were
The Arbitral Tribunal gravely erred in making 23 May 1996 as constantly present in the project and the "intervention" (not
the cut-off date for purposes of delineating the financial takeover) by CHATHAM was justified to ensure completion of
obligations of the parties. the project on time.14

The Arbitral Tribunal erred in denying CHATHAM its claim for 4. Documentary exhibits evincing the nature and extent of
actual damages pursuant to Article 27.8 of the Construction MCI's work during the takeover period which belied its claims
Contract. that it was not in control of the project because of the takeover
thus:
The facts set forth in CHATHAM's Answer with Compulsory
Counterclaim as well as its documentary and testamentary Exhibit "4" Letter dated 15 February 1995 of Engr. Kapunan
evidence were not overturned or controverted by any contrary of RKDCCI to John Lai of MCI stating that the takeover of
evidence.8 directions or management of the field operations is interim, i.e.
while the takeover is effective immediately it will extend only
In its decision of 30 September 1999, 9 the Court of Appeals after concreting Level B-1 or approximately until 30 May 1995
simplified the assigned errors into one core issue, namely, the which ever is later.
"propriety" of the CIAC's factual findings and conclusions. In
upholding the decision of the CIAC, the Court of Appeals Exhibit "4-A" Letter dated 17 February 1995 written by Dr.
confirmed the jurisprudential principle that absent any showing Lai of MCI to Engr. Kapunan in response to the latter's 15
of arbitrariness, the CIAC's findings as an administrative February 1995 letter stating that "[Also we were assured that
agency and quasi judicial body should not only be accorded we will not be responsible for any errors or accidents that may
great respect but also given the stamp of finality. However, the occur during this INTERIM period," indicating that Dr. Lai was
Court of Appeals found exception in the CIAC's disquisition of very much aware of the interim period.
Issue No.9 on the matter of liquidated damages.
Exhibit "4-C" Letter dated 18 February 1995 written by Engr.
The Court of Appeals disagreed with the CIAC's finding that Ben C. Ruiz of RKDCCI to Dr. Lai containing the reasons for
there was an implied takeover by CHATHAM of the project and the takeover.
that it was unnecessary for the CIAC to rule on whether MCI
completed and/or delivered the project within the approved
Exhibit "8A" Letter dated 5 September 1995 written by Dr.
completion schedule of the project since CHATHAM failed to
E.G. Tabujara to Dr. Lai/Romy Laron (Project Manager of MCI)
observe the antecedent acts required for the termination of the
requesting for an engineer of MCI to accompany the inspector
contract, as set forth in the Construction Agreement.
of RKDCCI to witness batching procedures. By so doing, Dr.
E.G. Tabujara acknowledged that Dr. Lai was in control of the
ADR || First Batch 37

project. determine whether MCI failed to complete the project on time


for which it may be held liable for liquidated damages based on
Exhibit "8" Letter dated 4 September 1995 by Engr. Romulo the delays in the overall schedule of completion pursuant to Art.
R Sugay to Dr. Lai offering an incentive to the workers of MCI 13.5 of the Construction Agreement, to wit:
to exert (their) best effort for topping off by the end of
December; another clear indication that Dr. Lai was in control of 13.5. Over-All Schedule For not meeting the final completion
the project. date of the PROJECT, the OWNER will deduct from the
Contract Sum or amounts due the CONTRACTOR, the amount
Exhibit "4-D" Letter dated 4 January 1996 indicating that Mr. equivalent to 1/10 of 1% of the Contract Sum for every calendar
H.T. Go offered Dr Lai an incentive of P1,800,000 on the day of delay, provided, however, that the maximum penalty
condition that MCI meets the new schedule/milestones. MCI's should not exceed 25% of the fee payable to the
acceptance of the incentive offer likewise shows that MCI was CONTRACTOR as stipulated in the Bill of Quantities. Penalties
in control of the Project. from concreting milestones shall be deducted from the penalty
of Over-All Schedule.15
Exhibits "5," "3-1," "3-M," "3-N," "3-W-1," 3-X," "3-Y," and "3-Z"
among others containing reminders to MCI of its duties and The Court of Appeals disposed of the controversy in this wise:
shortcomings, likewise attest to the fact that MCI was in control
(of) and responsible for the Project, although markedly As is extant from the records, the completion date of the Project
deficient. under the Construction Contract or under the revised
construction schedule was never met by reason of [MCI's] lack
Exhibits "5," "5-A," "5-B," "5-C," "5-D," "5-E," "5-F," "5-O," "C-7," of manpower, necessary equipment, qualified engineers and
and "E-9" evidencing that MCI continued to manage other inefficient management of construction works on the Project.
works on the project even during the time of the interim Thus, under the Contract (Exhibit '1'), [MCI] had 780 days, or
takeover of the basement works, as seen in the series of until 22 January 1996, from starting date, or April 12, 1994, to
communications between CHATHAM or RKDCCI and MCI finish the project. The completion date, however, was not
within the period beginning February 1995 to 30 May 1995. followed and was revised as early as December 17, 1994,
extending the milestone dates up to March 15, 1996 (Exhibits
'3-G' and '3-H'). As of December 25, 1995, the number of days
5. Respondent's Request for Adjudication, Annex G, Records,
delayed was already 294 days. Thus, on February 22, 1996,
Folder No. 6 which incorporated Change Order No. 12,
the contract milestones were again revised, inclusive of 53 days
among others, dated 28 August 1995, recommended by the
extension, to May 23, 1996 (Exhibits '3-I' and '3-O'). The May
RKDCCI and accepted by Dr. Lai, and which request for an
23, 1996 turnover milestone nor the July 22, 1996 turnover of
extension of 25 days readily showed that even after 30 May
the whole project were neither met (Exhibits '3-P', '3-R', '3-S'
1995, after the close of the supposed takeover period, MCI was
and '3-T' but [CHATHAM] was again constrained to allow [MCI]
still the contractor in complete control of the project for it would
to continue working on the Project to complete the balance of
not have otherwise accepted the said change order if it (were)
the works (Exhibit 'M'). And all throughout the construction of
no longer the Contractor of the project due to the termination of
the Project, [CHATHAM] had to assist [MCI] along the way to
the Construction agreement as of said date on account of the
expedite the execution and completion of the Project (Exhibits
alleged takeover.
'3-K' and '3-V').
6. Exhibits "3-J," "3-M," "3-Q," "3-R," "3-V," "3- W-1," "3-W-2,"
From the foregoing disquisitions, it is clear that [MCI] is liable
"5-F," "5-1," "6," "12-II," "12-JJ," "12-MM," and "12-NN"
for liquidated damages, as per Article 13.5 of the Construction
tending to prove that RKDCCI monitored the work from start to
Contract, for its failure to complete the project within the period
finish and had zealously pointed out to MCI the defects or
stipulated in the Construction Contract and even despite an
improper execution of the construction works, and gave MCI all
extension of 53 days from the original schedule or of the overall
the opportunity to rectify the construction deficiencies and
schedule of completion. [MCI] should therefore pay
complete the works of the project.
[CHATHAM] the amount of liquidated damages equivalent to
P24,125,000.00 for 193 days of delay in the overall schedule of
The Court of Appeals concluded that the interim takeover was completion counted from overall completion date on July 22,
necessitated by CHATHAM's insistence to meet its own 1996 up to the date of completion on February 15, 1997, as
turnover dates with the buyers of the project's units. Thus, stated in the Certificate of Occupancy, computed as follows, to
CHATHAM was constrained to hire subcontractors with wit:
sufficient manpower and supervision and incur various
expenses to facilitate the completion of the project and/or assist
1/10[1%(P125,000,000.00)] per day x 193 days
MCI in making up for its delay.

= [1/10 (P1,250,000.00)] per day x 193 days


The Court of Appeals then considered it imperative to
ADR || First Batch 38

= P125,000.00 per day x 193 days MCI then asserts that as signatories to the contract, it and
CHATHAM complied with this legal provision when they
= P24,125,000.00 included as part of their TOR the stipulation that "[t]he decision
of the Arbitral Tribunal shall be final and non-appealable except
on questions of law." Accordingly, the binding character of this
IN VIEW OF ALL THE FOREGOING, judgment is hereby
provision upon the parties is conclusive and final.
rendered partially granting [CHATHAM's] claim for liquidated
damages. The Tribunal's Decision dated 19 October 1998 is
hereby AFFIRMED with the modification on [MCI's] liability for MCI also contends that while it may be argued that recent (1)
liquidated damages in the amount of P24,125,000.00. Thus, issuances by the Supreme Court, specifically, Circular No. 1-
91, which eventually became Revised Administrative Circular
No. 1-95; (2) legislation in particular, Republic Act No. 7902,
A. AMOUNT [MCI] IS ENTITLED TO:
which amended Batas Pambansa Blg. 129; and (3)
A.1. From the original contract: 117,650,000.00
amendments to the Rules on Civil Procedure, modifying E.O.
No. 1008 in the sense that "questions of facts, of law, or mixed
94.12% of P125,000,000.00 questions of facts and law may be the subject of an appeal of
A.2 Approved Change Orders the CIAC's 5,353,091.08
decision to the Court of Appeals," it is still E.O. No.
A.3 Pending Change Orders 1008 which1,648,560.46
remains to be the fundamental and substantive law
A.4 CHB Works that endows 1,248,654.71
parties to an arbitral controversy the right to
A.5 Workers Bonus -0- the provisions on appeal of E.O. No. 1008
appeal. Hence,
A.6 Disputed Deductions should be 909,484.70
controlling, i.e., only questions of law should be
A.7 Labor Escalation entertained.076,256.00
Therefore, the only effect of these rules on E.O.
A.8 Attendance Fee No. 1008 is508,162.73
the transfer of the appeal forum from the Supreme
Total Court to theP128,394,209.68
Court of Appeals.
Less: Total payments-item 11-6 of TOR 104,875,792.37
Balance Due Respondent P23,518,417.31
MCI further asserts that, even assuming that the CIAC's
B. AMOUNTS [CHATHAM] IS ENTITLED TO:
findings of facts are reviewable on appeal, the Court of Appeals
B.1. liquidated Damages P24,125,000.00
gravely abused its discretion when it accepted "hook, line and
B.2. Actual Damages 335,994.50
sinker" CHATHAM's contention that MCI was in delay, and
B.3. Penalties 1,778,285.44
ignored competent, clear and substantial evidence that prove
B.4. Cash Payments in behalf of MCI I2,214,715.68
the contrary, and that CHATHAM is not entitled to liquidated
Total Amount Due CPI P28,453,995.62
damages.
C. NET AMOUNT DUE [CHATHAM] (B minus A)
Correspondingly, Respondent [MCI] is hereby directed to pay
the Petitioner [CHATHAM] the net sum of FOUR MILLION For its part, CHATHAM avers that the evolution on the rules
NINE HUNDRED THIRTY-FIVE THOUSAND FIVE HUNDRED governing appeals from judgments, decisions, resolutions,
SEVENTY-EIGHT & 31/100 (P4,935,578.31) PESOS.16 orders or awards of the CIAC convincingly discloses that E.O.
No. 1008 has already been superseded. With the power of the
Supreme Court to promulgate rules concerning the protection
MCI promptly filed on 25 October 1999 a motion for
and enforcement of constitutional rights, pleadings, practice,
reconsideration. In its Resolution of 4 February 2000, the Court
and procedure in all courts, its issuances and amendments to
of Appeals denied MCI's motion for reconsideration for lack of
the Rules on Civil Procedure, not to mention R A. No. 7902, as
merit, as well as CHATHAM's Motion to Lift Garnishment and
enacted by Congress, effectively modified E.O. No. 1008.
Levy Pending Appeal, filed on 13 October 1999, for being
Accordingly, the judgments, awards, decisions, resolutions,
premature.17
orders or awards of the CIAC are now appealable to the Court
of Appeals on questions of facts, mixed questions of facts and
Thus, MCI filed the instant petition for review to challenge the law, and questions of law, and no longer with the Supreme
decision of the Court of Appeals. MCI alleges that the Court of Court on exclusively questions of law. Further, the TOR cannot
Appeals erred in reviewing and reversing the CIAC's factual limit the expanded jurisdiction of the Court of Appeals based on
findings, that there was an implied takeover by CHATHAM of the latest rules. Thus, the Court of Appeals did not err in
the project, and that MCI was not in delay in the overall reviewing the factual findings of the CIAC.
schedule. In so doing, the Court of Appeals contravened
Section 19 of Executive Order (E.O.) No. 1008,18 which limits
CHATHAM also contends that, even if the Court of Appeals can
the review of an Arbitral Award to only questions of law, thus:
only review questions of law, said court did not err in rendering
the questioned decision as the conclusions therein, drawn as
SECTION 19. Finality of Awards The arbitral award shall be they were from factual determinations, can be considered
binding upon the parties. It shall be final and inappealable (sic), questions of law. .
except on questions of law which shall be appealable to the
Supreme Court.
Finally, CHATHAM asseverates that the Court of Appeals did
ADR || First Batch 39

not commit grave abuse of discretion in reversing the CIAC's to the Court of Appeals within the period and in the manner
ascertainment on the implied take-over and liquidated herein provided, whether the appeal involves questions of fact
damages. or of law or mixed questions of fact and law. From final
judgments or decisions of the Court of Appeals, the aggrieved
This Court shall now resolve the primary issue raised in this party may appeal by certiorari to the Supreme Court as
case. provided in Rule 45 of the Rules of Court.

EO. No. 1008 vest upon the CIAC original and exclusive Subsequently, on 23 February 1995, RA. No. 7902 was
jurisdiction over disputes arising from, or connected with, enacted. It expanded the jurisdiction of the Court of Appeals
contracts entered into by parties involved in construction in the and amended for that purpose Section 9 of B.P. Blg. 129,
Philippines, whether the dispute arises before or after the otherwise known as the Judiciary Reorganization Act of 1980.20
completion of the contract, or after the abandonment or breach
thereof.19 By express provision of Section 19 thereof, the Section 9(3) thereof reads:
arbitral award of the CIAC is final and unappealable, except on
questions of law, which are appealable to the Supreme Court. SECTION 9. Jurisdiction. The Court of Appeals shall
exercise:
The parties, however, disagree on whether the subsequent
Supreme Court issuances on appellate procedure and R.A. No. xxx xxx xxx
7902 removed from the Supreme Court its appellate jurisdiction
in Section 19 of E.O. No. 1008 and vested the same in the
(3) Exclusive appellate jurisdiction over all final judgments,
Court of Appeals, and whether appeals from CISC awards are
decisions, resolutions, orders or awards of Regional Trial
no longer confined to questions of law.
Courts and quasi-judicial agencies, instrumentalities, boards or
commissions, including the Securities and Exchange
On 27 February 1991, this Court issued Circular No. 1-91, Commission, the Social Security Commission, the Employees
which prescribes the Rules Governing Appeals to the Court of Compensation Commission and the Civil Service Commission,
Appeals from Final Orders or Decisions of the Court of Tax except those falling within the appellate jurisdiction of the
Appeals and Quasi-Judicial Agencies. Pertinent portions Supreme Court in accordance with the Constitution, the Labor
thereof read as follows: Code of the Philippines under Presidential Decree No. 442, as
amended, the provisions of this Act, and of subparagraph (1) of
1. Scope. These rules shall apply to appeals from final the third paragraph and subparagraph (4) of the fourth
orders or decisions of the Court of Tax Appeals. They shall also paragraph of Section 17 of the Judiciary Act of 1948.
apply to appeals from final orders or decisions of any quasi-
judicial agency from which an appeal is now allowed by statute The Court of Appeals shall have the power to try cases and
to the Court of Appeals or the Supreme Court. Among these conduct hearings, receive evidence and perform any and all
agencies are the Securities and Exchange Commission, Land acts necessary to resolve factual issues raised in cases falling
Registration Authority, Social Security Commission, Civil within its original and appellate jurisdiction, including the power
Aeronautics Board, Bureau of Patents, Trademarks and to grant and conduct new trials or further proceedings. x x x
Technology Transfer, National Electrification Administration,
Energy Regulatory Board, National Telecommunications
Then this Court issued Administrative Circular No. 1-95,21 which
Commission, Secretary of Agrarian Reform and Special
revised Circular No. 1-91. Relevant portions of the former reads
Agrarian Courts under RA. No. 6657, Government Service
as follows:
Insurance System, Employees Compensation Commission,
Agricultural Inventions Board, Insurance Commission and
Philippine Atomic Energy Commission. 1. Scope. These rules shall apply to appeals from judgments
or final orders of the Court of Tax Appeals and from awards,
judgments, final orders or resolutions of any quasi-judicial
2. Cases not Covered. These rules shall not apply to
agency from which an appeal is authorized to be taken to the
decisions and interlocutory orders of the National Labor
Court of Appeals or the Supreme Court. Among these agencies
Relations Commission or the Secretary of Labor and
are the Securities and Exchange Commission, Land
Employment under the Labor Code of the Philippines, the
Registration Authority, Social Security Commission, Civil
Central Board of Assessment Appeals, and other quasi-judicial
Aeronautics Board, Bureau of Patents, Trademarks and
agencies from which no appeal to the courts is prescribed or
Technology Transfer, National Electrification Administration,
allowed by statute.
Energy Regulatory Board, National Telecommunication
Commission, Department of Agrarian Reform under Republic
3. Who may appeal and where to appeal. The appeal of a Act No. 6657, Government Service Insurance System,
party affected by a final order, decision, or judgment of the Employees Compensation Commission, Agricultural Inventions
Court of Tax Appeals or a quasi judicial agency shall be taken Board, Insurance Commission, Philippine Atomic Energy
ADR || First Batch 40

Commission, Board of Investments, and Construction Industry body has been defined as an organ of government other than a
Arbitration Commission. court and other than a legislature, which affects the rights of
private parties through either adjudication or rule-making.22 The
SECTION 2. Cases Not Covered. These rules shall not very definition of an administrative agency includes its being
apply to judgments or final orders issued under the Labor Code vested with quasi judicial powers. The ever increasing variety of
of the Philippines, Central Board of Assessment Appeals, and powers and functions given to administrative agencies
by other quasi-judicial agencies from which no appeal to the recognizes the need for the active intervention of administrative
court is prescribed or allowed. agencies in matters calling for technical knowledge and speed
in countless controversies which cannot possibly be handled by
regular courts.23 The CIAC's primary function is that of a quasi-
SECTION 3. Where to Appeal. An appeal under these rules
judicial agency, which is to adjudicate claims and/or determine
may be taken to the Court of Appeals within the period and in
rights in accordance with procedures set forth in E.O. No. 1008.
the manner herein provided, whether the appeal involves
questions of fact, of law, or mixed questions of fact and law.
In the second place, the language of Section 1 of Circular No.
1-91 emphasizes the obvious inclusion of the CIAC even if it is
Thereafter, this Court promulgated the 1997 Rules on Civil
not named in the enumeration of quasi-judicial agencies. The
Procedure. Sections 1, 2 and 3 of Rule 43 thereof provides:
introductory words "[a] among these agencies are" preceding
the enumeration of specific quasi-judicial agencies only
SECTION 1. Scope. This Rule shall apply to appeals from highlight the fact that the list is not exclusive or conclusive.
judgments or final orders of the Court of Tax Appeals and from Further, the overture stresses and acknowledges the existence
awards, judgments, final orders or resolutions of or authorized of other quasi-judicial agencies not included in the enumeration
by any quasi-judicial agency in the exercise of its quasi-judicial but should be deemed included. In addition, the CIAC is
functions. Among these agencies are the Civil Service obviously excluded in the catalogue of cases not covered by
Commission, Central Board of Assessment Appeals, Securities the Circular and mentioned in Section 2 thereof for the reason
and Exchange Commission, Office of the President, Land that at the time the Circular took effect, E.O. No. 1008 allows
Registration Authority, Social Security Commission, Civil appeals to the Supreme Court on questions of law.
Aeronautics Board, Bureau of Patents, Trademarks and
Technology Transfer, National Electrification Administration,
In sum, under Circular No. 1-91, appeals from the arbitral
Energy Regulatory Board, National Telecommunications
awards of the CIAC may be brought to the Court of Appeals,
Commission, Department of Agrarian Reform under Republic
and not to the Supreme Court alone. The grounds for the
Act No. 6657, Government Service Insurance System,
appeal are likewise broadened to include appeals on questions
Employees Compensation Commission, Agricultural Inventions
of facts and appeals involving mixed questions of fact and law.
Board, Insurance Commission, Philippine Atomic Energy
Commission, Board of Investments, Construction Industry
Arbitration Commission, and voluntary arbitrators authorized by The jurisdiction of the Court of Appeals over appeals from final
law. orders or decisions of the CIAC is further fortified by the
amendments to B.P. Blg. 129, as introduced by RA. No. 7902.
With the amendments, the Court of Appeals is vested with
SECTION 2. Cases Not Covered. This Rule shall not apply
appellate jurisdiction over all final judgments, decisions,
to judgments or final orders issued under the Labor Code of the
resolutions, orders or awards of Regional Trial Courts and
Philippines.
quasi-judicial agencies, instrumentalities, boards or
commissions, except "those within the appellate jurisdiction of
SECTION 3. Were to Appeal. An appeal under this Rule may the Supreme Court in accordance with the Constitution, the
be taken to the Court of Appeals within the period and in the Labor Code of the Philippines under Presidential Decree No.
manner herein provided, whether the appeal involves question 442, as amended, the provisions of this Act, and of
of fact, of law, or mixed questions of fact and law. subparagraph (1) of the third paragraph and subparagraph (4)
of the fourth paragraph of Section 17 of the Judiciary Act of
Through Circular No. 1-91, the Supreme Court intended to 1948."
establish a uniform procedure for the review of the final orders
or decisions of the Court of Tax Appeals and other quasi While, again, the CIAC was not specifically named in said
judicial agencies provided that an appeal therefrom is then provision, its inclusion therein is irrefutable. The CIAC was not
allowed under existing statutes to either the Court of Appeals or expressly covered in the exclusion. Further, it is a quasi-judicial
the Supreme Court. The Circular designated the Court of agency or instrumentality. The decision in Luzon Development
Appeals as the reviewing body to resolve questions of fact or of Bank v. Luzon Development Bank Employees24 sheds light on
law or mixed questions of fact and law. the matter, thus:

It is clear that Circular No. 1-91 covers the CIAC. In the first Assuming arguendo that the voluntary arbitrator or the panel of
place, it is a quasi judicial agency. A quasi-judicial agency or voluntary arbitrators may not strictly be considered as a quasi-
ADR || First Batch 41

judicial agency, board or commission, still both he and the exercise or application of this right was initially outlined in E.O.
panel are comprehended within the concept of a 'quasi-judicial No. 1008. While R. A. No. 7902 and circulars subsequently
instrumentality.' It may even be stated that it was to meet the issued by the Supreme Court and its amendments to the 1997
very situation presented by the quasi-judicial functions of the Rules on Procedure effectively modified the manner by which
voluntary arbitrators here, as well as the subsequent the right to appeal ought to be exercised, nothing in these
arbitrator/arbitral tribunal operating under the Construction changes impaired vested rights. The new rules do not take
Industry Arbitration Commission, that the broader term away the right to appeal allowed in E.O. No. 1008. They only
'instrumentalities' was purposely included in [Section 9 of B.P. prescribe a new procedure to enforce the right.27 No litigant has
Blg. 129 as amended by RA. No. 7902]. a vested right in a particular remedy, which may be changed by
substitution without impairing vested rights; hence, he can have
An instrumentality' is anything used as a means or agency. none in rules of procedure which relate to remedy."28
Thus, the terms governmental 'agency' or 'instrumentality' are
synonymous in the sense that either of them is a means by The foregoing discussion renders academic MCI's assertion on
which a government acts, or by which a certain government act the binding effect of its stipulation with CHATHAM in the TOR
or function is performed. The word 'instrumentality,' with respect that the decision of the CIAC shall be final and non-appealable
to a state, contemplates an authority to which the state except on questions of law. The agreement merely adopted
delegates governmental power for the performance of a state Section 19 of E.O. No. 1008, which, as shown above, had been
function. modified.

Any remaining doubt on the procedural mutation of the The TOR, any contract or agreement of the parties cannot
provisions on appeal in E.O. No. 1008, vis-a-vis Circular No. 1- amend, modify, limit, restrict or circumscribe legal remedies or
91 and R A. No. 7902, was completely removed with the the jurisdiction of courts. Rules of procedure are matters of
issuance by the Supreme Court of Revised Administrative public order and interest and unless the rules themselves so
Circular No. 1-95 and the 1997 Rules of Civil Procedure. Both allow, they cannot be altered, changed or regulated by
categorically include the CIAC in the enumeration of quasi- agreements between or stipulations of the parties for their
judicial agencies comprehended therein. Section 3 of the singular convenience.29
former and Section 3, Rule 43 of the latter, explicitly expand the
issues that may be raised in an appeal from quasi judicial Having resolved the existence of the authority of the Court of
agencies or instrumentalities to the Court of Appeals within the Appeals to review the decisions, awards, or final orders of the
period and in the manner therein provided. Indisputably, the CIAC, the Court shall now determine whether the Court of
review of the CIAC award may involve either questions of fact, Appeals erred in rendering the questioned decision of30
of law, or of fact and law. September 1999.

In view of all the foregoing, we reject MCI's submission that Settled is the general rule that the findings of facts of the Court
Circular No. 1-91, B.P. Blg. 129, as amended by RA. 7902, of Appeals are binding on us. There are recognized exceptions
Revised Administrative Circular 1-95, and Rule 43 of the 1997 to the rule, such as when the findings are contrary to those of
Rules of Civil Procedure failed to efficaciously modify the the trial court 30 as in this case. Hence, we have to take a
provision on appeals in E.O. No. 1008. We further discard closer reexamination of this case.
MCI's claim that these amendments have the effect of merely
changing the forum for appeal from the Supreme Court to the
The CIAC is certain that the evidence overwhelmingly tended to
Court of Appeals.
prove that the manner by which CHATHAM took charge in the
procurement of materials, fielding of labor, control of MCI
There is no controversy on the principle that the right to appeal engineers and the subcontracting of various phases of the
is statutory. However, the mode or manner by which this right work, constituted an implied takeover of the project. The CIAC
may be exercised is a question of procedure which may be then concludes that the cut-off date for delineating the fiscal
altered and modified provided that vested rights are not liabilities of the parties is 23 May 1996 when CHATHAM
impaired. The Supreme Court is bestowed by the Constitution evaluated MCI's work accomplishment at 94.12% and then
with the power and prerogative, inter alia, to promulgate rules suspended all further progress payments to MCI. For these
concerning pleadings, practice and procedure in all courts, as reasons, the CIAC found it trifling to determine whether MCI
well as to review rules of procedure of special courts and quasi- was in delay based on the Overall Schedule. However, the
judicial bodies, which, however, shall remain in force until CIAC discovered that MCI was in delay for 294 days in the
disapproved by the Supreme Court.25 This power is concreting milestone and held the latter liable for liquidated
constitutionally enshrined to enhance the independence of the damages in the amount of P3,062,498.78.
Supreme Court.26
The Court of Appeals made a contrary conclusion and declared
The right to appeal from judgments, awards, or final orders of that MCI was in delay for 193 days based on the overall
the CIAC is granted in E.O. No. 1008. The procedure for the schedule of completion of the project and should incur
ADR || First Batch 42

liquidated damages in the amount of P24,125,000.00. matter of mutual benefit to and convenience of the parties.

It is undisputed that the CIAC and the Court of Appeals found WHEREFORE, IN VIEW OF ALL THE FOREGOING, the
MCI liable for liquidated damages but on different premises. assailed 30 September 1999 decision of the Court of Appeals
Based on the CIAC's assessment, MCI's responsibility was in CA-G.R SP No. 49429 is hereby PARTIALLY MODIFIED by
anchored on its delay in the concreting milestone, while the setting aside the order directing Metro Construction, Inc. to pay
Court of Appeal's evaluation concentrated on MCI's delay in Chatham Properties, Inc. the amount of P4,935,578.31. The
completing the project based on the overall schedule of work. arbitral award of the Construction Industry Arbitration
The variance in the evaluation spells a staggering difference in Commission in CIAC Case 10-98, promulgated on 19 October
the party who should ultimately be held liable and the net 1998, directing Chatham Properties, Inc. to pay Metro
amount involved. Construction, Inc. the sum of SIXTEEN MILLION ONE
HUNDRED TWENTY-SIX THOUSAND NINE HUNDRED
A study of the final computation of the net amount due in both TWENTY-TWO & 91/100 (P16,126,922.91) PESOS, is
the final disquisition of the CIAC and the Court of Appeals accordingly REINSTATED.
shows that all the other figures therein are constant, save for
the amount of liquidated damages for which MCI should be No pronouncement as to costs.
accountable. If this Court concurs with the CIAC's conclusions,
MCI's responsibility for liquidated damages is, as already SO ORDERED.
stated, P3,062,498.78. Setting this off against CHATHAM's
overall fiscal accountability would bring the latter's total liability
Puno, Kapunan, Pardo, and Ynares-Santiago, JJ ., concur.
to MCI to P16,126,922.91. If the Court of Appeals is correct,
MCI would be held liable for a much higher P24,125,000
liquidated damages. Setting this off against CHATHAM's
monetary responsibilities, MCI would still have to pay
CHATHAM P4,935,578.31. Footnotes

After painstakingly combing through the voluminous records, 1 Rollo, 101-107; Annex "C".
we affirm the findings of the CIAC. The evidence taken as a
whole or in their totality reveals that there was an implied 2 Id., 108-110; Annex "C-1." All references to the owner and
takeover by CHATHAM on the completion of the project. The claimant or contractor were changed to CHATHAM and MCI,
evidence that appears to accentuate the Court of Appeals' respectively.
decision ironically bolstered the CIAC's conclusion. The
testimonies of Engr. Kapunan, Engr. Bautista, Dr. Lai, and the 3 Rollo, 103-107.
letter of Engr. Ruiz,31 acknowledging the "temporary takeover"
by CHATHAM of the project, underscore the palpable fact that 4 Decision of the CIAC, Rollo, 276-325; Annex "E."
there was indeed a takeover. We confer particular credit to Dr.
Lai's testimony that as of 15 February 1995, MCI was relieved
of full control of the construction operations, that it was
5 Rollo, 280-285.
relegated to a mere supplier of labor, materials and equipment,
and that the alleged interim takeover actually extended through 6 Rollo, Decision of CIAC, 304-305.
the completion of the project. Even CHATHAM admits the
takeover but sugarcoated the same with words like "interim" did 7 Id., 324-325.
"charging the costs to MCI." With these glaring admissions, we
can even consider that the takeover was not implied but 8MCI's Petition for Review with the Court of Appeals, 8-9; OR,
blatant. 15-16.

Exhibits "4," "4-A," "4-C," "8A," "8," "4-D," '43," "3-I," "3-M," "3- 9 Per Rivera, J., with Abad Santos, Jr. and Salas, B., JJ.,
N," "3-W-1," "3-X," "3-Y," "3-Z," "5,""5-A," "5-B," "5-C," "5-D," "5- concurring.
E," "5-F," "5-O," "C-7," "E-9," etc.,32 relied upon by the Court of
Appeals when considered by themselves and singly, seemingly
and initially evince MCI's control over the project. However,
10 See Decision of the Court of Appeals, Rollo, 88-90.
they eventually lose evidentiary puissance to support the Court
of Appeals' conclusion when reckoned against the totality of the 11 Exhibit 19-Q and 19-R; TSN 5 August 1998, 82-83.
evidence that CHATHAM took charge of the completion of the
project, particularly, the fact that CHATHAM suspended all 12 TSN, 5 August 1998, 84-85.
progress billing payments to MCI. The continued presence and
participation of MCI in the project was, as found by the CIAC, a 13 TSN, 19 August 19 1998, 173-182.
ADR || First Batch 43
14 TSN, 7 September 1998 62-63. Republic of the Philippines
SUPREME COURT
15 OR, 487-488. Manila
THIRD DIVISION
16 Rollo, 91-92.
G.R. No. 132848-49 June 26, 2001
17 Id., 94-99
PHILROCK, INC., petitioner,
18 Entitled a "Creating an Arbitration Machinery for the
Philippine Construction Industry," which took effect on 4 vs.
February 1985.
CONSTRUCTION INDUSTRY ARBITRATION COMMISSION
19See National Irrigation Administration v. Court of Appeals, and Spouses VICENTE and NELIA CID, respondents.
318 SCRA 255, 266 [1999].
PANGANIBAN, J.:
20 B.P. Blg. 129 was signed into law on 14 August 1981.
Courts encourage the use of alternative methods of dispute
21 This took effect on 1 June 1995. resolution. When parties agree to settle their disputes arising
from or connected with construction contracts, the Construction
Industry Arbitration Commission (CIAC) acquires primary
22 See The Presidential Anti-Dollar Salting Task Force v. Court
jurisdiction. It may resolve not only the merits of such
of Appeals, 171 SCRA 348 [1989].
controversies; when appropriate, it may also award damages,
interests, attorneys fees and expenses of litigation.
23See Tropical Homa v. National Housing Authority, 152 SCRA
540 [1987]; See also Antipolo Realty Corp. v. NHA, 153 SCRA
399 119871; Solid Homa, Inc. v. Payawal, 177 SCRA 572 The Case
[19891]
Before us is a Petition for Review under Rule 45 of the Rules of
Court. The Petition seeks the reversal of the July 9, 1997
24 249 SCRA 162 [1995].
Decision1 and the February 24, 1998 Resolution of the Court of
Appeals (CA) in the consolidated cases docketed as CA-GR SP
25 Article VIII, Section 5 of the 1987 Constitution. Nos. 39781 and 42443. The assailed Decision disposed as
follows:
26See Echegaray v. Secretary of Justice, 301 SCRA 96 [1991];
also GSIS v. Court of Appeals, 222 SCRA 685 [19931]. "WHEREFORE, judgment is hereby rendered DENYING the
petitions and, accordingly, AFFIRMING in toto the CIACs
27 Fabian v. Desierto, 295 SCRA 470119981. decision. Costs against petitioner."2

28 Ibid., The assailed Resolution ruled in this wise:

29See Republic of the Philippines v. Hernandez, 253 SCRA 509 "Considering that the matters raised and discussed in the
119961. motion for reconsideration filed by appellants counsel are
substantially the same arguments which the Court had passed
30 Litonjua v. Court of Appeals, 286 SCRA 136 [1998]; Rosario upon and resolved in the decision sought to be reconsidered,
v. Court of Appeals, 310 SCRA 464 [1999]; Republic v. Court of and there being no new issue raised, the subject motion is
Appeals, 314 SCRA 230 [1999]. hereby DENIED."3

31 Decision of the Court of Appeals, Rollo, 88-90. The Facts

32 Id. The undisputed facts of the consolidated cases are


summarized by the CA as follows:

"On September 14, 1992, the Cid spouses, herein private


respondents, filed a Complaint for damages against Philrock
and seven of its officers and engineers with the Regional Trial
Court of Quezon City, Branch 82.
ADR || First Batch 44

"On December 7, 1993, the initial trial date, the trial court "On September 12, 1995, [P]etitioner Philrock filed its Motion to
issued an Order dismissing the case and referring the same to Dismiss, alleging therein that the CIAC had lost jurisdiction to
the CIAC because the Cid spouses and Philrock had filed an hear the arbitration case due to the parties' withdrawal of their
Agreement to Arbitrate with the CIAC. consent to arbitrate. The motion was denied by x x x CIAC per
Order dated September 22, 1995. On November 8, public
"Thereafter, preliminary conferences were held among the respondent ordered the parties to appear before it on
parties and their appointed arbitrators. At these conferences, November 28, 1995 for the continuation of the arbitral
disagreements arose as to whether moral and exemplary proceedings, and on February 7, 1996, public respondent
damages and tort should be included as an issue along with directed [P]etitioner Philrock to set two hearing dates in the
breach of contract, and whether the seven officers and month of February to present its evidence and to pay all fees
engineers of Philrock who are not parties to the Agreement to assessed by it, otherwise x x x Philrock would be deemed to
Arbitrate should be included in the arbitration proceedings. No have waived its right to present evidence.
common ground could be reached by the parties, hence, on
April 2, 1994, both the Cid spouses and Philrock requested that "Hence, petitioner instituted the petition for certiorari but while
the case be remanded to the trial court. On April 13, 1994, the said petition was pending, the CIAC rendered its Decision
CIAC issued an Order stating, thus: dated September 24, 1996, the dispositive portion of which
reads, as follows:
'x x x the Arbitral Tribunal hereby formally dismisses the above-
captioned case for referral to Branch 82 of the Regional Trial 'WHEREFORE, judgment is hereby rendered in favor of the
Court, Quezon City where it first originated. Claimant, directing Respondent to pay Claimant as follows:

SO ORDERED.' 1. P23,276.25 representing the excess cash payment for


materials ordered by the Claimants, (No. 7 of admitted facts)
"The Cid spouses then filed with said Branch of the Regional plus interests thereon at the rate of 6% per annum from
Trial Court of Quezon City a Motion To Set Case for Hearing September 26, 1995 to the date payment is made.
which motion was opposed by Philrock.
2. P65,000.00 representing retrofitting costs.
"On June 13, 1995, the trial court declared that it no longer had
jurisdiction over the case and ordered the records of the case to 3. P13,404.54 representing refund of the value of delivered but
be remanded anew to the CIAC for arbitral proceedings. unworkable concrete mix that was laid to waste.

"Pursuant to the aforementioned Order of the Regional Trial 4. P50,000.00 representing moral damages.
C[o]urt of Quezon City, the CIAC resumed conducting
preliminary conferences. On August 21, 1995, herein 5. P50,000.00 representing nominal damages.
[P]etitioner Philrock requested to suspend the proceedings until
the court clarified its ruling in the Order dated June 13, 1995.
6. P50,000.00 representing attorney's fees and expenses of
Philrock argued that said Order was based on a mistaken
litigation.
premise that 'the proceedings in the CIAC fell through because
of the refusal of [Petitioner] Philrock to include the issue of
damages therein,' whereas the true reason for the withdrawal of 7. P144,756.80 representing arbitration fees, minus such
the case from the CIAC was due to Philrock's opposition to the amount that may already have been paid to CIAC by
inclusion of its seven officers and engineers, who did not give respondent.
their consent to arbitration, as party defendants. On the other
hand, private respondent Nelia Cid manifested that she was "Let a copy of this Decision be furnished the Honorable
willing to exclude the seven officers and engineers of Philrock Salvador C. Ceguera, presiding judge, Branch 82 of Regional
as parties to the case so as to facilitate or expedite the Trial Court of Quezon City who referred this case to the
proceedings. With such manifestation from the Cid spouses, Construction Industry Arbitration Commission for arbitration and
the Arbitral Tribunal denied Philrock's request for the proper disposition.' (pp. 44-45, Rollo, CA-G.R. SP No. 42443) "4
suspension of the proceedings. Philrock's counsel agreed to
the continuation of the proceedings but reserved the right to file Before the CA, petitioner filed a Petition for Review, docketed
a pleading elucidating the position he [had] raised regarding the as CA-GR SP No. 42443, contesting the jurisdiction of the
Court's Order dated June 13, 1995. The parties then proceeded CIAC and assailing the propriety of the monetary awards in
to finalize, approve and sign the Terms of Reference. Philrock's favor of respondent spouses. This Petition was consolidated by
counsel and representative, Atty. Pericles C. Consunji affixed the CA with CA-GR SP No. 39781, a Petition for Certiorari
his signature to said Terms of Reference which stated that 'the earlier elevated by petitioner questioning the jurisdiction of the
parties agree that their differences be settled by an Arbitral CIAC.
Tribunal x x x x' (p. 9, Terms of Reference, p. 200, Rollo).
ADR || First Batch 45

Ruling of the Court of Appeals Whether or not the awarding of the amount of P23,276.75 for
materials ordered by Respondent Spouses Cid plus interest
The CA upheld the jurisdiction of the CIAC5 over the dispute thereon at the rate of 6% from 26 September 1995 is proper.
between petitioner and private respondent. Under Executive
Order No. 1008, the CIAC acquires jurisdiction when the parties "D.
agree to submit their dispute to voluntary arbitration. Thus, in
the present case, its jurisdiction continued despite its April 13, Whether or not the awarding of the amount of P65,000.00 as
1994 Order referring the case back to the Regional Trial Court retrofitting costs is proper.
(RTC) of Quezon City, Branch 82, the court of origin. The
CIACs action was based on the principle that once acquired,
"E.
jurisdiction remains "until the full termination of the case unless
a law provides the contrary." No such "full termination" of the
case was evident in the said Order; nor did the CIAC or private Whether or not the awarding of the amount of P1,340,454 for
respondents intend to put an end to the case. the value of the delivered but the allegedly unworkable
concrete which was wasted is proper.
Besides, according to Section 3 of the Rules of Procedure
Governing Construction Arbitration, technical rules of law or "F.
procedure are not applicable in a single arbitration or arbitral
tribunal. Thus, the "dismissal" could not have divested the CIAC Whether or not the awarding o[f] moral and nominal damages
of jurisdiction to ascertain the facts of the case, arrive at a and attorney's fees and expenses of litigation in favor of
judicious resolution of the dispute and enforce its award or respondents is proper.
decision.
"G.
Since the issues concerning the monetary awards were
questions of fact, the CA held that those awards were Whether or not Petitioner Philrock should be held liable for the
inappropriate in a petition for certiorari. Such questions are final payment of arbitration fees."7
and not appealable according to Section 19 of EO 1008, which
provides that "arbitral awards shall be x x x final and In sum, petitioner imputes reversible error to the CA (1) for
[u]nappealable except on questions of law which shall be upholding the jurisdiction of the CIAC after the latter had
appealable to the Supreme Court x x x." Nevertheless, the CA dismissed the case and referred it to the regular court, (2) for
reviewed the records and found that the awards were ruling that respondent spouses had a cause of action against
supported by substantial evidence. In matters falling under the petitioner, and (3) for sustaining the award of damages.
field of expertise of quasi-judicial bodies, their findings of fact
are accorded great respect when supported by substantial
This Courts Ruling
evidence.

The Petition has no merit.


Hence, this Petition.6

First Issue:
Issues

Jurisdiction
The petitioner, in its Memorandum, raises the following issues:

Petitioner avers that the CIAC lost jurisdiction over the


"A.
arbitration case after both parties had withdrawn their consent
to arbitrate. The June 13, 1995 RTC Order remanding the case
Whether or not the CIAC could take jurisdiction over the case of to the CIAC for arbitration was allegedly an invalid mode of
Respondent Cid spouses against Petitioner Philrock after the referring a case for arbitration.
case had been dismissed by both the RTC and the CIAC.
We disagree. Section 4 of Executive Order 1008 expressly
"B. vests in the CIAC original and exclusive jurisdiction over
disputes arising from or connected with construction contracts
Whether or not Respondent Cid spouses have a cause of entered into by parties that have agreed to submit their dispute
action against Petitioner Philrock. to voluntary arbitration.8

"C. It is undisputed that the parties submitted themselves to the


jurisdiction of the Commission by virtue of their Agreement to
ADR || First Batch 46

Arbitrate dated November 24, 1993. Signatories to the indicated the following: (1) the legal right of the plaintiff, (2) the
Agreement were Atty. Ismael J. Andres and Perry Y. Uy correlative obligation of the defendant, and (3) the act or the
(president of Philippine Rock Products, Inc.) for petitioner, and omission of the defendant in violation of the said legal right.13
Nelia G. Cid and Atty. Esteban A. Bautista for respondent The cause of action against petitioner was clearly established.
spouses.9 Respondents were purchasers of ready-mix concrete from
petitioner. The concrete delivered by the latter turned out to be
Petitioner claims, on the other hand, that this Agreement was of substandard quality. As a result, respondents sustained
withdrawn by respondents on April 8, 1994, because of the damages when the structures they built using such cement
exclusion of the seven engineers of petitioners in the arbitration developed cracks and honeycombs. Consequently, the
case. This withdrawal became the basis for the April 13, 1994 construction of their residence had to be stopped.
CIAC Order dismissing the arbitration case and referring the
dispute back to the RTC. Consequently, the CIAC was divested Further, the CIAC Decision clearly spelled out respondents
of its jurisdiction to hear and decide the case. cause of action against petitioner, as follows:

This contention is untenable. First, private respondents "Accordingly, this Tribunal finds that the mix was of the right
removed the obstacle to the continuation of the arbitration, proportions at the time it left the plant. This, however, does not
precisely by withdrawing their objection to the exclusion of the necessarily mean that all of the concrete mix delivered had
seven engineers. Second, petitioner continued participating in remained workable when it reached the jobsite. It should be
the arbitration even after the CIAC Order had been issued. It noted that there is no evidence to show that all the transit
even concluded and signed the Terms of Reference10 on mixers arrived at the site within the allowable time that would
August 21, 1995, in which the parties stipulated the ensure the workability of the concrete mix delivered.
circumstances leading to the dispute; summarized their
respective positions, issues, and claims; and identified the "On the other hand, there is sufficiently strong evidence to
composition of the tribunal of arbitrators. The document clearly show that difficulties were encountered in the pouring of
confirms both parties intention and agreement to submit the concrete mix from certain transit mixers necessitating the
dispute to voluntary arbitration. In view of this fact, we fail to [addition] of water and physically pushing the mix, obviously
see how the CIAC could have been divested of its jurisdiction. because the same [was] no longer workable. This Tribunal
holds that the unworkability of said concrete mix has been
Finally, as pointed out by the solicitor general, petitioner firmly established.
maneuvered to avoid the RTCs final resolution of the dispute
by arguing that the regular court also lost jurisdiction after the "There is no dispute, however, to the fact that there are defects
arbitral tribunals April 13, 1994 Order referring the case back to in some areas of the poured structures. In this regard, this
the RTC. In so doing, petitioner conceded and estopped itself Tribunal holds that the only logical reason is that the
from further questioning the jurisdiction of the CIAC. The Court unworkable concrete was the one that was poured in the
will not countenance the effort of any party to subvert or defeat defective sections."14
the objective of voluntary arbitration for its own private motives.
After submitting itself to arbitration proceedings and actively
Third Issue:
participating therein, petitioner is estopped from assailing the
jurisdiction of the CIAC, merely because the latter rendered an
adverse decision.11 Monetary Awards

Second Issue: Petitioner assails the monetary awards given by the arbitral
tribunal for alleged lack of basis in fact and in law. The solicitor
general counters that the basis for petitioners assigned errors
Cause of Action
with regard to the monetary awards is purely factual and
beyond the review of this Court. Besides, Section 19, EO 1008,
Petitioner contends that respondent spouses were negligent in expressly provides that monetary awards by the CIAC are final
not engaging the services of an engineer or architect who and unappealable.
should oversee their construction, in violation of Section 308 of
the National Building Code. It adds that even if the concrete it
We disagree with the solicitor general. As pointed out earlier,
delivered was defective, respondent spouses should bear the
factual findings of quasi-judicial bodies that have acquired
loss arising from their illegal operation. In short, it alleges that
expertise are generally accorded great respect and even
they had no cause of action against it.
finality, if they are supported by substantial evidence.15 The
Court, however, has consistently held that despite statutory
We disagree. Cause of action is defined as an act or omission provisions making the decisions of certain administrative
by which a party violates the right of another.12 A complaint is agencies "final," it still takes cognizance of petitions showing
deemed to have stated a cause of action provided it has want of jurisdiction, grave abuse of discretion, violation of due
ADR || First Batch 47

process, denial of substantial justice or erroneous interpretation We are unconvinced. Not only did respondents disprove the
of the law.16 Voluntary arbitrators, by the nature of their contention of petitioner; they also showed that they sustained
functions, act in a quasi-judicial capacity, such that their damages due to the defective concrete it had delivered. These
decisions are within the scope of judicial review.17 were items of actual damages they sustained due to its breach
of contract.
Petitioner protests the award to respondent spouses of
P23,276.25 as excess payment with six percent interest Moral and Nominal Damages, Attorneys Fees and Costs
beginning September 26, 1995. It alleges that this item was
neither raised as an issue by the parties during the arbitration Petitioner assails the award of moral damages, claiming no
case, nor was its justification discussed in the CIAC Decision. It malice or bad faith on its part.
further contends that it could not be held liable for interest,
because it had earlier tendered a check in the same amount to
We disagree. Respondents were deprived of the comfort and
respondent spouses, who refused to receive it.
the safety of a house and were exposed to the agony of
witnessing the wastage and the decay of the structure for more
Petitioners contentions are completely untenable. Respondent than seven years. In her Memorandum, Respondent Nelia G.
Nelia G. Cid had already raised the issue of overpayment even Cid describes her familys sufferings arising from the
prior to the formal arbitration. In paragraph 9 of the Terms of unreasonable delay in the construction of their residence, as
Reference, she stated: follows: "The family lives separately for lack of space to stay in.
Mrs. Cid is staying in a small dingy bodega, while her son
"9. Claimants were assured that the problem and her demands occupies another makeshift room. Their only daughter stayed
had been the subject of several staff meetings and that Arteche with her aunt from 1992 until she got married in 1996. x x x."21
was very much aware of it, a memorandum having been The Court also notes that during the pendency of the case,
submitted citing all the demands of [c]laimants. This assurance Respondent Vicente Cid died without seeing the completion of
was made on July 31, 1992 when Respondents Secillano, their home.22 Under the circumstances, the award of moral
Martillano and Lomibao came to see Claimant Nelia Cid and damages is proper.
offered to refund P23,276.25, [t]he difference between the
billing by Philrocks Marketing Department in the amount of Petitioner also contends that nominal damages should not have
P125,586.25 and the amount charged by Philrock's Batching been granted, because it did not breach its obligation to
Plant Department in the amount of only P102,586.25, which respondent spouses.
[c]laimant refused to accept by saying, Saka na lang."18
Nominal damages are recoverable only if no actual or
The same issue was discussed during the hearing before the substantial damages resulted from the breach, or no damage
arbitration tribunal on December 19, 1995.19 It was also was or can be shown.23 Since actual damages have been
mentioned in that tribunals Decision dated September 24, proven by private respondents for which they were amply
1996.20 compensated, they are no longer entitled to nominal damages.

The payment of interest is based on Article 2209 of the Civil Petitioner protests the grant of attorneys fees, arguing that
Code, which provides that if the obligation consists of the respondent spouses did not engage the services of legal
payment of a sum of money, and the debtor incurs delay, the counsel. Also, it contends that attorneys fees and litigation
indemnity for damages shall be the payment of legal interest expenses are awarded only if the opposing party acted in gross
which is six per cent per annum, in the absence of a stipulation and evident bad faith in refusing to satisfy plaintiffs valid, just
of the rate. and demandable claim.

Awards for Retrofitting Costs, Wasted Unworkable But We disagree. The award is not only for attorneys fees, but also
Delivered Concrete, and Arbitration Fees for expenses of litigation. Hence, it does not matter if
respondents represented themselves in court, because it is
Petitioner maintains that the defects in the concrete structure obvious that they incurred expenses in pursuing their action
were due to respondent spouses failure to secure the services before the CIAC, as well as the regular and the appellate
of an engineer or architect to supervise their project. Hence, it courts. We find no reason to disturb this award. 1wphi1.nt

claims that the award for retrofitting cost was without legal
basis. It also denies liability for the wasted unworkable but WHEREFORE, the Petition is DENIED and the assailed
delivered concrete, for which the arbitral court awarded Decision AFFIRMED; however, the award of nominal damages
P13,404.54. Finally, it complains against the award of litigation is DELETED for lack of legal basis. Costs against petitioner.
expenses, inasmuch as the case should not have been
instituted at all had respondents complied with the requirements
SO ORDERED.
of the National Building Code.
ADR || First Batch 48

Melo, Vitug, Gonzaga-Reyes, Sandoval-Gutierrez, JJ., concur. 10 Annex "F"; CA rollo for GR SP No. 39781, pp. 188-203.

11See Spouses Benitez v. Court of Appeals, 266 SCRA 242,


January 16, 1997.
Footnote
12Camara v. Court of Appeals, 310 SCRA 608, 618, July 20,
1Penned by Justice Ramon A. Barcelona with the concurrence 1999; Delos Reyes v. Court of Appeals, 285 SCRA 81, 85,
of Justices Jesus M. Elbinias, Division chairman; and January 27, 1998; Leberman Realty Corporation v. Typingco,
Maximiano C. Asuncion, member. By the time the assailed 293 SCRA 316, 327, July 29, 1998.
Resolution was promulgated, Justice Asuncion had died and
had thus been replaced by Justice Jorge S. Imperial.[1] 13Baluyot v. Court of Appeals, 311 SCRA 29, 45, July 22, 1999;
Vergara v. Court of Appeals, 319 SCRA 323, 327, November
2 CA Decision, p. 10; rollo, p. 55. 26, 1999; Leberman v. Typinco, ibid., p. 328.

3 Rollo, p. 44.
14CIAC Decision dated September 24, 1996; CA rollo for GR
SP No. 42443, p. 42.
4 CA Decision, pp. 1-5; rollo, pp. 46-50.
15Villaflor v. Court of Appeals, 280 SCRA 297, 330, October 9,
1997; Philippine Merchant Marine School, Inc. v. Court of
5 The Arbitral Tribunal was composed of Joven B. Joaquin,
Appeals, 244 SCRA 770, 785, June 2, 1995; COCOFED v.
chairman; Atty. Alfredo F. Tadiar and Engr. Loreto C. Aquino,
Trajano, 241 SCRA 262, 268, February 15, 1995.
members.
16Villaflor v. CA, ibid.; De Ysasi III v. National Labor Relations
6 This case was deemed submitted for decision upon this
Commission, 231 SCRA 173, 185, March 11, 1994.
Courts receipt on October 21, 1999, of the Memorandum filed
and personally signed by Respondent Nelia Cid; Vicente, her
husband, had died in the meantime. The Memorandum for
17Chung Fu Industries (Phils.), Inc. v. Court of Appeals, 206
petitioner was signed by Atty. Pericles C. Consunji of Ponce SCRA 545, 556, February 25, 1992.
Enrile Reyes & Manalastas, while the Memorandum for Public
Respondent was signed by Assistant Solicitor General Carlos 18 CA rollo for GR SP No. 39781, p. 195.
N. Ortega and Solicitor Geraldine C. Fiel-Macaraig.
19 Ibid., pp. 118-120.
7 Rollo, pp. 155-156.
20 CA rollo for GR SP No. 42443, p. 36.
8 "SECTION 4. Jurisdiction The CIAC shall have original and
exclusive jurisdiction over disputes arising from, or connected 21 Rollo, p. 198.
with, contracts entered into by parties involved in construction
in the Philippines, whether the dispute arises before or after the 22 Respondent Nelia Cids Explanation; rollo, pp. 184-186.
completion of the contract, or after the abandonment or breach
thereof. These disputes may involve government or private
contracts. For the Board to acquire jurisdiction, the parties to a
23 Go v. Intermediate Appellate Court, 197 SCRA 22, 28-29,
dispute must agree to submit the same to voluntary arbitration. May 13, 1991; Ventanilla v. Centeno, 1 SCRA 215, 220,
January 28, 1961; Robes-Francisco Realty v. Court of First
Instance, 86 SCRA 59, 65-66, October 30, 1978.
"The jurisdiction of the CIAC may include but is not limited to
violation of specifications for materials and workmanship;
violation of the terms of agreement; interpretation and/or
application of contractual provisions; amount of damages and
penalties; commencement time and delays; maintenance and
defects; payment; default of employer or contractor and
changes in contract cost.

"Excluded from the coverage of this law are disputes arising


from employer-employee relationships which shall continue to
be covered by the Labor Code of the Philippines." (EO 1008)

9 Annex "C"; CA rollo for GR SP No. 39781, p. 29.


ADR || First Batch 49

Republic of the Philippines of the cargo and other charges.3 According to Florex, the cargo
SUPREME COURT was received by the consignee only on June 28, 1991, since it
Manila was discharged in Long Beach, California, instead of in
FIRST DIVISION Oakland, California on June 5, 1991 as stipulated.

G.R. No. 126212 March 2, 2000 Respondent AMML filed its Answer4 alleging that even on the
assumption that Florex was entitled to reimbursement, it was
SEA-LAND SERVICE, INC., petitioner, petitioner who should be liable. Accordingly, respondent AMML
filed a Third Party Complaint5 against petitioner on November
10, 1992, averring that whatever damages sustained by Florex
vs.
were caused by petitioner, which actually received and
transported Florex's cargo on its vessels and unloaded them.
COURT OF APPEALS, A.P. MOLLER/MAERSK LINE and
MAERSK-TABACALERA SHIPPING AGENCY (FILIPINAS),
On January 1, 1993, petitioner filed a Motion to Dismiss the
INC., respondents.
Third Party Complaint6 on the ground of failure to state a cause
of action and lack of jurisdiction, the amount of damages not
YNARES-SANTIAGO, J.: having been specified therein. Petitioner also prayed either for
dismissal or suspension of the Third Party Complaint on the
This petition for review on certiorari seeks to annul and set ground that there exists an arbitration agreement between it
aside the decision of the Court of Appeals dated September 29, and respondent AMML. On September 27, 1993, the lower
1995 in CA-G.R. SP No. 35777,1 dismissing the petition for court issued an Order denying petitioner's Motion to Dismiss.
certiorari filed by petitioner to annul the two (2) orders issued by Petitioner's Motion for Reconsideration was likewise denied by
the Regional Trial Court of Quezon City, Branch 216, in Civil the lower court in its August 22, 1994 Order.
Case No. Q-92-12593.
Undaunted, petitioner filed a petition for certiorari7 with the
The facts are as follows: Court of Appeals on November 23, 1994. Meanwhile, petitioner
also filed its Answer to the Third Party Complaint in the trial
On April 29, 1991, petitioner Sea-Land Services, Inc. and court.
private respondent A.P. Moller/Maersk Line (hereinafter
referred to as "AMML"), both carriers of cargo in containerships On September 29, 1995, respondent Court of Appeals
as well as common carriers, entered into a contract entitled, rendered the assailed Decision dismissing the petition for
"Co-operation in the Pacific"2 (hereinafter referred to as the certiorari. With the denial of its Motion for Reconsideration,
"Agreement"), a vessel sharing agreement whereby they petitioner filed the instant petition for review, raising the
mutually agreed to purchase, share and exchange needed following issues
space for cargo in their respective containerships. Under the
Agreement, they could be, depending on the occasion, either a I.
principal carrier (with a negotiable bill of lading or other contract
of carriage with respect to cargo) or a containership operator
THE COURT OF APPEALS DISREGARDED AN AGREEMENT
(owner, operator or charterer of containership on which the
TO ARBITRATE IN VIOLATION OF STATUTE AND
cargo is carried).
SUPREME COURT DECISIONS HOLDING THAT
ARBITRATION IS A CONDITION PRECEDENT TO SUIT
During the lifetime of the said Agreement, or on 18 May 1991, WHERE SUCH AN AGREEMENT TO ARBITRATE EXISTS.
Florex International, Inc. (hereinafter referred to as "Florex")
delivered to private respondent AMML cargo of various
II.
foodstuffs, with Oakland, California as port of discharge and
San Francisco as place of delivery. The corresponding Bill of
Lading No. MAEU MNL110263 was issued to Florex by THE COURT OF APPEALS HAS RULED IN A MANNER NOT
respondent AMML. Pursuant to the Agreement, respondent IN ACCORD WITH JURISPRUDENCE WHEN IT REFUSED
AMML loaded the subject cargo on MS Sealand Pacer, a TO HAVE THE THIRD-PARTY COMPLAINT DISMISSED FOR
vessel owned by petitioner. Under this arrangement, therefore, FAILURE TO STATE A CAUSE OF ACTION AND FOR
respondent AMML was the principal carrier while petitioner was RULING THAT THE FAILURE TO STATE A CAUSE OF
the containership operator. ACTION MAY BE REMEDIED BY REFERENCE TO ITS
ATTACHMENTS.8
The consignee refused to pay for the cargo, alleging that
delivery thereof was delayed. Thus, on June 26, 1992, Florex Resolving first the issue of failure to state a cause of action,
filed a complaint against respondent Maersk-Tabacalera respondent Court of Appeals did not err in reading the
Shipping Agency (Filipinas), Inc. for reimbursement of the value Complaint of Florex and respondent AMML's Answer together
ADR || First Batch 50

with the Third Party Complaint to determine whether a cause of nature of the dispute or claim and requiring reference of such
action is properly alleged. In Fil-Estate Golf and Development, dispute or claim to arbitration pursuant to this Article.
Inc. vs. Court of Appeals,9 this Court ruled that in the
determination of whether or not the complaint states a cause of 32.2 Failing agreement upon an arbitrator within such period of
action, the annexes attached to the complaint may be 14 days, the dispute shall be settled by three Arbitrators, each
considered, they being parts of the complaint. party appointing one Arbitrator, the third being appointed by the
President of the London Maritime Arbitrators Association.
Coming now to the main issue of arbitration, the pertinent
clauses of the "Co-operation in the Pacific" contract entered 32.3 If either of the appointed Arbitrators refuses or is incapable
into by the parties provide: of acting, the party who appointed him shall appoint a new
Arbitrator in his place.
16.2 For the purposes of this agreement the Containership
Operator shall be deemed to have issued to the Principal 32.4 If one of the parties fails to appoint an Arbitrator either
Carrier for good consideration and for both loaded and empty originally or by way of substitution for two weeks after the
containers its non-negotiable memo bills of lading in the form other party having appointed his Arbitrator has sent the party
attached hereto as Appendix 6, consigned only to the Principal making default notice by mail, fax or telex to make the
Carrier or its agents, provisions of which shall govern the appointment, the party appointing the third Arbitrator shall, after
liability between the Principal Carrier and the Containership application from the party having appointed his Arbitrator, also
Operator and that for the purpose of determining the liability in appoint an Arbitrator in behalf of the party making default.
accordance with either Lines' memo bill of lading, the number of
packages or customary freight units shown on the bill of lading
32.5 Any such arbitration shall be in accordance with the
issued by the Principal Carrier to its shippers shall be
Arbitration Act 1950 as amended by the Arbitration Act 1979 or
controlling.
any other subsequent legislation and the arbitrator's award
shall be final and binding upon Lines. To the extent permitted
16.3 The Principal Carrier shall use all reasonable endeavours by the Arbitration Act 1979 the Lines hereto exclude pursuant
to defend all in personam and in rem suits for loss of or damage to S 3(1) of that Act the jurisdiction of the English High Court of
to cargo carried pursuant to bills of lading issued by it, or to Justice to entertain any appeal or application under Section 1
settle such suits for as low a figure as reasonably possible. The and 2 of the Arbitration Act 1979. 10
Principal Carrier shall have the right to seek damages and/or an
indemnity from the Containership Operator by arbitration
From the foregoing, the following matters are clear: First,
pursuant to Clause 32 hereof. Notwithstanding the provisions of
disputes between the Principal Carrier and the Containership
the Lines' memo bills of lading or any statutory rules
Operator arising from contracts of carriage shall be governed
incorporated therein or applicable thereto, the Principal Carrier
by the provisions of the bills of lading issued to the Principal
shall be entitled to commence such arbitration at any time until
Carrier by the Containership Operator. Second, the Principal
one year after its liability has been finally determined by
Carrier shall use its best efforts to defend or settle all suits
agreement, arbitration award or judgment, such award or
against it for loss of or damage to cargo pursuant to bills of
judgment not being the subject of appeal, provided that the
lading issued by it. Third, the Principal Carrier shall have the
Containership Operator has been given notice of the said claim
right to seek damages and/or indemnity from the Containership
in writing by the Principal Carrier within three months of the
Operator by arbitration, pursuant to Clause 32 of the
Principal Carrier receiving notice in writing of the claim. Further
agreement. Fourth, the Principal Carrier shall have the right to
the Principal Carrier shall have the right to grant extensions of
commence such arbitration any time until one year after its
time for the commencement of suit to any third party interested
liability has been finally determined by agreement, arbitration
in the cargo without prior reference to the Containership
award or judgment, provided that the Containership Operator
Operator provided that notice of any extension so granted is
was given notice in writing by the Principal Carrier within three
given to the Containership Operator within 30 days of any such
months of the Principal Carrier receiving notice in writing of said
extension being granted.
claim.

xxx xxx xxx


Prescinding from the foregoing matters, we find that both the
trial court and the Court of Appeals erred in denying petitioner's
32. ARBITRATION prayer for arbitration.

32.1 If at any time a dispute or claim arises out of or in To begin with, allowing respondent AMML's Third Party Claim
connection with the Agreement the Lines shall endeavour to against petitioner to proceed would be in violation of Clause
settle such amicably, failing which it shall be referred to 16.2 of the Agreement. As summarized, the clause provides
arbitration by a single arbitrator in London, such arbitrator to be that whatever dispute there may be between the Principal
appointed by agreement between the Lines within 14 days after Carrier and the Containership Operator arising from contracts
service by one Line upon the other of a notice specifying the
ADR || First Batch 51

of carriage shall be governed by the provisions of the bills of vaunted as "the wave of the future" in international relations,
lading deemed issued to the Principal Carrier by the and is recognized worldwide. To brush aside a contractual
Containership Operator. On the other hand, to sustain the Third agreement calling for arbitration in case of disagreement
Party Complaint would be to allow private respondent to hold between the parties would therefore be a step backward. 12
petitioner liable under the provisions of the bill of lading issued
by the Principal Carrier to Florex, under which the latter is suing WHEREFORE, premises considered, the instant Petition for
in its Complaint, not under the bill of lading petitioner, as Review on Certiorari is GRANTED. The decision of the Court of
containership operator, issued to respondent AMML, as Appeals in CA-G.R. SP No. 35777 is REVERSED and SET
Principal Carrier, contrary to what is contemplated in Clause ASIDE. The Regional Trial Court of Quezon City, Branch 77, is
16.2. ordered to DISMISS Respondent AMML's Third Party
Complaint in Civil Case No. Q-92-12593. No pronouncement as
The Court of Appeals ruled that the terms of the Agreement to costs.
"explicitly required that the principal carrier's claim against the
containership operator first be finally determined by, among SO ORDERED. 1wphi1.nt

others, a court judgment, before the right to arbitration


accrues." However, the Court of Appeals failed to consider that,
Davide, Jr., C.J., Puno, Kapunan and Pardo, JJ., concur.
precisely, arbitration is the mode by which the liability of the
Containership Operator may be finally determined. This is clear
from the mandate of Clause 16.3 that "(T)he Principal Carrier
shall have the right to seek damages and/or an indemnity from
the Containership Operator by arbitration" and that it "shall be Footnotes
entitled to commence such arbitration at any time until one year
after its liability has been finally determined by agreement, 1 Petition, Annex "A"; Rollo, pp. 71-83.
arbitration award or judgment".
2 Id., Annex "O" of Annex "L"; Rollo, pp. 298-352.
For respondent Court of Appeals to say that the terms of the
contract do not require arbitration as a condition precedent to 3 Id., Annex "D"; Rollo, pp. 88-110.
judicial action is erroneous. In the light of the Agreement
clauses aforequoted, it is clear that arbitration is the mode 4 Id., Annex "A-1" of Annex "E"; Rollo, pp. 122-125.
provided by which respondent AMML as Principal Carrier can
seek damages and/or indemnity from petitioner, as
Containership Operator. Stated differently, respondent AMML is
5 Id., Annex "E"; Rollo, pp. 111-127.
barred from taking judicial action against petitioner by the clear
terms of their Agreement. 6 Id., Annex "F"; Rollo, pp. 128-135.

As the Principal Carrier with which Florex directly dealt with, 7 Id., Annex "L"; Rollo, pp. 170-186.
respondent AMML can and should be held accountable by
Florex in the event that it has a valid claim against the former. 8 Id., p. 7; Rollo, p. 53.
Pursuant to Clause 16.3 of the Agreement, respondent AMML,
when faced with such a suit "shall use all reasonable 9 G.R. No. 120958, 265 SCRA 614 [1996].
endeavours to defend" itself or "settle such suits for as low a
figure as reasonably possible". In turn, respondent AMML can
seek damages and/or indemnity from petitioner as
10 Rollo, pp. 326-327, 336-337; emphasis provided.
Containership Operator for whatever final judgment may be
adjudged against it under the Complaint of Florex. The crucial 11Cruz vs. Court of Appeals, G.R. No. 126713, 293 SCRA 239
point is that collection of said damages and/or indemnity from [1998].
petitioner should be by arbitration.
12BF Corporation vs. Court of Appeals, G.R. No. 120105, 288
All told, when the text of a contract is explicit and leaves no SCRA 267, 286 [1998].
doubt as to its intention, the court may not read into it any other
intention that would contradict its plain import. 11 Arbitration
being the mode of settlement between the parties expressly
provided for by their Agreement, the Third Party Complaint
should have been dismissed.

This Court has previously held that arbitration is one of the


alternative methods of dispute resolution that is now rightfully
ADR || First Batch 52

Republic of the Philippines reason, but instead informed him that the Employment
SUPREME COURT Agreement is terminated for cause, effective November 19,
Manila 1995, in accordance with Section 7 (a) (v) of the said
SECOND DIVISION agreement, on account of his breach of Section 12 thereof.
Respondent Zosa was further advised that he shall have no
G.R. No. 129916 March 26, 2001 further rights under the said Agreement or any claims against
the Manager or the Corporation except the right to receive
within thirty (30) days from November 19, 1995, the amounts
MAGELLAN CAPITAL MANAGEMENT CORPORATION and
stated in Section 8 (a) (i) (ii) of the Agreement.8
MAGELLAN CAPITAL HOLDINGS CORPORATION,
petitioners,
Disagreeing with the position taken by petitioners, respondent
Zosa invoked the Arbitration Clause of the Employment
vs.
Agreement, to wit:
ROLANDO M. ZOSA and HON. JOSE P. SOBERANO, JR., in
"23. Arbitration. In the event that any dispute, controversy or
his capacity as Presiding Judge of Branch 58 of the
claim arises out of or under any provisions of this Agreement,
Regional Trial Court of Cebu, 7th Judicial Region,
then the parties hereto agree to submit such dispute,
respondents.
controversy or claim to arbitration as set forth in this Section
and the determination to be made in such arbitration shall be
BUENA, J.: final and binding. Arbitration shall be effected by a panel of
three arbitrators. The Manager, Employee and Corporation
Under a management agreement entered into on March 18, shall designate one (1) arbitrator who shall, in turn, nominate
1994, Magellan Capital Holdings Corporation [MCHC] and elect who among them shall be the chairman of the
appointed Magellan Capital Management Corporation [MCMC] committee. Any such arbitration, including the rendering of an
as manager for the operation of its business and affairs.1 arbitration award, shall take place in Metro Manila. The
Pursuant thereto, on the same month, MCHC, MCMC, and arbitrators shall interpret this Agreement in accordance with the
private respondent Rolando M. Zosa entered into an substantive laws of the Republic of the Philippines. The
"Employment Agreement" designating Zosa as President and arbitrators shall have no power to add to, subtract from or
Chief Executive Officer of MCHC. otherwise modify the terms of Agreement or to grant injunctive
relief of any nature. Any judgment upon the award of the
Under the "Employment Agreement", the term of respondent arbitrators may be entered in any court having jurisdiction
Zosa's employment shall be co-terminous with the thereof, with costs of the arbitration to be borne equally by the
management agreement, or until March 1996,2 unless sooner parties, except that each party shall pay the fees and expenses
terminated pursuant to the provisions of the Employment of its own counsel in the arbitration."
Agreement.3 The grounds for termination of employment are
also provided in the Employment Agreement. On November 10, 1995, respondent Zosa designated his
brother, Atty. Francis Zosa, as his representative in the
On May 10, 1995, the majority of MCHC's Board of Directors arbitration panel9 while MCHC designated Atty. Inigo S. Fojas10
decided not to re-elect respondent Zosa as President and Chief and MCMC nominated Atty. Enrique I. Quiason11 as their
Executive Officer of MCHC on account of loss of trust and respective representatives in the arbitration panel. However,
confidence4 arising from alleged violation of the resolution instead of submitting the dispute to arbitration, respondent
issued by MCHC's board of directors and of the non- Zosa, on April 17, 1996, filed an action for damages against
competition clause of the Employment Agreement.5 petitioners before the Regional Trial Court of Cebu12 to enforce
Nevertheless, respondent Zosa was elected to a new position his benefits under the Employment Agreement.
as MCHC's Vice-Chairman/Chairman for New Ventures
Development.6 On July 3, 1996, petitioners filed a motion to dismiss13 arguing
that (1) the trial court has no jurisdiction over the instant case
On September 26, 1995, respondent Zosa communicated his since respondent Zosa's claims should be resolved through
resignation for good reason from the position of Vice-Chairman arbitration pursuant to Section 23 of the Employment
under paragraph 7 of the Employment Agreement on the Agreement with petitioners; and (2) the venue is improperly laid
ground that said position had less responsibility and scope than since respondent Zosa, like the petitioners, is a resident of
President and Chief Executive Officer. He demanded that he be Pasig City and thus, the venue of this case, granting without
given termination benefits as provided for in Section 8 (c) (i) (ii) admitting that the respondent has a cause of action against the
and (iii) of the Employment Agreement.7 petitioners cognizable by the RTC, should be limited only to
RTC-Pasig City.14
In a letter dated October 20, 1995, MCHC communicated its
non-acceptance of respondent Zosa's resignation for good Meanwhile, respondent Zosa filed an amended complaint dated
ADR || First Batch 53

July 5, 1996. On March 21, 1997, the Court of Appeals rendered a decision,
giving due course to the petition, the decretal portion of which
On August 1, 1996, the RTC Branch 58 of Cebu City issued an reads:
Order denying petitioners motion to dismiss upon the findings
that (1) the validity and legality of the arbitration provision can "WHEREFORE, the petition is GIVEN DUE COURSE. The
only be determined after trial on the merits; and (2) the amount respondent court is directed to resolve the issue on the validity
of damages claimed, which is over P100,000.00, falls within the or effectivity of the arbitration clause in the Employment
jurisdiction of the RTC.15 Petitioners filed a motion for Agreement, and to suspend further proceedings in the trial on
reconsideration which was denied by the RTC in an order dated the merits until the said issue is resolved. The questioned
September 5, 1996.16 orders are set aside insofar as they contravene this Court's
resolution of the issues raised as herein pronounced.
In the interim, on August 22, 1996, in compliance with the
earlier order of the court directing petitioners to file responsive "The petitioner is required to remit to this Court the sum of
pleading to the amended complaint, petitioners filed their P81.80 for cost within five (5) days from notice.
Answer Ad Cautelam with counterclaim reiterating their position
that the dispute should be settled through arbitration and the "SO ORDERED."22
court had no jurisdiction over the nature of the action.17
Petitioners filed a motions for partial reconsideration of the CA
On October 21, 1996, the trial court issued its pre-trial order decision praying (1) for the dismissal of the case in the trial
declaring the pre-trial stage terminated and setting the case for court, on the ground of lack of jurisdiction, and (2) that the
hearing. The order states: parties be directed to submit their dispute to arbitration in
accordance with the Employment Agreement dated March
"ISSUES: 1994. The CA, in a resolution promulgated on June 20, 1997,
denied the motion for partial reconsideration for lack of merit.
"The Court will only resolve one issue in so far as this case is
concerned, to wit: In compliance with the CA decision, the trial court, on July 18,
1997, rendered a decision declaring the "arbitration clause" in
"Whether or not the Arbitration Clause contained in Sec. 23 of the Employment Agreement partially void and of no effect. The
the Employment Agreement is void and of no effect: and, if it is dispositive portion of the decision reads:
void and of no effect, whether or not the plaintiff is entitled to
damages in accordance with his complaint and the defendants "WHEREFORE, premises considered, judgment is hereby
in accordance with their counterclaim. rendered partially declaring the arbitration clause of the
Employment Agreement void and of no effect, only insofar as it
"It is understood, that in the event the arbitration clause is valid concerns the composition of the panel of arbitrators, and
and binding between the parties, the parties shall submit their directing the parties to proceed to arbitration in accordance with
respective claim to the Arbitration Committee in accordance the Employment Agreement under the panel of three (3)
with the said arbitration clause, in which event, this case shall arbitrators, one for the plaintiff, one for the defendants, and the
be deemed dismissed."18 third to be chosen by both the plaintiff and defendants. The
other terms, conditions and stipulations in the arbitration clause
remain in force and effect."23
On November 18, 1996, petitioners filed their Motion Ad
Cautelam for the Correction, Addition and Clarification of the
Pre-trial Order dated November 15, 1996,19 which was denied In view of the trial court's decision, petitioners filed this petition
by the court in an order dated November 28, 1996.20 for review on certiorari, under Rule 45 of the Rules of Court,
assigning the following errors for the Court's resolution:
Thereafter, petitioners MCMC and MCHC filed a Motion Ad
Cautelam for the parties to file their Memoranda to support their "I. The trial court gravely erred when it ruled that the arbitration
respective stand on the issue of the validity of the "arbitration clause under the employment agreement is partially void and of
clause" contained in the Employment Agreement. In an order no effect, considering that:
dated December 13, 1996, the trial court denied the motion of
petitioners MCMC and MCHC. "A. The arbitration clause in the employment agreement dated
March 1994 between respondent Zosa and defendants MCHC
On January 17, 1997, petitioners MCMC and MCHC filed a and MCMC is valid and binding upon the parties thereto.
petition for certiorari and prohibition under Rule 65 of the Rules
of Court with the Court of Appeals, questioning the trial court "B. In view of the fact that there are three parties to the
orders dated August 1, 1996, September 5, 1996, and employment agreement, it is but proper that each party be
December 13, 1996.21 represented in the arbitration panel.
ADR || First Batch 54

"C. The trial court grievously erred in its conclusion that "The determination and validity of the agreement is not a matter
petitioners MCMC and MCHC represent the same interest. intrinsically connected with the regulation and internal affairs of
corporations (see Pereyra vs. IAC, 181 SCRA 244; Sales vs.
"D. Respondent Zosa is estopped from questioning the validity SEC, 169 SCRA 121); it is rather an ordinary case to be
of the arbitration clause, including the right of petitioner MCMC decided in accordance with the general laws, and do not
to nominate its own arbitrator, which he himself has invoked. require any particular expertise or training to interpret and apply
(Viray vs. CA, 191 SCRA 308)."26
"II. In any event, the trial court acted without jurisdiction in
hearing the case below, considering that it has no jurisdiction Furthermore, the decision of the Court of Appeals in CA-G.R.
over the nature of the action or suit since controversies in the SP No. 43059 affirming the trial court's assumption of
election or appointment of officers or managers of a jurisdiction over the case has become the "law of the case"
corporation, such as the action brought by respondent Zosa, which now binds the petitioners. The "law of the case" doctrine
fall within the original and exclusive jurisdiction of the Securities has been defined as "a term applied to an established rule that
and Exchange Commission. when an appellate court passes on a question and remands the
cause to the lower court for further proceedings, the question
there settled becomes the law of the case upon subsequent
"III. Contrary to respondent Zosa's allegation, the issue of the
appeal."27 To note, the CA's decision in CA-G.R. SP No. 43059
trial court's jurisdiction over the case below has not yet been
has already attained finality as evidenced by a Resolution of
resolved with finality considering that petitioners have expressly
this Court ordering entry of judgment of said case, to wit:
reserved their right to raise said issue in the instant petition.
Moreover, the principle of the law of the case is not applicable
in the instant case. "ENTRY OF JUDGMENT

"IV. Contrary to respondent Zosa's allegation, petitioners This is to certify that on September 8, 1997 a
MCMC and MCHC are not guilty of forum shopping. decision/resolution rendered in the above-entitled case was
filed in this Office, the dispositive part of which reads as follows:
"V. Contrary to respondent Zosa's allegation, the instant petition
for review involves only questions of law and not of fact."24 'G.R. No. 129615. (Magellan Capital Management Corporation,
et al. vs. Court of Appeals, Rolando Zosa, et al.). Considering
the petitioner's manifestation dated August 11, 1997 and
We rule against the petitioners.
withdrawal of intention to file petition for review on certiorari, the
Court Resolved to DECLARE THIS CASE TERMINATED and
It is error for the petitioners to claim that the case should fall DIRECT the Clerk of Court to INFORM the parties that the
under the jurisdiction of the Securities and Exchange judgment sought to be reviewed has become final and
Commission [SEC, for brevity]. The controversy does not in executory, no appeal therefore having been timely perfected.'
anyway involve the election/appointment of officers of petitioner
MCHC, as claimed by petitioners in their assignment of errors.
and that the same has, on September 17, 1997, become final
Respondent Zosa's amended complaint focuses heavily on the
and executory and is hereby recorded in the Book of Entries of
illegality of the Employment Agreement's "Arbitration Clause"
Judgments."28
initially invoked by him in seeking his termination benefits under
Section 8 of the employment contract. And under Republic Act
No. 876, otherwise known as the "Arbitration Law," it is the Petitioners, therefore, are barred from challenging anew,
regional trial court which exercises jurisdiction over questions through another remedial measure and in any other forum, the
relating to arbitration. We thus advert to the following authority of the regional trial court to resolve the validity of the
discussions made by the Court of Appeals, speaking thru arbitration clause, lest they be truly guilty of forum-shopping
Justice Minerva P. Gonzaga-Reyes,25 in C.A.-G.R. S.P. No. which the courts consistently consider as a contumacious
43059, viz. practice that derails the orderly administration of justice.

"As regards the fourth assigned error, asserting that jurisdiction Equally unavailing for the petitioners is the review by this Court,
lies with the SEC, which is raised for the first time in this via the instant petition, of the factual findings made by the trial
petition, suffice it to state that the Amended Complaint squarely court that the composition of the panel of arbitrators would, in
put in issue the question whether the Arbitration Clause is valid all probability, work injustice to respondent Zosa. We have
and effective between the parties. Although the controversy repeatedly stressed that the jurisdiction of this Court in a
which spawned the action concerns the validity of the petition for review on certiorari under Rule 45 of the Revised
termination of the service of a corporate officer, the issue on the Rules of Court is limited to reviewing only errors of law, not of
validity and effectivity of the arbitration clause is determinable fact, unless the factual findings complained of are devoid of
by the regular courts, and do not fall within the exclusive and support by the evidence on record, or the assailed judgment is
original jurisdiction of the SEC. based on misapprehension of facts.29
ADR || First Batch 55

Even if procedural rules are disregarded, and a scrutiny of the plaintiff [herein defendant]. Hence, apparently, plaintiff
merits of the case is undertaken, this Court finds the trial court's [defendant] would never get or receive justice and fairness in
observations on why the composition of the panel of arbitrators the arbitration proceedings from the panel of arbitrators as
should be voided, incisively correct so as to merit our approval. provided in the aforequoted arbitration clause. In fairness and
Thus, justice to the plaintiff [defendant], the two defendants (MCMC
and MCHC) [herein petitioners] which represent the same
"From the memoranda of both sides, the Court is of the view interest should be considered as one and should be entitled to
that the defendants [petitioner] MCMC and MCHC represent only one arbitrator to represent them in the arbitration
the same interest. There is no quarrel that both defendants are proceedings. Accordingly, the arbitration clause, insofar as the
entirely two different corporations with personalities distinct and composition of the panel of arbitrators is concerned should be
separate from each other and that a corporation has a declared void and of no effect, because the law says, "Any
personality distinct and separate from those persons clause giving one of the parties power to choose more
composing the corporation as well as from that of any other arbitrators than the other is void and of no effect" (Article 2045,
legal entity to which it may be related. Civil Code).

"But as the defendants [herein petitioner] represent the same "The dispute or controversy between the defendants (MCMC
interest, it could never be expected, in the arbitration and MCHC) [herein petitioners] and the plaintiff [herein
proceedings, that they would not protect and preserve their own defendant] should be settled in the arbitration proceeding in
interest, much less, would both or either favor the interest of the accordance with the Employment Agreement, but under the
plaintiff. The arbitration law, as all other laws, is intended for the panel of three (3) arbitrators, one (1) arbitrator to represent the
good and welfare of everybody. In fact, what is being plaintiff, one (1) arbitrator to represent both defendants (MCMC
challenged by the plaintiff herein is not the law itself but the and MCHC) [herein petitioners] and the third arbitrator to be
provision of the Employment Agreement based on the said law, chosen by the plaintiff [defendant Zosa] and defendants
which is the arbitration clause but only as regards the [petitioners].
composition of the panel of arbitrators. The arbitration clause in
question provides, thus: "xxx xxx xxx"30

'In the event that any dispute, controversy or claim arise out of In this connection, petitioners' attempt to put respondent in
or under any provisions of this Agreement, then the parties estoppel in assailing the arbitration clause must be struck
hereto agree to submit such dispute, controversy or claim to down. For one, this issue of estoppel, as likewise noted by the
arbitration as set forth in this Section and the determination to Court of Appeals, found its way for the first time only on appeal.
be made in such arbitration shall be final and binding. Well-settled is the rule that issues not raised below cannot be
Arbitration shall be effected by a panel of three arbitrators. The resolved on review in higher courts.31 Secondly, employment
Manager, Employee, and Corporation shall designate one (1) agreements such as the one at bar are usually contracts of
arbitrator who shall, in turn, nominate and elect as who among adhesion. Any ambiguity in its provisions is generally resolved
them shall be the chairman of the committee. Any such against the party who drafted the document. Thus, in the
arbitration, including the rendering of an arbitration award, shall relatively recent case of Phil. Federation of Credit
take place in Metro Manila. The arbitrators shall interpret this Cooperatives, Inc. (PFCCI) and Fr. Benedicto Jayoma vs.
Agreement in accordance with the substantive laws of the NLRC and Victoria Abril,32 we had the occasion to stress that
Republic of the Philippines. The arbitrators shall have no power "where a contract of employment, being a contract of adhesion,
to add to, subtract from or otherwise modify the terms of this is ambiguous, any ambiguity therein should be construed
Agreement or to grant injunctive relief of any nature. Any strictly against the party who prepared it." And, finally,
judgment upon the award of the arbitrators may be entered in respondent Zosa never submitted himself to arbitration
any court having jurisdiction thereof, with costs of the arbitration proceedings (as there was none yet) before bewailing the
to be borne equally by the parties, except that each party shall composition of the panel of arbitrators. He in fact, lost no time in
pay the fees and expenses of its own counsel in the arbitration.' assailing the "arbitration clause" upon realizing the inequities
(Emphasis supplied). that may mar the arbitration proceedings if the existing line-up
of arbitrators remained unchecked.
"From the foregoing arbitration clause, it appears that the two
(2) defendants [petitioners] (MCMC and MCHC) have one (1) We need only to emphasize in closing that arbitration
arbitrator each to compose the panel of three (3) arbitrators. As proceedings are designed to level the playing field among the
the defendant MCMC is the Manager of defendant MCHC, its parties in pursuit of a mutually acceptable solution to their
decision or vote in the arbitration proceeding would naturally conflicting claims. Any arrangement or scheme that would give
and certainly be in favor of its employer and the defendant undue advantage to a party in the negotiating table is
MCHC would have to protect and preserve its own interest; anathema to the very purpose of arbitration and should,
hence, the two (2) votes of both defendants (MCMC and therefore, be resisted.
MCHC) would certainly be against the lone arbitrator for the
ADR || First Batch 56

WHEREFORE, premises considered, the petition is hereby 20 Annex "DD," Rollo, p. 252.
DISMISSED and the decision of the trial court dated July 18,
1997 is AFFIRMED. 21 The issues submitted to the Court of Appeals are as follows:

SO ORDERED. "I.

Bellosillo, Mendoza and De Leon, Jr., JJ., concur. RESPONDENT COURT ACTED WITH GRAVE ABUSE OF
DISCRETION AMOUNTING TO LACK OF JURISDICTION
Quisumbing, J ., is on leave. WHEN IT ISSUED THE QUESTIONED ORDERS DATED 1
AUGUST 1996 (ANNEX 'A'), 05 SEPTEMBER 1996 (ANNEX
'B') AND 13 DECEMBER 1996 (ANNEX 'C') WHICH
DEFERRED THE RESOLUTION OF THE ISSUE REGARDING
THE VALIDITY OF THE ARBITRATION CLAUSE IN THE
Footnotes
EMPLOYMENT AGREEMENT UNTIL AFTER TRIAL ON THE
MERITS.
1Section 1 of Amended and Restated Management Agreement,
Annex, "B," Rollo p. 74.
"II.
2 par. 2 of the Pre-Trial Order dated October 21, 1996; Annex
RESPONDENT COURT ACTED WITH GRAVE ABUSE OF
"BB," Rollo, p. 241.
DISCRETION AMOUNTING TO LACK OF JURISDICTION
WHEN IT FAILED TO RULE THAT THE ARBITRATION
3 Annex "C" of Petition, Rollo, pp. 89-101; 217-229. CLAUSE UNDER THE EMPLOYMENT AGREEMENT IS
VALID AND BINDING ON THE PARTIES THERETO.
4 par. 5 of Petitioner's Memorandum, Rollo, p. 560.
"III.
5 par. 5.1 - 6.4, ibid., Rollo, pp. 560-562.
RESPONDENT COURT ACTED WITHOUT OR IN EXCESS
6 par. 4, ibid., Rollo, p. 559. OF JURISDICTION WHEN IT TOOK COGNIZANCE OF
RESPONDENT ZOSA'S AMENDED COMPLAINT INSTEAD
7 par. 6-7, Amended Complaint, Rollo, pp. 173-174; p. 562. OF REFERRING THE SAME IMMEDIATELY TO
ARBITRATION PURSUANT TO THE EMPLOYMENT
8 Annex "O" of Petition, Rollo, p. 130. AGREEMENT BETWEEN PETITIONERS AND RESPONDENT
ZOSA.
9 Annex "P", of Petition, Rollo, p. 131.
"IV.
10 Annex "R", of Petition, Rollo, p. 133.
IN ANY EVENT, RESPONDENT COURT ACTED AND IS
CONTINUING TO ACT WITHOUT JURISDICTION IN
11 Annex "Q", of Petition, Rollo, p. 132.
HEARING THE CASE BELOW, CONSIDERING THAT IT HAS
NO JURISDICTION OVER THE NATURE OF THE ACTION
12 Annex "BB," Rollo, p. 241. OR SUIT SINCE CONTROVERSIES IN THE ELECTION OR
APPOINTMENT OF OFFICERS OR MANAGERS OF A
13 Annex "S," Rollo, pp. 134-145. CORPORATION, SUCH AS THE ACTION BROUGHT BY
RESPONDENT ZOSA, FALL WITHIN THE ORIGINAL AND
14 Annex "U," Rollo, p. 179. EXCLUSIVE JURISDICTION OF THE SECURITIES AND
EXCHANGE COMMISSION.
15 Annex "X," Rollo, p. 185-186.
"V.
16 Annex "AA," Rollo, p. 240.
RESPONDENT COURT ACTED WITH GRAVE ABUSE OF
17 Par. 9, Petitioner's Memorandum, Rollo, p. 566. DISCRETION AMOUNTING TO LACK OF JURISDICTION
WHEN IT REFUSED TO DISMISS THE ACTION BELOW FOR
IMPROPER VENUE.
18 Pre-trial Order, Annex "BB," Rollo, pp. 241-243.
"VI.
19 Annex "CC," Rollo, pp. 248; 566-567.
ADR || First Batch 57

RESPONDENT COURT ACTED WITH GRAVE ABUSE OF Republic of the Philippines


DISCRETION AMOUNTING TO LACK OF JURISDICTION SUPREME COURT
WHEN IT FAILED TO DISMISS THE AMENDED COMPLAINT Manila
FOR LACK OF THE REQUISITE CERTIFICATION OF NON- SECOND DIVISION
FORUM SHOPPING."
G.R. No. 136154 February 7, 2001
Court of Appeals' Decision, pp. 5-6; Rollo, pp. 316-317.
DEL MONTE CORPORATION-USA, PAUL E. DERBY, JR.,
22 Ibid., pp. 329-330. DANIEL COLLINS and LUIS HIDALGO, petitioners,

23 Annex "A," RTC Decision, pp. 72-73. vs.

24 Rollo, pp. 571-573. COURT OF APPEALS, JUDGE BIENVENIDO L. REYES in his


capacity as Presiding Judge, RTC-Br. 74, Malabon, Metro
25 Now Associate Justice of this Court. Manila, MONTEBUENO MARKETING, INC., LIONG LIONG C.
SY and SABROSA FOODS, INC., respondents.
26 Court of Appeals Decision, p. 16; Rollo, p. 321.
BELLOSILLO, J.:
Loevillo C. Agustin vs. Court of Appeals and Filinvest Finance
27

Corporation, 271 SCRA 457 [1997]. This Petition for Review on certiorari assails the 17 July 1998
Decision1 of the Court of Appeals affirming the 11 November
1997 Order2 of the Regional Trial Court which denied
28 Rollo, p. 350.
petitioners' Motion to Suspend Proceedings in Civil Case No.
2637-MN. It also questions the appellate court's Resolution3 of
Congregation of the Religious of the Virgin Mary vs. CA, 291
29
30 October 1998 which denied petitioners' Motion for
SCRA 385 [1998]. Reconsideration.
30 Rollo, pp. 71-72. On 1 July 1994, in a Distributorship Agreement, petitioner Del
Monte Corporation-USA (DMC-USA) appointed private
31Casolita, Sr. vs. Court of Appeals, 275 SCRA 257 [1997]; respondent Montebueno Marketing, Inc. (MMI) as the sole and
Manalili vs. Court of Appeals, 280 SCRA 400 [1997]. exclusive distributor of its Del Monte products in the Philippines
for a period of five (5) years, renewable for two (2) consecutive
32 G.R. No. 121071, December 11, 1998. five (5) year periods with the consent of the parties. The
agreement provided, among others, for an arbitration clause
which states

12. GOVERNING LAW AND ARBITRATION4

This Agreement shall be governed by the laws of the State of


California and/or, if applicable, the United States of America. All
disputes arising out of or relating to this Agreement or the
parties' relationship, including the termination thereof, shall be
resolved by arbitration in the City of San Francisco, State of
California, under the Rules of the American Arbitration
Association. The arbitration panel shall consist of three
members, one of whom shall be selected by DMC-USA, one of
whom shall be selected by MMI, and third of whom shall be
selected by the other two members and shall have relevant
experience in the industry x x x x

In October 1994 the appointment of private respondent MMI as


the sole and exclusive distributor of Del Monte products in the
Philippines was published in several newspapers in the country.
Immediately after its appointment, private respondent MMI
appointed Sabrosa Foods, Inc. (SFI), with the approval of
petitioner DMC-USA, as MMI's marketing arm to concentrate
ADR || First Batch 58

on its marketing and selling function as well as to manage its In a Resolution14 dated 23 December 1996 the trial court
critical relationship with the trade. deferred consideration of petitioners' Motion to Suspend
Proceedings as the grounds alleged therein did not constitute
On 3 October 1996 private respondents MMI, SFI and MMI's the suspension of the proceedings considering that the action
Managing Director Liong Liong C. Sy (LILY SY) filed a was for damages with prayer for the issuance of Writ of
Complaint5 against petitioners DMC-USA, Paul E. Derby, Jr.,6 Preliminary Attachment and not on the Distributorship
Daniel Collins7 and Luis Hidalgo,8 and Dewey Ltd.9 before the Agreement.
Regional Trial Court of Malabon, Metro Manila. Private
respondents predicated their complaint on the alleged On 15 January 1997 petitioners filed a Motion for
violations by petitioners of Arts. 20,10 2111 and 2312 of the Civil Reconsideration to which respondents filed their
Code. According to private respondents, DMC-USA products Comment/Opposition. On 31 January 1997 petitioners filed their
continued to be brought into the country by parallel importers Reply. Subsequently, private respondents filed an Urgent
despite the appointment of private respondent MMI as the sole Motion for Leave to Admit Supplemental Pleading dated 2 April
and exclusive distributor of Del Monte products thereby causing 1997. This Motion was admitted, over petitioners' opposition, in
them great embarrassment and substantial damage. They an Order of the trial court dated 27 June 1997.
alleged that the products brought into the country by these
importers were aged, damaged, fake or counterfeit, so that in As a result of the admission of the Supplemental Complaint,
March 1995 they had to cause, after prior consultation with petitioners filed on 22 July 1997 a Manifestation adopting their
Antonio Ongpin, Market Director for Special Markets of Del Motion to Suspend Proceedings of 17 October 1996 and
Monte Philippines, Inc., the publication of a "warning to the Motion for Reconsideration of 14 January 1997.
trade" paid advertisement in leading newspapers. Petitioners
DMC-USA and Paul E. Derby, Jr., apparently upset with the
On 11 November 1997 the Motion to Suspend Proceedings
publication, instructed private respondent MMI to stop
was denied by the trial court on the ground that it "will not serve
coordinating with Antonio Ongpin and to communicate directly
the ends of justice and to allow said suspension will only delay
instead with petitioner DMC-USA through Paul E. Derby, Jr.
the determination of the issues, frustrate the quest of the
parties for a judicious determination of their respective claims,
Private respondents further averred that petitioners knowingly and/or deprive and delay their rights to seek redress."15
and surreptitiously continued to deal with the former in bad faith
by involving disinterested third parties and by proposing
On appeal, the Court of appeals affirmed the decision of the
solutions which were entirely out of their control. Private
trial court. It held that the alleged damaging acts recited in the
respondents claimed that they had exhausted all possible
Complaint, constituting petitioners' causes of action, required
avenues for an amicable resolution and settlement of their
the interpretation of Art. 21 of the Civil Code16 and that in
grievances; that as a result of the fraud, bad faith, malice and
determining whether petitioners had violated it "would require a
wanton attitude of petitioners, they should be held responsible
full blown trial" making arbitration "out of the question."17
for all the actual expenses incurred by private respondents in
Petitioners' Motion for Reconsideration of the affirmation was
the delayed shipment of orders which resulted in the extra
denied. Hence, this Petition for Review.
handling thereof, the actual expenses and cost of money for the
unused Letters of Credit (LCs) and the substantial opportunity
losses due to created out-of-stock situations and unauthorized The crux of the controversy boils down to whether the dispute
shipments of Del Monte-USA products to the Philippine Duty between the parties warrants an order compelling them to
Free Area and Economic zone; that the bad faith, fraudulent submit to arbitration.
acts and willful negligence of petitioners, motivated by their
determination to squeeze private respondents out of the Petitioners contend that the subject matter of private
outstanding and ongoing Distributorship Agreement in favor of respondents' causes of action arises out of or relates to the
another party, had placed private respondent LILY SY on Agreement between petitioners and private respondents. Thus,
tenterhooks since then; and, that the shrewd and subtle considering that the arbitration clause of the Agreement
manner with which petitioners concocted imaginary violations provides that all disputes arising out of or relating to the
by private respondent MMI of the Distributorship Agreement in Agreement or the parties' relationship, including the termination
order to justify the untimely termination thereof was a thereof, shall be resolved by arbitration, they insist on the
subterfuge. For the foregoing, private respondents claimed, suspension of the proceedings in Civil Case No. 2637-MN as
among other reliefs, the payment of actual damages, exemplary mandated by Sec. 7 of RA 87618
damages, attorney's fees and litigation expenses.
Sec. 7. Stay of Civil Action. If any suit or proceeding be brought
On 21 October 1996 petitioners filed a Motion to Suspend upon an issue arising out of an agreement providing for
Proceedings13 invoking the arbitration clause in their Agreement arbitration thereof, the court in which such suit or proceeding is
with private respondents. 1wphi1.nt
pending, upon being satisfied that the issue involved in such
suit or proceeding is referable to arbitration, shall stay the
ADR || First Batch 59

action or proceeding until an arbitration has been had in the dispute between the parties is arbitrable. However, this
accordance with the terms of the agreement. Provided, That the Court must deny the petition.
applicant for the stay is not in default in proceeding with such
arbitration. The Agreement between petitioner DMC-USA and private
respondent MMI is a contract. The provision to submit to
Private respondents claim, on the other hand, that their causes arbitration any dispute arising therefrom and the relationship of
of action are rooted in Arts. 20, 21 and 23 of the Civil Code,19 the parties is part of that contract and is itself a contract. As a
the determination of which demands a full blown trial, as rule, contracts are respected as the law between the
correctly held by the Court of Appeals. Moreover, they claim contracting parties and produce effect as between them, their
that the issues before the trial court were not joined so that the assigns and heirs.24 Clearly, only parties to the Agreement, i.e.,
Honorable Judge was not given the opportunity to satisfy petitioners DMC-USA and its Managing Director for Export
himself that the issue involved in the case was referable to Sales Paul E. Derby, Jr., and private respondents MMI and its
arbitration. They submit that, apparently, petitioners filed a Managing Director LILY SY are bound by the Agreement and
motion to suspend proceedings instead of sending a written its arbitration clause as they are the only signatories thereto.
demand to private respondents to arbitrate because petitioners Petitioners Daniel Collins and Luis Hidalgo, and private
were not sure whether the case could be a subject of respondent SFI, not parties to the Agreement and cannot even
arbitration. They maintain that had petitioners done so and be considered assigns or heirs of the parties, are not bound by
private respondents failed to answer the demand, petitioners the Agreement and the arbitration clause therein.
could have filed with the trial court their demand for arbitration Consequently, referral to arbitration in the State of California
that would warrant a determination by the judge whether to pursuant to the arbitration clause and the suspension of the
refer the case to arbitration. Accordingly, private respondents proceedings in Civil Case No. 2637-MN pending the return of
assert that arbitration is out of the question. the arbitral award could be called for25 but only as to petitioners
DMC-USA and Paul E. Derby, Jr., and private respondents MMI
Private respondents further contend that the arbitration clause and LILY SY, and not as to the other parties in this case. This is
centers more on venue rather than on arbitration. They finally consistent with the recent case of Heirs of Augusto L. Salas, Jr.
allege that petitioners filed their motion for extension of time to v. Laperal Realty Corporation,26 which superseded that of
file this petition on the same date20 petitioner DMC-USA filed a Toyota Motor Philippines Corp. v. Court of Appeals.27
petition to compel private respondent MMI to arbitrate before
the United States District Court in Northern California, docketed In Toyota, the Court ruled that "[t]he contention that the
as Case No. C-98-4446. They insist that the filing of the petition arbitration clause has become dysfunctional because of the
to compel arbitration in the United States made the petition filed presence of third parties is untenable" ratiocinating that
before this Court an alternative remedy and, in a way, an "[c]ontracts are respected as the law between the contracting
abandonment of the cause they are fighting for her in the parties"28 and that "[a]s such, the parties are thereby expected
Philippines, thus warranting the dismissal of the present petition to abide with good faith in their contractual commitments."29
before this Court. However, in Salas, Jr., only parties to the Agreement, their
assigns or heirs have the right to arbitrate or could be
There is no doubt that arbitration is valid and constitutional in compelled to arbitrate. The Court went further by declaring that
our jurisdiction.21 Even before the enactment of RA 876, this in recognizing the right of the contracting parties to arbitrate or
Court has countenanced the settlement of disputes through to compel arbitration, the splitting of the proceedings to
arbitration. Unless the agreement is such as absolutely to close arbitration as to some of the parties on one hand and trial for
the doors of the courts against the parties, which agreement the others on the other hand, or the suspension of trial pending
would be void, the courts will look with favor upon such arbitration between some of the parties, should not be allowed
amicable arrangement and will only interfere with great as it would, in effect, result in multiplicity of suits, duplicitous
reluctance to anticipate or nullify the action of the arbitrator. 22 procedure and unnecessary delay.30
Moreover, as RA 876 expressly authorizes arbitration of
domestic disputes, foreign arbitration as a system of settling The object of arbitration is to allow the expeditious
commercial disputes was likewise recognized when the determination of a dispute.31 Clearly, the issue before us could
Philippines adhered to the United Nations "Convention on the not be speedily and efficiently resolved in its entirety if we allow
Recognition and the Enforcement of Foreign Arbitral Awards of simultaneous arbitration proceedings and trial, or suspension of
1958" under the 10 May 1965 Resolution No. 71 of the trial pending arbitration. Accordingly, the interest of justice
Philippine Senate, giving reciprocal recognition and allowing would only be served if the trial court hears and adjudicates the
enforcement of international arbitration agreements between case in a single and complete proceeding.32
parties of different nationalities within a contracting state.23
WHEREFORE, the petition is DENIED. The Decision of the
A careful examination of the instant case shows that the Court of Appeals affirming the Order of the Regional Trial Court
arbitration clause in the Distributorship Agreement between of Malabon, Metro Manila, in Civil Case No. 2637-MN, which
petitioner DMC-USA and private respondent MMI is valid and denied petitioners' Motion to Suspend Proceedings, is
ADR || First Batch 60

AFFIRMED. The Regional Trial Court concerned is directed to Br. 73, Malabon, Metro Manila.
proceed with the hearing of Civil Case No. 2637-MN with
dispatch. No costs. 15 See Note 2.

SO ORDERED. 16 See Note 10.

Mendoza, Quisumbing Buena, and De Leon, Jr., JJ., concur. 1wphi1.nt 17 See Note 1.

18 The Arbitration Law.

Footnotes: 19 See Notes 9, 10 and 11.

1 Penned by Associate Justice Demetrio G. Demetria, 20 18 November 1998.


concurred in by Associate Justices Ramon A. Barcelona and
Omar U. Amin. 21 Chapter 2, Title XIV, Book IV, New Civil Code of the
Philippines.
2 Penned by Judge Bienvenido L. Reyes (now Associate
Justice of the Court of Appeals), RTC-Br. 74, Malabon, Metro 22Puromines, Inc. v. Court of Appeals, G.R. No. 91228, 22
Manila.
March 1993, 220 SCRA 281.
3 See Note 1., 23National Union Fire Insurance Company of Pittsburg v. Stolt-
Nielsen Philippines, Inc., G.R. No. 87958, 26 April 1990.
4 Rollo, p. 68.
24 Art. 1311, New Civil Code of the Philippines.
5 Id., pp. 40-82.
25 See Note 22.
6Managing Director of Del Monte Corporation's Export Sales
Department. 26 G.R. No. 135362, 13 December 1999, 320 SCRA 610.
7Regional Director of Del Monte Corporation's Export Sales 27 G.R. No. 102881, 7 December 1992, 216 SCRA 236.
Department.
28 Citing Mercantile Ins. Co., Inc. v. Felipe Ysmael, Jr. & Co.,
8 Head of Credit Services Department of Del Monte
Inc., G.R. NO. 43862, 13 January 1989, 169 SCRA 66.
Corporation.
29Citing Quillian v. Court of Appeals, G.R. No. 55457, 20
9 Owner by assignment of Del Monte Trademarks in the
January 1989, 169 SCRA 279.
Philippines.
30 Ibid.
10 Art. 20. Every person who, contrary to law, willfully and
negligently causes damage to another, shall indemnify the
latter for the same.
31Coquia, Jorge R., Annotation, Arbitration as a Means of
Reducing Court Congestion, 29 July 1977, 78 SCRA 121.
11Art. 21. Any person who willfully causes loss or damage to
another in a manner that is contrary to morals, good custom or
32 See Note 26.
public policy shall compensate the latter for damages.

12 Art. 23. Even when an act or event causing damage to


another's property was not due to the fault or negligence of the
defendant, the latter shall be liable to indemnity, if through the
act or event, he was benefited.

13 Rollo, pp. 83-88..

14 Penned by Presiding Judge Amanda Valera Cabigao, RTCj-


ADR || First Batch 61

Republic of the Philippines The trial opened with the following dialogue, which for the great
SUPREME COURT bearing it has on this case, is here reproduced:.
Manila
EN BANC COURT:

G.R. No. L-29169 August 19, 1968 The parties may proceed.

ROGER CHAVEZ, petitioner, FISCAL GRECIA:

vs. Our first witness is Roger Chavez [one of the accused].

THE HONORABLE COURT OF APPEALS, THE PEOPLE OF ATTY. CARBON [Counsel for petitioner Chavez]:
THE PHILIPPINES and THE WARDEN OF THE CITY JAIL OF
MANILA, respondents.
I am quite taken by surprise, as counsel for the accused Roger
Chavez, with this move of the Fiscal in presenting him as his
Estanislao E. Fernandez and Fausto Arce for petitioner. Office witness. I object.
of the Solicitor General for respondents.
COURT:
SANCHEZ, J.:
On what ground, counsel? .
The thrust of petitioner's case presented in his original and
supplementary petitions invoking jurisdiction of this Court is that
ATTY. CARBON:
he is entitled, on habeas corpus, to be freed from imprisonment
upon the ground that in the trial which resulted in his conviction1
he was denied his constitutional right not to be compelled to On the ground that I have to confer with my client. It is really
testify against himself. There is his prayer, too, that, should he surprising that at this stage, without my being notified by the
fail in this, he be granted the alternative remedies of certiorari to Fiscal, my client is being presented as witness for the
strike down the two resolutions of the Court of Appeals prosecution. I want to say in passing that it is only at this very
dismissing his appeal for failure to file brief, and of mandamus moment that I come to know about this strategy of the
to direct the said court to forward his appeal to this Court for the prosecution.
reason that he was raising purely questions of law.
COURT (To the Fiscal):
The indictment in the court below the third amended
information upon which the judgment of conviction herein You are not withdrawing the information against the accused
challenged was rendered, was for qualified theft of a motor Roger Chavez by making [him a] state witness?.
vehicle, one (1) Thunderbird car, Motor No. H9YH-143003, with
Plate No. H-16648 Pasay City '62 together with its accessories FISCAL GRECIA:
worth P22,200.00. Accused were the following: Petitioner
herein, Roger Chavez, Ricardo Sumilang alias "Romeo I am not making him as state witness, Your Honor.
Vasquez", Edgardo P. Pascual alias "Ging" Pascual, Pedro
Rebullo alias "Pita", Luis Asistio alias "Baby" Asistio, Lorenzo
I am only presenting him as an ordinary witness.
Meneses alias "Lory" Meneses, Peter Doe, Charlie Doe and
Paul Doe.2
ATTY. CARBON:
Averred in the aforesaid information was that on or about the
14th day of November, 1962, in Quezon City, the accused As a matter of right, because it will incriminate my client, I
conspired, with intent of gain, abuse of confidence and without object.
the consent of the owner thereof, Dy Sun Hiok y Lim, in
asporting the motor vehicle above-described. COURT:

Upon arraignment, all the accused, except the three Does who The Court will give counsel for Roger Chavez fifteen minutes
have not been identified nor apprehended, pleaded not guilty. 1wph1.t within which to confer and explain to his client about the giving
of his testimony.
On July 23, 1963, trial commenced before the judge presiding
Branch IX of the Court of First Instance of Rizal in Quezon City. xxx xxx xxx
ADR || First Batch 62

COURT: [after the recess] For which reason I pray this court that I be given at least some
days to meet whatever testimony this witness will bring about. I
Are the parties ready? . therefore move for postponement of today's hearing.

FISCAL: COURT:

We are ready to call on our first witness, Roger Chavez. The court will give counsel time within which to prepare his
cross-examination of this witness.
ATTY. CARBON:
ATTY. CRUZ:
As per understanding, the proceeding was suspended in order
to enable me to confer with my client. I labored under the impression that the witnesses for the
prosecution in this criminal case are those only listed in the
information.
I conferred with my client and he assured me that he will not
testify for the prosecution this morning after I have explained to
him the consequences of what will transpire. I did not know until this morning that one of the accused will
testify as witness for the prosecution.
COURT:
COURT:
What he will testify to does not necessarily incriminate him,
counsel. That's the reason why the court will go along with counsels for
the accused and will give them time within which to prepare for
their cross-examination of this witness.
And there is the right of the prosecution to ask anybody to act
as witness on the witness-stand including the accused.
The court will not defer the taking of the direct examination of
the witness.
If there should be any question that is incriminating then that is
the time for counsel to interpose his objection and the court will
sustain him if and when the court feels that the answer of this Call the witness to the witness stand.
witness to the question would incriminate him.
EVIDENCE FOR THE PROSECUTION
Counsel has all the assurance that the court will not require the
witness to answer questions which would incriminate him. ROGER CHAVEZ, 31 years old, single, buy and sell merchant,
presently detained at the Manila Police Department
But surely, counsel could not object to have the accused called headquarters, after being duly sworn according to law, declared
on the witnessstand. as follows:

ATTY. CARBON: ATTY. IBASCO [Counsel for defendant Luis Asistio]:

I submit. WITH THE LEAVE OF THE COURT:

xxx xxx xxx This witness, Roger Chavez is one of the accused in this case
No. Q-5311.
ATTY. CRUZ [Counsel for defendants Pascual and Meneses]: .
The information alleges conspiracy. Under Rule 123, Section
12, it states:
MAY IT PLEASE THE COURT:

'The act or declaration of a conspirator relating to the


This incident of the accused Roger Chavez being called to
conspiracy and during its existence, may be given in evidence
testify for the prosecution is something so sudden that has
against the co-conspirator after the conspiracy is shown by
come to the knowledge of this counsel.
evidence other than such act or declaration.'
This representation has been apprised of the witnesses
COURT:
embraced in the information.

That is premature, counsel. Neither the court nor counsels for


ADR || First Batch 63

the accused know what the prosecution events to establish by Johnson Lee.
calling this witness to the witness stand.
At Eugene's, a man approached Sumilang with a note which
ATTY. IBASCO: stated that the money was ready at the Dalisay Theater.
Sumilang then wrote on the same note that the money should
I submit. be brought to the restaurant. At the same time he requested
Lee to exhibit the deed of sale of the car to the note bearer.4
COURT: The Fiscal may proceed.3
Then, the two Chinese were left alone in the restaurant. For
Sumilang, who had left the table to pose for pictures with some
And so did the trial proceed. It began with the "direct
fans and come back, again left never to return. So did Chavez,
examination" of Roger Chavez by "Fiscal Grecia".
who disappeared after he left on the pretext of buying
cigarettes. The two Chinese could not locate Sumilang and
Came the judgment of February 1, 1965. The version of the Chavez. They went out to the place where the Thunderbird was
prosecution as found by the court below may be briefly narrated parked, found that it was gone. They then immediately reported
as follows: its loss to the police. Much later, the NBI recovered the already
repainted car and impounded it.
A few days before November 12, 1962, Roger Chavez saw
Johnson Lee, a Chinese, driving a Thunderbird car. With Right after the meeting at Eugene's, Chavez, Sumilang and
Ricardo Sumilang (movie actor Romeo Vasquez) in mind, Asistio converged that same day at Barrio Fiesta, a restaurant
whom he knew was in the market for such a car, Chavez asked at Highway 54 near the Balintawak monument in Caloocan.
Lee whether his car was for sale. Lee answered affirmatively There, Asistio handed to Sumilang P1,000.00 cash and a golf
and left his address with Chavez. Then, on November 12, set worth P800.00 as the latter's share in the transaction. On
Chavez met Sumilang at a barbershop informed him about the the 14th of November, the registration of the car was
Thunderbird. But Sumilang said that he had changed his mind transferred in the name of Sumilang in Cavite City, and three
about buying a new car. Instead, he told Chavez that he days later, in the name of Asistio in Caloocan.
wanted to mortgage his Buick car for P10,000.00 to cover an
indebtedness in Pasay City. Upon the suggestion of Chavez,
From the court's decision, Ricardo Sumilang's version,
they went to see Luis Asistio, who he knew was lending money
corroborated in part by Asistio, may be condensed as follows:
on car mortgages and who, on one occasion, already lent
Romeo Vasquez P3,000.00 on the same Buick car. Asistio
however told the two that he had a better idea on how to raise In the last week of September, 1962, Sumilang saw Roger
the money. His plan was to capitalize on Romeo Vasquez' Chavez at a gas station. The latter informed him that there was
reputation as a wealthy movie star, introduce him as a buyer to a Thunderbird from Clark Field for sale for a price between
someone who was selling a car and, after the deed of sale is P20,000.00 and P22,000.00. Chavez said that it could be held
signed, by trickery to run away with the car. Asistio would then for him with a down payment of P10,000.00.
register it, sell it to a third person for a profit. Chavez known to
be a car agent was included in the plan. He furnished the name To raise this sum, Sumilang and Chavez, on October 1, went to
of Johnson Lee who was selling his Thunderbird. 1wph1.t the house of a certain Nena Hernaez de los Reyes who wrote
out a check for P5,000.00 as a loan to Sumilang. That check
In the morning of November 14, Chavez telephoned Johnson was exhibited in court. Sumilang and Chavez then went to
Lee and arranged for an appointment. Sometime in the Pasay City to see a certain Mario Baltazar, an agent of the
afternoon. Chavez and Sumilang met Lee in his Thunderbird on Pasay City Mayor, and Narsing Cailles, Chief of the Fire
Highway 54. Sumilang was introduced as the interested buyer. Department. Sumilang asked the two for a P10,000-loan
Sumilang's driver inspected the car, took the wheel for a while. backed up by the P5,000.00-check aforesaid on condition that it
After Sumilang and Lee agreed on the purchase price should not be cashed immediately as there were not enough
(P21.000.00), they went to Binondo to Johnson Lee's cousin, funds therefor. Baltazar and Cailles agreed to give the money
Dy Sun Hiok, in whose name the car was registered. the nextday as long as the check would be left with them and
Thereafter, they went to see a lawyer notary public in Quezon Sumilang would sign a promissory note for P10,000.00.
City, known to Chavez for the drafting of the deed of sale. After Baltazar later informed Sumilang that Chavez picked up the
the deed of sale was drawn up, it was signed by Sumilang as money the next day. Four or five days afterwards, Chavez
the vendee, Dy Sun Hiok the vendor, and Sumilang's driver and returned P4,000.00 to Sumilang because P6,000.00 was
Johnson Lee the witnesses thereto. enough for the deposit. And so, Sumilang gave back the
P4,000.00 to Baltazar.
As payment was to be made at Eugene's restaurant in Quezon
City, all of them then drove in the Thunderbird car to that place. About the end of October or at the beginning of November,
The deed of sale and other papers remained in the pockets of Chavez asked Sumilang for another P3,000.00. Sumilang sent
ADR || First Batch 64

Chavez to Baltazar and Cailles, with a note requesting that they As to the other accused, the court found no case against Pedro
accommodate him once more. He also sent a check, again Rebullo alias "Pita" and Lorenzo Meneses alias "Lory". The
without funds. Baltazar gave the money after verifying the accused "Ging" Pascual was also acquitted for in the first place
authenticity of the note. he was not identified by Johnson Lee in court.

On November 14, Chavez appeared at Sumilang's house with As to Roger Chavez, however, the court had this to say: "Roger
the news that the car was ready if Sumilang was ready with the Chavez does not offer any defense. As a matter of fact, his
rest of the money. So Sumilang got P9,000.00 from his mother testimony as witness for the prosecution establishes his guilt
and another P4,000.00 from his aparador. He immediately gave beyond reasonable doubt."5 The trial court branded him "a self-
P6,000.00 to Chavez, intending to pay out the balance upon confessed culprit".6 The court further continued:
the car's delivery. It was then that Chavez told Sumilang that
the car was already bought by a Chinese who would be the It is not improbable that true to the saying that misery loves
vendor. company Roger Chavez tried to drag his co-accused down with
him by coloring his story with fabrications which he expected
The purchase price finally agreed upon between Sumilang and would easily stick together what with the newspaper notoriety of
Johnson Lee was P21,000.00, plus P500.00 agents one and the sensationalism caused by the other. But Roger
commission at the expense of the buyer. Sumilang told Lee that Chavez' accusations of Asistio's participation is utterly
he already paid part of the price to Chavez. uncorroborated. And coming, as it does, from a man who has
had at least two convictions for acts not very different from
At Eugene's, Chavez asked Sumilang for the balance. those charged in this information, the Court would be too
Sumilang accommodated. There, Sumilang, also saw a friend, gullible if it were to give full credence to his words even if they
"Ging" Pascual. In the course of their conversation at the bar, concerned a man no less notorious than himself.7
Sumilang mentioned the proposed transaction thru Chavez.
Pascual warned that Chavez was a "smart" agent and advised The trial court then came to the conclusion that if Johnson Lee
that Sumilang should have a receipt for his money. A certain was not paid for his car, he had no one but Roger Chavez to
Bimbo, a friend of Pascual, offered to make out a receipt for blame.
Chavez to sign.
The sum of all these is that the trial court freed all the accused
After Sumilang returned from posing for some photographs with except Roger Chavez who was found guilty beyond reasonable
some of his fans, Bimbo showed him the receipt already signed doubt of the crime of qualified theft. He was accordingly
by Chavez. Sumilang requested Pascual and Bimbo to sign the sentenced to suffer an indeterminate penalty of not less than
receipt as witnesses. And they did. This receipt was offered as ten (10) years, one (1) day, as minimum and not more than
an exhibit by the prosecution and by Sumilang. fourteen (14) years, eight (8) months and one (1) day as
maximum, to indemnify Dy Sun Hiok and/or Johnson Lee in the
When Sumilang was ready to leave Eugene's, Johnson Lee sum of P21,000.00 without subsidiary imprisonment in case of
turned over to him the deed of sale, the registration papers and insolvency, to undergo the accessory penalties prescribed by
the keys to the car. After shaking hands with Lee, Sumilang law, and to pay the costs. The Thunderbird car then in the
drove away in the car with his driver at the wheel. custody of the NBI was ordered to be turned over to Ricardo
Sumilang, who was directed to return to Asistio the sum of
P1,000.00 unless the latter chose to pay P21,500.00,
Two or three days afterwards, Sumilang dropped by the Barrio
representing the balance of the contract price for the car.
Fiesta on his way to a film shooting at Bulacan. He saw Asistio
with many companions. Asistio liked his Thunderbird parked
outside. Asistio offered to buy it from him for P22,500.00. As The foregoing sentence was promulgated on March 8, 1965.
the offer was good, and knowing Asistio's and his friends' Roger Chavez appealed to the Court of Appeals.
reputation for always getting what they wanted, Sumilang
consented to the sale. Asistio tendered a down payment of On April 18, 1968, the Court of Appeals required Atty. Natividad
P1,000.00; the balance he promised to pay the next day after Marquez, counsel for Roger Chavez, to show cause within ten
negotiating with some financing company. Before said balance days from notice why Chavez' appeal should not be considered
could be paid, the car was impounded. abandoned and dismissed. Reason for this is that said lawyer
received notice to file brief on December 28, 1967 and the
The trial court gave evidence to Sumilang's averment, period for the filing thereof lapsed on January 27, 1968 without
strengthened by Baltazar's and Cailles' corroborations, that he any brief having been filed.
paid good money for the car. Sumilang was thus cleared. So
was Asistio whom the trial court believed to be a mere buyer of On May 13, 1968, Atty. Marquez registered a detailed written
the car. And so, the prosecution's theory of conspiracy was explanation. She also stated that if she were allowed to file
discounted. appellant's brief she would go along with the factual findings of
ADR || First Batch 65

the court below but will show however that its conclusion is witness unduly, to browbeat him if he be timid or reluctant, to
erroneous.8 push him into a corner, and to entrap him into fatal
contradictions, which is so painfully evident in many of the
On May 14, 1968, the Court of Appeals, despite the foregoing earlier state trials, notably in those of Sir Nicholas
explanation, resolved to dismiss the appeal. A move to Throckmorton, and Udal, the Puritan minister, made the system
reconsider was unavailing. For, on June 21, 1968, the Court of so odious as to give rise to a demand for its total abolition. The
Appeals, through a per curiam resolution, disposed to maintain change in the English criminal procedure in that particular
its May 14 resolution dismissing the appeal, directed the City seems to be founded upon no statute and no judicial opinion,
Warden of Manila where Chavez is confined by virtue of the but upon a general and silent acquiescence of the courts in a
warrant of arrest issued by the Court of Appeals, to turn him popular demand. But, however adopted, it has become firmly
over to Muntinlupa Bilibid Prisons pending execution of the embedded in English, as well as in American jurisprudence. So
judgment below, and ordered remand of the case to the deeply did the iniquities of the ancient system impress
Quezon City court for execution of judgment. themselves upon the minds of the American colonists that the
states, with one accord, made a denial of the right to question
an accused person a part of their fundamental law, so that a
It was at this stage that the present proceedings were
maxim which in England was a mere rule of evidence, became
commenced in this Court.
clothed in this country with the impregnability of a constitutional
enactment." (Brown vs. Walker, 161 U.S., 591, 597; 40 Law.
Upon the petitions, the return, and the reply, and after hearing ed., 819, 821)." 12 Mr. Justice Malcolm, in expressive language,
on oral arguments, we now come to grips with the main tells us that this maxim was recognized in England in the early
problem presented. days "in a revolt against the thumbscrew and the rack." 13 An
old Philippine case [1904] 14 speaks of this constitutional
We concentrate attention on that phase of the issues which injunction as "older than the Government of the United States";
relates petitioner's assertion that he was compelled to testify as having "its origin in a protest against the inquisitorial
against himself. For indeed if this one question is resolved in methods of interrogating the accused person"; and as having
the affirmative, we need not reach the others; in which case, been adopted in the Philippines "to wipe out such practices as
these should not be pursued here. formerly prevailed in these Islands of requiring accused
persons to submit to judicial examinations, and to give
1. Petitioner's plea on this score rests upon his averment, with testimony regarding the offenses with which they were
proof, of violation of his right constitutionally entrenched charged."
against self-incrimination. He asks that the hand of this Court
be made to bear down upon his conviction; that he be relieved So it is then that this right is "not merely a formal technical rule
of the effects thereof. He asks us to consider the constitutional the enforcement of which is left to the discretion of the court"; it
injunction that "No person shall be compelled to be a witness is mandatory; it secures to a defendant a valuable and
against himself,"9 fully echoed in Section 1, Rule 115, Rules of substantive right; 15 it is fundamental to our scheme of justice.
Court where, in all criminal prosecutions, the defendant shall be Just a few months ago, the Supreme Court of the United States
entitled: "(e) To be exempt from being a witness against (January 29, 1968), speaking thru Mr. Justice Harlan warned
himself." . that "[t]he constitutional privilege was intended to shield the
guilty and imprudent as well as the innocent and foresighted." 16
It has been said that forcing a man to be a witness against
himself is at war with "the fundamentals of a republican It is in this context that we say that the constitutional guarantee
government"; 10 that [i]t may suit the purposes of despotic may not be treated with unconcern. To repeat, it is mandatory;
power but it can not abide the pure atmosphere of political it secures to every defendant a valuable and substantive right.
liberty and personal freedom."11 Mr. Justice Abad Santos Taada and Fernando (Constitution of the Philippines, 4th ed.,
recounts the historical background of this constitutional vol. I, pp. 583-584) take note of U.S. vs. Navarro, supra, which
inhibition, thus: " "The maxim Nemo tenetur seipsum accusare reaffirms the rule that the constitutional proscription was
had its origin in a protest against the inquisitorial and manifestly established on broad grounds of public policy and humanity; of
unjust methods of interrogating accused persons, which has policy because it would place the witness against the strongest
long obtained in the continental system, and, until the expulsion temptation to commit perjury, and of humanity because it would
of the Stuarts from the British throne in 1688, and the erection be to extort a confession of truth by a kind of duress every
of additional barriers for the protection of the people against the species and degree of which the law abhors. 17
exercise of arbitrary power, was not uncommon even in
England. While the admissions of confessions of the prisoner, Therefore, the court may not extract from a defendant's own
when voluntarily and freely made, have always ranked high in lips and against his will an admission of his guilt. Nor may a
the scale of incriminating evidence, if an accused person be court as much as resort to compulsory disclosure, directly or
asked to explain his apparent connection with a crime under indirectly, of facts usable against him as a confession of the
investigation, the ease with which the questions put to him may crime or the tendency of which is to prove the commission of a
assume an inquisitorial character, the temptation to press, the
ADR || First Batch 66

crime. Because, it is his right to forego testimony, to remain sustain him if and when the court feels that the answer of this
silent, unless he chooses to take the witness stand with witness to the question would incriminate him.
undiluted, unfettered exercise of his own free, genuine will.
Counsel has all the assurance that the court will not require the
Compulsion as it is understood here does not necessarily witness to answer questions which would incriminate him.
connote the use of violence; it may be the product of
unintentional statements. Pressure which operates to overbear But surely, counsel could not object to have the accused called
his will, disable him from making a free and rational choice, or on the witness stand.
impair his capacity for rational judgment would in our opinion be
sufficient. So is moral coercion "tending to force testimony from
Paraphrasing Chief Justice Marshall in Aaron Burr's Trial,
the unwilling lips of the defendant." 18
Robertsons Rep. I, 208, 244, quoted in VIII Wigmore, p. 355, 25
While a defendant's knowledge of the facts remains concealed
2. With the foregoing as guideposts, we now turn to the facts. within his bosom, he is safe; but draw it from thence, and he is
Petitioner is a defendant in a criminal case. He was called by exposed" to conviction.
the prosecution as the first witness in that case to testify for the
People during the first day of trial thereof. Petitioner objected
The judge's words heretofore quoted "But surely counsel
and invoked the privilege of self-incrimination. This he
could not object to have the accused called on the witness
broadened by the clear cut statement that he will not testify. But
stand" wielded authority. By those words, petitioner was
petitioner's protestations were met with the judge's emphatic
enveloped by a coercive force; they deprived him of his will to
statement that it "is the right of the prosecution to ask anybody
resist; they foreclosed choice; the realities of human nature tell
to act as witness on the witness stand including the accused,"
us that as he took his oath to tell the truth, the whole truth and
and that defense counsel "could not object to have the accused
nothing but the truth, no genuine consent underlay submission
called on the witness stand." The cumulative impact of all these
to take the witness stand. Constitutionally sound consent was
is that accused-petitioner had to take the stand. He was thus
absent.
peremptorily asked to create evidence against himself. The
foregoing situation molds a solid case for petitioner, backed by
the Constitution, the law, and jurisprudence. 3. Prejudice to the accused for having been compelled over his
objections to be a witness for the People is at once apparent.
The record discloses that by leading questions Chavez, the
Petitioner, as accused, occupies a different tier of protection
accused, was made to affirm his statement given to the NBI
from an ordinary witness. Whereas an ordinary witness may be
agents on July 17, 1963 at 5:00 o'clock in the afternoon. 26 And
compelled to take the witness stand and claim the privilege as
this statement detailed the plan and execution thereof by
each question requiring an incriminating answer is shot at him,
19 and accused may altogether refuse to take the witness stand
Sumilang (Vasquez), Asistio and himself to deprive the Chinese
of his Thunderbird car. And he himself proceeded to narrate the
and refuse to answer any and all questions. 20 For, in reality, the
same anew in open court. He identified the Thunderbird car
purpose of calling an accused as a witness for the People
involved in the case. 27
would be to incriminate him. 21 The rule positively intends to
avoid and prohibit the certainly inhuman procedure of
compelling a person "to furnish the missing evidence necessary The decision convicting Roger Chavez was clearly of the view
for his conviction." 22 This rule may apply even to a co- that the case for the People was built primarily around the
defendant in a joint trial.23 admissions of Chavez himself. The trial court described Chavez
as the "star witness for the prosecution". Indeed, the damaging
facts forged in the decision were drawn directly from the lips of
And the guide in the interpretation of the constitutional precept
Chavez as a prosecution witness and of course Ricardo
that the accused shall not be compelled to furnish evidence
Sumilang for the defense. There are the unequivocal
against himself "is not the probability of the evidence but it is
statements in the decision that "even accused Chavez"
the capability of abuse." 24 Thus it is, that it was undoubtedly
identified "the very same Thunderbird that Johnson Lee had
erroneous for the trial judge to placate petitioner with these
offered for sale"; that Chavez "testimony as witness for the
words:.
prosecution establishes his guilt beyond reasonable doubt and
that Chavez is "a self-confessed culprit".1wph1.t

What he will testify to does not necessarily incriminate him,


counsel.
4. With all these, we have no hesitancy in saying that petitioner
was forced to testify to incriminate himself, in full breach of his
And there is the right of the prosecution to ask anybody to act constitutional right to remain silent. It cannot be said now that
as witness on the witness-stand including the accused. he has waived his right. He did not volunteer to take the stand
and in his own defense; he did not offer himself as a witness;
If there should be any question that is incriminating then that is on the contrary, he claimed the right upon being called to
the time for counsel to interpose his objection and the court will testify. If petitioner nevertheless answered the questions inspite
ADR || First Batch 67

of his fear of being accused of perjury or being put under Since the Sixth Amendment constitutionally entitles one
contempt, this circumstance cannot be counted against him. charged with crime to the assistance of Counsel, compliance
His testimony is not of his own choice. To him it was a case of with this constitutional mandate is an essential jurisdictional
compelled submission. He was a cowed participant in prerequisite to a Federal Court's authority. When this right is
proceedings before a judge who possessed the power to put properly waived, the assistance of Counsel is no longer a
him under contempt had he chosen to remain silent. Nor could necessary element of the Court's jurisdiction to proceed to
he escape testifying. The court made it abundantly clear that conviction and sentence. If the accused, however, is not
his testimony at least on direct examination would be taken represented by Counsel and has not competently and
right then and thereon the first day of the trial. intelligently waived his constitutional right, the Sixth
Amendment stands as a jurisdictional bar to a valid conviction
It matters not that, after all efforts to stave off petitioner's taking and sentence depriving him of his liberty. A court's jurisdiction
the stand became fruitless, no objections to questions at the beginning of trial may be lost "in the course of the
propounded to him were made. Here involve is not a mere proceedings" due to failure to complete the court as the
question of self-incrimination. It is a defendant's constitutional Sixth Amendment requires by providing Counsel for an
immunity from being called to testify against himself. And the accused who is unable to obtain Counsel, who has not
objection made at the beginning is a continuing one. 1wph1.t
intelligently waived this constitutional guaranty, and whose life
or liberty is at stake. If this requirement of the Sixth Amendment
is not complied with, the court no longer has jurisdiction to
There is therefore no waiver of the privilege. "To be effective, a
proceed. The judgment of conviction pronounced by a court
waiver must be certain and unequivocal, and intelligently,
without jurisdiction is void, and one imprisoned thereunder may
understandably, and willingly made; such waiver following only
obtain release of habeas corpus. 41
where liberty of choice has been fully accorded. After a claim a
witness cannot properly be held to have waived his privilege on
vague and uncertain evidence." 28 The teaching in Johnson vs. Under our own Rules of Court, to grant the remedy to the
Zerbst 29 is this: "It has been pointed out that "courts indulge accused Roger Chavez whose case presents a clear picture of
every reasonable presumption against waiver" of fundamental disregard of a constitutional right is absolutely proper. Section 1
constitutional rights and that we "do not presume acquiescence of Rule 102 extends the writ, unless otherwise expressly
in the loss of fundamental rights." A waiver is ordinarily an provided by law, "to all cases of illegal confinement or detention
intentional relinquishment or abandonment of a known right or by which any person is deprived of his liberty, or by which the
privilege." Renuntiatio non praesumitur. rightful custody of any person is withheld from the person
entitled thereto.
The foregoing guidelines, juxtaposed with the circumstances of
the case heretofore adverted to, make waiver a shaky defense. Just as we are about to write finis to our task, we are prompted
It cannot stand. If, by his own admission, defendant proved his to restate that: "A void judgment is in legal effect no judgment.
guilt, still, his original claim remains valid. For the privilege, we By it no rights are divested. From it no rights can be obtained.
say again, is a rampart that gives protection - even to the guilty. Being worthless in itself, all proceedings founded upon it are
30 equally worthless. It neither binds nor bars any one. All acts
performed under it and all claims flowing out of it are void. The
5. The course which petitioner takes is correct. Habeas corpus parties attempting to enforce it may be responsible as
is a high prerogative writ. 31 It is traditionally considered as an trespassers. ... " 42
exceptional remedy to release a person whose liberty is illegally
restrained such as when the accused's constitutional rights are 6. Respondents' return 43 shows that petitioner is still serving
disregarded. 32 Such defect results in the absence or loss of under a final and valid judgment of conviction for another
jurisdiction 33 and therefore invalidates the trial and the offense. We should guard against the improvident issuance of
consequent conviction of the accused whose fundamental right an order discharging a petitioner from confinement. The
was violated. 34 That void judgment of conviction may be position we take here is that petitioner herein is entitled to
challenged by collateral attack, which precisely is the function liberty thru habeas corpus only with respect to Criminal Case
of habeas corpus. 35 This writ may issue even if another remedy Q-5311 of the Court of First Instance of Rizal, Quezon City
which is less effective may be availed of by the defendant. 36 Branch, under which he was prosecuted and convicted.
Thus, failure by the accused to perfect his appeal before the
Court of Appeals does not preclude a recourse to the writ. 37 Upon the view we take of this case, judgment is hereby
The writ may be granted upon a judgment already final. 38 For, rendered directing the respondent Warden of the City Jail of
as explained in Johnson vs. Zerbst, 39 the writ of habeas corpus Manila or the Director of Prisons or any other officer or person
as an extraordinary remedy must be liberally given effect 40 so in custody of petitioner Roger Chavez by reason of the
as to protect well a person whose liberty is at stake. The judgment of the Court of First Instance of Rizal, Quezon City
propriety of the writ was given the nod in that case, involving a Branch, in Criminal Case Q-5311, entitled "People of the
violation of another constitutional right, in this wise: Philippines, plaintiff, vs. Ricardo Sumilang, et al., accused," to
discharge said Roger Chavez from custody, unless he is held,
ADR || First Batch 68

kept in custody or detained for any cause or reason other than investigating committee to testify, it was because it was thought
the said judgment in said Criminal Case Q-5311 of the Court of that proceedings for forfeiture of illegally acquired property
First Instance of Rizal, Quezon City Branch, in which event the under Republic Act 13797 were civil and not criminal in nature.
discharge herein directed shall be effected when such other Thus Mr. Justice (now Chief Justice) Concepcion could
cause or reason ceases to exist. confidently say:

No costs. So ordered. At the outset, it is not disputed that the accused in a criminal
case may refuse not only to answer incriminatory questions but
Concepcion, C.J., Reyes, J.B.L., Dizon, Makalintal, Zaldivar, also to take the witness stand. (3 Whartons Criminal Evidence,
Angeles and Fernando, JJ., concur. Castro, J., concurs in a pp. 1959-1960; 98 C.J.S., p. 264). Hence, the issue before us
separate opinion. boils down to whether or not the proceedings before the
aforementioned Committee is civil or criminal in character.

Today, perhaps because of long separation from our past, we


need what Holmes called "education in the obvious, more than
Separate Opinions
investigation of the obscure."8 The past may have receded so
far into the distance that our perspectives may have been
CASTRO, J., dissenting : altered and our vision blurred.

In 1901, early in the history of constitutional government in this When the court in the case at bar required the petitioner to
country, this Court reversed the conviction of an accused who, testify, it in effect undid the libertarian gains made over half a
having pleaded "not guilty," was required by the judge to testify century and overturned the settled law. The past was recreated
and answer the complaint. The case was that of United States with all its vividness and all its horrors: John Lilburne in England
v. Junio, reported in the first volume of the Philippine Reports, in 1637, refusing to testify before the Council of the Star
on page 50 thereof. Chamber and subsequently condemned by it to be whipped
and pilloried for his "boldness in refusing to take a legal oath;"9
Resolution of the case did not require an extended opinion (it the Filipino priests Gomez, Burgos and Zamora in 1872
consumed no more than a page in the Reports). For indeed the condemned by the Inquisition to die by their own testimony. 10
facts fitted exactly into the prohibition contained in The
President's Instruction to the (Second) Philippine Commission1 It is for this reason that I deem this occasion important for the
"that no person shall ... be compelled in any criminal case to be expression of my views on the larger question of constitutional
a witness against himself.". dimension.

There was no need either for a dissertation on the Rights of No doubt the constitutional provision that "No person shall be
Man, though occasion for this was not lacking as the compelled to be a witness against himself" 11 may, on occasion,
predominant American members of the Court were under a save a guilty man from his just deserts, but it is aimed against a
special commission to prepare the Filipinos for self- more far reaching evil recurrence of the Inquisition and the
government. The privilege against self-incrimination was fully Star Chamber, even if not in their stark brutality. Prevention of
understood by the Filipinos, whose own history provided the the greater evil was deemed of more importance than
necessary backdrop for this privilege. 2 occurrence of the lesser evil. 12 As Dean Griswold put the
matter with eloquence:.
The Supreme Court simply said, "The judge had no right to
compel the accused to make any statement whatever," and [T]he privilege against self-incrimination is one of the great
declared the proceedings void. landmarks in man's struggle to make himself civilized ... [W]e
do not make even the most hardened criminal sign his own
Nor was there a similar judicial error likely to be committed in death warrant, or dig his own grave, or pull the lever that
the years to come, what with the constant reminder of a Bill of springs the trap on which he stands. We have through the
Rights enshrined in successive organic acts intended for the course of history developed considerable feeling of the dignity
Philippines.3 This is not to say that the Philippine history of the and intrinsic importance of the individual man. Even the evil
privilege ended with the Junio case. To be sure, violations of man is a human being. 13
the privilege took other, and perhaps subtle, forms4 but not the
form directly prohibited by the privilege. Even in the recent case The Government must thus establish guilt by evidence
of Cabal v. Kapunan5 it was assumed as a familiar learning that independently and freely secured; it can not by coercion prove
the accused in a criminal case cannot be required to give a charge against an accused out of his own mouth. 14
testimony and that if his testimony is needed at all against his
co-accused, he must first be discharged.6 If Cabal, the
This is not what was done here. What was done here was to
respondent in an administrative case, was required by an
ADR || First Batch 69

force the petitioner to take the witness stand and state his part forthwith. From that judgment the State appealed.
in the crime charged as "star witness for the prosecution," to
use the very words of the decision, and, by means of his As the Supreme Court of the United States phrased the issue,
testimony, prove his guilt. Thus, the trial court said in its the "narrow question is whether the respondent Noia may be
decision: granted federal habeas corpus relief from imprisonment under a
New York conviction now admitted by the State to rest upon a
Roger Chavez does not offer any defense. As a matter of fact, confession obtained from him in violation of the Fourteenth
his testimony as a witness for the prosecution establishes his Amendment, after he was denied state post-conviction relief
guilt beyond reasonable doubt. because the coerced confession claim had been decided
against him at the trial and Noia had allowed the time for a
The petitioner has been variously described by the trial court as direct appeal to lapse without seeking review by a state
"a car agent ... well versed in this kind of chicanery" "a self- appellate court."
confessed culprit," and "a man with at least two convictions for
acts not very different from those charged in [the] information." In affirming the judgment of the Court of Appeals, the United
But if he has thus been described it was on the basis of States Supreme Court, through Mr. Justice Brennan, spoke in
evidence wrung from his lips. If he was ultimately found guilty of enduring language that may well apply to the case of Roger
the charge against him it was because of evidence which he Chavez. Said the Court: 1wph1.t

was forced to give. In truth he was made the "star witness for
the prosecution" against himself. Today as always few indeed is the number of State prisoners
who eventually win their freedom by means of federal habeas
But neither torture nor an oath nor the threat of punishment corpus. These few who are ultimately successful are persons
such as imprisonment for contempt can be used to compel him whom society has grievously wronged and for whom belated
to provide the evidence to convict himself. No matter how evil liberation is little enough compensation. Surely no fair minded
he is, he is still a human being. person will contend that those who have been deprived of their
liberty without due process of law ought nevertheless to
The fact that the judgment of conviction became final with the languish in prison. Noia, no less than his co-defendants
dismissal of the appeal to the Court of Appeals for failure of the Caminito and Bonino, is conceded to have been the victim of
petitioner's former counsel to file a brief,15 is of no moment. unconstitutional state action. Noia's case stands on its own; but
That judgment is void, and it is precisely the abiding concern of surely no just and humane legal system can tolerate a result
the writ of habeas corpus to provide redress for unconstitutional whereby a Caminito and a Bonino are at liberty because their
and wrongful convictions. Vindication of due process, it has confessions were found to have been coerced yet Noia, whose
been well said, is precisely the historic office of the Great Writ. confession was also coerced, remains in jail for life. For such
16 anomalies, such affronts to the conscience of a civilized
society, habeas corpus is predestined by its historical role in the
In many respects, this case is similar to that of Fay v. Noia. 17 struggle for personal liberty to be the ultimate remedy. If the
Noia was convicted of murder in 1942 with Santo Caminito and States withhold effective remedy, the federal courts have the
Frank Bonino in the County Court of Kings County, New York, power and the duty to provide it. Habeas Corpus is one of the
in the killing of one Hemmeroff during the commission of a precious heritages of Anglo-American civilization. We do no
robbery. The sole evidence against each defendant was his more today than confirm its continuing efficacy.
signed confession. Caminito and Bonino, but not Noia appealed
their convictions to the Appellate Division of the New York A fitting conclusion of this separate opinion may perhaps be
Supreme Court. These appeals were unsuccessful but found in two memorable admonitions from Marjorie G. Fribourg
subsequent legal proceedings resulted in the releases of and Justice William O. Douglas.
Caminito and Bonino upon findings that their confessions had
been coerced and their conviction therefore procured in Mrs. Fribourg, in her inimitable phrase, warns us that
violation of the Fourteenth Amendment. Although Noia's
confession was found to have been coerced, the United States ... Time has taught its age-old lesson. Well-meaning people
District Court for the Southern District of New York held that, burnt witches. Well-meaning prosecutors have convicted the
because of Noia's failure to appeal, he must be denied reliefin innocent. Well-meaning objectives espoused by those not
view of the provision of 28 U.S.C. sec. 2254 that "An grounded in history can lure us from protecting our heritage of
application for a writ of habeas corpus in behalf of a person in equal justice under the law. They can entice us, faster than we
custody pursuant to the judgment of a State court shall not be like to believe, into endangering our liberties.18
granted unless it appears that the applicant has exhausted the
remedies available in the courts of the State. ..." The Court of
And these are the unforgettable words of Justice Douglas:
Appeals for the Second Circuit reversed the judgment of the
District Court and ordered Noia's conviction set aside, with
direction to discharge him from custody unless given a new trial The challenge to our liberties comes frequently not from those
ADR || First Batch 70

who consciously seek to destroy our system of government, but 8Petitioner here submits the theory that the facts found by the
from men of goodwill - good men who allow their proper trial court make out a case of estafa, not qualified theft.
concerns to blind them to the fact that what they propose to
accomplish involves an impairment of liberty. 9Section 1 (18), Bill of Rights, Article III, Constitution of the
Philippines.
xxx xxx xxx
10 Villaflor vs. Summers. 41 Phil. 62, 68.
The motives of these men are often commendable. What we
must remember, however, is that preservation of liberties does 11 U.S. vs. Navarro, 3 Phil. 143, 155.
not depend on motives. A suppression of liberty has the same
effect whether the suppressor be a reformer or an outlaw. The 12 Bermudez vs. Castillo, 64 Phil. 483, 495-496.
only protection against misguided zeal is constant alertness to
infractions of the guarantees of liberty contained in our
Constitution. Each surrender of liberty to the demands of the
13 Villaflor vs. Summers, supra at p. 68.
moment makes easier another, larger surrender. The battle
over the Bill of Rights is a never ending one. 1wph1.t
U.S. vs. Navarro, supra, at p. 152, cited in Taada and
14

Carreon, Political Law of the Philippines, vol. II, 1962 ed., up.
xxx xxx xxx 278-279.

The liberties of any person are the liberties of all of us. III Martin, Rules of Court, 1964 ed., p. 262, citing 14 Am. Jur.,
15

869.
xxx xxx xxx
Marchetti vs. United States (U.S. Supreme Court), No. 2-
16

October Term, 1967, January 29 1968.


In short, the liberties of none are safe unless the liberties of all
are protected.
See also: III Martin, p. 262; Taada and Carreon, op. cit., pp.
17

278-279.
But even if we should sense no danger to our own liberties,
even if we feel secure because we belong to a group that is
important and respected, we must recognize that our Bill of State vs. Wolfe, 266 N.W. 116, 125; 104 ALR 464, 476;
18

Rights is a code of fair play for the less fortunate that we in all Anno., p. 479.
honor and good conscience must observe.19
19 Gonzales vs. Secretary of Labor, 94 Phil. 325, 326.
Footnotes
Cabal vs. Kapunan, L-19052, December 29, 1962; 21 Am. Jur
20

Criminal Case No. Q-5311, Court of First Instance of Rizal,


1 2d., p. 383; 98 C.J.S., p. 265; 8 Wigmore, Evidence 1961 ed.,
Quezon City, Branch IX. p. 406; 3 Wharton's Criminal Evidence, 11th ed., pp. 1959-
1960.
2The original information named only the accused Sumilang,
Chavez, John Doe and Richard Doe. It was amended by
21 Navarro, Criminal Procedure, 1960; ed., p. 302.
substituting Edgardo P. Pascual for John Doe. Then, another
amendment included the rest of the accused abovenamed. 22 Bermudez vs. Castillo supra, at pp. 488-489.

3 Tr., July 23, 1963, pp. 2-11; emphasis supplied. 4 Moran, Comments on the Rules of Court, 1963 ed., p. 160;
23

98 C.J.S., p. 274; 3 Wharton's Criminal Evidence, 11th ed., pp.


4Chavez at this point testified on direct examination that the 1959-1960.
Chinese (Johnson Lee) handed the deed of sale to Romeo
Vasquez who, in turn, delivered it to the emissary. Tr., (Annex Allen vs. State, 171 ALR 1138, 1143, citing Emery's Case,
24

A), p. 39. 107 Mass. 172, 9 Am. Rep. 22.

5 Annex C, p. 7, Rollo, p. 101. Isabela Sugar Company, Inc. vs. Macadaeg, 93 Phil. 995,
25

1000.
6 Id., p. 14, Rollo, p. 108.
26 Tr., pp. 11, 13-23.
7 Id., pp. 14-15, Rollo, pp. 108-109.
27 Tr., pp. 56-57.
ADR || First Batch 71
28 98 C.J.S., p. 314; emphasis supplied. Manchester vs. Martin, 9 Smedes & M., 613; Hargis vs. Morse,
7 Kan., 259. See also Cornell vs. Barnes, 7 Hill. 35; Dawson
29 304 U.S. 458, 464, 82 L. ed. 1461, 1466. and Another vs. Wells, 3 Ind., 899; Meyer vs. Mintonye, 106 Ill.,
414; Olson vs. Nunnally, 47 Kan., 391; White vs. Foote L. & M.
Co, 29 W. Va. 385.
30 Marchetti vs. United States, supra.
43 Par. 2 (d).
31 25 Am. Jur., p. 150.

CASTRO J.:, dissenting :


32See: Santiago vs. Director of Prisons, 77 Phil. 927, 930;
Camasura vs. Provost Marshall, 78 Phil. 131; Harden vs.
Director of Prisons, 81 Phil. 741, 746; Parulan vs. Director of
1 Pub. Laws lxiii, lxvi (1900).
Prisons, 1968A Phild. 514, 516; see also Counselman vs.
Hitchcock (1867), 142 U.S. 547, 35 L. ed. 1110, a case 2See United States v. Navarro, 3 Phil. 143 (1904). In his
involving a violation of the privilege against self-incrimination majority opinion, Mr. Justice McDonough said that under the
and the writ of habeas corpus was allowed; Sunal vs. Large, Spanish system of criminal procedure the privilege against self-
332 U.S. 174, 178-179, 91 L. ed. 1982, 1986-1987. incrimination was unavailing, a point seriously disputed in the
dissenting opinion of Mr. Justice Mapa. Are both Justices half
33 39 C.J.S., pp. 449-450. right and half wrong? Is it more accurate to say that while the
Spanish system allowed no more than a comment on the failure
of the accused to testify, no unfavorable inference being drawn
Mitchell vs. Youell, 130 F. 2d. 880, 882; U.S. vs. Lawn, 115 F.
34
therefrom (as Justice Mapa said at p. 161), in practice the
Supp. 674, 677.
accused was actually denied the privilege against self-
incrimination (as Justice McDonough said at p. 152)? See, e.g.,
Abriol vs. Homeres, 84 Phil. 525, 530, 534. See the dissenting
35
T. Agoncillo & 0. Alfonso, A Short History of the Filipino People,
opinion affirming the same view at pp. 538-539. See also: 103-132 (1961).
Camasura vs. Provost Marshall, supra, at p. 137.
3Act of July 1, 1902, sec. 5, par. 3, 1 Pub. Laws 1056; Jones
36 25 Am. Jur., p. 155. Act of August 29, 1916, sec. 3, par. 3, 12 Pub. Laws 237; Act of
March 24, 1934, ch. 84, 48 Stat. 456; see also General Orders
37 39 C.J.S. p. 446, citing Johnson vs. Zerbst, supra. 58, sec. 15(4), 1 Pub. Laws 1082 (1900).

38 Abriol vs. Homeres, supra, at pp. 527, 534-535. 4Beltran v. Samson, 53 Phil. 570 (1929) (preliminary
investigation; respondent required to give a specimen of his
39Supra, at p. 1467: "True, habeas corpus cannot be used as a handwriting); Bermudes v. Castillo, 64 Phil. 483 (1937)
means of reviewing errors of law and irregularities not (administrative investigation; person required to copy certain
involving the question of jurisdiction occurring during the letters to establish her authorship of the letters).
course of trial; and the "writ of habeas corpus cannot be used
as a writ of error." These principles, however, must be 5 L-19052, Dec. 29, 1962.
construed and applied so as to preserve not destroy
constitutional - safeguards of human life and liberty.". 6E.g., 4 M. Moran, Comments on the Rules of Court 160 (6th
Ed., 1963).
40III Martin, p. 267: "The prohibition against self-incrimination, in
order that it may produce its desired purpose and may not be 7 10 Laws & Res. 345 (1955).
rendered a dead letter, should be interpreted liberally in favor of
the person invoking the same." See: Bermudez vs. Castillo, 8 O.W. Holmes, Law and the Court, in Speeches 98, 99 (1913).
supra, at p. 489.
9 E. Griswold, The Fifth Amendment Today 3 (1955).
Cited in Abriol vs. Homeres, supra, at pp. 533-534; emphasis
41

supplied.
10 T. Agoncillo & O. Alfonso, op. cit. supra note 2, at 156.
Gomez vs. Concepcion, 47 Phil. 717, 722, giving as authority
42

Freeman on Judgments, see. 117 citing Campbell vs.


11 Phil. Const. art. III, sec. 1(18).
McCahan, 41 Ill., 45; Roberts vs. Stowers, 7 Bush, 295; Huls
vs. Buntin, 47 Ill., 396; Sherrell vs. Goodrum, 3 Humph., 418; 12 Ullmann v. United States, 356 U.S. 422 (1956).
Andrews vs. State, 2 Sheed, 549; Hollingsworth vs. Bagley, 35
Tex., 345; Morton vs. Root, 2 Dill., 312; Commercial Bank of 13 Op. cit. supra note 9, at 7.
ADR || First Batch 72

Malley v. Hogan, 378 U.S. 1 (1964); accord, Murphy v.


14 Republic of the Philippines
Waterfront Comm'n, 378 U.S. 52 (1964). SUPREME COURT
Manila
Resolutions of May 14, 1968 and June 21, 1968, CA-G.R.
15 SECOND DIVISION
06776-CR.
G.R. No. 163582 August 9, 2010
16 Fay v. Noia, 372 U.S. 391 (1963).
WILLIAM GOLANGCO CONSTRUCTION CORPORATION,
17Id. For an account of a convict who served twenty-two years Petitioner,
in prison before finally being released on habeas corpus or a
finding that he was denied due process, see Marino v. Ragen, vs.
332 U.S. 651 (1947).
RAY BURTON DEVELOPMENT CORPORATION,
18 The Bill of Rights (1967), p. 233. Respondent.

19 A Living Bill of Rights (1961), pp. 61, 62, 64. DECISION

PERALTA, J.:

This resolves the Petition for Review on Certiorari under Rule


45 of the Rules of Court, praying that the Decision1 of the Court
of Appeals (CA) dated December 19, 2003, holding that the
Construction Industry Arbitration Commission (CIAC) had no
jurisdiction over the dispute between herein parties, and the CA
Resolution2 dated May 24, 2004, denying herein petitioner's
motion for reconsideration, be reversed and set aside.

The undisputed facts, as accurately narrated in the CA


Decision, are as follows.

On July 20, 1995, petitioner Ray Burton Development


Corporation [herein respondent] (RBDC for brevity) and private
respondent William Golangco Construction Corporation [herein
petitioner] (WGCC) entered into a Contract for the construction
of the Elizabeth Place (Office/Residential Condominium).

On March 18, 2002, private respondent WGCC filed a


complaint with a request for arbitration with the Construction
Industry Arbitration Commission (hereinafter referred to as
CIAC). In its complaint, private respondent prayed that CIAC
render judgment ordering petitioner to pay private respondent
the amount of, to wit:

1. P24,703,132.44 for the unpaid balance on the contract price;

2. P10,602,670.25 for the unpaid balance on the labor cost


adjustment;

3. P9,264,503.70 for the unpaid balance of additive works;

4. P2,865,615.10 for extended overhead expenses;

5. P1,395,364.01 for materials cost adjustment and trade


contractors' utilities expenses;
ADR || First Batch 73

6. P4,835,933.95 for interest charges on unpaid overdue dispute, the same does not exclude disputes relating to claims
billings on labor cost adjustment and change orders. for payment in as much as the said dispute originates from
execution of the works. As such, the subject dispute falls within
or for a total of Fifty Three Million Six Hundred Sixty-Seven the original and exclusive jurisdiction of the CIAC.
Thousand Two Hundred Nineteen and 45/xx (P53,667,219.45)
and interest charges based on the prevailing bank rates on the WHEREFORE, in view of the foregoing, Respondent's Motion
foregoing amount from March 1, 2002 and until such time as to Dismiss is DENIED for lack of merit. Respondent is given
the same shall be fully paid. anew an inextendible period of ten (10) days from receipt
hereof within which to file its Answer and nominees for the
On April 12, 2002, petitioner RBDC filed a Motion to Dismiss Arbitral Tribunal. If Respondent shall fail to comply within the
the aforesaid complaint on the ground of lack of jurisdiction. It is prescribed period, the Commission shall proceed with
petitioner's contention that the CIAC acquires jurisdiction over arbitration in accordance with its Rules. x x x
disputes arising from or connected with construction contracts
only when the parties to the contract agree to submit the same Thereafter, petitioner filed a Motion to Suspend Proceedings
to voluntary arbitration. In the contract between petitioner and praying that the CIAC order a suspension of the proceedings in
private respondent, petitioner claimed that only disputes by Case No. 13-2002 until the resolution of the negotiations
reason of differences in interpretation of the contract between the parties, and consequently, that the period to file an
documents shall be deemed subject to arbitration. Answer be held in abeyance.

Private respondent filed a Comment and Opposition to the Private respondent filed an Opposition to the aforesaid Motion
aforesaid Motion dated April 15, 2002. Private respondent and a Counter-Motion to Declare respondent to Have Refused
averred that the claims set forth in the complaint require to Arbitrate and to Proceed with Arbitration Ex Parte.
contract interpretation and are thus cognizable by the CIAC
pursuant to the arbitration clause in the construction contract On May 24, 2002 the CIAC issued an Order, the pertinent
between the parties. Moreover, even assuming that the claims portion of which reads:
do not involve differing contract interpretation, they are still
cognizable by the CIAC as the arbitration clause mandates their
In view of the foregoing, Respondent's (petitioner's) Motion to
direct filing therewith.
Suspend Proceedings is DENIED. Accordingly, respondent is
hereby given a non-extendible period of five (5) days from
On May 6, 2002, the CIAC rendered an Order the pertinent receipt thereof within which to submit its Answer and nominees
portion of which reads as follows: for the Arbitral Tribunal. In default thereof, claimant's (private
respondent's) Counter-Motion is deemed granted and
The Commission has taken note of the foregoing arguments of arbitration shall proceed in accordance with the CIAC Rules
the parties. After due deliberations, the Commission resolved to Governing Construction Arbitration.
DENY Respondent's motion on the following grounds:
SO ORDERED. x x x
[1] Clause 17.2 of Art. XVII of the Contract Agreement explicitly
provides that "any dispute" arising under the construction On June 3, 2002, petitioner RBDC filed [with the Court of
contract shall be submitted to "the Construction Arbitration Appeals (CA)] a petition for Certiorari and Prohibition with
Authority created by the Government." Even without this prayer for the issuance of a temporary restraining order and a
provision, the bare agreement to submit a construction dispute writ of preliminary injunction. Petitioner contended that CIAC
to arbitration vests in the Commission original and exclusive acted without or in excess of its jurisdiction when it issued the
jurisdiction by virtue of Sec. 4 of Executive Order No. 1008, questioned order despite the clear showing that there is lack of
whether or not a dispute involves a collection of sum of money jurisdiction on the issue submitted by private respondent for
or contract interpretation as long as the same arises from, or in arbitration.3
connection with, contracts entered into by the parties involved.
The Supreme Court jurisprudence on Tesco vs. Vera case
On December 19, 2003, the CA rendered the assailed Decision
referred to by respondent is no longer controlling as the same
granting the petition for certiorari, ruling that the CIAC had no
was based on the old provision of Article III, Sec. 1 of the CIAC
jurisdiction over the subject matter of the case because the
Rules which has long been amended.
parties agreed that only disputes regarding differences in
interpretation of the contract documents shall be submitted for
[2] The issue raised by Respondent in its Motion to Dismiss is arbitration, while the allegations in the complaint make out a
similar to the issue set forth in CA-G.R. Sp. No. 67367, case for collection of sum of money. Petitioner moved for
Continental Cement Corporation vs. CIAC and EEI Corporation, reconsideration of said ruling, but the same was denied in a
where the appellate court upheld the ruling of the CIAC thereon Resolution dated May 24, 2004.
that since the parties agreed to submit to arbitration any
ADR || First Batch 74

Hence, this petition where it is alleged that: The aforementioned issues boil down to (1) whether the CA
acted with grave abuse of discretion in failing to dismiss the
I. petition for certiorari filed by herein respondent, in view of the
latter's failure to file a motion for reconsideration of the assailed
CIAC Order and for failure to attach to the petition the relevant
THE COURT OF APPEALS ACTED WITH GRAVE ABUSE OF
pleadings in CIAC Case No. 13-2002; and (2) whether the CA
DISCRETION IN FAILING TO DISMISS PRIVATE
gravely erred in not upholding the jurisdiction of the CIAC over
RESPONDENT RBDC'S PETITION IN CA-G.R. SP NO. 70959
the subject complaint.
OUTRIGHT IN VIEW OF RBDC'S FAILURE TO FILE A
MOTION FOR RECONSIDERATION OF THE CIAC'S ORDER,
AS WELL AS FOR RBDC'S FAILURE TO ATTACH TO THE Petitioner is correct that it was grave error for the CA to have
PETITION THE RELEVANT PLEADINGS IN CIAC CASE NO. given due course to respondent's petition for certiorari despite
13-2002, IN VIOLATION OF THE REQUIREMENT UNDER its failure to attach copies of relevant pleadings in CIAC Case
RULE 65, SECTIONS 1 AND 2, PARAGRAPH 2 THEREOF, No. 13-2002. In Tagle v. Equitable PCI Bank,5 the party filing
AND RULE 46, SECTION 3, PARAGRAPH 2 THEREOF. the petition for certiorari before the CA failed to attach the
Motion to Stop Writ of Possession and the Order denying the
same. On the ground of non-compliance with the rules, the CA
II.
dismissed said petition for certiorari. When the case was
elevated to this Court via a petition for certiorari, the same was
THE COURT OF APPEALS ERRED GRAVELY IN NOT likewise dismissed. In said case, the Court emphasized the
RULING THAT THE CIAC HAS JURISDICTION OVER importance of complying with the formal requirements for filing
WGCC'S CLAIMS, WHICH ARE IN THE NATURE OF a petition for certiorari and held as follows:
ARBITRABLE DISPUTES COVERED BY CLAUSE 17.1 OF
ARTICLE XVII INVOLVING CONTRACT INTERPRETATION.
x x x Sec. 1, Rule 65, in relation to Sec. 3, Rule 46, of the
Revised Rules of Court. Sec. 1 of Rule 65 reads:
xxxx
SECTION 1. Petition for certiorari. When any tribunal, board
III. or officer exercising judicial or quasi-judicial functions has acted
without or in excess of its or his jurisdiction, or with grave abuse
THE COURT OF APPEALS ERRED GRAVELY IN FAILING TO of discretion amounting to lack or excess of [its or his]
DISCERN THAT CLAUSE 17.2 OF ARTICLE XVII CANNOT jurisdiction, and there is no appeal, or any plain, speedy, and
BE TREATED AS BEING "LIMITED TO DISPUTES ARISING adequate remedy in the ordinary course of law, a person
FROM INTERPRETATION OF THE CONTRACT." aggrieved thereby may file a verified petition in the proper court,
alleging the facts with certainty and praying that judgment be
xxxx rendered annulling or modifying the proceedings of such
tribunal, board or officer, and granting such incidental reliefs as
IV. law and justice may require.

THE COURT OF APPEALS ERRED GRAVELY IN NOT The petition shall be accompanied by a certified true copy of
RULING THAT RBDC IS ESTOPPED FROM DISPUTING THE the judgment, order or resolution subject thereof, copies of all
JURISDICTION OF THE CIAC. pleadings and documents relevant and pertinent thereto, and a
sworn certification of non-forum shopping as provided in the
third paragraph of Section 3, Rule 46. (Emphasis supplied.)
xxxx
And Sec. 3 of Rule 46 provides:
V.
SEC. 3. Contents and filing of petition; effect of non-compliance
FINALLY, THE COURT OF APPEALS COMMITTED GRAVE
with requirements. The petition shall contain the full names
ABUSE OF DISCRETION IN REFUSING TO PAY HEED TO
and actual addresses of all the petitioners and respondents, a
THE DECLARATION IN EXECUTIVE ORDER NO. 1008 THAT
concise statement of the matters involved, the factual
THE POLICY OF THE STATE IS IN FAVOR OF
background of the case, and the grounds relied upon for the
ARBITRATION OF CONSTRUCTION DISPUTES, WHICH
relief prayed for.
POLICY HAS BEEN REINFORCED FURTHER BY THE
RECENT PASSAGE OF THE "ALTERNATIVE DISPUTE
RESOLUTION ACT OF 2004"(R.A. NO. 9285).4 In actions filed under Rule 65, the petition shall further indicate
the material dates showing when notice of the judgment or final
order or resolution subject thereof was received, when a motion
The petition is meritorious.
for new trial or reconsideration, if any, was filed and when
ADR || First Batch 75

notice of the denial thereof was received. Even on the main issue regarding the CIAC's jurisdiction, the
CA erred in ruling that said arbitration body had no jurisdiction
It shall be filed in seven (7) clearly legible copies together with over the complaint filed by herein petitioner. There is no
proof of service thereof on the respondent with the original copy question that, as provided under Section 4 of Executive Order
intended for the court indicated as such by the petitioner and No. 1008, also known as the "Construction Industry Arbitration
shall be accompanied by a clearly legible duplicate original or Law," the CIAC has original and exclusive jurisdiction over
certified true copy of the judgment, order, resolution, or ruling disputes arising from, or connected with, contracts entered into
subject thereof, such material portions of the record as are by parties involved in construction in the Philippines and all that
referred to therein, and other documents relevant or pertinent is needed for the CIAC to acquire jurisdiction is for the parties
thereto. The certification shall be accomplished by the proper to agree to submit the same to voluntary arbitration.
clerk of court or by his duly-authorized representative, or by the Nevertheless, respondent insists that the only disputes it
proper officer of the court, tribunal, agency or office involved or agreed to submit to voluntary arbitration are those arising from
by his duly authorized representative. The other requisite interpretation of contract documents. It argued that the claims
number of copies of the petition shall be accompanied by alleged in petitioner's complaint are not disputes arising from
clearly legible plain copies of all documents attached to the interpretation of contract documents; hence, the CIAC cannot
original. assume jurisdiction over the case.

xxxx Respondent's contention is tenuous.

The failure of the petitioner to comply with any of the foregoing The contract between herein parties contained an arbitration
requirements shall be sufficient ground for the dismissal of the clause which reads as follows:
petition. (Emphasis supplied.)
17.1.1. Any dispute arising in the course of the execution of this
The afore-quoted provisions are plain and unmistakable. Contract by reason of differences in interpretation of the
Failure to comply with the requirement that the petition be Contract Documents which the OWNER and the
accompanied by a duplicate original or certified true copy of the CONTRACTOR are unable to resolve between themselves,
judgment, order, resolution or ruling being challenged is shall be submitted by either party for resolution or decision, x x
sufficient ground for the dismissal of said petition. x to a Board of Arbitrators composed of three (3) members, to
Consequently, it cannot be said that the Court of Appeals be chosen as follows:
acted with grave abuse of discretion amounting to lack or
excess of jurisdiction in dismissing the petition x x x for One (1) member each shall be chosen by the OWNER and the
non-compliance with Sec. 1, Rule 65, in relation to Sec. 3, CONTRACTOR. The said two (2) members, in turn, shall select
Rule 46, of the Revised Rules of Court.6 a third member acceptable to both of them. The decision of the
Board of Arbitrators shall be rendered within fifteen (15) days
In the present case, herein petitioner (private respondent from the first meeting of the Board. The decision of the Board of
below) strongly argued against the CA's granting due course to Arbitrators when reached through the affirmative vote of at least
the petition, pointing out that pertinent pleadings such as the two (2) of its members shall be final and binding upon the
Complaint before the CIAC, herein respondent's Motion to OWNER and the CONTRACTOR.
Dismiss, herein petitioner's Comment and Opposition (Re:
Motion to Dismiss), and the Motion to Suspend Proceedings, 17.2 Matters not otherwise provided for in this Contract or by
have not been attached to the petition. Herein respondent special agreement of the parties shall be governed by the
(petitioner before the CA) argued in its Reply7 before the CA provisions of the Construction Arbitration Law of the
that it did not deem such pleadings or documents germane to Philippines. As a last resort, any dispute which is not resolved
the petition. However, in the CA Resolution8 dated July 4, 2002, by the Board of Arbitrators shall be submitted to the
the appellate court itself revealed the necessity of such Construction Arbitration Authority created by the government.9
documents by ordering the submission of copies of pleadings
relevant to the petition. Indeed, such pleadings are necessary In gist, the foregoing provisions mean that herein parties
for a judicious resolution of the issues raised in the petition and agreed to submit disputes arising by reason of differences in
should have been attached thereto. As mandated by the rules, interpretation of the contract to a Board of Arbitrators the
the failure to do so is sufficient ground for the dismissal of the composition of which is mutually agreed upon by the parties,
petition. The CA did not give any convincing reason why the and, as a last resort, any other dispute which had not been
rule regarding requirements for filing a petition should be resolved by the Board of Arbitrators shall be submitted to the
relaxed in favor of herein respondent. Therefore, it was error for Construction Arbitration Authority created by the government,
the CA to have given due course to the petition for certiorari which is no other than the CIAC. Moreover, other matters not
despite herein respondent's failure to comply with the dealt with by provisions of the contract or by special
requirements set forth in Section 1, Rule 65, in relation to agreements shall be governed by provisions of the Construction
Section 3, Rule 46, of the Revised Rules of Court. Industry Arbitration Law, or Executive Order No. 1008.
ADR || First Batch 76

The Court finds that petitioner's claims that it is entitled to unambiguous and unequivocal, application, not interpretation
payment for several items under their contract, which claims thereof, is imperative.1avvphi1

are, in turn, refuted by respondent, involves a "dispute arising


from differences in interpretation of the contract." Verily, the Hence, the bare fact that the parties herein incorporated an
matter of ascertaining the duties and obligations of the parties arbitration clause in the EPCC is sufficient to vest the CIAC with
under their contract all involve interpretation of the provisions of jurisdiction over any construction controversy or claim between
the contract. Therefore, if the parties cannot see eye to eye the parties. The arbitration clause in the construction contract
regarding each others obligations, i.e., the extent of work to be ipso facto vested the CIAC with jurisdiction. This rule applies,
expected from each of the parties and the valuation thereof, regardless of whether the parties specifically choose another
this is properly a dispute arising from differences in the forum or make reference to another arbitral body. Since the
interpretation of the contract. jurisdiction of CIAC is conferred by law, it cannot be subjected
to any condition; nor can it be waived or diminished by the
Note, further, that in respondent's letter10 dated February 14, stipulation, act or omission of the parties, as long as the parties
2000, it stated that disputed items of work such as Labor Cost agreed to submit their construction contract dispute to
Adjustment and interest charges, retention, processing of arbitration, or if there is an arbitration clause in the construction
payment on Cost Retained by WGCC, Determination of Cost of contract. The parties will not be precluded from electing to
Deletion for miscellaneous Finishing Works, are considered submit their dispute to CIAC, because this right has been
"unresolved dispute[s] as to the proper interpretation of our vested in each party by law.
respective obligations under the Contract," which should be
referred to the Board of Arbitrators. Even if the dispute subject xxxx
matter of said letter had been satisfactorily settled by herein
parties, the contents of the letter evinces respondent's frame of
It bears to emphasize that the mere existence of an
mind that the claims being made by petitioner in the complaint
arbitration clause in the construction contract is
subject of this petition, are indeed matters involving disputes
considered by law as an agreement by the parties to
arising from differences in interpretation.
submit existing or future controversies between them to
CIAC jurisdiction, without any qualification or condition
Clearly, the subject matter of petitioner's claims arose from precedent. To affirm a condition precedent in the construction
differences in interpretation of the contract, and under the terms contract, which would effectively suspend the jurisdiction of the
thereof, such disputes are subject to voluntary arbitration. CIAC until compliance therewith, would be in conflict with the
Since, under Section 4 of Executive Order No. 1008 the CIAC recognized intention of the law and rules to automatically vest
shall have original and exclusive jurisdiction over disputes CIAC with jurisdiction over a dispute should the construction
arising from, or connected with, contracts entered into by contract contain an arbitration clause.
parties involved in construction in the Philippines and all that is
needed for the CIAC to acquire jurisdiction is for the parties to
Moreover, the CIAC was created in recognition of the
agree to submit the same to voluntary arbitration, there can be
contribution of the construction industry to national
no other conclusion but that the CIAC had jurisdiction over
development goals. Realizing that delays in the resolution of
petitioner's complaint. Furthermore, Section 1, Article III of the
construction industry disputes would also hold up the
CIAC Rules of Procedure Governing Construction Arbitration
development of the country, Executive Order No. 1008
(CIAC Rules) further provide that "[a]n arbitration clause in a
expressly mandates the CIAC to expeditiously settle
construction contract or a submission to arbitration of a
construction industry disputes and, for this purpose, vests in the
construction dispute shall be deemed an agreement to submit
CIAC original and exclusive jurisdiction over disputes arising
an existing or future controversy to CIAC jurisdiction,
from, or connected with, contracts entered into by the parties
notwithstanding the reference to a different arbitration institution
involved in construction in the Philippines.12
or arbitral body in such contract or submission." Thus, even if
there is no showing that petitioner previously brought its claims
before a Board of Arbitrators constituted under the terms of the Thus, there is no question that in this case, the CIAC properly
contract, this circumstance would not divest the CIAC of took cognizance of petitioner's complaint as it had jurisdiction
jurisdiction. In HUTAMA-RSEA Joint Operations, Inc. v. Citra over the same.
Metro Manila Tollways Corporation,11 the Court held that:
IN VIEW OF THE FOREGOING, the Petition is GRANTED. The
Under Section 1, Article III of the CIAC Rules, an arbitration Decision of the Court of Appeals, dated December 19, 2003,
clause in a construction contract shall be deemed as an and its Resolution dated May 24, 2004 in CA-G.R. SP No.
agreement to submit an existing or future controversy to CIAC 70959 are REVERSED and SET ASIDE. The Order of the
jurisdiction, "notwithstanding the reference to a different Construction Industry Arbitration Commission is REINSTATED.
arbitration institution or arbitral body in such contract x x x."
Elementary is the rule that when laws or rules are clear, it is SO ORDERED.
incumbent on the court to apply them. When the law (or rule) is
ADR || First Batch 77

DIOSDADO M. PERALTA 3 Rollo, pp. 88-91.

Associate Justice 4 Id. at 34-36.

WE CONCUR: 5 G.R. No. 172299, April 22, 2008, 552 SCRA 424.

ANTONIO T. CARPIO 6 Id. at 442-444. (Emphasis supplied.)

Associate Justice 7 CA rollo, pp. 293-303.

Chairperson 8 Id. at 62-63.

ANTONIO EDUARDO B. NACHURA 9 Rollo, pp. 494-495.


ROBERTO A. ABAD

Associate Justice 10 Id. at 270-271.Associate Justice


JOSE CATRAL MENDOZA
11 G.R. No. 180640, April 24, 2009, 586 SCRA 746.
Associate Justice
12 Id. at 760-763. (Emphasis supplied.)
ATTESTATION

I attest that the conclusions in the above Decision had been


reached in consultation before the case was assigned to the
writer of the opinion of the Courts Division.

ANTONIO T. CARPIO

Associate Justice

Second Division, Chairperson

CERTIFICATION

Pursuant to Section 13, Article VIII of the Constitution and the


Division Chairpersons Attestation, I certify that the conclusions
in the above Decision had been reached in consultation before
the case was assigned to the writer of the opinion of the Courts
Division.

RENATO C. CORONA

Chief Justice

Footnotes

1Penned by Associate Justice Eloy R. Bello, Jr., with Associate


Justices Amelita G. Tolentino and Arturo D. Brion (now a
member of this Court), concurring; rollo, pp. 88-94.

2 Id. at 96.
ADR || First Batch 78

Republic of the Philippines published an invitation to pre-qualify and bid for the supply of
SUPREME COURT the needed machine readable passports and visas, and
Manila conducted the public bidding for the MRP/V Project on January
FIRST DIVISION 10, 2000. Several bidders responded and BCA was among
those that pre-qualified and submitted its technical and financial
G.R. No. 176657 September 1, 2010 proposals. On June 29, 2000, the PBAC found BCAs bid to be
the sole complying bid; hence, it permitted the DFA to engage
in direct negotiations with BCA. On even date, the PBAC
DEPARTMENT OF FOREIGN AFFAIRS and BANGKO
recommended to the DFA Secretary the award of the MRP/V
SENTRAL NG PILIPINAS, Petitioners,
Project to BCA on a BOT arrangement.
vs.
In compliance with the Notice of Award dated September 29,
2000 and Section 11.3, Rule 11 of the IRR of the BOT Law,6
HON. FRANCO T. FALCON, IN HIS CAPACITY AS THE BCA incorporated a project company, the Philippine Passport
PRESIDING JUDGE OF BRANCH 71 OF THE REGIONAL Corporation (PPC) to undertake and implement the MRP/V
TRIAL COURT IN PASIG CITY and BCA INTERNATIONAL Project.
CORPORATION, Respondents.
On February 8, 2001, a Build-Operate-Transfer Agreement7
DECISION (BOT Agreement) between the DFA and PPC was signed by
DFA Acting Secretary Lauro L. Baja, Jr. and PPC President
LEONARDO-DE CASTRO, J.: Bonifacio Sumbilla. Under the BOT Agreement, the MRP/V
Project was defined as follows:
Before the Court is a Petition for Certiorari and prohibition
under Rule 65 of the Rules of Court with a prayer for the Section 1.02 MRP/V Project refers to all the activities and
issuance of a temporary restraining order and/or a writ of services undertaken in the fulfillment of the Machine Readable
preliminary injunction filed by petitioners Department of Foreign Passport and Visa Project as defined in the Request for
Affairs (DFA) and Bangko Sentral ng Pilipinas (BSP). Proposals (RFP), a copy of which is hereto attached as Annex
Petitioners pray that the Court declare as null and void the A, including but not limited to project financing, systems
Order1 dated February 14, 2007 of respondent Judge Franco T. development, installation and maintenance in the Philippines
Falcon (Judge Falcon) in Civil Case No. 71079, which granted and Foreign Service Posts (FSPs), training of DFA personnel,
the application for preliminary injunction filed by respondent provision of all project consumables (related to the production
BCA International Corporation (BCA). Likewise, petitioners of passports and visas, such as printer supplies, etc.), scanning
seek to prevent respondent Judge Falcon from implementing of application and citizenship documents, creation of data
the corresponding Writ of Preliminary Injunction dated February bases, issuance of machine readable passports and visas, and
23, 20072 issued pursuant to the aforesaid Order. site preparation in the Central Facility and Regional Consular
Offices (RCOs) nationwide.8
The facts of this case, as culled from the records, are as
follows: On April 5, 2002, former DFA Secretary Teofisto T. Guingona
and Bonifacio Sumbilla, this time as BCA President, signed an
Being a member state of the International Civil Aviation Amended BOT Agreement9 in order to reflect the change in the
Organization (ICAO),3 the Philippines has to comply with the designation of the parties and to harmonize Section 11.3 with
commitments and standards set forth in ICAO Document No. Section 11.810 of the IRR of the BOT Law. The Amended BOT
93034 which requires the ICAO member states to issue Agreement was entered into by the DFA and BCA with the
machine readable travel documents (MRTDs)5 by April 2010. conformity of PPC.

Thus, in line with the DFAs mandate to improve the passport The two BOT Agreements (the original version signed on
and visa issuance system, as well as the storage and retrieval February 8, 2001 and the amended version signed April 5,
of its related application records, and pursuant to our 2002) contain substantially the same provisions except for
governments ICAO commitments, the DFA secured the seven additional paragraphs in the whereas clauses and two
approval of the President of the Philippines, as Chairman of the new provisions Section 9.05 on Performance and Warranty
Board of the National Economic and Development Authority Securities and Section 20.15 on Miscellaneous Provisions. The
(NEDA), for the implementation of the Machine Readable two additional provisions are quoted below:
Passport and Visa Project (the MRP/V Project) under the Build-
Operate-and-Transfer (BOT) scheme, provided for by Republic Section 9.05. The PPC has posted in favor of the DFA the
Act No. 6957, as amended by Republic Act No. 7718 (the BOT performance security required for Phase 1 of the MRP/V
Law), and its Implementing Rules and Regulations (IRR). Thus, Project and shall be deemed, for all intents and purposes, to be
a Pre-qualification, Bids and Awards Committee (PBAC) full compliance by BCA with the provisions of this Article 9.
ADR || First Batch 79

xxxx Regional Consular Offices This phase represents the


replication of the systems as approved from the Central Facility
Section 20.15 It is clearly and expressly understood that BCA to the RCOs throughout the country, as identified in the RFP
may assign, cede and transfer all of its rights and obligations [Request for Proposal]. The approved systems are those
under this Amended BOT Agreement to PPC, as fully as if PPC implemented, evaluated, and finally approved by DFA as
is the original signatory to this Amended BOT Agreement, described in Phase 1. The Project Proponent [BCA] will be
provided however that BCA shall nonetheless be jointly and permitted to begin site preparation and the scanning and
severally liable with PPC for the performance of all the database building operations in all offices as soon as the plans
obligations and liabilities under this Amended BOT are agreed upon and accepted. This includes site preparation
Agreement.11 and database building operations in these Phase-3 offices.

Also modified in the Amended BOT Agreement was the Project Within six (6) months from issuance of CA for Phase 2, the
Completion date of the MRP/V Project which set the completion Project Proponent [BCA] shall complete site preparation and
of the implementation phase of the project within 18 to 23 implementation of the approved systems in the ten (10) RCOs,
months from the date of effectivity of the Amended BOT including a fully functional network connection between all
Agreement as opposed to the previous period found in the equipment at the Central Facility and the RCOs.
original BOT Agreement which set the completion within 18 to
23 months from receipt of the NTP (Notice to Proceed) in Phase 4. Full Implementation, including all Foreign Service
accordance with the Project Master Plan. Posts Within three (3) to eight (8) months from issuance of
the CA for Phase-3, the Project Proponent [BCA] shall
On April 12, 2002, an Assignment Agreement12 was executed complete all preparations and fully implement the approved
by BCA and PPC, whereby BCA assigned and ceded its rights, systems in the eighty (80) FSPs, including a fully functional
title, interest and benefits arising from the Amended BOT network connection between all equipment at the Central
Agreement to PPC. Facility and the FSPs. Upon satisfactory completion of Phase 4,
a CA shall be issued by the DFA.
As set out in Article 8 of the original and the Amended BOT
Agreement, the MRP/V Project was divided into six phases: Phase 5. In Service Phase Operation and maintenance of
the complete MRP/V Facility to provide machine readable
passports and visas in all designated locations around the
Phase 1. Project Planning Phase The Project Proponent
world.
[BCA] shall prepare detailed plans and specifications in
accordance with Annex A of this [Amended] BOT Agreement
within three (3) months from issuance of the NTP (Notice to Phase 6. Transition/Turnover Transition/Turnover to the
Proceed) [from the date of effectivity of this Amended BOT DFA of all operations and equipment, to include an orderly
Agreement]. This phase shall be considered complete upon the transfer of ownership of all hardware, application system
review, acceptance and approval by the DFA of these plans software and its source code and/or licenses (subject to Section
and the resulting Master Plan, including the Master Schedule, 5.02 [H]), peripherals, leasehold improvements, physical and
the business process specifications, the acceptance criteria, computer security improvements, Automated Fingerprint
among other plans. Identification Systems, and all other MRP/V facilities shall
commence at least six (6) months prior to the end of the
[Amended] BOT Agreement. The transition will include the
xxxx
training of DFA personnel who will be taking over the
responsibilities of system operation and maintenance from the
The DFA must approve all detailed plans as a condition Project Proponent [BCA]. The Project Proponent [BCA] shall
precedent to the issuance of the CA [Certificate of Acceptance] bear all costs related to this transfer.13 (Words in brackets
for Phase 1. appear in the Amended BOT Agreement)

Phase 2. Implementation of the MRP/V Project at the To place matters in the proper perspective, it should be pointed
Central Facility Within six (6) months from issuance of the out that both the DFA and BCA impute breach of the Amended
CA for Phase 1, the PROJECT PROPONENT [BCA] shall BOT Agreement against each other.
complete the implementation of the MRP/V Project in the DFA
Central Facility, and establish the network design between the
According to the DFA, delays in the completion of the phases
DFA Central Facility, the ten (10) RCOs [Regional Consular
permeated the MRP/V Project due to the submission of
Offices] and the eighty (80) FSPs [Foreign Service Posts].
deficient documents as well as intervening issues regarding
BCA/PPCs supposed financial incapacity to fully implement the
xxxx project.

Phase 3. Implementation of the MRP/V Project at the


ADR || First Batch 80

On the other hand, BCA contends that the DFA failed to regarding the true ownership and control of PPC. The DFA
perform its reciprocal obligation to issue to BCA a Certificate of implied that the disputes among the shareholders of PPC and
Acceptance of Phase 1 within 14 working days of operation between PPC and BCA appeared to be part of the reason for
purportedly required by Section 14.04 of the Amended BOT the hampered implementation of the MRP/V Project.
Agreement. BCA bewailed that it took almost three years for the
DFA to issue the said Certificate allegedly because every BCA, in turn, submitted various letters and documents to prove
appointee to the position of DFA Secretary wanted to review its financial capability to complete the MRP/V Project.20
the award of the project to BCA. BCA further alleged that it was However, the DFA claimed these documents were
the DFAs refusal to approve the location of the DFA Central unsatisfactory or of dubious authenticity. Then on August 1,
Facility which prevented BCA from proceeding with Phase 2 of 2005, BCA terminated its Assignment Agreement with PPC and
the MRP/V Project. notified the DFA that it would directly implement the MRP/V
Project.21 BCA further claims that the termination of the
Later, the DFA sought the opinion of the Department of Finance Assignment Agreement was upon the instance, or with the
(DOF) and the Department of Justice (DOJ) regarding the conformity, of the DFA, a claim which the DFA disputed.
appropriate legal actions in connection with BCAs alleged
delays in the completion of the MRP/V Project. In a Letter dated On December 9, 2005, the DFA sent a Notice of Termination22
February 21, 2005,14 the DOJ opined that the DFA should issue to BCA and PPC due to their alleged failure to submit proof of
a final demand upon BCA to make good on its obligations, financial capability to complete the entire MRP/V Project in
specifically on the warranties and responsibilities regarding the accordance with the financial warranty under Section 5.02(A) of
necessary capitalization and the required financing to carry out the Amended BOT Agreement. The Notice states:
the MRP/V Project. The DOJ used as basis for said
recommendation, the Letter dated April 19, 2004 15 of DOF
After a careful evaluation and consideration of the matter,
Secretary Juanita Amatong to then DFA Secretary Delia Albert
including the reasons cited in your letters dated March 3, May
stating, among others, that BCA may not be able to infuse more
3, and June 20, 2005, and upon the recommendation of the
capital into PPC to use for the completion of the MRP/V Project.
Office of the Solicitor General (OSG), the Department is of the
view that your continuing default in complying with the requisite
Thus, on February 22, 2005, DFA sent a letter16 to BCA, bank guarantee and/or credit facility, despite repeated notice
through its project company PPC, invoking BCAs financial and demand, is legally unjustified.
warranty under Section 5.02(A) of the Amended BOT
Agreement.17 The DFA required BCA to submit (a) proof of
In light of the foregoing considerations and upon the instruction
adequate capitalization (i.e., full or substantial payment of stock
of the Secretary of Foreign Affairs, the Department hereby
subscriptions); (b) a bank guarantee indicating the availability of
formally TERMINATE (sic) the Subject Amended BOT
a credit facility of P700 million; and (c) audited financial
Agreement dated 5 April 2005 (sic)23 effective 09 December
statements for the years 2001 to 2004.
2005. Further, and as a consequence of this termination, the
Department formally DEMAND (sic) that you pay within ten (10)
In reply to DFAs letter, BCA, through PPC, informed the former days from receipt hereof, liquidated damages equivalent to the
of its position that its financial capacity was already passed corresponding performance security bond that you had posted
upon during the prequalification process and that the Amended for the MRP/V Project.
BOT Agreement did not call for any additional financial
requirements for the implementation of the MRP/V Project.
Please be guided accordingly.
Nonetheless, BCA submitted its financial statements for the
years 2001 and 2002 and requested for additional time within
which to comply with the other financial requirements which the On December 14, 2005, BCA sent a letter24 to the DFA
DFA insisted on.18 demanding that it immediately reconsider and revoke its
previous notice of termination, otherwise, BCA would be
compelled to declare the DFA in default pursuant to the
According to the DFA, BCAs financial warranty is a continuing
Amended BOT Agreement. When the DFA failed to respond to
warranty which requires that it shall have the necessary
said letter, BCA issued its own Notice of Default dated
capitalization to finance the MRP/V Project in its entirety and
December 22, 200525 against the DFA, stating that if the default
not on a "per phase" basis as BCA contends. Only upon
is not remedied within 90 days, BCA will be constrained to
sufficient proof of its financial capability to complete and
terminate the MRP/V Project and hold the DFA liable for
implement the whole project will the DFAs obligation to choose
damages.
and approve the location of its Central Facility arise. The DFA
asserted that its approval of a Central Facility site was not
ministerial and upon its review, BCAs proposed site for the BCAs request for mutual discussion under Section 19.01 of the
Central Facility was purportedly unacceptable in terms of Amended BOT Agreement26 was purportedly ignored by the
security and facilities. Moreover, the DFA allegedly received DFA and left the dispute unresolved through amicable means
conflicting official letters and notices19 from BCA and PPC within 90 days. Consequently, BCA filed its Request for
ADR || First Batch 81

Arbitration dated April 7, 200627 with the Philippine Dispute to submit its Answer to the Request for Arbitration within 30
Resolution Center, Inc. (PDRCI), pursuant to Section 19.02 of days from receipt of said letter and also requested both the
the Amended BOT Agreement which provides: DFA and BCA to nominate their chosen arbitrator within the
same period of time.
Section 19.02 Failure to Settle Amicably If the Dispute
cannot be settled amicably within ninety (90) days by mutual Initially, the DFA, through a letter dated May 22, 2006,31
discussion as contemplated under Section 19.01 herein, the requested for an extension of time to file its answer, "without
Dispute shall be settled with finality by an arbitrage tribunal prejudice to jurisdictional and other defenses and objections
operating under International Law, hereinafter referred to as the available to it under the law." Subsequently, however, in a letter
"Tribunal", under the UNCITRAL Arbitration Rules contained in dated May 29, 2006,32 the DFA declined the request for
Resolution 31/98 adopted by the United Nations General arbitration before the PDRCI. While it expressed its willingness
Assembly on December 15, 1976, and entitled "Arbitration to resort to arbitration, the DFA pointed out that under Section
Rules on the United Nations Commission on the International 19.02 of the Amended BOT Agreement, there is no mention of
Trade Law". The DFA and the BCA undertake to abide by and a specific body or institution that was previously authorized by
implement the arbitration award. The place of arbitration shall the parties to settle their dispute. The DFA further claimed that
be Pasay City, Philippines, or such other place as may mutually the arbitration of the dispute should be had before an ad hoc
be agreed upon by both parties. The arbitration proceeding arbitration body, and not before the PDRCI which has as its
shall be conducted in the English language.28 accredited arbitrators, two of BCAs counsels of record.
Likewise, the DFA insisted that PPC, allegedly an
As alleged in BCAs Request for Arbitration, PDRCI is a non- indispensable party in the instant case, should also participate
stock, non-profit organization composed of independent in the arbitration.
arbitrators who operate under its own Administrative Guidelines
and Rules of Arbitration as well as under the United Nations The DFA then sought the opinion of the DOJ on the Notice of
Commission on the International Trade Law (UNCITRAL) Termination dated December 9, 2005 that it sent to BCA with
Model Law on International Commercial Arbitration and other regard to the MRP/V Project.
applicable laws and rules. According to BCA, PDRCI can act as
an arbitration center from whose pool of accredited arbitrators In DOJ Opinion No. 35 (2006) dated May 31, 2006,33 the DOJ
both the DFA and BCA may select their own nominee to concurred with the steps taken by the DFA, stating that there
become a member of the arbitral tribunal which will render the was basis in law and in fact for the termination of the MRP/V
arbitration award. Project. Moreover, the DOJ recommended the immediate
implementation of the project (presumably by a different
BCAs Request for Arbitration filed with the PDRCI sought the contractor) at the soonest possible time.
following reliefs:
Thereafter, the DFA and the BSP entered into a Memorandum
1. A judgment nullifying and setting aside the Notice of of Agreement for the latter to provide the former passports
Termination dated December 9, 2005 of Respondent [DFA], compliant with international standards. The BSP then solicited
including its demand to Claimant [BCA] to pay liquidated bids for the supply, delivery, installation and commissioning of a
damages equivalent to the corresponding performance security system for the production of Electronic Passport Booklets or e-
bond posted by Claimant [BCA]; Passports.34

2. A judgment (a) confirming the Notice of Default dated For BCA, the BSPs invitation to bid for the supply and
December 22, 2005 issued by Claimant [BCA] to Respondent purchase of e-Passports (the e-Passport Project) would only
[DFA]; and (b) ordering Respondent [DFA] to perform its further delay the arbitration it requested from the DFA.
obligation under the Amended BOT Agreement dated April 5, Moreover, this new e-Passport Project by the BSP and the DFA
2002 by approving the site of the Central Facility at the Star would render BCAs remedies moot inasmuch as the e-
Mall Complex on Shaw Boulevard, Mandaluyong City, within Passport Project would then be replacing the MRP/V Project
five days from receipt of the Arbitral Award; and which BCA was carrying out for the DFA.

3. A judgment ordering respondent [DFA] to pay damages to Thus, BCA filed a Petition for Interim Relief35 under Section 28
Claimant [BCA], reasonably estimated at P50,000,000.00 as of of the Alternative Dispute Resolution Act of 2004 (R.A. No.
this date, representing lost business opportunities; financing 9285),36 with the Regional Trial Court (RTC) of Pasig City,
fees, costs and commissions; travel expenses; legal fees and Branch 71, presided over by respondent Judge Falcon. In that
expenses; and costs of arbitration, including the fees of the RTC petition, BCA prayed for the following:
arbitrator/s.29
WHEREFORE, BCA respectfully prays that this Honorable
PDRCI, through a letter dated April 26, 2006,30 invited the DFA Court, before the constitution of the arbitral tribunal in PDRCI
ADR || First Batch 82

Case No. 30-2006/BGF, grant petitioner interim relief in the Project or any similar electronic passport or visa project, or if
following manner: such contract has been awarded, from implementing such or
similar projects.39 The trial court also set for hearing BCAs
(a) upon filing of this Petition, immediately issue an order application for preliminary injunction.
temporarily restraining Respondents [DFA and BSP], their
agents, representatives, awardees, suppliers and assigns (i) Consequently, the DFA filed a Motion for Reconsideration40 of
from awarding a new contract to implement the Project, or any the January 23, 2007 Order. The BSP, in turn, also sought to lift
similar electronic passport or visa project; or (ii) if such contract the TRO and to dismiss the petition. In its Urgent Omnibus
has been awarded, from implementing such Project or similar Motion dated February 1, 2007,41 the BSP asserted that BCA is
projects until further orders from this Honorable Court; not entitled to an injunction, as it does not have a clear right
which ought to be protected, and that the trial court has no
(b) after notice and hearing, issue a writ of preliminary jurisdiction to enjoin the implementation of the e-Passport
injunction ordering Respondents [DFA and BSP], their agents, Project which, the BSP alleged, is a national government
representatives, awardees, suppliers and assigns to desist (i) project under Republic Act No. 8975.
from awarding a new contract to implement the Project or any
similar electronic passport or visa project; or (ii) if such contract In the hearings set for BCAs application for preliminary
has been awarded, from implementing such Project or similar injunction, BCA presented as witnesses, Mr. Bonifacio
projects, and to maintain the status quo ante pending the Sumbilla, its President, Mr. Celestino Mercader, Jr. from the
resolution on the merits of BCAs Request for Arbitration; and Independent Verification and Validation Contractor
commissioned by the DFA under the Amended BOT
(c) render judgment affirming the interim relief granted to BCA Agreement, and DFA Assistant Secretary Domingo Lucenario,
until the dispute between the parties shall have been resolved Jr. as adverse party witness.
with finality.
The DFA and the BSP did not present any witness during the
BCA also prays for such other relief, just and equitable under hearings for BCAs application for preliminary injunction.
the premises.37 According to the DFA and the BSP, the trial court did not have
any jurisdiction over the case considering that BCA did not pay
the correct docket fees and that only the Supreme Court could
BCA alleged, in support for its application for a Temporary
issue a TRO on the bidding for a national government project
Restraining Order (TRO), that unless the DFA and the BSP
like the e-Passport Project pursuant to the provisions of
were immediately restrained, they would proceed to undertake
Republic Act No. 8975. Under Section 3 of Republic Act No.
the project together with a third party to defeat the reliefs BCA
8975, the RTC could only issue a TRO against a national
sought in its Request for Arbitration, thus causing BCA to suffer
government project if it involves a matter of extreme urgency
grave and irreparable injury from the loss of substantial
involving a constitutional issue, such that unless a TRO is
investments in connection with the implementation of the
issued, grave injustice and irreparable injury will arise.
MRP/V Project.

Thereafter, BCA filed an Omnibus Comment [on Opposition


Thereafter, the DFA filed an Opposition (to the Application for
and Supplemental Opposition (To the Application for
Temporary Restraining Order and/or Writ of Preliminary
Temporary Restraining Order and/or Writ of Preliminary
Injunction) dated January 18, 2007,38 alleging that BCA has no
Injunction)] and Opposition [to Motion for Reconsideration (To
cause of action against it as the contract between them is for
the Temporary Restraining Order dated January 23, 2007)] and
machine readable passports and visas which is not the same
Urgent Omnibus Motion [(i) To Lift Temporary Restraining
as the contract it has with the BSP for the supply of electronic
Order; and (ii) To Dismiss the Petition] dated January 31,
passports. The DFA also pointed out that the Filipino people
2007.42 The DFA and the BSP filed their separate Replies (to
and the governments international standing would suffer great
BCAs Omnibus Comment) dated February 9, 200743 and
damage if a TRO would be issued to stop the e-Passport
February 13, 2007,44 respectively.
Project. The DFA mainly anchored its opposition on Republic
Act No. 8975, which prohibits trial courts from issuing a TRO,
preliminary injunction or mandatory injunction against the On February 14, 2007, the trial court issued an Order granting
bidding or awarding of a contract or project of the national BCAs application for preliminary injunction, to wit:
government.
WHEREFORE, in view of the above, the court resolves that it
On January 23, 2007, after summarily hearing the parties oral has jurisdiction over the instant petition and to issue the
arguments on BCAs application for the issuance of a TRO, the provisional remedy prayed for, and therefore, hereby GRANTS
trial court ordered the issuance of a TRO restraining the DFA petitioners [BCAs] application for preliminary injunction.
and the BSP, their agents, representatives, awardees, suppliers Accordingly, upon posting a bond in the amount of Ten Million
and assigns from awarding a new contract to implement the Pesos (P10,000,000.00), let a writ of preliminary injunction
issue ordering respondents [DFA and BSP], their agents,
ADR || First Batch 83

representatives, awardees, suppliers and assigns to desist (i) Foreign Affairs and Bangko Sentral ng Pilipinas, and from
from awarding a new contract to implement the project or any conducting further proceedings in said case until further orders
similar electronic passport or visa project or (ii) if such contract from this Court.
has been awarded from implementing such project or similar
projects. BCA filed on April 2, 2007 its Comment with Urgent Motion to
Lift TRO,50 to which the DFA and the BSP filed their Reply
The motion to dismiss is denied for lack of merit. The motions dated August 14, 2007.51
for reconsideration and to lift temporary restraining Order are
now moot and academic by reason of the expiration of the In a Resolution dated June 4, 2007,52 the Court denied BCAs
TRO.45 motion to lift TRO. BCA filed another Urgent Omnibus Motion
dated August 17, 2007, for the reconsideration of the
On February 16, 2007, BCA filed an Amended Petition,46 Resolution dated June 4, 2007, praying that the TRO issued on
wherein paragraphs 3.3(b) and 4.3 were modified to add March 12, 2007 be lifted and that the petition be denied.
language to the effect that unless petitioners were enjoined
from awarding the e-Passport Project, BCA would be deprived In a Resolution dated September 10, 2007,53 the Court denied
of its constitutionally-protected right to perform its contractual BCAs Urgent Omnibus Motion and gave due course to the
obligations under the original and amended BOT Agreements instant petition. The parties were directed to file their respective
without due process of law. Subsequently, on February 26, memoranda within 30 days from notice of the Courts
2007, the DFA and the BSP received the Writ of Preliminary September 10, 2007 Resolution.
Injunction dated February 23, 2007.
Petitioners DFA and BSP submit the following issues for our
Hence, on March 2, 2007, the DFA and the BSP filed the consideration:
instant Petition for Certiorari47 and prohibition under Rule 65 of
the Rules of Court with a prayer for the issuance of a temporary
Issues
restraining order and/or a writ of preliminary injunction, imputing
grave abuse of discretion on the trial court when it granted
interim relief to BCA and issued the assailed Order dated I
February 14, 2007 and the writ of preliminary injunction dated
February 23, 2007. Whether or not the respondent judge gravely abused his
discretion amounting to lack or excess of jurisdiction when he
The DFA and the BSP later filed an Urgent Motion for Issuance issued the assailed order, which effectively enjoined the
of a Temporary Restraining Order and/or Writ of Preliminary implementation of the e-passport project -- A national
Injunction dated March 5, 2007.48 government project under Republic Act No. 8975.

On March 12, 2007, the Court required BCA to file its comment II
on the said petition within ten days from notice and granted the
Office of the Solicitor Generals urgent motion for issuance of a Whether or not the respondent judge acted with grave abuse of
TRO and/or writ of preliminary injunction,49 thus: discretion amounting to lack or excess of jurisdiction in granting
respondent BCAs "interim relief" inasmuch as:
After deliberating on the petition for certiorari and prohibition
with temporary restraining order and/or writ of preliminary (I) Respondent BCA has not established a clear right that can
injunction assailing the Order dated 14 February 2007 of the be protected by an injunction; and
Regional Trial Court, Branch 71, Pasig City, in Civil Case No.
71079, the Court, without necessarily giving due course thereto, (II) Respondent BCA has not shown that it will sustain grave
resolves to require respondents to COMMENT thereon (not to and irreparable injury that must be protected by an injunction.
file a motion to dismiss) within ten (10) days from notice. On the contrary, it is the Filipino people, who petitioners protect,
that will sustain serious and severe injury by the injunction.54
The Court further resolves to GRANT the Office of the Solicitor
Generals urgent motion for issuance of a temporary restraining At the outset, we dispose of the procedural objections of BCA
order and/or writ of preliminary injunction dated 05 March 2007 to the petition, to wit: (a) petitioners did not follow the hierarchy
and ISSUE a TEMPORARY RESTRAINING ORDER, as of courts by filing their petition directly with this Court, without
prayed for, enjoining respondents from implementing the filing a motion for reconsideration with the RTC and without
assailed Order dated 14 February 2007 and the Writ of filing a petition first with the Court of Appeals; (b) the person
Preliminary Injunction dated 23 February 2007, issued by who verified the petition for the DFA did not have personal
respondent Judge Franco T. Falcon in Civil Case No. 71079 knowledge of the facts of the case and whose appointment to
entitled BCA International Corporation vs. Department of his position was highly irregular; and (c) the verification by the
ADR || First Batch 84

Assistant Governor and General Counsel of the BSP of only evidence on this point. Good faith is always presumed.
selected paragraphs of the petition was with the purported Paragraph 3 of Mr. Zunigas verification indicates that his partial
intent to mislead this Court. verification is due to the fact that he is verifying only the
allegations in the petition peculiar to the BSP. We see no
Although the direct filing of petitions for certiorari with the reason to doubt that this is the true reason for his partial or
Supreme Court is discouraged when litigants may still resort to selective verification.
remedies with the lower courts, we have in the past overlooked
the failure of a party to strictly adhere to the hierarchy of courts In sum, BCA failed to successfully rebut the presumption that
on highly meritorious grounds. Most recently, we relaxed the the official acts (of Mr. Custodio and Mr. Zuniga) were done in
rule on court hierarchy in the case of Roque, Jr. v. Commission good faith and in the regular performance of official duty.58
on Elections,55 wherein we held: Even assuming the verifications of the petition suffered from
some defect, we have time and again ruled that "[t]he ends of
The policy on the hierarchy of courts, which petitioners indeed justice are better served when cases are determined on the
failed to observe, is not an iron-clad rule. For indeed the Court merits after all parties are given full opportunity to ventilate
has full discretionary power to take cognizance and assume their causes and defenses rather than on technicality or
jurisdiction of special civil actions for certiorari and mandamus some procedural imperfections."59 In other words, the Court
filed directly with it for exceptionally compelling reasons or if may suspend or even disregard rules when the demands of
warranted by the nature of the issues clearly and specifically justice so require.60
raised in the petition.56 (Emphases ours.)
We now come to the substantive issues involved in this case.
The Court deems it proper to adopt a similarly liberal attitude in
the present case in consideration of the transcendental On whether the trial court had jurisdiction to issue a writ of
importance of an issue raised herein. This is the first time that preliminary injunction in the present case
the Court is confronted with the question of whether an
information and communication technology project, which does In their petition, the DFA and the BSP argue that respondent
not conform to our traditional notion of the term "infrastructure," Judge Falcon gravely abused his discretion amounting to lack
is covered by the prohibition on the issuance of court or excess of jurisdiction when he issued the assailed orders,
injunctions found in Republic Act No. 8975, which is entitled which effectively enjoined the bidding and/or implementation of
"An Act to Ensure the Expeditious Implementation and the e-Passport Project. According to petitioners, this violated
Completion of Government Infrastructure Projects by the clear prohibition under Republic Act No. 8975 regarding the
Prohibiting Lower Courts from Issuing Temporary Restraining issuance of TROs and preliminary injunctions against national
Orders, Preliminary Injunctions or Preliminary Mandatory government projects, such as the e-Passport Project.
Injunctions, Providing Penalties for Violations Thereof, and for
Other Purposes." Taking into account the current trend of
The prohibition invoked by petitioners is found in Section 3 of
computerization and modernization of administrative and
Republic Act No. 8975, which reads:
service systems of government offices, departments and
agencies, the resolution of this issue for the guidance of the
bench and bar, as well as the general public, is both timely and Section 3. Prohibition on the Issuance of Temporary
imperative. Restraining Orders, Preliminary Injunctions and Preliminary
Mandatory Injunctions. No court, except the Supreme Court,
shall issue any temporary restraining order, preliminary
Anent BCAs claim that Mr. Edsel T. Custodio (who verified the
injunction or preliminary mandatory injunction against the
Petition on behalf of the DFA) did not have personal knowledge
government, or any of its subdivisions, officials or any person or
of the facts of the case and was appointed to his position as
entity, whether public or private, acting under the governments
Acting Secretary under purportedly irregular circumstances, we
direction, to restrain, prohibit or compel the following acts:
find that BCA failed to sufficiently prove such allegations. In any
event, we have previously held that "[d]epending on the nature
of the allegations in the petition, the verification may be based (a) Acquisition, clearance and development of the right-of-way
either purely on personal knowledge, or entirely on authentic and/or site or location of any national government project;
records, or on both sources."57 The alleged lack of personal
knowledge of Mr. Custodio (which, as we already stated, BCA (b) Bidding or awarding of contract/project of the national
failed to prove) would not necessarily render the verification government as defined under Section 2 hereof;
defective for he could have verified the petition purely on the
basis of authentic records. (c) Commencement, prosecution, execution, implementation,
operation of any such contract or project;
As for the assertion that the partial verification of Assistant
Governor and General Counsel Juan de Zuniga, Jr. was for the (d) Termination or rescission of any such contract/project; and
purpose of misleading this Court, BCA likewise failed to adduce
ADR || First Batch 85

(e) The undertaking or authorization of any other lawful activity (b) all projects covered by R.A. No. 6975, as amended by R.A.
necessary for such contract/project. No. 7718, or the Build-Operate-and-Transfer ( BOT) Law; and

This prohibition shall apply in all cases, disputes or (c) other related and necessary activities, such as site
controversies instituted by a private party, including but not acquisition, supply and/or installation of equipment and
limited to cases filed by bidders or those claiming to have rights materials, implementation, construction, completion, operation,
through such bidders involving such contract/project. This maintenance, improvement repair and rehabilitation, regardless
prohibition shall not apply when the matter is of extreme of the source of funding.
urgency involving a constitutional issue, such that unless a
temporary restraining order is issued, grave injustice and Under Section 2(a) of the BOT Law as amended by Republic
irreparable injury will arise. The applicant shall file a bond, in an Act No. 7718,61 private sector infrastructure or development
amount to be fixed by the court, which bond shall accrue in projects are those normally financed and operated by the public
favor of the government if the court should finally decide that sector but which will now be wholly or partly implemented by
the applicant was not entitled to the relief sought. the private sector, including but not limited to, power plants,
highways, ports, airports, canals, dams, hydropower projects,
If after due hearing the court finds that the award of the contract water supply, irrigation, telecommunications, railroads and
is null and void, the court may, if appropriate under the railways, transport systems, land reclamation projects,
circumstances, award the contract to the qualified and winning industrial estates or townships, housing, government buildings,
bidder or order a rebidding of the same, without prejudice to tourism projects, markets, slaughterhouses, warehouses, solid
any liability that the guilty party may incur under existing laws. waste management, information technology networks and
database infrastructure, education and health facilities,
From the foregoing, it is indubitable that no court, aside from sewerage, drainage, dredging, and other infrastructure and
the Supreme Court, may enjoin a "national government project" development projects as may be authorized by the appropriate
unless the matter is one of extreme urgency involving a agency.
constitutional issue such that unless the act complained of is
enjoined, grave injustice or irreparable injury would arise. In contrast, Republic Act No. 9184,62 also known as the
Government Procurement Reform Act, defines infrastructure
What then are the "national government projects" over which projects in Section 5(k) thereof in this manner:
the lower courts are without jurisdiction to issue the injunctive
relief as mandated by Republic Act No. 8975? (k) Infrastructure Projects - include the construction,
improvement, rehabilitation, demolition, repair, restoration or
Section 2(a) of Republic Act No. 8975 provides: maintenance of roads and bridges, railways, airports, seaports,
communication facilities, civil works components of information
technology projects, irrigation, flood control and drainage, water
Section 2. Definition of Terms.
supply, sanitation, sewerage and solid waste management
systems, shore protection, energy/power and electrification
(a) "National government projects" shall refer to all current and facilities, national buildings, school buildings, hospital buildings
future national government infrastructure, engineering works and other related construction projects of the government.
and service contracts, including projects undertaken by (Emphasis supplied.)
government-owned and -controlled corporations, all projects
covered by Republic Act No. 6975, as amended by Republic
In the present petition, the DFA and the BSP contend that the
Act No. 7718, otherwise known as the Build-Operate-and-
bidding for the supply, delivery, installation and commissioning
Transfer Law, and other related and necessary activities, such
of a system for the production of Electronic Passport Booklets,
as site acquisition, supply and/or installation of equipment and
is a national government project within the definition of Section
materials, implementation, construction, completion, operation,
2 of Republic Act No. 8975. Petitioners also point to the Senate
maintenance, improvement, repair and rehabilitation,
deliberations on Senate Bill No. 203863 (later Republic Act No.
regardless of the source of funding.
8975) which allegedly show the legislatives intent to expand
the scope and definition of national government projects to
As petitioners themselves pointed out, there are three types of cover not only the infrastructure projects enumerated in
national government projects enumerated in Section 2(a), to Presidential Decree No. 1818, but also future projects that may
wit: likewise be considered national government infrastructure
projects, like the e-Passport Project, to wit:
(a) current and future national government infrastructure
projects, engineering works and service contracts, including Senator Cayetano. x x x Mr. President, the present bill, the
projects undertaken by government-owned and controlled Senate Bill No. 2038, is actually an improvement of P.D. No.
corporations; 1818 and definitely not a repudiation of what I have earlier said,
as my good friend clearly stated. But this is really an effort to
ADR || First Batch 86

improve both the scope and definition of the term "government projects refer to the "civil works components" thereof. (R.A. No.
projects" and to ensure that lower court judges obey and 9184 [2003], Sec. 5[c]{sic}).64
observe this prohibition on the issuance of TROs on
infrastructure projects of the government. Respondent BSPs request for bid, for the supply, delivery,
installation and commissioning of a system for the production of
xxxx Electronic Passport Booklets appears to be beyond the scope
of the term "civil works." Respondents did not present evidence
Senator Cayetano. That is why, Mr. President, I did try to to prove otherwise.65 (Emphases ours.)
explain why I would accept the proposed amendment, meaning
the totality of the repeal of P.D. 1818 which is not found in the From the foregoing, it can be gleaned that the trial court
original version of the bill, because of my earlier explanation accepted BCAs reasoning that, assuming the e-Passport
that the definition of the term government infrastructure project Project is a project under the BOT Law, Section 2 of the BOT
covers all of those enumerated in Section 1 of P.D. No. 1818. Law must be read in conjunction with Section 5(c) of Republic
And the reason for that, as we know, is we do not know what Act No. 9184 or the Government Procurement Reform Act to
else could be considered government infrastructure project in the effect that only the civil works component of information
the next 10 or 20 years. technology projects are to be considered "infrastructure." Thus,
only said civil works component of an information technology
x x x So, using the Latin maxim of expression unius est project cannot be the subject of a TRO or writ of injunction
exclusion alterius, which means what is expressly mentioned is issued by a lower court.
tantamount to an express exclusion of the others, that is the
reason we did not include particularly an enumeration of certain Although the Court finds that the trial court had jurisdiction to
activities of the government found in Section 1 of P.D. No. issue the writ of preliminary injunction, we cannot uphold the
1818. Because to do that, it may be a good excuse for a theory of BCA and the trial court that the definition of the term
brilliant lawyer to say Well, you know, since it does not cover "infrastructure project" in Republic Act No. 9184 should be
this particular activity, ergo, the Regional Trial Court may issue applied to the BOT Law.
TRO.
Section 5 of Republic Act No. 9184 prefaces the definition of
Using the foregoing discussions to establish that the intent of the terms therein, including the term "infrastructure project,"
the framers of the law was to broaden the scope and definition with the following phrase: "For purposes of this Act, the
of national government projects and national infrastructure following terms or words and phrases shall mean or be
projects, the DFA and the BSP submit that the said scope and understood as follows x x x."
definition had since evolved to include the e-Passport Project.
They assert that the concept of "infrastructure" must now refer This Court has stated that the definition of a term in a statute is
to any and all elements that provide support, framework, or not conclusive as to the meaning of the same term as used
structure for a given system or organization, including elsewhere.66 This is evident when the legislative definition is
information technology, such as the e-Passport Project. expressly made for the purposes of the statute containing such
definition.67
Interestingly, petitioners represented to the trial court that the e-
Passport Project is a BOT project but in their petition with this There is no legal or rational basis to apply the definition of the
Court, petitioners simply claim that the e-Passport Project is a term "infrastructure project" in one statute to another statute
national government project under Section 2 of Republic Act enacted years before and which already defined the types of
No. 8975. This circumstance is significant, since relying on the projects it covers. Rather, a reading of the two statutes involved
claim that the e-Passport Project is a BOT project, the trial court will readily show that there is a legislative intent to treat
ruled in this wise: information technology projects differently under the BOT Law
and the Government Procurement Reform Act.
The prohibition against issuance of TRO and/or writ of
preliminary injunction under RA 8975 applies only to national In the BOT Law as amended by Republic Act No. 7718, the
government infrastructure project covered by the BOT Law, (RA national infrastructure and development projects covered by
8975, Sec 3[b] in relation to Sec. 2). said law are enumerated in Section 2(a) as follows:

The national government projects covered under the BOT are SEC. 2. Definition of Terms. - The following terms used in this
enumerated under Sec. 2 of RA6957, as amended, otherwise Act shall have the meanings stated below:
known as the BOT Law. Notably, it includes "information
technology networks and database infrastructure."
(a) Private sector infrastructure or development projects - The
general description of infrastructure or development projects
In relation to information technology projects, infrastructure normally financed and operated by the public sector but which
ADR || First Batch 87

will now be wholly or partly implemented by the private sector, management, information technology networks and database
including but not limited to, power plants, highways, ports, infrastructure, education and health facilities, sewerage,
airports, canals, dams, hydropower projects, water supply, drainage, dredging, and other infrastructure and development
irrigation, telecommunications, railroads and railways, transport projects as may otherwise be authorized by the appropriate
systems, land reclamation projects, industrial estates of Agency/LGU pursuant to the Act or these Revised IRR. Such
townships, housing, government buildings, tourism projects, projects shall be undertaken through Contractual Arrangements
markets, slaughterhouses, warehouses, solid waste as defined herein, including such other variations as may be
management, information technology networks and database approved by the President of the Philippines.
infrastructure, education and health facilities, sewerage,
drainage, dredging, and other infrastructure and development xxxx
projects as may be authorized by the appropriate agency
pursuant to this Act. Such projects shall be undertaken through
SECTION 2.2 - ELIGIBLE TYPES OF PROJECTS
contractual arrangements as defined hereunder and such other
variations as may be approved by the President of the
Philippines. The Construction, rehabilitation, improvement, betterment,
expansion, modernization, operation, financing and
maintenance of the following types of projects which are
For the construction stage of these infrastructure projects, the
normally financed and operated by the public sector which will
project proponent may obtain financing from foreign and/or
now be wholly or partly financed, constructed and operated by
domestic sources and/or engage the services of a foreign
the private sector, including other infrastructure and
and/or Filipino contractor: Provided, That, in case an
development projects as may be authorized by the appropriate
infrastructure or a development facility's operation requires a
agencies, may be proposed under the provisions of the Act and
public utility franchise, the facility operator must be a Filipino or
these Revised IRR, provided however that such projects have a
if a corporation, it must be duly registered with the Securities
cost recovery component which covers at least 50% of the
and Exchange Commission and owned up to at least sixty
Project Cost, or as determined by the Approving Body:
percent (60%) by Filipinos: Provided, further, That in the case
of foreign contractors, Filipino labor shall be employed or hired
in the different phases of construction where Filipino skills are xxxx
available: Provided, finally, That projects which would have
difficulty in sourcing funds may be financed partly from direct h. Information technology (IT) and data base infrastructure,
government appropriations and/or from Official Development including modernization of IT, geo-spatial resource mapping
Assistance (ODA) of foreign governments or institutions not and cadastral survey for resource accounting and planning.
exceeding fifty percent (50%) of the project cost, and the (Underscoring supplied.)
balance to be provided by the project proponent. (Emphasis
supplied.) Undeniably, under the BOT Law, wherein the projects are to be
privately funded, the entire information technology project,
A similar provision appears in the Revised IRR of the BOT Law including the civil works component and the technological
as amended, to wit: aspect thereof, is considered an infrastructure or development
project and treated similarly as traditional "infrastructure"
SECTION 1.3 - DEFINITION OF TERMS projects. All the rules applicable to traditional infrastructure
projects are also applicable to information technology projects.
In fact, the MRP/V Project awarded to BCA under the BOT Law
For purposes of these Implementing Rules and Regulations,
appears to include both civil works (i.e., site preparation of the
the terms and phrases hereunder shall be understood as
Central Facility, regional DFA offices and foreign service posts)
follows:
and non-civil works aspects (i.e., development, installation and
maintenance in the Philippines and foreign service posts of a
xxxx computerized passport and visa issuance system, including
creation of databases, storage and retrieval systems, training of
v. Private Sector Infrastructure or Development Projects - personnel and provision of consumables).
The general description of infrastructure or Development
Projects normally financed, and operated by the public sector In contrast, under Republic Act No. 9184 or the Government
but which will now be wholly or partly financed, constructed and Procurement Reform Act, which contemplates projects to be
operated by the private sector, including but not limited to, funded by public funds, the term "infrastructure project" was
power plants, highways, ports, airports, canals, dams, limited to only the "civil works component" of information
hydropower projects, water supply, irrigation, technology projects. The non-civil works component of
telecommunications, railroad and railways, transport systems, information technology projects would be treated as an
land reclamation projects, industrial estates or townships, acquisition of goods or consulting services as the case may be.
housing, government buildings, tourism projects, public
markets, slaughterhouses, warehouses, solid waste
ADR || First Batch 88

This limited definition of "infrastructure project" in relation to The IRR-B for foreign-funded procurement activities shall be
information technology projects under Republic Act No. 9184 is the subject of a subsequent issuance. (Emphases supplied.)
significant since the IRR of Republic Act No. 9184 has some
provisions that are particular to infrastructure projects and other The foregoing provision in the IRR can be taken as an
provisions that are applicable only to procurement of goods or administrative interpretation that the provisions of Republic Act
consulting services.68 No. 9184 are inapplicable to a BOT project except only insofar
as such portions of the BOT project that are financed by the
Implicitly, the civil works component of information technology government.
projects are subject to the provisions on infrastructure projects
while the technological and other components would be Taking into account the different treatment of information
covered by the provisions on procurement of goods or technology projects under the BOT Law and the Government
consulting services as the circumstances may warrant. Procurement Reform Act, petitioners contention the trial court
had no jurisdiction to issue a writ of preliminary injunction in the
When Congress adopted a limited definition of what is to be instant case would have been correct if the e-Passport Project
considered "infrastructure" in relation to information technology was a project under the BOT Law as they represented to the
projects under the Government Procurement Reform Act, trial court.
legislators are presumed to have taken into account previous
laws concerning infrastructure projects (the BOT Law and However, petitioners presented no proof that the e-Passport
Republic Act No. 8975) and deliberately adopted the limited Project was a BOT project. On the contrary, evidence adduced
definition. We can further presume that Congress had written by both sides tended to show that the e-Passport Project was a
into law a different treatment for information technology projects procurement contract under Republic Act No. 9184.
financed by public funds vis-a-vis privately funded projects for a
valid legislative purpose.
The BSPs on-line request for expression of interest and to bid
for the e-Passport Project69 from the BSP website and the
The idea that the definitions of terms found in the Government newspaper clipping70 of the same request expressly stated that
Procurement Reform Act were not meant to be applied to "[t]he two stage bidding procedure under Section 30.4 of the
projects under the BOT Law is further reinforced by the Implementing Rules and Regulation (sic) Part-A of Republic Act
following provision in the IRR of the Government Procurement No. 9184 relative to the bidding and award of the contract shall
Reform Act: apply." During the testimony of DFA Assistant Secretary
Domingo Lucenario, Jr. before the trial court, he admitted that
Section 1. Purpose and General Coverage the e-Passport Project is a BSP procurement project and that it
is the "BSP that will pay the suppliers."71 In petitioners
This Implementing Rules and Regulations (IRR) Part A, Manifestation dated July 29, 200872 and the Erratum73 thereto,
hereinafter called "IRR-A," is promulgated pursuant to Section petitioners informed the Court that a contract "for the supply of
75 of Republic Act No. 9184 (R.A. 9184), otherwise known as a complete package of systems design, technology, hardware,
the "Government Procurement Reform Act" (GPRA), for the software, and peripherals, maintenance and technical support,
purpose of prescribing the necessary rules and regulations for ecovers and datapage security laminates for the centralized
the modernization, standardization, and regulation of the production and personalization of Machine Readable Electronic
procurement activities of the government. This IRR-A shall Passport" was awarded to Francois Charles Oberthur
cover all fully domestically-funded procurement activities from Fiduciaire. In the Notice of Award dated July 2, 200874 attached
procurement planning up to contract implementation and to petitioners pleading, it was stated that the failure of the
termination, except for the following: contractor/supplier to submit the required performance bond
would be sufficient ground for the imposition of administrative
penalty under Section 69 of the IRR-A of Republic Act No.
a) Acquisition of real property which shall be governed by
9184.
Republic Act No. 8974 (R.A. 8974), entitled "An Act to Facilitate
the Acquisition of Right-of-Way Site or Location for National
Government Infrastructure Projects and for Other Purposes," Being a government procurement contract under Republic Act
and other applicable laws; and No. 9184, only the civil works component of the e-Passport
Project would be considered an infrastructure project that may
not be the subject of a lower court-issued writ of injunction
b) Private sector infrastructure or development projects and
under Republic Act No. 8975.
other procurement covered by Republic Act No. 7718 (R.A.
7718), entitled "An Act Authorizing the Financing, Construction,
Operation and Maintenance of Infrastructure Projects by the Could the e-Passport Project be considered as "engineering
Private Sector, and for Other Purposes," as amended: works or a service contract" or as "related and necessary
Provided, however, That for the portions financed by the activities" under Republic Act No. 8975 which may not be
Government, the provisions of this IRR-A shall apply. enjoined?
ADR || First Batch 89

We hold in the negative. Under Republic Act No. 8975, a (2) Such relief may be granted:
"service contract" refers to "infrastructure contracts entered into
by any department, office or agency of the national government (i) to prevent irreparable loss or injury;
with private entities and nongovernment organizations for
services related or incidental to the functions and operations of
(ii) to provide security for the performance of any obligation;
the department, office or agency concerned." On the other
hand, the phrase "other related and necessary activities"
obviously refers to activities related to a government (iii) to produce or preserve any evidence; or
infrastructure, engineering works, service contract or project
under the BOT Law. In other words, to be considered a service (iv) to compel any other appropriate act or omission.
contract or related activity, petitioners must show that the e-
Passport Project is an infrastructure project or necessarily (3) The order granting provisional relief may be conditioned
related to an infrastructure project. This, petitioners failed to do upon the provision of security or any act or omission specified
for they saw fit not to present any evidence on the details of the in the order.
e-Passport Project before the trial court and this Court. There is
nothing on record to indicate that the e-Passport Project has a (4) Interim or provisional relief is requested by written
civil works component or is necessarily related to an application transmitted by reasonable means to the Court or
infrastructure project. arbitral tribunal as the case may be and the party against whom
the relief is sought, describing in appropriate detail the precise
Indeed, the reference to Section 30.475 of the IRR of Republic relief, the party against whom the relief is requested, the
Act No. 9184 (a provision specific to the procurement of goods) grounds for the relief, and the evidence supporting the request.
in the BSPs request for interest and to bid confirms that the e-
Passport Project is a procurement of goods and not an (5) The order shall be binding upon the parties.
infrastructure project. Thus, within the context of Republic Act
No. 9184 which is the governing law for the e-Passport
(6) Either party may apply with the Court for assistance in
Project the said Project is not an infrastructure project that is
implementing or enforcing an interim measure ordered by an
protected from lower court issued injunctions under Republic
arbitral tribunal.
Act No. 8975, which, to reiterate, has for its purpose the
expeditious and efficient implementation and completion of
government infrastructure projects. (7) A party who does not comply with the order shall be liable
for all damages resulting from noncompliance, including all
expenses and reasonable attorneys fees, paid in obtaining the
We note that under Section 28, Republic Act No. 9285 or the
orders judicial enforcement.
Alternative Dispute Resolution Act of 2004,76 the grant of an
interim measure of protection by the proper court before the
constitution of an arbitral tribunal is allowed: Section 3(h) of the same statute provides that the "Court" as
referred to in Article 6 of the Model Law shall mean a Regional
Trial Court.
Sec. 28. Grant of Interim Measure of Protection. (a) It is not
incompatible with an arbitration agreement for a party to
request, before constitution of the tribunal, from a Court an Republic Act No. 9285 is a general law applicable to all matters
interim measure of protection and for the Court to grant such and controversies to be resolved through alternative dispute
measure. After constitution of the arbitral tribunal and during resolution methods. This law allows a Regional Trial Court to
arbitral proceedings, a request for an interim measure of grant interim or provisional relief, including preliminary
protection, or modification thereof, may be made with the injunction, to parties in an arbitration case prior to the
arbitral tribunal or to the extent that the arbitral tribunal has no constitution of the arbitral tribunal. This general statute,
power to act or is unable to act effectively, the request may be however, must give way to a special law governing national
made with the Court. The arbitral tribunal is deemed constituted government projects, Republic Act No. 8975 which prohibits
when the sole arbitrator or the third arbitrator, who has been courts, except the Supreme Court, from issuing TROs and writs
nominated, has accepted the nomination and written of preliminary injunction in cases involving national government
communication of said nomination and acceptance has been projects.
received by the party making the request.
However, as discussed above, the prohibition in Republic Act
(a) The following rules on interim or provisional relief shall be No. 8975 is inoperative in this case, since petitioners failed to
observed: prove that the e-Passport Project is national government project
as defined therein. Thus, the trial court had jurisdiction to issue
a writ of preliminary injunction against the e-Passport Project.
(1) Any party may request that provisional relief be granted
against the adverse party.
On whether the trial courts issuance of a writ of injunction was
ADR || First Batch 90

proper stipulated in the Amended BOT Agreement that BCA would be


solidarily liable with its assignee. For convenient reference, we
Given the above ruling that the trial court had jurisdiction to reproduce the relevant provision of the Amended BOT
issue a writ of injunction and going to the second issue raised Agreement here:
by petitioners, we answer the question: Was the trial courts
issuance of a writ of injunction warranted under the Section 20.15. It is clearly and expressly understood that BCA
circumstances of this case? may assign, cede and transfer all of its rights and obligations
under this Amended BOT Agreement to PPC [Philippine
Petitioners attack on the propriety of the trial courts issuance Passport Corporation], as fully as if PPC is the original
of a writ of injunction is two-pronged: (a) BCA purportedly has signatory to this Amended BOT Agreement, provided however
no clear right to the injunctive relief sought; and (b) BCA will that BCA shall nonetheless be jointly and severally liable
suffer no grave and irreparable injury even if the injunctive relief with PPC for the performance of all the obligations and
were not granted. liabilities under this Amended BOT Agreement. (Emphasis
supplied.)
To support their claim that BCA has no clear right to injunctive
relief, petitioners mainly allege that the MRP/V Project and the Furthermore, a review of the records shows that the DFA
e-Passport Project are not the same project. Moreover, the continued to address its correspondence regarding the MRP/V
MRP/V Project purportedly involves a technology (the 2D Project to both BCA and PPC, even after the execution of the
optical bar code) that has been rendered obsolete by the latest assignment agreement. Indeed, the DFAs Notice of
ICAO developments while the e-Passport Project will comply Termination dated December 9, 2005 was addressed to Mr.
with the latest ICAO standards (the contactless integrated Bonifacio Sumbilla as President of both BCA and PPC and
circuit). Parenthetically, and not as a main argument, petitioners referred to the Amended BOT Agreement "executed between
imply that BCA has no clear contractual right under the the Department of Foreign Affairs (DFA), on one hand, and the
Amended BOT Agreement since BCA had previously assigned BCA International Corporation and/or the Philippine Passport
all its rights and obligations under the said Agreement to PPC. Corporation (BCA/PPC)." At the very least, the DFA is
estopped from questioning the personality of BCA to bring suit
in relation to the Amended BOT Agreement since the DFA
BCA, on the other hand, claims that the Amended BOT
continued to deal with both BCA and PPC even after the
Agreement also contemplated the supply and/or delivery of e-
signing of the assignment agreement. In any event, if the DFA
Passports with the integrated circuit technology in the future
truly believes that PPC is an indispensable party to the action,
and not only the machine readable passport with the 2D optical
the DFA may take necessary steps to implead PPC but this
bar code technology. Also, it is BCAs assertion that the
should not prejudice the right of BCA to file suit or to seek relief
integrated circuit technology is only optional under the ICAO
for causes of action it may have against the DFA or the BSP,
issuances. On the matter of its assignment of its rights to PPC,
for undertaking the e-Passport Project on behalf of the DFA.
BCA counters that it had already terminated (purportedly at
DFAs request) the assignment agreement in favor of PPC and
that even assuming the termination was not valid, the Amended With respect to petitioners contention that BCA will suffer no
BOT Agreement expressly stated that BCA shall remain grave and irreparable injury so as to justify the grant of
solidarily liable with its assignee, PPC. injunctive relief, the Court finds that this particular argument
merits consideration.
Most of these factual allegations and counter-allegations
already touch upon the merits of the main controversy between The BOT Law as amended by Republic Act No. 7718, provides:
the DFA and BCA, i.e., the validity and propriety of the
termination of the Amended BOT Agreement (the MRP/V SEC. 7. Contract Termination. - In the event that a project is
Project) between the DFA and BCA. The Court deems it best to revoked, cancelled or terminated by the Government through
refrain from ruling on these matters since they should be no fault of the project proponent or by mutual agreement, the
litigated in the appropriate arbitration or court proceedings Government shall compensate the said project proponent for its
between or among the concerned parties. actual expenses incurred in the project plus a reasonable rate
of return thereon not exceeding that stated in the contract as of
One preliminary point, however, that must be settled here is the date of such revocation, cancellation or termination:
whether BCA retains a right to seek relief against the DFA Provided, That the interest of the Government in this instances
under the Amended BOT Agreement in view of BCAs previous shall be duly insured with the Government Service Insurance
assignment of its rights to PPC. Without preempting any factual System [GSIS] or any other insurance entity duly accredited by
finding that the appropriate court or arbitral tribunal on the the Office of the Insurance Commissioner: Provided, finally,
matter of the validity of the assignment agreement with PPC or That the cost of the insurance coverage shall be included in the
its termination, we agree with BCA that it remained a party to terms and conditions of the bidding referred to above.
the Amended BOT Agreement, notwithstanding the execution
of the assignment agreement in favor of PPC, for it was In the event that the government defaults on certain major
ADR || First Batch 91

obligations in the contract and such failure is not remediable or D. In all cases of termination due to the default of the BCA,
if remediable shall remain unremedied for an unreasonable it shall pay DFA liquidated damages equivalent to the
length of time, the project proponent/contractor may, by prior applicable the (sic) Performance Security.
notice to the concerned national government agency or local
government unit specifying the turn-over date, terminate the Section 17.03 DFAs Default If this Amended BOT Agreement
contract. The project proponent/contractor shall be reasonably is terminated by the BCA by reason of the DFAs Default, the
compensated by the Government for equivalent or DFA shall:
proportionate contract cost as defined in the contract.
(Emphases supplied.)
A. Be obligated to take over the MRP/V Facility on an "as is,
where is" basis, and shall forthwith assume attendant liabilities
In addition, the Amended BOT Agreement, which is the law thereof; and
between and among the parties to it, pertinently provides:
B. Pay liquidated damages to the BCA equivalent to the
Section 17.01 Default In case a party commits an act following amounts, which may be charged to the insurance
constituting an event of default, the non-defaulting party proceeds referred to in Article 12:
may terminate this Amended BOT Agreement by serving a
written notice to the defaulting party specifying the grounds for
(1) In the event of termination prior to completion of the
termination and giving the defaulting party a period of ninety
implementation of the MRP/V Project, damages shall be paid
(90) days within which to rectify the default. If the default is not
equivalent to the value of completed implementation,
remedied within this period to the satisfaction of the non-
minus the aggregate amount of the attendant liabilities
defaulting party, then the latter will serve upon the former a
assumed by the DFA, plus ten percent (10%) thereof. The
written notice of termination indicating the effective date of
amount of such compensation shall be determined as of the
termination.
date of the notice of termination and shall become due and
demandable ninety (90) days after the date of this notice of
Section 17.02 Proponents Default If this Amended BOT termination. Under this Amended BOT Agreement, the term
Agreement is terminated by reason of the BCAs default, the "Value of the Completed Implementation" shall mean the
DFA shall have the following options: aggregate of all reasonable costs and expenses incurred by the
BCA in connection with, in relation to and/or by reason of the
A. Allow the BCAs unpaid creditors who hold a lien on the MRP/V Project, excluding all interest and capitalized interest,
MRP/V Facility to foreclose on the MRP/V Facility. The right of as certified by a reputable and independent accounting firm to
the BCAs unpaid creditors to foreclose on the MRP/V Facility be appointed by the BCA and subject to the approval by the
shall be valid for the duration of the effectivity of this Amended DFA, such approval shall not be unreasonably withheld.
BOT Agreement; or,
(2) In the event of termination after completion of design,
B. Allow the BCAs unpaid creditors who hold a lien on the development, and installation of the MRP/V Project, just
MRP/V Facility to designate a substitute BCA for the MRP/V compensation shall be paid equivalent to the present value
Project, provided the designated substitute BCA is qualified of the net income which the BCA expects to earn or realize
under existing laws and acceptable to the DFA. This substitute during the unexpired or remaining term of this Amended
BCA shall hereinafter be referred to as the "Substitute BCA." BOT Agreement using the internal rate of return on equity
The Substitute BCA shall assume all the BCAs rights and (IRRe) defined in the financial projections of the BCA and
privileges, as well as the obligations, duties and responsibilities agreed upon by the parties, which is attached hereto and made
hereunder; provided, however, that the DFA shall at all times as an integral part of this Amended BOT Agreement as
and its sole option, have the right to invoke and exercise any Schedule "1". (Emphases supplied.)
other remedy which may be available to the DFA under any
applicable laws, rules and/or regulations which may be in effect The validity of the DFAs termination of the Amended BOT
at any time and from time to time. The DFA shall cooperate with Agreement and the determination of the party or parties in
the creditors with a view to facilitating the choice of a Substitute default are issues properly threshed out in arbitration
BCA, who shall take-over the operation, maintenance and proceedings as provided for by the agreement itself. However,
management of the MRP/V Project, within three (3) months even if we hypothetically accept BCAs contention that the DFA
from the BCAs receipt of the notice of termination from the terminated the Amended BOT Agreement without any default or
DFA. The Substituted BCA shall have all the rights and wrongdoing on BCAs part, it is not indubitable that BCA is
obligations of the previous BCA as contained in this Amended entitled to injunctive relief.
BOT Agreement; or
The BOT Law expressly allows the government to terminate a
C. Take-over the MRP/V Facility and assume all attendant BOT agreement, even without fault on the part of the project
liabilities thereof. proponent, subject to the payment of the actual expenses
ADR || First Batch 92

incurred by the proponent plus a reasonable rate of return. An injury is considered irreparable if it is of such constant and
frequent recurrence that no fair and reasonable redress can be
Under the BOT Law and the Amended BOT Agreement, in the had therefor in a court of law, or where there is no standard by
event of default on the part of the government (in this case, the which their amount can be measured with reasonable accuracy,
DFA) or on the part of the proponent, the non-defaulting party is that is, it is not susceptible of mathematical computation. It is
allowed to terminate the agreement, again subject to proper considered irreparable injury when it cannot be adequately
compensation in the manner set forth in the agreement. compensated in damages due to the nature of the injury itself
or the nature of the right or property injured or when there
exists no certain pecuniary standard for the measurement of
Time and again, this Court has held that to be entitled to
damages. (Emphases supplied.)
injunctive relief the party seeking such relief must be able to
show grave, irreparable injury that is not capable of
compensation. It is still contentious whether this is a case of termination by the
DFA alone or both the DFA and BCA. The DFA contends that
BCA, by sending its own Notice of Default, likewise terminated
In Lopez v. Court of Appeals, 77 we held:
or "abandoned" the Amended BOT Agreement. Still, whether
this is a termination by the DFA alone without fault on the part
Generally, injunction is a preservative remedy for the protection of BCA or a termination due to default on the part of either
of one's substantive right or interest. It is not a cause of action party, the BOT Law and the Amended BOT Agreement lay
in itself but merely a provisional remedy, an adjunct to a main down the measure of compensation to be paid under the
suit. It is resorted to only when there is a pressing necessity to appropriate circumstances.
avoid injurious consequences which cannot be remedied under
any standard compensation. The application of the injunctive
Significantly, in BCAs Request for Arbitration with the PDRCI, it
writ rests upon the existence of an emergency or of a special
prayed for, among others, "a judgment ordering respondent
reason before the main case can be regularly heard. The
[DFA] to pay damages to Claimant [BCA], reasonably estimated
essential conditions for granting such temporary injunctive relief
at P50,000,000.00 as of [the date of the Request for
are that the complaint alleges facts which appear to be
Arbitration], representing lost business opportunities; financing
sufficient to constitute a proper basis for injunction and that on
fees, costs and commissions; travel expenses; legal fees and
the entire showing from the contending parties, the injunction is
expenses; and costs of arbitration, including the fees of the
reasonably necessary to protect the legal rights of the plaintiff
arbitrator/s."80 All the purported damages that BCA claims to
pending the litigation. Two requisites are necessary if a
have suffered by virtue of the DFAs termination of the
preliminary injunction is to issue, namely, the existence of a
Amended BOT Agreement are plainly determinable in
right to be protected and the facts against which the injunction
pecuniary terms and can be "reasonably estimated" according
is to be directed are violative of said right. In particular, for a
to BCAs own words.
writ of preliminary injunction to issue, the existence of the right
and the violation must appear in the allegation of the complaint
and a preliminary injunction is proper only when the plaintiff Indeed, the right of BCA, a party which may or may not have
(private respondent herein) appears to be entitled to the relief been in default on its BOT contract, to have the termination of
demanded in his complaint. (Emphases supplied.) its BOT contract reversed is not guaranteed by the BOT Law.
Even assuming BCAs innocence of any breach of contract, all
the law provides is that BCA should be adequately
We reiterated this point in Transfield Philippines, Inc. v. Luzon
compensated for its losses in case of contract termination by
Hydro Corporation,78 where we likewise opined:
the government.
Before a writ of preliminary injunction may be issued, there
There is one point that none of the parties has highlighted but is
must be a clear showing by the complaint that there exists a
worthy of discussion. In seeking to enjoin the government from
right to be protected and that the acts against which the writ is
awarding or implementing a machine readable passport project
to be directed are violative of the said right. It must be shown
or any similar electronic passport or visa project and praying for
that the invasion of the right sought to be protected is material
the maintenance of the status quo ante pending the resolution
and substantial, that the right of complainant is clear and
on the merits of BCAs Request for Arbitration, BCA effectively
unmistakable and that there is an urgent and paramount
seeks to enjoin the termination of the Amended BOT
necessity for the writ to prevent serious damage. Moreover, an
Agreement for the MRP/V Project.
injunctive remedy may only be resorted to when there is a
pressing necessity to avoid injurious consequences which
cannot be remedied under any standard compensation. There is no doubt that the MRP/V Project is a project covered
(Emphasis supplied.) by the BOT Law and, in turn, considered a "national
government project" under Republic Act No. 8795. Under
Section 3(d) of that statute, trial courts are prohibited from
As the Court explained previously in Philippine Airlines, Inc. v.
issuing a TRO or writ of preliminary injunction against the
National Labor Relations Commission79:
government to restrain or prohibit the termination or rescission
ADR || First Batch 93

of any such national government project/contract. constitutional issue involved in this case, much less a
constitutional issue of extreme urgency.
The rationale for this provision is easy to understand. For if a
project proponent that the government believes to be in As for the DFAs purported failure to appropriate sufficient
default is allowed to enjoin the termination of its contract on amounts in its budget to pay for liquidated damages to BCA,
the ground that it is contesting the validity of said termination, this argument does not support BCAs position that it will suffer
then the government will be unable to enter into a new contract grave and irreparable injury if it is denied injunctive relief. The
with any other party while the controversy is pending litigation. DFAs liability to BCA for damages is contingent on BCA
Obviously, a courts grant of injunctive relief in such an instance proving that it is entitled to such damages in the proper
is prejudicial to public interest since government would be proceedings. The DFA has no obligation to set aside funds to
indefinitely hampered in its duty to provide vital public goods pay for liquidated damages, or any other kind of damages, to
and services in order to preserve the private proprietary rights BCA until there is a final and executory judgment in favor of
of the project proponent. On the other hand, should it turn out BCA. It is illogical and impractical for the DFA to set aside a
that the project proponent was not at fault, the BOT Law itself significant portion of its budget for an event that may never
presupposes that the project proponent can be adequately happen when such idle funds should be spent on providing
compensated for the termination of the contract. Although BCA necessary services to the populace. For if it turns out at the end
did not specifically pray for the trial court to enjoin the of the arbitration proceedings that it is BCA alone that is in
termination of the Amended BOT Agreement and thus, there is default, it would be the one liable for liquidated damages to the
no direct violation of Republic Act No. 8795, a grant of DFA under the terms of the Amended BOT Agreement.
injunctive relief as prayed for by BCA will indirectly contravene
the same statute. With respect to BCAs allegation that the e-Passport Project is
grossly disadvantageous to the Filipino people since it is the
Verily, there is valid reason for the law to deny preliminary government that will be spending for the project unlike the
injunctive relief to those who seek to contest the governments MRP/V Project which would have been privately funded, the
termination of a national government contract. The only same is immaterial to the issue at hand. If it is true that the
circumstance under which a court may grant injunctive relief is award of the e-Passport Project is inimical to the public good or
the existence of a matter of extreme urgency involving a tainted with some anomaly, it is indeed a cause for grave
constitutional issue, such that unless a TRO or injunctive writ is concern but it is a matter that must be investigated and litigated
issued, grave injustice and irreparable injury will result. in the proper forum. It has no bearing on the issue of whether
BCA would suffer grave and irreparable injury such that it is
Now, BCA likewise claims that unless it is granted injunctive entitled to injunctive relief from the courts.
relief, it would suffer grave and irreparable injury since the
bidding out and award of the e-Passport Project would be In all, we agree with petitioners DFA and BSP that the trial
tantamount to a violation of its right against deprivation of courts issuance of a writ of preliminary injunction, despite the
property without due process of law under Article III, Section 1 lack of sufficient legal justification for the same, is tantamount to
of the Constitution. We are unconvinced. 1avvphi1 grave abuse of discretion.

Article III, Section 1 of the Constitution provides "[n]o person To be very clear, the present decision touches only on the twin
shall be deprived of life, liberty, or property without due process issues of (a) the jurisdiction of the trial court to issue a writ of
of law, nor shall any person be denied the equal protection of preliminary injunction as an interim relief under the factual
the laws." Ordinarily, this constitutional provision has been milieu of this case; and (b) the entitlement of BCA to injunctive
applied to the exercise by the State of its sovereign powers relief. The merits of the DFA and BCAs dispute regarding the
such as, its legislative power,81 police power,82 or its power of termination of the Amended BOT Agreement must be threshed
eminent domain.83 out in the proper arbitration proceedings. The civil case pending
before the trial court is purely for the grant of interim relief since
In the instant case, the State action being assailed is the DFAs the main case is to be the subject of arbitration proceedings.
termination of the Amended BOT Agreement with BCA.
Although the said agreement involves a public service that the BCAs petition for interim relief before the trial court is
DFA is mandated to provide and, therefore, is imbued with essentially a petition for a provisional remedy (i.e., preliminary
public interest, the relationship of DFA to BCA is primarily injunction) ancillary to its Request for Arbitration in PDRCI Case
contractual and their dispute involves the adjudication of No. 30-2006/BGF. BCA specifically prayed that the trial court
contractual rights. The propriety of the DFAs acts, in relation to grant it interim relief pending the constitution of the arbitral
the termination of the Amended BOT Agreement, should be tribunal in the said PDRCI case. Unfortunately, during the
gauged against the provisions of the contract itself and the pendency of this case, PDRCI Case No. 30-2006/BGF was
applicable statutes to such contract. These contractual and dismissed by the PDRCI for lack of jurisdiction, in view of the
statutory provisions outline what constitutes due process in the lack of agreement between the parties to arbitrate before the
present case. In all, BCA failed to demonstrate that there is a PDRCI.84 In Philippine National Bank v. Ritratto Group, Inc.,85
ADR || First Batch 94

we held: Associate Justice

A writ of preliminary injunction is an ancillary or preventive CERTIFICATION


remedy that may only be resorted to by a litigant to protect or
preserve his rights or interests and for no other purpose during Pursuant to Section 13, Article VIII of the Constitution, I certify
the pendency of the principal action. The dismissal of the that the conclusions in the above Decision had been reached in
principal action thus results in the denial of the prayer for the consultation before the case was assigned to the writer of the
issuance of the writ. x x x. (Emphasis supplied.) opinion of the Courts Division.

In view of intervening circumstances, BCA can no longer be RENATO C. CORONA


granted injunctive relief and the civil case before the trial court
should be accordingly dismissed. However, this is without
Chief Justice
prejudice to the parties litigating the main controversy in
arbitration proceedings, in accordance with the provisions of the
Amended BOT Agreement, which should proceed with
dispatch.
Footnotes
It does not escape the attention of the Court that the delay in
the submission of this controversy to arbitration was caused by 1 Rollo, pp. 84-92.
the ambiguity in Section 19.02 of the Amended BOT Agreement
regarding the proper body to which a dispute between the 2 Id. at 93.
parties may be submitted and the failure of the parties to agree
on such an arbitral tribunal. However, this Court cannot allow 3 The International Civil Aviation Organization (ICAO) is a
this impasse to continue indefinitely. The parties involved must specialized agency of the United Nations which was
sit down together in good faith and finally come to an established on December 7, 1944 by 52 nations whose aim
understanding regarding the constitution of an arbitral tribunal was to assure the safe, orderly and economic development of
mutually acceptable to them. international air transport. ICAO was created with the signing in
Chicago of the Convention on International Civil Aviation. ICAO
WHEREFORE, the instant petition is hereby GRANTED. The is the permanent body charged with the administration of the
assailed Order dated February 14, 2007 of the Regional Trial principles laid out in the Convention. (see
Court of Pasig in Civil Case No. 71079 and the Writ of http://www.icao.int/icao/en/m_about.html.)
Preliminary Injunction dated February 23, 2007 are
REVERSED and SET ASIDE. Furthermore, Civil Case No. 4 ICAO's mandate to develop MRTDs is provided by Articles 22,
71079 is hereby DISMISSED. 23 and 37 of the Chicago Convention which oblige Contracting
States to develop and adopt international standards for
No pronouncement as to costs. customs, immigration and other procedures to facilitate the
border-crossing processes involved in international air
SO ORDERED. transport. In order to address the clearance of increased
passengers volumes that came with the emergence of wide
TERESITA J. LEONARDO-DE CASTRO body aircraft, ICAO took the initiative and published the first
edition of Document No. 9303 in 1980.
(http://www2.icao.int/en/MRTD/Pages/Overview.aspx.)
Associate Justice
5 A Machine Readable Travel Document (MRTD) is an
WE CONCUR:
international travel document (e.g., a passport or visa)
containing eye- and machine-readable data. Each type of
RENATO C. CORONA MRTD contains, in a standard format, the holder's identification
details, including a photograph or digital image, with mandatory
Chief Justice identity elements reflected in a two-line machine readable zone
(MRZ) printed in Optical Character Recognition-B (OCR-B)
Chairperson style. (Id.)

PRESBITERO J. VELASCO, JR.


6 The relevant MARIANO
portion of Section 11.3, IRR of the BOT Law,
C. DEL CASTILLO
states:
Associate Justice Associate Justice
JOSE PORTUGAL PEREZ Sec. 11.3. Notice of Award. The Notice of Award shall
ADR || First Batch 95

indicate, among others, that the awardee must submit within 20 Id. at 671-675.
thirty (30) calendar days from official receipt of the Notice of
Award the following: 21 Id. at 692.

a. prescribed performance security; 22 Id. at 256-257.

b. proof of commitment of equity contribution as specified by 23The Amended BOT Agreement was dated April 2, 2002 and
the Agency/LGU and subject to current monetary rules and not 2005.
regulations, and indications of financing resources;
24 Rollo, pp. 697-699.
c. in the case of a joint venture/consortium, the agreement
indicating that the members are jointly, severally and solidarily 25 Id. at 258-259.
liable for the obligations of the project proponent under the
contract; or
26 Section 19.01 of the Amended BOT Agreement provides:
d. in case a project company is formed, proof of registration in
accordance with Philippine laws. Section 19.01 Dispute Settlement Any dispute or
controversy of any kind whatsoever between the DFA and the
BCA (such dispute or controversy being referred to herein as a
7 Rollo, pp. 177-200.
"Dispute") which may arise out of or in connection with this
Agreement, in the first instance shall be settled within ninety
8 Id. at 178. (90) days through amicable means, such as, but not limited to,
mutual discussion.
9 Id. at 201-226.
27 Rollo, pp. 260-266.
10Section 11.8 of the IRR of the BOT Law provides that "[t]he
successful bidder should sign the contract within seven (7) 28 Id. at 222.
calendar days from receipt of the advice of the Agency/LGU
that all requirements for award, as provided for in Section 11.3 29 Id. at 266; page 7 of the Request for Arbitration.
are fully complied with."
30 Id. at 711-740.
11 Rollo, pp. 214-224.
31 Id. at 741-742.
12 Id. at 227-232.
32 Id. at 743-745.
13 Id. at 187-189.
33 Id. at 268-269.
14 Id. at 234-237.
34 Id. at 273-275.
15 Id. at 238-239.
35 Id. at 276-286.
16 Id. at 240; erroneously dated as February 22, 2004.
36 Section 28. Grant of Interim Measure of Protection. (a) It is
17 Section 5.02(A) of the Amended BOT Agreement provides:
not incompatible with an arbitration agreement for a party to
request, before constitution of the tribunal, from a Court an
Section 5.02 The BCA further warrants to the DFA that: interim measure of protection and for the Court to grant such
measure. After constitution of the arbitral tribunal and during
A. It shall have the necessary capitalization and shall obtain the arbitral proceedings, a request for an interim measure of
required financing to carry out the MRP/V Project in accordance protection, or modification thereof, may be made with the
with this amended BOT Agreement; x x x. (Rollo, p. 208.) arbitral tribunal or to the extent that the arbitral tribunal has no
power to act or is unable to act effectively, the request may be
18 Rollo, pp. 241-243. made with the Court. The arbitral tribunal is deemed constituted
when the sole arbitrator or the third arbitrator, who has been
nominated, has accepted the nomination and written
19 Id. at 252-255.
communication of said nomination and acceptance has been
ADR || First Batch 96

received by the party making the request. 54 Id. at 2185-2186.

(b) The following rules on interim or provisional relief shall be 55 G.R. No. 188456, September 10, 2009, 599 SCRA 69.
observed:
56Id. at 112-113, citing Chavez v. National Housing Authority,
(1) Any party may request that provisional relief be granted G.R. No. 164527, August 15, 2007, 530 SCRA 235, 285;
against the adverse party. Cabarles v. Maceda, G.R. No. 161330, February 20, 2007, 516
SCRA 303, 320.
(2) Such relief may be granted:
57Aparece v. J. Marketing Corporation, G.R. No. 174224,
(i) to prevent irreparable loss or injury; October 17, 2008, 569 SCRA 636, 643.

(ii) to provide security for the performance of any obligation;


58See Rules of Court, Rule 131, Section 3(m); Philippine Agila
Satellite, Inc. v. Trinidad-Lichauco, G.R. No. 142362, May 3,
2006, 489 SCRA 22, 31.
(iii) to produce or preserve any evidence; or
59Ateneo de Naga University v. Manalo, 497 Phil. 635, 646-647
(iv) to compel any other appropriate act or omission.
(2005).
37 Rollo, p. 284; page 9 of the Petition for Interim Relief. 60See, for example, Chuidian v. Sandiganbayan, G.R. Nos.
156383 & 160723, July 31, 2006, 497 SCRA 327, 339.
38 Id. at 287-289.
61An Act Amending Certain Sections of Republic Act No. 6957,
39 Id. at 290-291. Entitled "An Act Authorizing the Financing, Construction,
Operation and Maintenance of Infrastructure Projects by the
40 Id. at 313-338. Private Sector, and for Other Purposes" or the Philippine Build-
Operate-Transfer (BOT) Law, Approved on May 5, 1994.
41 Id. at 339-356.
62An Act Providing for the Modernization, Standardization and
42 Id. at 357-408. Regulation of the Procurement Activities of the Government
and for Other Purposes, Approved on January 18, 2003.
43 Id. at 409-424.
63 Transcript of Senate Deliberations on Senate Bill 2038
44 Id. at 425-440. (August 2 and 9, 2000), DFA and BSP Petition; rollo, pp. 53-54.

45 Id. at 92.
64 The definition of "infrastructure" under Republic Act No. 9184
is found in Section 5(k), not Section 5(c).
46 Id. at 473-484.
65 Rollo, pp. 88-89.
47 Id. at 3-485.
66Endencia v. David, 93 Phil. 696, 701 (1953); Misamis Lumber
Co., Inc. v. Collector of Internal Revenue, 102 Phil. 116, 122
48 Id. at 491-495.
(1957); Calderon v. Carale, G.R. No. 91636, April 23, 1992, 208
SCRA 254, 263.
49 Id. at 497-502.
67City of Manila v. Manila Remnant Co., Inc., 100 Phil. 796, 800
50 Id. at 511-1169. (1957).

51 Id. at 1931-1965. 68Some examples of provisions in the IRR of Republic Act No.
9184 which differentiate among infrastructure projects, goods
52 Id. at 1837. procurement and consulting services procurement follow:

53 Id. at 1978-1980. In Section 13.1, the IRR specifies who may be observers during
the bidding process for the different types of procurement
activities.
ADR || First Batch 97

Section 21 sets out different guidelines for the contents of the technical specifications/requirements of the contract. Once the
invitation to bid and the periods for advertising and posting the final revised technical specifications are completed and duly
invitation to bid for each type of procurement activity. approved by the concerned BAC, copies of the same shall be
issued to all the bidders identified in the first stage who shall
Section 23 enumerates the proponents eligibility requirements then be required to submit their revised technical tenders,
for the procurement of goods and infrastructure projects while including their price proposals in two (2) separate sealed
the eligibility requirements for consulting services are specified envelopes in accordance with this IRR-A, at a specified
in Section 24. deadline, after which time no more bids shall be received. The
concerned BAC shall then proceed in accordance with the
procedure prescribed in this IRR-A. (Emphasis supplied.)
Section 25 lays down different documentation requirements for
bids for each type of procurement activity.
76 An Act to Institutionalize the Use of an Alternative Dispute
Resolution System in the Philippines and to Establish the Office
Section 32 sets out the guidelines for bids evaluation for the
for Alternative Dispute Resolution, and for Other Purposes;
procurement of goods and infrastructure projects while Section
approved on April 2, 2004.
33 contains the guidelines for bids evaluation for consulting
services.
77 379 Phil. 743, 749-750 (2000).
Section 42 states that the contract implementation guidelines
for the procurement of goods, infrastructure projects and
78 G.R. No. 146717, November 22, 2004, 443 SCRA 307, 336;
consulting services are set out in separate annexes (Annexes citing Philippine National Bank v. Ritratto Group, Inc., 414 Phil.
D, E and F of the IRR). 494, 507 (2001).

69Rollo pp. 273-275 and 787-789; Annex AA of the Petition and


79 351 Phil. 172, 186 (1998).
Annex 30 of BCAs Comment.
80 Rollo, p. 266.
70 Id. at 790; Annex 31 of BCAs Comment.
81 Smith, Bell & Company (Ltd.) v. Natividad, 40 Phil. 136
71 Id. at 1713; TSN of the hearing held on February 7, 2007. (1919); Central Bank (now Bangko Sentral ng Pilipinas)
Employees Association, Inc. v. Bangko Sentral ng Pilipinas,
G.R. No. 148208, December 15, 2004, 446 SCRA 299; Serrano
72 Id. at 2347-2353.
v. Gallant Maritime Services, Inc., G.R. No. 167614, March 24,
2009.
73 Id. at 2354-2358.
82Roxas & Co., Inc. v. Court of Appeals, 378 Phil. 727 (1999);
74 Id. at 2357. Kuwait Airways Corporation v. Philippine Airlines, Inc., G.R. No.
156087, May 8, 2009, 587 SCRA 399.
75 Section 30.4 of the IRR of Republic Act No. 9184 states:
83Roxas & Co., Inc. v. Court of Appeals, id.; Brgy. Sindalan,
30.4. For the procurement of goods where, due to the nature of San Fernando, Pampanga v. Court of Appeals, G.R. No.
the requirements of the project, the required technical 150640, March 22, 2007, 518 SCRA 649.
specifications/requirements of the contract cannot be precisely
defined in advance of bidding, or where the problem of 84 PDRCI Letter dated March 28, 2007, rollo pp. 1856-57.
technically unequal bids is likely to occur, a two (2)-stage
bidding procedure may be employed. In these cases, the 85 Supra note 78 at 507.
procuring entity concerned shall prepare the bidding
documents, including the technical specification in the form of
performance criteria only. Under this procedure, prospective
bidders shall be requested at the first stage to submit their
respective Letter of Intent, eligibility requirements if needed,
and initial technical proposals only (no price tenders). The
concerned BAC shall then evaluate the technical merits of the
proposals received from eligible bidders vis--vis the required
performance standards. A meeting/discussion shall then be
held by the BAC with those eligible bidders whose technical
tenders meet the minimum required standards stipulated in the
bidding documents for purposes of drawing up the final revised
ADR || First Batch 98

Republic of the Philippines TOPSOIL ALSO BECAUSE THE EVIDENCE ON RECORD


SUPREME COURT CONFIRMS THE EXISTENCE OF RESPONDENT PEAS
Manila WRITTEN CONSENT, AND THE FACT THAT IT IS
SPECIAL THIRD DIVISION INDESPENSABLE TO COMPLETING THE PROJECT.
WITHOUT SUCH ASSURANCE OF REIMBURSEMENT,
G.R. Nos. 147925-26 July 7, 2010 PETITIONER WOULD NOT HAVE TAKEN SUCH PRUDENT
ACTION.
ELPIDIO S. UY, doing business under the name and style
of EDISON DEVELOPMENT & CONSTRUCTION, Petitioner, III

vs. x x x PETITIONER SHOULD BE ALLOWED TO RECOVER


THE COSTS HE INCURRED FOR THE MOBILIZATION OF
WATER TRUCKS ALSO BECAUSE RESPONDENT
PUBLIC ESTATES AUTHORITY, Respondent.
BREACHED ITS OBLIGATIONS UNDER THE CONTRACT.
RESOLUTION
IV
NACHURA, J.:
WITH REGARD TO THE COURT OF APPEALS ILLEGAL
INJUNCTION PREVENTING PETITIONER FROM
Before us are (i) the Motion for Partial Reconsideration filed by RECOVERING HIS CLAIMS AGAINST RESPONDENT PEA IN
petitioner Elpidio S. Uy (Uy), doing business under the name CIAC CASE NO. 03-2001, THIS SHOULD HAVE BEEN
and style of Edison Development & Construction (EDC), and (ii) LIFTED SINCE IT INVOLVES CLAIMS SEPARATE AND
the Motion for Reconsideration filed by respondent Public DISTINCT FROM THE CASE A QUO.2
Estates Authority (PEA) of our June 8, 2009 Decision, the fallo
of which reads:
PEA, on the other hand, assails the Decision on the following
grounds:
WHEREFORE, the petition is PARTIALLY GRANTED. The
assailed Joint Decision and Joint Resolution of the Court of
I.
Appeals in CA-G.R. SP Nos. 59308 and 59849 are AFFIRMED
with MODIFICATIONS. Respondent Public Estates Authority is
ordered to pay Elpidio S. Uy, doing business under the name THE FACTUAL FINDINGS AND CONCLUSIONS OF THE
and style Edison Development and Construction, CONSTRUCTION INDUSTRY ARBITRATION COMMISSION
P55,680,492.38 for equipment rentals on standby; (CIAC) INSOFAR AS THE ARBITRAL AWARD TO
P2,275,721.00 for the cost of idle manpower; and PETITIONER IS CONCERNED, WHICH THE COURT OF
P6,050,165.05 for the construction of the nursery shade net APPEALS AND THE FIRST DIVISION OF THIS HONORABLE
area; plus interest at 6% per annum to be computed from the COURT AFFIRMED, HAS LONG BECOME FINAL AND
date of the filing of the complaint until finality of this Decision EXECUTORY.
and 12% per annum thereafter until full payment. Respondent
PEA is further ordered to pay petitioner Uy 10% of the total II.
award as attorneys fees.
THE CIAC ARBITRAL AWARD HAD ALREADY BEEN
SO ORDERED.1 IMPLEMENTED UNDER WRIT OF EXECUTION DATED 19
SEPTEMBER 2000, WRIT OF EXECUTION DATED 31
Uy seeks partial reconsideration of our Decision. He argues AUGUST 2001 AND SUPPLEMENTAL WRIT OF EXECUTION
that: DATED 10 APRIL 2002.3

I We will deal first with Uys motion.

x x x THE HONORABLE COURT ERRED IN THE Uy objects to the factor rate used in the computation of the
COMPUTATION OF THE DAMAGES DUE THE PETITIONER award for standby equipment costs. He points out that the
FOR THE STANDBY EQUIPMENT COST. actual number of equipment deployed and which remained on
standby, occasioned by the delay in delivery of work areas, has
not been considered in the computation. The Association of
II
Carriers and Equipment Lessors (ACEL) rate or the factor rate
used was only the total average rate, without regard to the
x x x PETITIONER SHOULD BE REIMBURSED FOR COSTS actual number of equipment deployed. He, therefore, insists
INCURRED FOR ADDITIONAL HAULING DISTANCE OF
ADR || First Batch 99

that an increase in the award is in order. We cannot sustain this claim that is premised mainly on the
principle of unjust enrichment. We stress that the principle of
We find Uys argument on this point meritorious; and this Court unjust enrichment cannot be validly invoked by a party who,
is swayed to modify the formula used in the computation of the through his own act or omission, took the risk of being denied
award. payment for additional costs by not giving the other party prior
notice of such costs and/or by not securing their written consent
thereto, as required by law and their contract.7
The Certification,4 dated December 6, 1996, shows that EDC
mobilized the following equipment for the Heritage Park Project,
viz.: Similarly, we find no cogent reason to lift the injunction issued
in CIAC Case No. 03-2001. We are not persuaded by Uys
argument that the claims under CIAC Case No. 03-2001 are
Description Number
different from his claims in CIAC Case No. 02-2000. As we
Road Grader 2
explained in our Decision, there is only one cause of action
Pay Loader 2
running through Uys undertakings the violation of his alleged
Dump Trucks 10
right under the Landscaping and Construction Agreement.
Tractor with attachments 2
Therefore, the landscaping agreement is indispensable in the
Backhoe 2
prosecution of his claims in both CIAC Cases No. 02-2000 and
Delivery Trucks 3
No. 03-2001. We reiterate that a party, either by varying the
Rolo-tiller 0
form or action or by bringing forward in a second case
Concrete Mixer 4
additional parties or arguments, cannot escape the effects of
Bar Cutter 2
res judicata when the facts remain the same, at least where
Welding Machine 2
such new parties or matter could have been impleaded or
Roller 1
pleaded in the prior action.
Bulldozer 1
1avvphi1

Concrete Cutter 2
Plate Compactor 2 In fine, except for the claim for standby equipment costs, this
Compressor/Jack Hammer 3 Court finds no cogent reason to depart from our June 8, 2009
Genset 5KVA 1 Decision.
Electric drill/ Holesaw 4
We now go to PEAs motion.

These equipment remained in the project site on the days that PEA insists that our Decision in this case transgresses the
EDC was waiting for the turnover of additional work areas.5 principle of res judicata. It asserts that the propriety of Uys
Thus, we agree with Uy that the actual number of equipment monetary claims against PEA had already been considered and
mobilized should be included in computing the award for passed upon by this Court in G.R. Nos. 147933-34.
standby equipment cost. The award must, therefore, be
modified using the following formula: The argument is specious.

Actual period of delay (18.2 months) x average rate per ACEL x In G.R. Nos. 147933-34, this Court was very explicit in its
number of equipment declaration that its Decision was independent of, and without
prejudice to, the appeal filed by Uy, viz.:
However, we cannot simply accept in full Uys claim that he is
entitled to P71,009,557.95 as standby equipment cost. The However, in order not to prejudice the deliberations of the
records show that not all of the equipment were operational; Courts Second Division in G.R. Nos. 147925-26, it should be
several were under repair.6 Accordingly, we find it necessary to stated that the findings made in this case, especially as regards
remand the records of the case to the Construction Industry the correctness of the findings of the CIAC, are limited to the
Arbitration Commission (CIAC), which decided the case in the arbitral awards granted to respondent Elpidio S. Uy and to the
first instance, for the proper computation of the award of denial of the counterclaims of petitioner Public Estates
standby equipment cost based on the foregoing formula. Authority. Our decision in this case does not affect the other
claims of respondent Uy which were not granted by the CIAC in
On the claim for costs for additional hauling distance of topsoil its questioned decision, the merits of which were not submitted
and for mobilization of water truck, we maintain our ruling that a to us for determination in the instant petition.8
written approval of PEAs general manager was indispensable
before the claim for additional cost can be granted. In this case, Indubitably, this Courts Decision in G.R. Nos. 147933-34 will
the additional costs were incurred without the written approval not bar the grant of additional award to Uy.
of PEA. The denial of Uys claims was, therefore, appropriate.
WHEREFORE, Uys Motion for Partial Reconsideration is
ADR || First Batch 10
0
PARTLY GRANTED. PEAs Motion for Reconsideration, on the
other hand, is DENIED with FINALITY. The assailed Decision
dated June 8, 2009 is AFFIRMED with MODIFICATION as to Footnotes
the award of standby equipment cost. The case is hereby
REMANDED to the Construction Industry Arbitration *Designated member vice Associate Justice Minita V. Chico-
Commission solely for the purpose of computing the exact
Nazario (ret.) per Special Order No. 631 dated April 29, 2009.
amount of standby equipment cost pursuant to the formula
herein specified. The CIAC is DIRECTED to compute the award
and effect payment thereof within thirty (30) days from receipt Designated member vice Associate Justice Conchita Carpio
**

of the records of this case. Morales per Special Order No. 649 dated May 25, 2009.

No further pleadings will be entertained.


***Designated member vice Associate Justice Consuelo
Ynares-Santiago (ret.) per Raffle dated October 21, 2009.
SO ORDERED.
1 Rollo, p. 995.
ANTONIO EDUARDO B. NACHURA
2 Id. at 999.
Associate Justice
3 Id. at 1047.
WE CONCUR:
4 Exhibit "J"; Folder No. 2, CIAC Case No. 02-2002.
RENATO C. CORONA*
5 See Exhibits "F," "H-1" to "H-29," "I"; id.
Chief Justice
6 See Exhibit C-1," id.
PRESBITERO J. VELASCO, JR. ** ARTURO D. BRION***
7 Powton Conglomerate, Inc. v. Agcolicol, 448 Phil. 643 (2003).
Associate Justice Associate Justice
DIOSDADO M. PERALTA
8 Public Estates Authority v. Uy, 423 Phil. 407, 419 (2001).

Associate Justice

ATTESTATION

I attest that the conclusions in the above Resolution had been


reached in consultation before the case was assigned to the
writer of the opinion of the Courts Division.

ANTONIO EDUARDO B. NACHURA

Chairperson, Special Third Division

CERTIFICATION

Pursuant to Section 13, Article VIII of the Constitution and the


Division Chairperson's Attestation, I certify that the conclusions
in the above Resolution had been reached in consultation
before the case was assigned to the writer of the opinion of the
Courts Division.

RENATO C. CORONA

Chief Justice
ADR || First Batch 10
1
Republic of the Philippines 4501200300-000275 amounting to P15,724,000.00 and
SUPREME COURT P9,276,000.00 respectively, or a total amount of
Manila P25,000,000.00. The parties also agreed that respondent will
SECOND DIVISION perform variation orders in the Project. In connection with the
Project, petitioner supplied manpower chargeable against
G.R. No. 172525 October 20, 2010 respondent.

SHINRYO (PHILIPPINES) COMPANY, INC., Petitioner, Respondent was not able to finish the entire works with
petitioner due to financial difficulties. Petitioner paid respondent
a total amount of P26,547,624.76. On June 25, 2005 [should
vs.
read 2003], respondent, through its former counsel sent a letter
to petitioner demanding for the payment of its unpaid balance
RRN INCORPORATED,* Respondent. amounting to P5,275,184.17. Petitioner claimed material back
charges in the amount of P4,063,633.43. On September 26,
DECISION 2003, respondent only acknowledged P2,371,895.33 as
material back charges. Thereafter, on October 16, 2003,
PERALTA, J.: respondent sent another letter to petitioner for them to meet
and settle their dispute.
This resolves the Petition for Review on Certiorari under Rule
45 of the Rules of Court, praying that the Decision1 of the Court On January 8, 2004, respondent sent another letter to petitioner
of Appeals (CA) dated February 22, 2006, affirming the regarding the cost of equipment rental and the use of
Decision of the Construction Industry Arbitration Commission scaffolding. Thereafter, on August 12, 2004, petitioner sent a
(CIAC), and the CA Resolution2 dated April 26, 2006, denying letter to respondent denying any unpaid account and the failure
herein petitioner's motion for reconsideration, be reversed and in their negotiations for amicable settlement.
set aside.
On September 3, 2004, respondent, through its new counsel,
The facts, as accurately narrated in the CA Decision, are as advised petitioner of their intention to submit the matter to
follows. arbitration. Thereafter, their dispute was submitted to
arbitration. During the preliminary conference, the parties
Petitioner Shinryo (Philippines) Company, Inc. (hereinafter agreed in their Terms of Reference to resolve eight issues, to
petitioner) is a domestic corporation organized under Philippine wit:
laws. Private respondent RRN Incorporated (hereinafter
respondent) is likewise a domestic corporation organized under 1. What should be the basis in evaluating the variation cost?
Philippine laws.
1.1 How much is the variation cost?
Respondent filed a claim for arbitration against petitioner before
CIAC for recovery of unpaid account which consists of unpaid 2. Is the Respondent (petitioner in the instant case) justified in
portions of the sub-contract, variations and unused materials in charging claimant (herein respondent) the equipment rental fee
the total sum of P5,275,184.17 and legal interest in the amount and for the use of the scaffoldings? If so, how much should be
of P442,014.73. Petitioner filed a counterclaim for overpayment charged to Claimant?
in the amount of P2,512,997.96.
3. What should be the basis in evaluating the total cost of
The parties admitted several facts before the CIAC. It was materials supplied by Respondent to the Project which is
shown that petitioner and respondent executed an Agreement chargeable to Claimant?
and Conditions of Sub-contract (hereafter Agreement signed on
June 11, 1996 and June 14, 1996, respectively. Respondent 3.1 How much is the total cost of materials supply chargeable
signified its willingness to accept and perform for petitioner in to Claimant?
any of its projects, a part or the whole of the works more
particularly described in Conditions of Sub-Contract and other
4. How much is the value of the remaining works left undone by
Sub-contract documents.
the Claimant in the project?
On June 11, 2002, the parties executed a "Supply of
5. Is the Claimant's claim for inventory of excess materials
Manpower, Tools/Equipment, Consumables for the Electrical
valid? If so, how much is the value thereof?
Works-Power and Equipment Supply, Bus Duct Installation" for
the Phillip Morris Greenfield Project (hereafter Project) covered
by Purchase Order Nos. 4501200300-000274 and 6. Is the Respondent entitled to its claim for an overpayment in
ADR || First Batch 10
2
the amount of P2,512,997.96? CONSIDERING THAT:

7. Is Claimant entitled to its claim for interest? If so, how much? A. RESPONDENT RRN ADMITTED THE VALIDITY OF THE
DEDUCTIONS ON ACCOUNT OF MATERIAL SUPPLY,
8. Who between the parties shall bear the cost of Arbitration? WHICH INCLUDED THE INVENTORIED MATERIALS.

The CIAC rendered the assailed decision after the presentation B. RESPONDENT RRN HAS NO BASIS TO CLAIM BECAUSE
of the parties' evidence. [The dispositive portion of said ENGR. BONIFACIO ADMITTED THAT RESPONDENT RRN
decision reads as follows: FAILED TO ESTABLISH WHETHER THE MATERIALS CAME
FROM RESPONDENT RRN OR FROM PETITIONER AND
THAT IT WAS PETITIONER THAT ACTUALLY INSTALLED
WHEREFORE, judgment is hereby rendered in favor of the
THE SAID MATERIALS AS PART OF REMAINING WORKS
claimant and respondent is ordered to pay claimant its unpaid
THAT PETITIONER TOOK OVER FROM RESPONDENT
account in the sum of P3,728,960.54 plus legal interest of 6%
RRN.
reckoned from June 25, 2003 up to the filing of the case on
October 11, 2004 and 12% of P3,728,960.54 from the finality of
the judgment until fully paid and arbitration cost of P104,333.82 C. THE CLAIM FOR THE VALUE OF INVENTORIED
representing claimant's share of the arbitration cost which MATERIALS IS A DOUBLE CLAIM OR DOUBLE ENTRY
respondent should reimburse. BECAUSE IN THE COMPUTATION OF THE FINAL
ACCOUNT, RESPONDENT RRN WAS CREDITED THE FULL
CONTRACT PRICE AND THE COST OF VARIATIONS,
SO ORDERED.]
WHICH INCLUDED THE INVENTORIED MATERIALS.
Petitioner accepts the ruling of the CIAC only in Issue No. 1 and
IV. IN RENDERING THE QUESTIONED DECISION AND
Sub-Issue No. 1.1 and in Issue No. 2 in so far as the amount of
QUESTIONED RESOLUTION, THE COURT OF APPEALS
P440,000.00 awarded as back charges for the use of
COMMITTED A GRAVE REVERSIBLE ERROR IN THAT IT
scaffoldings. x x x3
COMPLETELY DISREGARDED THE PROVISION OF THE
SUBCONTRACT, WHICH ALLOWED PAYMENT OF ACTUAL
On February 22, 2006, the CA promulgated the assailed COST INCURRED BY PETITIONER IN COMPLETING THE
Decision affirming the decision of the CIAC. The CA upheld the REMAINING WORKS THAT PRIVATE RESPONDENT
CIAC ruling that petitioner failed to adduce sufficient proof that ADMITTEDLY FAILED TO COMPLETE.
the parties had an agreement regarding charges for
respondent's use of the manlift. As to the other charges for
V. THE COURT OF APPEALS COMMITTED A GRAVE
materials, the CA held that the evidence on record amply
REVERSIBLE ERROR WHEN IT COMPLETELY
supports the CIAC findings. Petitioner moved for
DISREGARDED THE EVIDENCE ON ACTUAL COST
reconsideration of said ruling, but the same was denied per
INCURRED BY PETITIONER IN COMPLETING THE
Resolution dated April 26, 2006.
REMAINING WORKS.
Hence, this petition where it is alleged that:
VI. THE COURT OF APPEALS COMMITTED GRAVE
REVERSIBLE ERROR WHEN IT AFFIRMED THE CIAC
I. THE HONORABLE COURT OF APPEALS COMMITTED AWARD FOR INTERESTS AND ARBITRATION COSTS IN
GRAVE REVERSIBLE ERROR WHEN IT DENIED FAVOR OF RESPONDENT RRN.4
PETITIONER'S CLAIM FOR MANLIFT EQUIPMENT RENTAL
IN THE AMOUNT OF P511,000.00 DESPITE EVIDENCE ON
The petition is bereft of merit.
RECORD THAT RESPONDENT RRN ACTUALLY USED AND
BENEFITED FROM THE MANLIFT EQUIPMENT.
Despite petitioner's attempts to make it appear that it is
advancing questions of law, it is quite clear that what petitioner
II. IN RENDERING THE QUESTIONED DECISION AND
seeks is for this Court to recalibrate the evidence it has
QUESTIONED RESOLUTION, THE HONORABLE COURT OF
presented before the CIAC. It insists that its evidence
APPEALS HAS DECIDED A QUESTION OF SUBSTANCE
sufficiently proves that it is entitled to payment for respondent's
NOT IN ACCORD WITH LAW AND/OR WITH THE
use of its manlift equipment, and even absent proof of the
APPLICABLE DECISIONS OF THE HONORABLE SUPREME
supposed agreement on the charges petitioner may impose on
COURT.
respondent for the use of said equipment, respondent should
be made to pay based on the principle of unjust enrichment.
III. THE COURT OF APPEALS COMMITTED A GRAVE Petitioner also questions the amounts awarded by the CIAC for
REVERSIBLE ERROR IN AFFIRMING THE CIAC AWARD inventoried materials, and costs incurred by petitioner for
FOR THE VALUE OF INVENTORIED MATERIALS completing the work left unfinished by respondent.
ADR || First Batch 10
3
As reiterated by the Court in IBEX International, Inc. v. Moreover, to substantiate a claim for unjust enrichment,
Government Service Insurance System,5 to wit: the claimant must unequivocally prove that another party
knowingly received something of value to which he was not
It is settled that findings of fact of quasi-judicial bodies, entitled and that the state of affairs are such that it would be
which have acquired expertise because their jurisdiction is unjust for the person to keep the benefit. Unjust enrichment is a
confined to specific matters, are generally accorded not term used to depict result or effect of failure to make
only respect, but also finality, especially when affirmed by remuneration of or for property or benefits received under
the Court of Appeals. In particular, factual findings of circumstances that give rise to legal or equitable obligation to
construction arbitrators are final and conclusive and not account for them; to be entitled to remuneration, one must
reviewable by this Court on appeal. confer benefit by mistake, fraud, coercion, or request. Unjust
enrichment is not itself a theory of reconvey. Rather, it is a
prerequisite for the enforcement of the doctrine of restitution.
This rule, however, admits of certain exceptions. In Uniwide
Sales Realty and Resources Corporation v. Titan-Ikeda
Construction and Development Corporation, we said: Article 22 of the New Civil Code reads:

In David v. Construction Industry and Arbitration Commission, Every person who, through an act of performance by another,
we ruled that, as exceptions, factual findings of construction or any other means, acquires or comes into possession of
arbitrators may be reviewed by this Court when the petitioner something at the expense of the latter without just or legal
proves affirmatively that: (1) the award was procured by ground, shall return the same to him.
corruption, fraud or other undue means; (2) there was evident
partiality or corruption of the arbitrators or any of them; (3) the In order that accion in rem verso may prosper, the essential
arbitrators were guilty of misconduct in refusing to hear elements must be present: (1) that the defendant has been
evidence pertinent and material to the controversy; (4) one or enriched, (2) that the plaintiff has suffered a loss, (3) that the
more of the arbitrators were disqualified to act as such under enrichment of the defendant is without just or legal ground, and
Section nine of Republic Act No. 876 and willfully refrained from (4) that the plaintiff has no other action based on contract,
disclosing such disqualifications or of any other misbehavior by quasi-contract, crime or quasi-delict.
which the rights of any party have been materially prejudiced;
or (5) the arbitrators exceeded their powers, or so imperfectly An accion in rem verso is considered merely an auxiliary action,
executed them, that a mutual, final and definite award upon the available only when there is no other remedy on contract,
subject matter submitted to them was not made. 1avvp++i1

quasi-contract, crime, and quasi-delict. If there is an obtainable


action under any other institution of positive law, that action
Other recognized exceptions are as follows: (1) when there is a must be resorted to, and the principle of accion in rem verso will
very clear showing of grave abuse of discretion resulting in lack not lie.9
or loss of jurisdiction as when a party was deprived of a fair
opportunity to present its position before the Arbitral Tribunal or As found by both the CIAC and affirmed by the CA, petitioner
when an award is obtained through fraud or the corruption of failed to prove that respondent's free use of the manlift was
arbitrators, (2) when the findings of the Court of Appeals are without legal ground based on the provisions of their contract.
contrary to those of the CIAC, and (3) when a party is deprived Thus, the third requisite, i.e., that the enrichment of respondent
of administrative due process.6 is without just or legal ground, is missing. In addition,
petitioner's claim is based on contract, hence, the fourth
A perusal of the records would reveal that none of the requisite that the plaintiff has no other action based on
aforementioned circumstances, which would justify exemption contract, quasi-contract, crime or quasi-delict is also absent.
of this case from the general rule, are present here. Such being Clearly, the principle of unjust enrichment is not applicable in
the case, the Court, not being a trier of facts, is not duty-bound this case.
to examine, appraise and analyze anew the evidence
presented before the arbitration body.7 The other issues raised by petitioner all boil down to whether
the CIAC or the CA erred in rejecting its claims for costs of
Petitioner's reliance on the principle of unjust enrichment is some materials.
likewise misplaced. The ruling of the Court in University of the
Philippines v. Philab Industries, Inc.8 is highly instructive, thus: Again, these issues are purely factual and cannot be properly
addressed in this petition for review on certiorari. In Hanjin
Unjust enrichment claims do not lie simply because one party Heavy Industries and Construction Co., Ltd. v. Dynamic
benefits from the efforts or obligations of others, but instead it Planners and Construction Corp.,10 it was emphasized that
must be shown that a party was unjustly enriched in the sense mathematical computations, the propriety of arbitral awards,
that the term unjustly could mean illegally or unlawfully. claims for "other costs" and "abandonment" are factual
questions. Since the discussions of the CIAC and the CA in
ADR || First Batch 10
4
their respective Decisions show that its factual findings are Associate Justice
supported by substantial evidence, there is no reason why this
Court should not accord finality to said findings. Verily, to ATTESTATION
accede to petitioner's request for a recalibration of its evidence,
which had been thoroughly studied by both the CIAC and the
I attest that the conclusions in the above Decision had been
CA would result in negating the objective of Executive Order
reached in consultation before the case was assigned to the
No. 1008, which created an arbitration body to ensure the
writer of the opinion of the Courts Division.
prompt and efficient settlement of disputes in the construction
industry. Thus, the Court held in Uniwide Sales Realty and
Resources Corporation v. Titan-Ikeda Construction and ANTONIO T. CARPIO
Development Corporation,11 that:
Associate Justice
x x x The Court will not review the factual findings of an arbitral
tribunal upon the artful allegation that such body had Second Division, Chairperson
"misapprehended facts" and will not pass upon issues which
are, at bottom, issues of fact, no matter how cleverly disguised CERTIFICATION
they might be as "legal questions." The parties here had
recourse to arbitration and chose the arbitrators themselves; Pursuant to Section 13, Article VIII of the Constitution and the
they must have had confidence in such arbitrators. The Court Division Chairpersons Attestation, I certify that the conclusions
will not, therefore, permit the parties to relitigate before it the in the above Decision had been reached in consultation before
issues of facts previously presented and argued before the the case was assigned to the writer of the opinion of the Courts
Arbitral Tribunal, save only where a clear showing is made that, Division.
in reaching its factual conclusions, the Arbitral Tribunal
committed an error so egregious and hurtful to one party as to
RENATO C. CORONA
constitute a grave abuse of discretion resulting in lack or loss of
jurisdiction.12
Chief Justice
As discussed above, there is nothing in the records that point to
any grave abuse of discretion committed by the CIAC.

The awards for interests and arbitration costs are, likewise, Footnotes
correct as they are in keeping with prevailing jurisprudence.13
* The Court of Appeals, Construction Industry Arbitration
IN VIEW OF THE FOREGOING, the Petition is DENIED. The Commission, the Honorable Beda G. Fajardo, Joel J. Marciano
Decision of the Court of Appeals dated February 22, 2006 and and Guillermo Claridad, in their capacities as Chairman and
its Resolution dated April 26, 2006 are AFFIRMED. Member of the Arbitral Tribunal, who were initially included as
respondents in the petition should not be included as such
pursuant to Section 4, Rule 45 of the Rules of Court.
SO ORDERED.
**Designated as an additional member in lieu of Associate
DIOSDADO M. PERALTA
Justice Antonio Eduardo B. Nachura, per raffle dated October
20, 2010.
Associate Justice
Designated as an additional member in lieu of Associate
***
WE CONCUR: Justice Roberto A. Abad, per Special Order No. 905, dated
October 5, 2010.
ANTONIO T. CARPIO
1 Penned by Associate Justice Juan Q. Enriquez, Jr., with
Associate Justice Associate Justices Godardo A. Jacinto and Vicente Q. Roxas,
concurring; rollo, pp. 66-76..
Chairperson
2 Id. at 78-79.
PRESBITERO J. VELASCO, JR. ** TERESITA J. LEONARDO-DE CASTRO***
3 Id. at 66-69.
Associate Justice Associate Justice
JOSE CATRAL MENDOZA 4 Id. at 17-19.
ADR || First Batch 10
5
5 G.R. No. 162095, October 12, 2009, 603 SCRA 306. Republic of the Philippines
SUPREME COURT
6 Id. at 314-315. (Emphasis supplied.) Manila
SECOND DIVISION
7Diesel Construction v. UPSI Property Holdings, Inc. G.R. No.
154885, March 24, 2008, 549 SCRA 12, ---30. G.R. No. 177556 December 8, 2010

8 482 Phil. 693 (2004) TRANSCEPT CONSTRUCTION AND MANAGEMENT


PROFESSIONALS, INC., Petitioner,
9 Id. at 709-711. (Emphasis and underscoring supplied.)
vs.
10G.R. Nos. 169408 & 170144, April 30, 2008, 553 SCRA 541,
558, 565, 568. TERESA C. AGUILAR, Respondent.

11 G.R. No. 126619, December 20, 2006 (quoting David v. DECISION


Construction Industry Arbitration Commission, 479 Phil. 578
[2004]), 511 SCRA 335. CARPIO, J.:

12 Id. at 362. The Case

13See Hanjin Heavy Industries and Construction Co., Ltd. v. Before the Court is a petition for review assailing the 24
Dynamic Planners and Construction Corp., supra note 10, at January 2007 Decision1 and the 20 April 2007 Resolution2 of
576. the Court of Appeals in CA-G.R. SP No. 93021.

The Antecedent Facts

From the decisions of the Court of Appeals and the


Construction Industry Arbitration Commission (CIAC), we
gathered the following facts:

On 18 August 2004, Teresa C. Aguilar (Aguilar) entered into an


Owner-General Contractor Agreement (First Contract) with
Transcept Construction and Management Professionals, Inc.
(Transcept) for the construction of a two-storey split level
vacation house (the Project) located at Phase 3, Block 3, Lot 7,
Canyon Woods, Laurel, Batangas. Under the First Contract, the
Project would cost P3,486,878.64 and was to be completed
within 2103 working days from the date of the First Contract or
on 7 June 2005. Aguilar paid a downpayment of P1 million on
27 August 2004.

On 30 November 2004, Transcept submitted its First Billing to


Aguilar for work accomplishments from start to 15 November
2004, in accordance with the Progressive Billing payment
scheme. Aguilar paid P566,356.

On 1 February 2005, Aguilar received the Second Billing


amounting to P334,488 for the period of 16 November 2004 to
15 December 2004. Transcept informed Aguilar that non-
payment would force them to halt all works on the Project.
Aguilar questioned the Second Billing as unusual for being 45
days ahead of actual accomplishment. Aguilar did not pay and
on 2 February 2005, Transcept stopped working on the Project.

Thereafter, Aguilar hired ASTEC, a duly accredited testing


ADR || First Batch 10
6
laboratory, to test Transcepts quality of work. The test showed Direct Costs for Labor and Materials P1,110,440.13
substandard works done by Transcept. In a letter dated 7 Indirect Costs for General Requirements 275,355.50
March 2005, Transcept outlined its program to reinforce or redo Septic Tank 7,300.00
the substandard works discovered by ASTEC. On 28 March Sub-Total P1,393,095.63
Plus 5% Contingencies 69,654.78
2005, ASTEC, through Engr. Jaime E. Rioflorido (Engr.
Add 10% of Sub-Total for Contractor's Profit 139,309.56
Rioflorido), sent Aguilar an Evaluation of Contractors Total P1,602,359.97
Performance which showed that aside from the substandard
workmanship and use of substandard materials, Transcept was
unreasonably and fraudulently billing Aguilar. Of the
downpayment amounting to P1,632,436.29, Engr. Riofloridos The CIAC ruled that the accomplishment of P1,602,359.97 was
reasonable assessment of Transcepts accomplishment 98.16% of P1,632,436.29, which was way above 95% and
amounted only to P527,875.94. Engr. Rioflorido recommended should therefore be considered as substantial completion of the
the partial demolition of Transcepts work. Project. As such, the CIAC ruled that liquidated damages could
not be awarded to Aguilar. The CIAC, however, ruled that
Aguilar was entitled to P75,000 as Consultancy Expenses.
On 30 May 2005, Transcept and Aguilar entered into a
Construction Contract (Second Contract) to extend the date of
completion from 7 June 2005 to 29 July 2005 and to use up the The CIAC also found that Aguilar demanded extra works which
P1.6 million downpayment paid by Aguilar. Aguilar hired the entailed additional working days. The CIAC computed that the
services of Engr. Edgardo Anonuevo (Engr. Anonuevo) to additional works performed over and above the Second
ensure that the works would comply with the plans in the Contract amounted to P189,909.91.
Second Contract.
The dispositive portion of the CIACs decision reads:
Transcept failed to finish the Project on 29 July 2005, alleging
that the delay was due to additional works ordered by Aguilar. In view of all the foregoing, it is hereby ordered that:
Transcept also asked for payment of the additional amount of
P290,824.96. Aguilar countered that the Second Contract did 1. Respondent [Transcept] shall pay Claimant [Aguilar] the
not provide for additional works. amount of P30,076.72, representing the unaccomplished works
in the contract, plus 6% interests from the date of the
On 2 September 2005, Aguilar sent a demand letter to promulgation of this case, until fully paid.
Transcept asking for payment of P581,844.54 for refund and
damages. Transcept ignored the demand letter. On 6 2. Respondent shall pay Claimant the amount of P75,000.00,
September 2005, Aguilar filed a complaint against Transcept representing the cost of Consultancy Services, plus 6%
before CIAC. interests from the date of the promulgation of this case, until
fully paid.
The Decision of the CIAC
3. Claimant shall pay Respondent the amount of P189,909.91,
CIAC assessed the work accomplished with the corresponding representing the cost of work performed over & above the
costs, as against the downpayment of P1,632,436.29 which scope of work in the contract.
was the contract price in the Second Contract. On 16 January
2006, the CIAC promulgated its Decision.4 4. The cost for liquidated damages and cost representing
interests of construction bond, prayed for the Claimant, are
For Labor and Materials of the Scope of Work, the CIAC denied for being without merit.
credited the accomplishment to be P1,110,440.13 representing
Aguilars estimate which was reassessed by the CIAC after the 5. Attorneys fees prayed for by both parties are denied for
ocular inspection conducted by the parties. For indirect costs being without merit.
for General Requirements of the Scope of Work, the CIACs
computation was P275,355.50. The CIAC noted that Aguilar did 6. Cost of Arbitration shall be shared equally by the parties.
not submit any evidence on indirect costs and her counsel did
not cross-examine Transcepts witnesses on the matter. For the
SO ORDERED.5
Septic Tank, which the CIAC found to be part of the Second
Contract, the CIAC assessed the accomplishment to amount to
P7,300. The CIAC added 5% Contingencies and 10% Aguilar assailed the CIACs decision before the Court of
Contractors Profit which are the minimum factors in making Appeals.
estimates practiced in the construction industry. The CIAC thus
estimated that the total accomplishment amounted to The Decision of the Court of Appeals
P1,602,359.97 which was P30,076.72 below the contract price
of P1,632,436.29. The tabulated amount shows:
ADR || First Batch 10
7
In its 24 January 2007 Decision, the Court of Appeals reversed Transcept filed a motion for reconsideration. In its 20 April
the CIACs decision. 2007 Resolution, the Court of Appeals denied the motion.

The Court of Appeals agreed with the CIAC that Aguilar did not Hence, the petition before this Court.
allege in her complaint the amount corresponding to the indirect
costs for General Requirements. However, the Court of The Issues
Appeals made a recomputation of the indirect costs for General
Requirements based on P1,632,436.29 and made the following
The issues in this case are the following:
findings:
1. Whether the Court of Appeals erred in holding that Aguilar is
Direct Costs for Labor and Materials P1,110,440.13
entitled to P198,916.02 instead of P30,076.72 for
Indirect Costs for General Requirements 128,799.22
unaccomplished works;
Septic Tank 7,300.00
Sub-Total P1,246,539.35
Plus 5% Contingencies 2.62,326.96
Whether the Court of Appeals erred in awarding Aguilar
Add 10% of Sub-Total for Contractor's Profit liquidated damages;
124,653.93
Total P1,433,520.24
The Court of Appeals then deducted P1,433,520.24 from 3. Whether the Court of Appeals erred in deleting the CIACs
P1,632,436.29 and concluded that Aguilar is entitled to award of P189,909.91 to Transcept representing additional
P198,916.05 instead of P30,076.72. works done under the Second Contract; and

From the above computation, the Court of Appeals ruled that 4. Whether the Court of Appeals erred in awarding Aguilar the
Transcept only accomplished 87.81% of the contract price thus amount of P135,000 for consultancy services.
entitling Aguilar to liquidated damages equivalent to 10% of
P1,632,436.29 or P163,243.63. The Ruling of this Court

The Court of Appeals further ruled that Transcept was not The petition is partly meritorious.
entitled to payment for additional works because they were in
fact only rectifications of the works poorly done by Transcept. Refund for Unaccomplished Works
Finally, the Court of Appeals ruled that Aguilar was able to
prove that she paid P135,000 for consultancy services.
The Court of Appeals ruled that CIAC erred in adopting
Transcepts computation of unaccomplished works. The Court
The dispositive portion of the Court of Appeals decision reads: of Appeals agreed with Aguilar that the CIACs computation
was based on what Transcept submitted which was based on
WHEREFORE, the foregoing considered, the instant petition is the original contract price of P3,486,878.64 instead of the
hereby GRANTED and the assailed decision REVERSED AND contract price of P1,632,436.29 under the Second Contract.
SET ASIDE. Accordingly, a new one is entered ordering
respondent to pay petitioner the following: However, the Court of Appeals failed to consider the CIACs as
well as its own finding that Aguilar did not present any evidence
1) P198,916.02 for unaccomplished works in the second on indirect costs for General Requirements. In addition,
contract, plus 6% interest from the date of the filing of the case, Aguilars counsel did not cross-examine Transcepts witnesses.
until fully paid; In short, Aguilar did not dispute but merely accepted
Transcepts computation on indirect expenses. Aguilar did not
2) P135,000.00, representing the cost of consultancy services, interpose any objection to the computation until after the CIAC
plus 6% interest from the filing of the case, until fully paid; and ruled that Transcept substantially complied with the Project. We
also note Transcepts explanation, as well as the CIACs
3) P163,243.63 as and by way of liquidated damages. finding, that General Requirements refer to mobilization,
overhead, insurance, hoarding and protection, temporary
facilities, equipment, materials testing, line set out, as-built
The award of P189,909.91 in favor of Aguilar for additional
drawings, and clean out. They had been used up at the start of
works is hereby deleted.
the Project. Hence, costs for General Requirements are not
dependent on the amount of the contract because they were
No costs. incurred at the beginning of the Project. We should therefore
revert to the computation made by the CIAC, as follows:
SO ORDERED.6
Direct Costs for Labor and Materials P1,1
ADR || First Batch 10
8
Indirect Costs for General Requirements The
275,355.50
CIAC found that Aguilar demanded additional works
Septic Tank from
7,300.00
Transcept. The CIAC found that the additional works
Sub-Total include
P1,393,095.63
the balcony, lifting of roof beams, and extra fast walls
Plus 5% Contingencies which
69,654.78
are not covered by the Second Contract. However, we
Add 10% of Sub-Total for Contractor's Profit agree
139,309.56
with the Court of Appeals that the works done were just
Total forP1,602,359.97
correction of the substandard works done under the First
Liquidated Damages Contract. During the ocular inspection, Aguilar pointed out that
the lifting of the roof beam was done because the construction
Section 20.11(A)(a) of the Construction Industry Authority of the was three meters short of that specified in the First Contact.9
Philippines (CIAP) Document No. 102 provides that "[t]here is Hence, while the roofing system is excluded from the Second
substantial completion when the Contractor completes 95% of Contract, it could not be said that the lifting of the roof beam is
the Work, provided that the remaining work and the an additional work on the part of Transcept.
performance of the work necessary to complete the Work shall
not prevent the normal use of the completed portion." The Court notes that the Second Contract was entered into by
the parties precisely to correct the substandard works
According to CIACs computation, Transcepts accomplishment discovered by ASTEC. Hence, Aguilar should not be made to
amounted to 98.16% of the contract price. It is beyond the 95% pay for works done to correct these substandard works.
required under CIAP Document No. 102 and is considered a
substantial completion of the Project. We thus agree with Consultancy Services
CIACs application of Article 1234 of the Civil Code, which
provides that "[i]f the obligation had been substantially The Court of Appeals correctly awarded Aguilar the cost of
performed in good faith, the obligor may recover as though consultancy services amounting to P135,000. While Engr.
there had been a strict and complete fulfillment, less damages Rioflorido was not presented as a witness, it was established
suffered by the obligee."7
lavvphil

that Aguilar hired ASTEC, a duly accredited testing laboratory,


to test Transcepts quality of work, and that Engr. Rioflorido
There being a substantial completion of the Project, Aguilar is represented ASTEC. As found by the Court of Appeals, Aguilar
not entitled to liquidated damages but only to actual damages paid Engr. Rioflorido the amount of P65,000 for the services,
of P30,076.72, representing the unaccomplished works in the which should be added to the P75,000 consultancy services
Second Contract as found by the CIAC, which is the difference awarded to Aguilar.10
between the contract price of P1,632,436.29 and the
accomplishment of P1,602,359.97. WHEREFORE, we AFFIRM the 24 January 2007 Decision and
the 20 April 2007 Resolution of the Court of Appeals in CA-G.R.
Additional Works SP No. 93021, with the MODIFICATION that the award of
P198,916.02 for unaccomplished works is reduced to
The Second Contract excluded the construction of the following P30,076.72, and the award of P163,243.63 for liquidated
works: damages is deleted.

1. Architectural Works - - Roofing System SO ORDERED.

2. Interior Fit-Out Works/Glass/Windows/CAB/CARP ANTONIO T. CARPIO

3. Truss System Associate Justice

4. Supply and Installation of Plumbing Fixtures and Bathroom WE CONCUR:


Accessories
RENATO C. CORONA*
5. Supply and Installation of Downspout System
Chief Justice
6. Electrical Roughing-in and Wiring Works
ANTONIO EDUARDO B. NACHURA
7. Supply and Installation of Wiring Devices
Associate Justice
8. Supply and Installation of Circuit Breakers JOSE C. MENDOZA

9. Testing and Commissioning.8 Associate Justice


ADR || First Batch 10
9
ATTESTATION 10 CA rollo, p. 292.

I attest that the conclusions in the above Decision had been


reached in consultation before the case was assigned to the
writer of the opinion of the Courts Division.

ANTONIO T. CARPIO

Associate Justice

Chairperson

CERTIFICATION

Pursuant to Section 13, Article VIII of the Constitution, and the


Division Chairpersons Attestation, I certify that the conclusions
in the above Decision had been reached in consultation before
the case was assigned to the writer of the opinion of the Courts
Division.

RENATO C. CORONA

Chief Justice

Footnotes

*Designated additional member per Raffle dated 8 December


2010.

1 Rollo, pp. 61-74. Penned by Associate Justice Josefina


Guevara-Salonga with Associate Justices Vicente Q. Roxas
and Ramon R. Garcia, concurring.

2 Id. at 76-77.

3 120 days in the Decision of the Court of Appeals.

4Rollo, pp. 107-123. Penned by Sole Arbitrator Jacinto M.


Butalid.

5 Id. at 123.

6 Id. at 73-74.

7 See Diesel Construction Co., Inc. v. UPSI Property Holdings,


Inc., G.R. No. 154885, 24 March 2008, 549 SCRA 12.

8 Rollo, pp. 111-112.

9 Transcript of the Ocular Inspection, pp. 28-29.


ADR || First Batch 11
0
Republic of the Philippines legally in existence and the RTC was not the proper
SUPREME COURT forum to ventilate such issue. It claimed that the contract
Manila contained an arbitration clause, to wit:
SECOND DIVISION
ARBITRATION
G.R. No. 175404 January 31, 2011
Any dispute which the Buyer and Seller may not be able to
CARGILL PHILIPPINES, INC., Petitioner, settle by mutual agreement shall be settled by arbitration in the
City of New York before the American Arbitration Association.
vs. The Arbitration Award shall be final and binding on both
parties.5
SAN FERNANDO REGALA TRADING, INC., Respondent.
that respondent must first comply with the arbitration clause
before resorting to court, thus, the RTC must either dismiss the
DECISION
case or suspend the proceedings and direct the parties to
proceed with arbitration, pursuant to Sections 66 and 77 of
PERALTA, J.: Republic Act (R.A.) No. 876, or the Arbitration Law.

Before us is a petition for review on certiorari seeking to reverse Respondent filed an Opposition, wherein it argued that the RTC
and set aside the Decision1 dated July 31, 2006 and the has jurisdiction over the action for rescission of contract and
Resolution2 dated November 13, 2006 of the Court of Appeals could not be changed by the subject arbitration clause. It cited
(CA) in CA G.R. SP No. 50304. cases wherein arbitration clauses, such as the subject clause in
the contract, had been struck down as void for being contrary to
The factual antecedents are as follows: public policy since it provided that the arbitration award shall be
final and binding on both parties, thus, ousting the courts of
On June 18, 1998, respondent San Fernando Regala Trading, jurisdiction.
Inc. filed with the Regional Trial Court (RTC) of Makati City a
Complaint for Rescission of Contract with Damages3 against In its Reply, petitioner maintained that the cited decisions were
petitioner Cargill Philippines, Inc. In its Complaint, respondent already inapplicable, having been rendered prior to the
alleged that it was engaged in buying and selling of molasses effectivity of the New Civil Code in 1950 and the Arbitration Law
and petitioner was one of its various sources from whom it in 1953.
purchased molasses. Respondent alleged that it entered into a
contract dated July 11, 1996 with petitioner, wherein it was In its Rejoinder, respondent argued that the arbitration clause
agreed upon that respondent would purchase from petitioner relied upon by petitioner is invalid and unenforceable,
12,000 metric tons of Thailand origin cane blackstrap molasses considering that the requirements imposed by the provisions of
at the price of US$192 per metric ton; that the delivery of the the Arbitration Law had not been complied with.
molasses was to be made in January/February 1997 and
payment was to be made by means of an Irrevocable Letter of
By way of Sur-Rejoinder, petitioner contended that respondent
Credit payable at sight, to be opened by September 15, 1996;
had even clarified that the issue boiled down to whether the
that sometime prior to September 15, 1996, the parties agreed
arbitration clause contained in the contract subject of the
that instead of January/February 1997, the delivery would be
complaint is valid and enforceable; that the arbitration clause
made in April/May 1997 and that payment would be by an
did not violate any of the cited provisions of the Arbitration Law.
Irrevocable Letter of Credit payable at sight, to be opened upon
petitioner's advice. Petitioner, as seller, failed to comply with its
obligations under the contract, despite demands from On September 17, 1998, the RTC rendered an Order,8 the
respondent, thus, the latter prayed for rescission of the contract dispositive portion of which reads:
and payment of damages.
Premises considered, defendant's "Motion To Dismiss/Suspend
On July 24, 1998, petitioner filed a Motion to Dismiss/Suspend Proceedings and To Refer Controversy To Voluntary
Proceedings and To Refer Controversy to Voluntary Arbitration" is hereby DENIED. Defendant is directed to file its
Arbitration,4 wherein it argued that the alleged contract between answer within ten (10) days from receipt of a copy of this order.9
the parties, dated July 11, 1996, was never consummated
because respondent never returned the proposed agreement In denying the motion, the RTC found that there was no clear
bearing its written acceptance or conformity nor did respondent basis for petitioner's plea to dismiss the case, pursuant to
open the Irrevocable Letter of Credit at sight. Petitioner Section 7 of the Arbitration Law. The RTC said that the
contended that the controversy between the parties was provision directed the court concerned only to stay the action or
whether or not the alleged contract between the parties was proceeding brought upon an issue arising out of an agreement
ADR || First Batch 11
1
providing for the arbitration thereof, but did not impose the parties did not exist or it was invalid; that the said contract
sanction of dismissal. However, the RTC did not find the bearing the arbitration clause was never consummated by the
suspension of the proceedings warranted, since the Arbitration parties, thus, it was proper that such issue be first resolved by
Law contemplates an arbitration proceeding that must be the court through an appropriate trial; that the issue involved a
conducted in the Philippines under the jurisdiction and control question of fact that the RTC should first resolve. Arbitration is
of the RTC; and before an arbitrator who resides in the country; not proper when one of the parties repudiated the existence or
and that the arbitral award is subject to court approval, validity of the contract.
disapproval and modification, and that there must be an appeal
from the judgment of the RTC. The RTC found that the Petitioner's motion for reconsideration was denied in a
arbitration clause in question contravened these procedures, Resolution dated November 13, 2006.
i.e., the arbitration clause contemplated an arbitration
proceeding in New York before a non-resident arbitrator
Hence, this petition.
(American Arbitration Association); that the arbitral award shall
be final and binding on both parties. The RTC said that to apply
Section 7 of the Arbitration Law to such an agreement would Petitioner alleges that the CA committed an error of law in
result in disregarding the other sections of the same law and ruling that arbitration cannot proceed despite the fact that: (a) it
rendered them useless and mere surplusages. had ruled, in its assailed decision, that the arbitration clause is
valid, enforceable and binding on the parties; (b) the case of
Gonzales v. Climax Mining Ltd.11 is inapplicable here; (c)
Petitioner filed its Motion for Reconsideration, which the RTC
parties are generally allowed, under the Rules of Court, to
denied in an Order10 dated November 25, 1998.
adopt several defenses, alternatively or hypothetically, even if
such
Petitioner filed a petition for certiorari with the CA raising the
sole issue that the RTC acted in excess of jurisdiction or with
defenses are inconsistent with each other; and (d) the
grave abuse of discretion in refusing to dismiss or at least
complaint filed by respondent with the trial court is premature.
suspend the proceedings a quo, despite the fact that the party's
agreement to arbitrate had not been complied with.
Petitioner alleges that the CA adopted inconsistent positions
when it found the arbitration clause between the parties as valid
Respondent filed its Comment and Reply. The parties were
and enforceable and yet in the same breath decreed that the
then required to file their respective Memoranda.
arbitration cannot proceed because petitioner assailed the
existence of the entire agreement containing the arbitration
On July 31, 2006, the CA rendered its assailed Decision clause. Petitioner claims the inapplicability of the cited
denying the petition and affirming the RTC Orders. Gonzales case decided in 2005, because in the present case, it
was respondent who had filed the complaint for rescission and
In denying the petition, the CA found that stipulation providing damages with the RTC, which based its cause of action against
for arbitration in contractual obligation is both valid and petitioner on the alleged agreement dated July 11, 2006
constitutional; that arbitration as an alternative mode of dispute between the parties; and that the same agreement contained
resolution has long been accepted in our jurisdiction and the arbitration clause sought to be enforced by petitioner in this
expressly provided for in the Civil Code; that R.A. No. 876 (the case. Thus, whether petitioner assails the genuineness and
Arbitration Law) also expressly authorized the arbitration of due execution of the agreement, the fact remains that the
domestic disputes. The CA found error in the RTC's holding agreement sued upon provides for an arbitration clause; that
that Section 7 of R.A. No. 876 was inapplicable to arbitration respondent cannot use the provisions favorable to him and
clause simply because the clause failed to comply with the completely disregard those that are unfavorable, such as the
requirements prescribed by the law. The CA found that there arbitration clause.
was nothing in the Civil Code, or R.A. No. 876, that require that
arbitration proceedings must be conducted only in the Petitioner contends that as the defendant in the RTC, it
Philippines and the arbitrators should be Philippine residents. It presented two alternative defenses, i.e., the parties had not
also found that the RTC ruling effectively invalidated not only entered into any agreement upon which respondent as plaintiff
the disputed arbitration clause, but all other agreements which can sue upon; and, assuming that such agreement existed,
provide for foreign arbitration. The CA did not find illegal or there was an arbitration clause that should be enforced, thus,
against public policy the arbitration clause so as to render it null the dispute must first be submitted to arbitration before an
and void or ineffectual. action can be instituted in court. Petitioner argues that under
Section 1(j) of Rule 16 of the Rules of Court, included as a
Notwithstanding such findings, the CA still held that the case ground to dismiss a complaint is when a condition precedent for
cannot be brought under the Arbitration Law for the purpose of filing the complaint has not been complied with; and that
suspending the proceedings before the RTC, since in its Motion submission to arbitration when such has been agreed upon is
to Dismiss/Suspend proceedings, petitioner alleged, as one of one such condition precedent. Petitioner submits that the
the grounds thereof, that the subject contract between the proceedings in the RTC must be dismissed, or at least
ADR || First Batch 11
2
suspended, and the parties be ordered to proceed with resolution of the Gonzales' motion for reconsideration in
arbitration. 2007, it had been ruled that an arbitration agreement is
effective notwithstanding the fact that one of the parties thereto
On March 12, 2007, petitioner filed a Manifestation12 saying that repudiated the main contract which contained it.
the CA's rationale in declining to order arbitration based on the
2005 Gonzales ruling had been modified upon a motion for We first address the procedural issue raised by respondent that
reconsideration decided in 2007; that the CA decision lost its petitioners petition for certiorari under Rule 65 filed in the CA
legal basis, because it had been ruled that the arbitration against an RTC Order denying a Motion to Dismiss/Suspend
agreement can be implemented notwithstanding that one of the Proceedings and to Refer Controversy to Voluntary Arbitration
parties thereto repudiated the contract which contained such was a wrong remedy invoking Section 29 of R.A. No. 876,
agreement based on the doctrine of separability. which provides:

In its Comment, respondent argues that certiorari under Rule Section 29.
65 is not the remedy against an order denying a Motion to
Dismiss/Suspend Proceedings and To Refer Controversy to x x x An appeal may be taken from an order made in a
Voluntary Arbitration. It claims that the Arbitration Law which proceeding under this Act, or from a judgment entered upon an
petitioner invoked as basis for its Motion prescribed, under its award through certiorari proceedings, but such appeals shall be
Section 29, a remedy, i.e., appeal by a petition for review on limited to question of law. x x x.
certiorari under Rule 45. Respondent contends that the
Gonzales case, which was decided in 2007, is inapplicable in
To support its argument, respondent cites the case of Gonzales
this case, especially as to the doctrine of separability
v. Climax Mining Ltd.13 (Gonzales case), wherein we ruled the
enunciated therein. Respondent argues that even if the
impropriety of a petition for certiorari under Rule 65 as a mode
existence of the contract and the arbitration clause is
of appeal from an RTC Order directing the parties to arbitration.
conceded, the decisions of the RTC and the CA declining
referral of the dispute between the parties to arbitration would
still be correct. This is so because respondent's complaint filed We find the cited case not in point.
in Civil Case No. 98-1376 presents the principal issue of
whether under the facts alleged in the complaint, respondent is In the Gonzales case, Climax-Arimco filed before the RTC of
entitled to rescind its contract with petitioner and for the latter to Makati a petition to compel arbitration under R.A. No. 876,
pay damages; that such issue constitutes a judicial question or pursuant to the arbitration clause found in the Addendum
one that requires the exercise of judicial function and cannot be Contract it entered with Gonzales. Judge Oscar Pimentel of the
the subject of arbitration. RTC of Makati then directed the parties to arbitration
proceedings. Gonzales filed a petition for certiorari with Us
Respondent contends that Section 8 of the Rules of Court, contending that Judge Pimentel acted with grave abuse of
which allowed a defendant to adopt in the same action several discretion in immediately ordering the parties to proceed with
defenses, alternatively or hypothetically, even if such defenses arbitration despite the proper, valid and timely raised argument
are inconsistent with each other refers to allegations in the in his Answer with counterclaim that the Addendum Contract
pleadings, such as complaint, counterclaim, cross-claim, third- containing the arbitration clause was null and void. Climax-
party complaint, answer, but not to a motion to dismiss. Finally, Arimco assailed the mode of review availed of by Gonzales,
respondent claims that petitioner's argument is premised on the citing Section 29 of R.A. No. 876 contending that certiorari
existence of a contract with respondent containing a provision under Rule 65 can be availed of only if there was no appeal or
for arbitration. However, its reliance on the contract, which it any adequate remedy in the ordinary course of law; that R.A.
repudiates, is inappropriate. No. 876 provides for an appeal from such order. We then ruled
that Gonzales' petition for certiorari should be dismissed as it
was filed in lieu of an appeal by certiorari which was the
In its Reply, petitioner insists that respondent filed an action for
prescribed remedy under R.A. No. 876 and the petition was
rescission and damages on the basis of the contract, thus,
filed far beyond the reglementary period.
respondent admitted the existence of all the provisions
contained thereunder, including the arbitration clause; that if
respondent relies on said contract for its cause of action We found that Gonzales petition for certiorari raises a question
against petitioner, it must also consider itself bound by the rest of law, but not a question of jurisdiction; that Judge Pimentel
of the terms and conditions contained thereunder acted in accordance with the procedure prescribed in R.A. No.
notwithstanding that respondent may find some provisions to be 876 when he ordered Gonzales to proceed with arbitration and
adverse to its position; that respondents citation of the appointed a sole arbitrator after making the determination that
Gonzales case, decided in 2005, to show that the validity of the there was indeed an arbitration agreement. It had been held
contract cannot be the subject of the arbitration proceeding and that as long as a court acts within its jurisdiction and does not
that it is the RTC which has the jurisdiction to resolve the gravely abuse its discretion in the exercise thereof, any
situation between the parties herein, is not correct since in the supposed error committed by it will amount to nothing more
ADR || First Batch 11
3
than an error of judgment reviewable by a timely appeal and not binding.20 Submission to arbitration is a contract 21 and a
assailable by a special civil action of certiorari.14 clause in a contract providing that all matters in dispute
between the parties shall be referred to arbitration is a
In this case, petitioner raises before the CA the issue that the contract.22 The provision to submit to arbitration any dispute
respondent Judge acted in excess of jurisdiction or with grave arising therefrom and the relationship of the parties is part of
abuse of discretion in refusing to dismiss, or at least suspend, the contract and is itself a contract.23
the proceedings a quo, despite the fact that the partys
agreement to arbitrate had not been complied with. Notably, the In this case, the contract sued upon by respondent provides for
RTC found the existence of the arbitration clause, since it said an arbitration clause, to wit:
in its decision that "hardly disputed is the fact that the
arbitration clause in question contravenes several provisions of ARBITRATION
the Arbitration Law x x x and to apply Section 7 of the
Arbitration Law to such an agreement would result in the
Any dispute which the Buyer and Seller may not be able to
disregard of the afore-cited sections of the Arbitration Law and
settle by mutual agreement shall be settled by arbitration in the
render them useless and mere surplusages." However,
City of New York before the American Arbitration Association,
notwithstanding the finding that an arbitration agreement
The Arbitration Award shall be final and binding on both parties.
existed, the RTC denied petitioner's motion and directed
petitioner to file an answer.
The CA ruled that arbitration cannot be ordered in this case,
since petitioner alleged that the contract between the parties
In La Naval Drug Corporation v. Court of Appeals, it was held
15
did not exist or was invalid and arbitration is not proper when
that R.A. No. 876 explicitly confines the courts authority only to
one of the parties repudiates the existence or validity of the
the determination of whether or not there is an agreement in
contract. Thus, said the CA:
writing providing for arbitration. In the affirmative, the statute
ordains that the court shall issue an order summarily directing
the parties to proceed with the arbitration in accordance with Notwithstanding our ruling on the validity and enforceability of
the terms thereof. If the court, upon the other hand, finds that the assailed arbitration clause providing for foreign arbitration, it
no such agreement exists, the proceedings shall be dismissed. is our considered opinion that the case at bench still cannot be
brought under the Arbitration Law for the purpose of
suspending the proceedings before the trial court. We note that
In issuing the Order which denied petitioner's Motion to
in its Motion to Dismiss/Suspend Proceedings, etc, petitioner
Dismiss/Suspend Proceedings and to Refer Controversy to
Cargill alleged, as one of the grounds thereof, that the alleged
Voluntary Arbitration, the RTC went beyond its authority of
contract between the parties do not legally exist or is invalid. As
determining only the issue of whether or not there is an
posited by petitioner, it is their contention that the said contract,
agreement in writing providing for arbitration by directing
bearing the arbitration clause, was never consummated by the
petitioner to file an answer, instead of ordering the parties to
parties. That being the case, it is but proper that such issue be
proceed to arbitration. In so doing, it acted in excess of its
first resolved by the court through an appropriate trial. The
jurisdiction and since there is no plain, speedy, and adequate
issue involves a question of fact that the trial court should first
remedy in the ordinary course of law, petitioners resort to a
resolve.
petition for certiorari is the proper remedy.
Arbitration is not proper when one of the parties repudiates the
We now proceed to the substantive issue of whether the CA
existence or validity of the contract. Apropos is Gonzales v.
erred in finding that this case cannot be brought under the
Climax Mining Ltd., 452 SCRA 607, (G.R.No.161957), where
arbitration law for the purpose of suspending the proceedings in
the Supreme Court held that:
the RTC.
The question of validity of the contract containing the
We find merit in the petition.
agreement to submit to arbitration will affect the
applicability of the arbitration clause itself. A party cannot
Arbitration, as an alternative mode of settling disputes, has long rely on the contract and claim rights or obligations under it
been recognized and accepted in our jurisdiction.16 R.A. No. and at the same time impugn its existence or validity.
87617 authorizes arbitration of domestic disputes. Foreign Indeed, litigants are enjoined from taking inconsistent
arbitration, as a system of settling commercial disputes of an positions....
international character, is likewise recognized.18 The enactment
of R.A. No. 9285 on April 2, 2004 further institutionalized the
Consequently, the petitioner herein cannot claim that the
use of alternative dispute resolution systems, including
contract was never consummated and, at the same time,
arbitration, in the settlement of disputes.19
invokes the arbitration clause provided for under the contract
which it alleges to be non-existent or invalid. Petitioner claims
A contract is required for arbitration to take place and to be that private respondent's complaint lacks a cause of action due
ADR || First Batch 11
4
to the absence of any valid contract between the parties. existence of the contract but merely assailed the validity
Apparently, the arbitration clause is being invoked merely as a thereof on the ground of fraud and oppression. Respondent
fallback position. The petitioner must first adduce evidence in claims that in the case before Us, petitioner who is the party
support of its claim that there is no valid contract between them insistent on arbitration also claimed in their Motion to
and should the court a quo find the claim to be meritorious, the Dismiss/Suspend Proceedings that the contract sought by
parties may then be spared the rigors and expenses that respondent to be rescinded did not exist or was not
arbitration in a foreign land would surely entail.24 consummated; thus, there is no room for the application of the
separability doctrine, since there is no container or main
However, the Gonzales case,25 which the CA relied upon for not contract or an arbitration clause to speak of.
ordering arbitration, had been modified upon a motion for
reconsideration in this wise: We are not persuaded.

x x x The adjudication of the petition in G.R. No. 167994 Applying the Gonzales ruling, an arbitration agreement which
effectively modifies part of the Decision dated 28 February forms part of the main contract shall not be regarded as invalid
2005 in G.R. No. 161957. Hence, we now hold that the or non-existent just because the main contract is invalid or did
validity of the contract containing the agreement to submit not come into existence, since the arbitration agreement shall
to arbitration does not affect the applicability of the be treated as a separate agreement independent of the main
arbitration clause itself. A contrary ruling would suggest contract. To reiterate. a contrary ruling would suggest that a
that a party's mere repudiation of the main contract is party's mere repudiation of the main contract is sufficient to
sufficient to avoid arbitration. That is exactly the situation avoid arbitration and that is exactly the situation that the
that the separability doctrine, as well as jurisprudence separability doctrine sought to avoid. Thus, we find that even
applying it, seeks to avoid. We add that when it was declared the party who has repudiated the main contract is not
in G.R. No. 161957 that the case should not be brought for prevented from enforcing its arbitration clause.
arbitration, it should be clarified that the case referred to is the
case actually filed by Gonzales before the DENR Panel of Moreover, it is worthy to note that respondent filed a complaint
Arbitrators, which was for the nullification of the main contract for rescission of contract and damages with the RTC. In so
on the ground of fraud, as it had already been determined that doing, respondent alleged that a contract exists between
the case should have been brought before the regular courts respondent and petitioner. It is that contract which provides for
involving as it did judicial issues.26 an arbitration clause which states that "any dispute which the
Buyer and Seller may not be able to settle by mutual agreement
In so ruling that the validity of the contract containing the shall be settled before the City of New York by the American
arbitration agreement does not affect the applicability of the Arbitration Association. The arbitration agreement clearly
arbitration clause itself, we then applied the doctrine of expressed the parties' intention that any dispute between them
separability, thus: as buyer and seller should be referred to arbitration. It is for the
arbitrator and not the courts to decide whether a contract
The doctrine of separability, or severability as other writers call between the parties exists or is valid.
it, enunciates that an arbitration agreement is independent of
the main contract. The arbitration agreement is to be treated as Respondent contends that assuming that the existence of the
a separate agreement and the arbitration agreement does not contract and the arbitration clause is conceded, the CA's
automatically terminate when the contract of which it is a part decision declining referral of the parties' dispute to arbitration is
comes to an end. still correct. It claims that its complaint in the RTC presents the
issue of whether under the facts alleged, it is entitled to rescind
The separability of the arbitration agreement is especially the contract with damages; and that issue constitutes a judicial
significant to the determination of whether the invalidity of the question or one that requires the exercise of judicial function
main contract also nullifies the arbitration clause. Indeed, the and cannot be the subject of an arbitration proceeding.
doctrine denotes that the invalidity of the main contract, also Respondent cites our ruling in Gonzales, wherein we held that
referred to as the "container" contract, does not affect the a panel of arbitrator is bereft of jurisdiction over the complaint
validity of the arbitration agreement. Irrespective of the fact that for declaration of nullity/or termination of the subject contracts
the main contract is invalid, the arbitration clause/agreement on the grounds of fraud and oppression attendant to the
still remains valid and enforceable.27 execution of the addendum contract and the other contracts
emanating from it, and that the complaint should have been
filed with the regular courts as it involved issues which are
Respondent argues that the separability doctrine is not
judicial in nature.
applicable in petitioner's case, since in the Gonzales case,
Climax-Arimco sought to enforce the arbitration clause of its
contract with Gonzales and the former's move was premised on Such argument is misplaced and respondent cannot rely on the
the existence of a valid contract; while Gonzales, who resisted Gonzales case to support its argument.
the move of Climax-Arimco for arbitration, did not deny the
ADR || First Batch 11
5
In Gonzales, petitioner Gonzales filed a complaint before the the Panel was not a dispute involving rights to mining
Panel of Arbitrators, Region II, Mines and Geosciences Bureau, areas, or was it a dispute involving claimholders or
of the Department of Environment and Natural Resources concessionaires, but essentially judicial issues. We then said
(DENR) against respondents Climax- Mining Ltd, Climax- that the Panel of Arbitrators did not have jurisdiction over such
Arimco and Australasian Philippines Mining Inc, seeking the issue, since it does not involve the application of technical
declaration of nullity or termination of the addendum contract knowledge and expertise relating to mining. It is in this context
and the other contracts emanating from it on the grounds of that we said that:
fraud and oppression. The Panel dismissed the complaint for
lack of jurisdiction. However, the Panel, upon petitioner's Arbitration before the Panel of Arbitrators is proper only when
motion for reconsideration, ruled that it had jurisdiction over the there is a disagreement between the parties as to some
dispute maintaining that it was a mining dispute, since the provisions of the contract between them, which needs the
subject complaint arose from a contract between the parties interpretation and the application of that particular knowledge
which involved the exploration and exploitation of minerals over and expertise possessed by members of that Panel. It is not
the disputed area. Respondents assailed the order of the
1wphi1

proper when one of the parties repudiates the existence or


Panel of Arbitrators via a petition for certiorari before the CA. validity of such contract or agreement on the ground of fraud or
The CA granted the petition and declared that the Panel of oppression as in this case. The validity of the contract cannot
Arbitrators did not have jurisdiction over the complaint, since its be subject of arbitration proceedings. Allegations of fraud and
jurisdiction was limited to the resolution of mining disputes, duress in the execution of a contract are matters within the
such as those which raised a question of fact or matter jurisdiction of the ordinary courts of law. These questions are
requiring the technical knowledge and experience of mining legal in nature and require the application and interpretation of
authorities and not when the complaint alleged fraud and laws and jurisprudence which is necessarily a judicial function.29
oppression which called for the interpretation and application of
laws. The CA further ruled that the petition should have been
In fact, We even clarified in our resolution on Gonzales motion
settled through arbitration under R.A. No. 876 the Arbitration
for reconsideration that "when we declared that the case should
Law as provided under the addendum contract.
not be brought for arbitration, it should be clarified that the case
referred to is the case actually filed by Gonzales before the
On a review on certiorari, we affirmed the CAs finding that the DENR Panel of Arbitrators, which was for the nullification of the
Panel of Arbitrators who, under R.A. No. 7942 of the Philippine main contract on the ground of fraud, as it had already been
Mining Act of 1995, has exclusive and original jurisdiction to determined that the case should have been brought before the
hear and decide mining disputes, such as mining areas, mineral regular courts involving as it did judicial issues." We made such
agreements, FTAAs or permits and surface owners, occupants clarification in our resolution of the motion for reconsideration
and claimholders/concessionaires, is bereft of jurisdiction over after ruling that the parties in that case can proceed to
the complaint for declaration of nullity of the addendum arbitration under the Arbitration Law, as provided under the
contract; thus, the Panels' jurisdiction is limited only to those Arbitration Clause in their Addendum Contract.
mining disputes which raised question of facts or matters
requiring the technical knowledge and experience of mining
WHEREFORE, the petition is GRANTED. The Decision dated
authorities. We then said:
July 31, 2006 and the Resolution dated November 13, 2006 of
the Court of Appeals in CA-G.R. SP No. 50304 are REVERSED
In Pearson v. Intermediate Appellate Court, this Court observed and SET ASIDE. The parties are hereby ORDERED to
that the trend has been to make the adjudication of mining SUBMIT themselves to the arbitration of their dispute, pursuant
cases a purely administrative matter. Decisions of the Supreme to their July 11, 1996 agreement.
Court on mining disputes have recognized a distinction
between (1) the primary powers granted by pertinent provisions
SO ORDERED.
of law to the then Secretary of Agriculture and Natural
Resources (and the bureau directors) of an executive or
administrative nature, such as granting of license, permits, DIOSDADO M. PERALTA
lease and contracts, or approving, rejecting, reinstating or
canceling applications, or deciding conflicting applications, and Associate Justice
(2) controversies or disagreements of civil or contractual nature
between litigants which are questions of a judicial nature that WE CONCUR:
may be adjudicated only by the courts of justice. This distinction
is carried on even in Rep. Act No. 7942.28 ANTONIO T. CARPIO

We found that since the complaint filed before the DENR Panel Associate Justice
of Arbitrators charged respondents with disregarding and
ignoring the addendum contract, and acting in a fraudulent and
Chairperson
oppressive manner against petitioner, the complaint filed before
ADR || First Batch 11
6
ANTONIO EDUARDO B. NACHURA hear the parties,ROBERTO
and upon being
A. ABAD
satisfied that the making
of the agreement or such failure to comply therewith is not in
Associate Justice issue, shall make an order
Associate directing the parties to proceed to
Justice
JOSE CATRAL MENDOZA arbitration in accordance with the terms of the agreement. If the
making of the agreement or default be in issue the court shall
proceed to summarily hear such issue. If the finding be that no
Associate Justice
agreement in writing providing for arbitration was made, or that
there is no default in the proceeding thereunder, the proceeding
ATTESTATION shall be dismissed. If the finding be that a written provision for
arbitration was made and there is a default in proceeding
I attest that the conclusions in the above Decision had been thereunder, an order shall be made summarily directing the
reached in consultation before the case was assigned to the parties to proceed with the arbitration in accordance with the
writer of the opinion of the Courts Division. terms thereof.

ANTONIO T. CARPIO The court shall decide all motions, petitions or applications filed
under the provisions of this Act, within ten days after such
Associate Justice motions, petitions, or applications have been heard by it.

Second Division, Chairperson 7 Sec. 7. Stay of civil action. - If any suit or proceeding be
brought upon an issue arising out of an agreement providing for
CERTIFICATION the arbitration thereof, the court in which such suit or
proceeding is pending, upon being satisfied that the issue
involved in such suit or proceeding is referable to arbitration,
Pursuant to Section 13, Article VIII of the Constitution and the
shall say the action or proceeding until an arbitration has been
Division Chairpersons Attestation, I certify that the conclusions
had in accordance with the terms of the agreement; Provided
in the above Decision had been reached in consultation before
that the applicant for the stay is not in default in proceeding with
the case was assigned to the writer of the opinion of the Courts
such arbitration.
Division.
8 Penned by Judge Lucia Violago Isnani; rollo, pp. 71-75.
RENATO C. CORONA
9 Id. at 75.
Chief Justice
10 Records, pp. 113-115.

11 G.R. No. 161957, February 28, 2005, 452 SCRA 607.


Footnotes
12 Rollo, pp. 311-314.
1 Penned by Associate Justice Edgardo F. Sundiam, with
Associate Justices Rodrigo V. Cosico and Japar B.
Dimaampao, concurring; rollo, pp. 32-45.
13G.R. Nos. 161957 & 167994, January 22, 1997, 512 SCRA
148, 163.
2 Id. at 47-48.
14 Id. at 165.
3 Docketed as Civil Case No. 98-1376; raffled off to Branch 59.
15 G.R. No. 103200, August 31, 1994, 236 SCRA 78, 91.
4 Rollo, pp. 61-70.
16 Gonzales v. Climax Mining Ltd., supra note 13, at 166.
5 Id. at 60.
17 An Act to Institutionalize the Use of An Alternative Dispute
Resolution System in the Philippines and to Establish the Office
6 Section 6. Hearing by court. - A party aggrieved by the failure,
for Alternative Dispute Resolution, and for other purposes.
neglect or refusal of another to perform under an agreement in
writing providing for arbitration may petition the court for an
order directing that such arbitration proceed in the manner
18 Gonzeles v. Climax Mining Ltd., supra note 13.
provided for in such agreement. Five days notice in writing of
the hearing of such application shall be served either personally 19 Id. at 167.
or by registered mail upon the party in default. The court shall
ADR || First Batch 11
7
20 Id. Republic of the Philippines
SUPREME COURT
21Id., citing Manila Electric Co. v. Pasay Transportation Co., 57 Baguio City
Phil 600 (1932). THIRD DIVISION

22 Id. at 167-168. G.R. No. 167022 April 4, 2011

23Id., citing Del Monte Corporation -USA v. Court of Appeals, LICOMCEN INCORPORATED, Petitioner,
404 Phil. 192 (2001).
vs.
24 Rollo, pp. 44-45. (Emphasis supplied.)
FOUNDATION SPECIALISTS, INC., Respondent.
25 Gonzales v. Climax Mining Ltd., supra note 11.
x - - - - - - - - - - - - - - - - - - - - - - -x
26Gonzales v. Climax Mining Ltd., supra note 13, at 172-173.
(Emphasis supplied.) G.R. No. 169678

27 Id. at 170. FOUNDATION SPECIALISTS, INC., Petitioner,

28 Gonzales v. Climax Mining Ltd., supra note 11, at 620. vs.

29 Id. at 624. LICOMCEN INCORPORATED, Respondent.

DECISION

BRION, J.:

THE FACTS

The petitioner, LICOMCEN Incorporated (LICOMCEN), is a


domestic corporation engaged in the business of operating
shopping malls in the country.

In March 1997, the City Government of Legaspi awarded to


LICOMCEN, after a public bidding, a lease contract over a lot
located in the central business district of the city. Under the
contract, LICOMCEN was obliged to finance the construction of
a commercial complex/mall to be known as the LCC Citimall
(Citimall). It was also granted the right to operate and manage
Citimall for 50 years, and was, thereafter, required to turn over
the ownership and operation to the City Government.1

For the Citimall project, LICOMCEN hired E.S. de Castro and


Associates (ESCA) to act as its engineering consultant. Since
the Citimall was envisioned to be a high-rise structure,
LICOMCEN contracted respondent Foundation Specialists, Inc.
(FSI) to do initial construction works, specifically, the
construction and installation of bored piles foundation.2
LICOMCEN and FSI signed the Construction Agreement,3 and
the accompanying Bid Documents4 and General Conditions of
Contract5 (GCC) on September 1, 1997. Immediately thereafter,
FSI purchased the materials needed for the Citimall6 project
and began working in order to meet the 90-day deadline set by
LICOMCEN.
ADR || First Batch 11
8
On December 16, 1997, LICOMCEN sent word to FSI that it Contract with the City Government of Legaspi.
was considering major design revisions and the suspension of LICOMCEN also assailed the CIACs jurisdiction, contending
work on the Citimall project. FSI replied on December 18, 1997, that FSIs claims were matters not subject to arbitration under
expressing concern over the revisions and the suspension, as it GC-61 of the GCC, but one that should have been filed before
had fully mobilized its manpower and equipment, and had the regular courts of Legaspi City pursuant to GC-05.20
ordered the delivery of steel bars. FSI also asked for the
payment of accomplished work amounting to P3,627,818.00.7 A During the preliminary conference of January 28, 2003,
series of correspondence between LICOMCEN and FSI then LICOMCEN reiterated its objections to the CIACs jurisdiction,
followed. which the arbitrators simply noted. Both FSI and LICOMCEN
then proceeded to draft the Terms of Reference.21
ESCA wrote FSI on January 6, 1998, stating that the revised
design necessitated a change in the bored piles requirement On February 4, 2003, LICOMCEN, through a collaborating
and a substantial reduction in the number of piles. Thus, ESCA counsel, filed its Ex Abundati Ad Cautela Omnibus Motion,
proposed to FSI that only 50% of the steel bars be delivered to insisting that FSIs petition before the CIAC should be
the jobsite and the rest be shipped back to Manila.8 dismissed for lack of jurisdiction; thus, it prayed for the
Notwithstanding this instruction, all the ordered steel bars suspension of the arbitration proceedings until the issue of
arrived in Legaspi City on January 14, 1998.9 jurisdiction was finally settled. The CIAC denied LICOMCENs
motion in its February 20, 2003 order,22 finding that the
On January 15, 1998, LICOMCEN instructed FSI to "hold all question of jurisdiction depends on certain factual conditions
construction activities on the project,"10 in view of a pending that have yet to be established by ample evidence. As the
administrative case against the officials of the City Government CIACs February 20, 2003 order stood uncontested, the
of Legaspi and LICOMCEN filed before the Ombudsman (OMB- arbitration proceedings continued, with both parties actively
ADM-1-97-0622).11 On January 19, 1998, ESCA formalized the participating.
suspension of construction activities and ordered the
constructions demobilization until the case was resolved.12 In The CIAC issued its decision on July 7, 2003,23 ruling in favor of
response, FSI sent ESCA a letter, dated February 3, 1998, FSI and awarding the following amounts:
requesting payment of costs incurred on account of the
suspension which totaled P22,667,026.97.13 FSI repeated its
a. Unpaid accomplished work billings.
demand for payment on March 3, 1998.14
b. Material costs at site
c. Equipment and labor standby costs
ESCA replied to FSIs demands for payment on March 24, d. Unrealized gross profit
1998, objecting to some of the claims.15 It denied the claim for LICOMCEN was also required to bear the costs of arbitration in
the cost of the steel bars that were delivered, since the delivery the total amount of P474,407.95.
was done in complete disregard of its instructions. It further
disclaimed liability for the other FSI claims based on the
LICOMCEN appealed the CIACs decision before the Court of
suspension, as its cause was not due to LICOMCENs fault. FSI
Appeals (CA). On November 23, 2004, the CA upheld the
rejected ESCAs evaluation of its claims in its April 15, 1998
CIACs decision, modifying only the amounts awarded by (a)
letter.16
reducing LICOMCENs liability for material costs at site to
P5,694,939.87, and (b) deleting its liability for equipment and
On March 14, 2001, FSI sent a final demand letter to labor standby costs and unrealized gross profit; all the other
LICOMCEN for payment of P29,232,672.83.17 Since awards were affirmed.24 Both parties moved for the
LICOMCEN took no positive action on FSIs demand for reconsideration of the CAs Decision; LICOMCENs motion was
payment,18 FSI filed a petition for arbitration with the denied in the CAs February 4, 2005 Resolution, while FSIs
Construction Industry Arbitration Commission (CIAC) on motion was denied in the CAs September 13, 2005 Resolution.
October 2, 2002, docketed as CIAC Case No. 37-2002.19 In the Hence, the parties filed their own petition for review on certiorari
arbitration petition, FSI demanded payment of the following before the Court.25
amounts:
LICOMCENs Arguments
a. Unpaid accomplished work billings. P 1,264,404.12
b. Material costs at site.. 15,143,638.51
c. Equipment and labor standby costs.. 3,058,984.34 LICOMCEM principally raises the question of the CIACs
d. Unrealized gross profit.. 9,023,575.29
e. Attorneys fees.. 300,000.00
jurisdiction, insisting that FSIs claims are non-arbitrable. In
f. Interest expenses ... support of its position, LICOMCEN cites GC-61 of the GCC:

LICOMCEN again denied liability for the amounts claimed by GC-61. DISPUTES AND ARBITRATION
FSI. It justified its decision to indefinitely suspend the Citimall
project due to the cases filed against it involving its Lease Should any dispute of any kind arise between the LICOMCEN
ADR || First Batch 11
9
INCORPORATED and the Contractor [referring to FSI] or the on the dispute, either party does not officially give notice
Engineer [referring to ESCA] and the Contractor in connection to contest such decision through arbitration, the said decision
with, or arising out of the execution of the Works, such dispute shall remain final and binding. However, should any party,
shall first be referred to and settled by the LICOMCEN, within 30 days from receipt of LICOMCENs decision, contest
INCORPORATED who shall within a period of thirty (30) days said decision, the dispute shall be submitted for arbitration
after being formally requested by either party to resolve the under the Construction Industry Arbitration Law.
dispute, issue a written decision to the Engineer and
Contractor. LICOMCEN considers its March 24, 1998 letter as its final
decision on FSIs claims, but declares that FSIs reply letter of
Such decision shall be final and binding upon the parties and April 15, 1998 is not the "notice to contest" required by GC-61
the Contractor shall proceed with the execution of the Works that authorizes resort to arbitration before the CIAC. It posits
with due diligence notwithstanding any Contractor's objection to that nothing in FSIs April 15, 1998 letter states that FSI will
the decision of the Engineer. If within a period of thirty (30) days avail of arbitration as a mode to settle its dispute with
from receipt of the LICOMCEN, INCORPORATED's decision LICOMCEN. While FSIs final demand letter of March 14, 2001
on the dispute, either party does not officially give notice to mentioned its intention to refer the matter to arbitration,
contest such decision through arbitration, the said decision LICOMCEN declares that the letter was made three years after
shall remain final and binding. However, should any party, its March 24, 1998 letter, hence, long after the 30-day period
within thirty (30) days from receipt of the LICOMCEN, provided in GC-61. Indeed, FSI filed the petition for arbitration
INCORPORATED's decision, contest said decision, the dispute with the CIAC only on October 2, 2002.29 Considering FSIs
shall be submitted for arbitration under the Construction delays in asserting its claims, LICOMCEN also contends that
Industry Arbitration Law, Executive Order 1008. The arbitrators FSIs action is barred by laches.
appointed under said rules and regulations shall have full power
to open up, revise and review any decision, opinion, direction, With respect to the monetary claims of FSI, LICOMCEM alleges
certificate or valuation of the LICOMCEN, INCORPORATED. that the CA erred in upholding its liability for material costs at
Neither party shall be limited to the evidence or arguments put site for the reinforcing steel bars in the amount of
before the LICOMCEN, INCORPORATED for the purpose of P5,694,939.87, computed as follows30:
obtaining his said decision. No decision given by the
LICOMCEN, INCORPORATED shall disqualify him from being 2nd initial rebar requirements purchased from
called as a witness and giving evidence in the arbitration. It is P 799,506.83
Pag-Asa Steel Works, Inc.
understood that the obligations of the LICOMCEN, Reinforcing steel bars purchased from ARCA
INCORPORATED, the Engineer and the Contractor shall not be Industrial Sales (total net weight of 744,197.66 5,395,433.04
kilograms) 50% of net amount due
altered by reason of the arbitration being conducted during the
progress of the Works.26
Subtotal 6,194,939.87
LICOMCEN posits that only disputes "in connection with or Less
arising out of the execution of the Works" are subject to Purchase cost of steel bars by Ramon
(500,000.00)
arbitration. LICOMCEN construes the phrase "execution of the Quinquileria
Works" as referring to the physical construction activities, since
"Works" under the GCC specifically refer to the "structures and TOTAL LIABILITY OF LICOMCEN TO FSI FOR
MATERIAL COSTS AT SITE 5,694,939.87
facilities" required to be constructed and completed for the
Citimall project.27 It considers FSIs claims as mere contractual
Citing GC-42(2) of the GCC, LICOMCEN says it shall be liable
monetary claims that should be litigated before the courts of
Legaspi City, as provided in GC-05 of the GCC: to pay FSI "[t]he cost of materials or goods reasonably ordered
for the Permanent or Temporary Works which have been
delivered to the Contractor but not yet used, and which delivery
GC-05. JURISDICTION has been certified by the Engineer."31 None of these requisites
were allegedly complied with. It contends that FSI failed to
Any question between the contracting parties that may arise out establish that the steel bars delivered in Legaspi City, on
of or in connection with the Contract, or breach thereof, shall be January 14, 1998, were for the Citimall project. In fact, the steel
litigated in the courts of Legaspi City except where otherwise bars were delivered not at the site of the Citimall project, but at
specifically stated or except when such question is submitted FSIs batching plant called Tuanzon compound, a few hundred
for settlement thru arbitration as provided herein.28 meters from the site. Even if delivery to Tuanzon was allowed,
the delivery was done in violation of ESCAs instruction to ship
LICOMCEN also contends that FSI failed to comply with the only 50% of the materials. Advised as early as December 1997
condition precedent for arbitration laid down in GC-61 of the to suspend the works, FSI proceeded with the delivery of the
GCC. An arbitrable dispute under GC-61 must first be referred steel bars in January 1998. LICOMCEN declared that it should
to and settled by LICOMCEN, which has 30 days to resolve it. If not be made to pay for costs that FSI willingly incurred for
within a period of 30 days from receipt of LICOMCENs decision itself.32
ADR || First Batch 12
0
Assuming that LICOMCEN is liable for the costs of the steel delivery certified by ESCA because by then the Citimall
bars, it argues that its liability should be minimized by the fact project had been suspended. It would be unfair to demand FSI
that FSI incurred no actual damage from the purchase and to perform an act that ESCA and LICOMCEN themselves had
delivery of the steel bars. During the suspension of the works, prevented from happening.38
FSI sold 125,000 kg of steel bars for P500,000.00 to a third
person (a certain Ramon Quinquileria). LICOMCEN alleges that The CA deleted the awards for equipment and labor standby
FSI sold the steel bars for a ridiculously low price of P 4.00/kilo, costs on the ground that FSIs documentary evidence was
when the prevailing rate was P20.00/kilo. The sale could have inadequate. FSI finds the ruling erroneous, since LICOMCEN
garnered a higher price that would offset LICOMCENs liability. never questioned the list of employees and equipments
LICOMCEN also wants FSI to account for and deliver to it the employed and rented by FSI for the duration of the
remaining 744 metric tons of steel bars not sold. Otherwise, FSI suspension.39
would be unjustly enriched at LICOMCENs expense, receiving
payment for materials not delivered to LICOMCEN.33
FSI also alleges that LICOMCEN maliciously and unlawfully
suspended the Citimall project. While LICOMCEN cited several
LICOMCEN also disagrees with the CA ruling that declared it other cases in its petition for review on certiorari as grounds for
solely liable to pay the costs of arbitration. The ruling was suspending the works, its letters/notices of suspension only
apparently based on the finding that LICOMCENs "failure or referred to one case, OMB-ADM-1-97-0622, an administrative
refusal to meet its obligations, legal, financial, and moral, case before the Ombudsman that was dismissed as early as
caused FSI to bring the dispute to arbitration."34 LICOMCEN October 12, 1998. LICOMCEN never notified FSI of the
asserts that it was FSIs decision to proceed with the delivery of dismissal of this case. More importantly, no restraining order or
the steel bars that actually caused the dispute; it insists that it is injunction was issued in any of these cases to justify the
not the party at fault which should bear the arbitration costs.35 suspension of the Citimall project.40 FSI posits that
LICOMCENs true intent was to terminate its contract with it,
FSIs Arguments but, to avoid paying damages for breach of contract, simply
declared it as "indefinitely suspended." That LICOMCEN
FSI takes exception to the CA ruling that modified the amount conducted another public bidding for the "new designs" is a
for material costs at site, and deleted the awards for equipment telling indication of LICOMCENs intent to ease out FSI.41 Thus,
and labor standby costs and unrealized profits. FSI states that LICOMCENs bad faith in indefinitely
suspending the Citimall project entitles it to claim unrealized
profit. The restriction under GC-41 that "[t]he contractor shall
Proof of damage to FSI is not required for LICOMCEN to be
have no claim for anticipated profits on the work thus
liable for the material costs of the steel bars. Under GC-42, it is
terminated,"42 will not apply because the stipulation refers to a
enough that the materials were delivered to the contractor,
contract lawfully and properly terminated. FSI seeks to recover
although not used. FSI said that the 744 metric tons of steel
unrealized profits under Articles 1170 and 2201 of the Civil
bars were ordered and paid for by it for the Citimall project as
Code.
early as November 1997. If LICOMCEN contends that these
were procured for other projects FSI also had in Legaspi City, it
should have presented proof of this claim, but it failed to do THE COURTS RULING
so.36
The jurisdiction of the CIAC
ESCAs January 6, 1998 letter simply suggested that only 50%
of the steel bars be shipped to Legaspi City; it was not a clear The CIAC was created through Executive Order No. 1008 (E.O.
and specific directive. Even if it was, the steel bars were 1008), in recognition of the need to establish an arbitral
ordered and paid for long before the notice to suspend was machinery that would expeditiously settle construction industry
given; by then, it was too late to stop the delivery. FSI also disputes. The prompt resolution of problems arising from or
claims that since it believed in good faith that the Citimall connected with the construction industry was considered of
project was simply suspended, it expected work to resume necessary and vital for the fulfillment of national development
soon after and decided to proceed with the shipment.37 goals, as the construction industry provides employment to a
large segment of the national labor force and is a leading
Contrary to LICOMCENs arguments, GC-42 of the GCC does contributor to the gross national product.43 Section 4 of E.O.
not require delivery of the materials at the site of the Citimall 1008 states:
project; it only requires delivery to the contractor, which is FSI.
Moreover, the Tuanzon compound, where the steel bars were Sec. 4. Jurisdiction. The CIAC shall have original and exclusive
actually delivered, is very close to the Citimall project site. FSI jurisdiction over disputes arising from, or connected with,
contends that it is a normal construction practice for contractors contracts entered into by parties involved in construction in the
to set up a "staging site," to prepare the materials and Philippines, whether the dispute arises before or after the
equipment to be used, rather than stock them in the crowded completion of the contract, or after the abandonment or breach
job/project site. FSI also asserts that it was useless to have the thereof. These disputes may involve government or private
ADR || First Batch 12
1
contracts. For the Board to acquire jurisdiction, the parties to a construction controversy or claim between the parties.
dispute must agree to submit the same to voluntary arbitration. The arbitration clause in the construction contract ipso facto
vested the CIAC with jurisdiction."
The jurisdiction of the CIAC may include but is not limited to
violation of specifications for materials and workmanship; Under GC-61 and GC-05 of the GCC, read singly and in
violation of the terms of agreement; interpretation and/or relation with one another, the Court sees no intent to limit resort
application of contractual time and delays; maintenance and to arbitration only to disputes relating to the physical
defects; payment, default of employer or contractor and construction activities.
changes in contract cost.
First, consistent with the intent of the law, an arbitration clause
Excluded from the coverage of this law are disputes arising pursuant to E.O. 1008 should be interpreted at its widest
from employer-employee relationships which shall continue to signification. Under GC-61, the voluntary arbitration clause
be covered by the Labor Code of the Philippines. covers any dispute of any kind, not only arising of out the
execution of the works but also in connection therewith. The
The jurisdiction of courts and quasi-judicial bodies is payments, demand and disputed issues in this case namely,
determined by the Constitution and the law.44 It cannot be fixed work billings, material costs, equipment and labor standby
by the will of the parties to a dispute;45 the parties can neither costs, unrealized profits all arose because of the construction
expand nor diminish a tribunals jurisdiction by stipulation or activities and/or are connected or related to these activities. In
agreement. The text of Section 4 of E.O. 1008 is broad enough other words, they are there because of the construction
to cover any dispute arising from, or connected with activities. Attorneys fees and interests payment, on the other
construction contracts, whether these involve mere contractual hand, are costs directly incidental to the dispute. Hence, the
money claims or execution of the works.46 Considering the scope of the arbitration clause, as worded, covers all the
intent behind the law and the broad language adopted, disputed items.
LICOMCEN erred in insisting on its restrictive interpretation of
GC-61. The CIACs jurisdiction cannot be limited by the parties Second and more importantly, in insisting that contractual
stipulation that only disputes in connection with or arising out of money claims can be resolved only through court action,
the physical construction activities (execution of the works) are LICOMCEN deliberately ignores one of the exceptions to the
arbitrable before it. general rule stated in GC-05:

In fact, all that is required for the CIAC to acquire jurisdiction is GC-05. JURISDICTION
for the parties to a construction contract to agree to submit their
dispute to arbitration. Section 1, Article III of the 1988 CIAC Any question between the contracting parties that may arise out
Rules of Procedure (as amended by CIAC Resolution Nos. 2- of or in connection with the Contract, or breach thereof, shall be
91 and 3-93) states: litigated in the courts of Legaspi City except where otherwise
specifically stated or except when such question is submitted
Section 1. Submission to CIAC Jurisdiction. An arbitration for settlement thru arbitration as provided herein.
clause in a construction contract or a submission to arbitration
of a construction dispute shall be deemed an agreement to The second exception clause authorizes the submission to
submit an existing or future controversy to CIAC jurisdiction, arbitration of any dispute between LICOMCEM and FSI, even if
notwithstanding the reference to a different arbitration institution the dispute does not directly involve the execution of physical
or arbitral body in such contract or submission. When a contract construction works. This was precisely the avenue taken by FSI
contains a clause for the submission of a future controversy to when it filed its petition for arbitration with the CIAC.
arbitration, it is not necessary for the parties to enter into a
submission agreement before the claimant may invoke the
If the CIACs jurisdiction can neither be enlarged nor diminished
jurisdiction of CIAC.
by the parties, it also cannot be subjected to a condition
precedent. GC-61 requires a party disagreeing with
An arbitration agreement or a submission to arbitration shall be LICOMCENs decision to "officially give notice to contest such
in writing, but it need not be signed by the parties, as long as decision through arbitration" within 30 days from receipt of the
the intent is clear that the parties agree to submit a present or decision. However, FSIs April 15, 1998 letter is not the notice
future controversy arising from a construction contract to contemplated by GC-61; it never mentioned FSIs plan to
arbitration. submit the dispute to arbitration and instead requested
LICOMCEN to reevaluate its claims. Notwithstanding FSIs
In HUTAMA-RSEA Joint Operations, Inc. v. Citra Metro Manila failure to make a proper and timely notice, LICOMCENs
Tollways Corporation,47 the Court declared that "the bare fact decision (embodied in its March 24, 1998 letter) cannot become
that the parties x x x incorporated an arbitration clause in [their "final and binding" so as to preclude resort to the CIAC
contract] is sufficient to vest the CIAC with jurisdiction over any arbitration. To reiterate, all that is required for the CIAC to
ADR || First Batch 12
2
acquire jurisdiction is for the parties to agree to submit their Works.
dispute to voluntary arbitration:
The Engineer through LICOMCEN, INCORPORATED shall
[T]he mere existence of an arbitration clause in the construction issue the order lifting the suspension of work when conditions
contract is considered by law as an agreement by the parties to to resume work shall have become favorable or the reasons for
submit existing or future controversies between them to CIAC the suspension have been duly corrected.50
jurisdiction, without any qualification or condition precedent. To
affirm a condition precedent in the construction contract, which GC-41 LICOMCEN, INCORPORATED's RIGHT TO SUSPEND
would effectively suspend the jurisdiction of the CIAC until WORK OR TERMINATE THE CONTRACT
compliance therewith, would be in conflict with the recognized
intention of the law and rules to automatically vest CIAC with
xxxx
jurisdiction over a dispute should the construction contract
contain an arbitration clause.48
2. For Convenience of LICOMCEN, INCORPORATED
The CIAC is given the original and exclusive jurisdiction over
disputes arising from, or connected with, contracts entered into If any time before completion of work under the Contract it shall
by parties involved in construction in the Philippines.49 This be found by the LICOMCEN, INCORPORATED that reasons
jurisdiction cannot be altered by stipulations restricting the beyond the control of the parties render it impossible or against
nature of construction disputes, appointing another arbitral the interest of the LICOMCEN, INCORPORATED to complete
body, or making that bodys decision final and binding. the work, the LICOMCEN, INCORPORATED at any time, by
written notice to the Contractor, may discontinue the work and
terminate the Contract in whole or in part. Upon the issuance of
The jurisdiction of the CIAC to resolve the dispute between
such notice of termination, the Contractor shall discontinue to
LICOMCEN and FSI is, therefore, affirmed.
work in such manner, sequence and at such time as the
LICOMCEN, INCORPORATED/Engineer may direct, continuing
The validity of the indefinitesuspension of the works on and doing after said notice only such work and only until such
theCitimall project time or times as the LICOMCEN, INCORPORATED/Engineer
may direct.51
Before the Court rules on each of FSIs contractual monetary
claims, we deem it important to discuss the validity of Under these stipulations, we consider LICOMCENs initial
LICOMCENs indefinite suspension of the works on the Citimall suspension of the works valid. GC-38 authorizes the
project. We quote below two contractual stipulations relevant to suspension of the works for factors or causes which ESCA
this issue: deems necessary in the interests of the works and LICOMCEN.
The factors or causes of suspension may pertain to a change or
GC-38. SUSPENSION OF WORKS revision of works, as cited in the December 16, 1997 and
January 6, 1998 letters of ESCA, or to the pendency of a case
The Engineer [ESCA] through the LICOMCEN, before the Ombudsman (OMB-ADM-1-97-0622), as cited in
INCORPORATED shall have the authority to suspend the LICOMCENs January 15, 1998 letter and ESCAs January 19,
Works wholly or partly by written order for such period as may 1998 and February 17, 1998 letters. It was not necessary for
be deemed necessary, due to unfavorable weather or other ESCA/LICOMCEN to wait for a restraining or injunctive order to
conditions considered unfavorable for the prosecution of the be issued in any of the cases filed against LICOMCEN before it
Works, or for failure on the part of the Contractor to correct can suspend the works. The language of GC-38 gives
work conditions which are unsafe for workers or the general ESCA/LICOMCEN sufficient discretion to determine whether
public, or failure or refusal to carry out valid orders, or due to the existence of a particular situation or condition necessitates
change of plans to suit field conditions as found necessary the suspension of the works and serves the interests of
during construction, or to other factors or causes which, in the LICOMCEN. 1avvphi1

opinion of the Engineer, is necessary in the interest of the


Works and to the LICOMCEN, INCORPORATED. The Although we consider the initial suspension of the works as
Contractor [FSI] shall immediately comply with such order to valid, we find that LICOMCEN wrongfully prolonged the
suspend the work wholly or partly directed. suspension of the works (or "indefinite suspension" as
LICOMCEN calls it). GC-38 requires ESCA/LICOMCEN to
In case of total suspension or suspension of activities along the "issue an order lifting the suspension of work when conditions
critical path of the approved PERT/CPM network and the cause to resume work shall have become favorable or the reasons for
of which is not due to any fault of the Contractor, the elapsed the suspension have been duly corrected." The Ombudsman
time between the effective order for suspending work and the case (OMB-ADM-1-97-0622), which ESCA and LICOMCEN
order to resume work shall be allowed the Contractor by cited in their letters to FSI as a ground for the suspension, was
adjusting the time allowed for his execution of the Contract dismissed as early as October 12, 1998, but neither ESCA nor
ADR || First Batch 12
3
LICOMCEN informed FSI of this development. The pendency of 2. The cost of materials or goods reasonably ordered for
the other cases52 may justify the continued suspension of the the Permanent or Temporary Works which have been delivered
works, but LICOMCEN never bothered to inform FSI of the to the Contractor but not yet used and which delivery has been
existence of these cases until the arbitration proceedings certified by the Engineer.
commenced. By May 28, 2002, the City Government of Legaspi
sent LICOMCEN a notice instructing it to proceed with the 3. The reasonable cost of demobilization
Citimall project;53 again, LICOMCEN failed to relay this
information to FSI. Instead, LICOMCEN conducted a rebidding
For any payment due the Contractor under the above
of the Citimall project based on the new design.54 LICOMCENs
conditions, the LICOMCEN, INCORPORATED, however, shall
claim that the rebidding was conducted merely to get cost
deduct any outstanding balance due from the Contractor for
estimates for the new design goes against the established
advances in respect to mobilization and materials, and any
practice in the construction industry. We find the CIACs
other sum the LICOMCEN, INCORPORATED is entitled to be
discussion on this matter relevant:
credited.56

But what is more appalling and disgusting is the allegation x x x


For LICOMCEN to be liable for the cost of materials or goods,
that the x x x invitation to bid was issued x x x solely to gather
item two of GC-42 requires that
cost estimates on the redesigned [Citimall project] x x x. This
Arbitral Tribunal finds said act of asking for bids, without any
intention of awarding the project to the lowest and qualified a. the materials or goods were reasonably ordered for the
bidder, if true, to be extremely irresponsible and highly Permanent or Temporary Works;
unprofessional. It might even be branded as fraudulent x x x
[since] the invited bidders [were required] to pay P2,000.00 b. the materials or goods were delivered to the Contractor but
each for a set of the new plans, which amount was non- not yet used; and
refundable. The presence of x x x deceit makes the whole story
repugnant and unacceptable.55 c. the delivery was certified by the Engineer.

LICOMCENs omissions and the imprudent rebidding of the Both the CIAC and the CA agreed that these requisites were
Citimall project are telling indications of LICOMCENs intent to met by FSI to make LICOMCEN liable for the cost of the steel
ease out FSI and terminate their contract. As with GC-31, GC- bars ordered for the Citimall project; the two tribunals differed
42(2) grants LICOMCEN ample discretion to determine what only to the extent of LICOMCENs liability because the CA
reasons render it against its interest to complete the work in opined that it should be limited only to 50% of the cost of the
this case, the pendency of the other cases and the revised steel bars. A review of the records compels us to uphold the
designs for the Citimall project. Given this authority, the Court CAs finding.
fails to the see the logic why LICOMCEN had to resort to an
"indefinite suspension" of the works, instead of outrightly Prior to the delivery of the steel bars, ESCA informed FSI of the
terminating the contract in exercise of its rights under GC-42(2). suspension of the works; ESCAs January 6, 1998 letter reads:

We now proceed to discuss the effects of these findings with As per our information to you on December 16, 1997, a major
regard to FSIs monetary claims against LICOMCEN. revision in the design of the Legaspi Citimall necessitated a
change in the bored piles requirement of the project. The
The claim for material costs at site change involved a substantial reduction in the number and
length of piles.
GC-42 of the GCC states:
We expected that you would have suspended the deliveries of
GC-42 PAYMENT FOR TERMINATED CONTRACT the steel bars until the new design has been approved.

If the Contract is terminated as aforesaid, the Contractor will be According to you[,] the steel bars had already been paid and
paid for all items of work executed, satisfactorily completed and loaded and out of Manila on said date.
accepted by the LICOMCEN, INCORPORATED up to the date
of termination, at the rates and prices provided for in the In order to avoid double handling, storage, security problems,
Contract and in addition: we suggest that only 50% of the total requirement of steel bars
be delivered at jobsite. The balance should be returned to
1. The cost of partially accomplished items of additional or extra Manila where storage and security is better.
work agreed upon by the LICOMCEN, INCORPORATED and
the Contractor. In order for us to consider additional cost due to the shipping of
the excess steel bars, we need to know the actual dates of
ADR || First Batch 12
4
purchase, payments and loading of the steel bars. Obviously, equipment and labor standby costs. We quote in
we cannot consider the additional cost if you have had the agreement pertinent portions of the CA decision:
chance to delay the shipping of the steel bars.57
The CIAC relied solely on the list of 37 pieces of equipment
From the above, it appears that FSI was informed of the respondent allegedly rented and maintained at the construction
necessity of suspending the works as early as December 16, site during the suspension of the project with the prorated
1997. Pursuant to GC-38 of the GCC, FSI was expected to rentals incurred x x x. To the mind of this Court, these lists are
immediately comply with the order to suspend the work.58 not sufficient to establish the fact that indeed [FSI] incurred the
Though ESCAs December 16, 1997 notice may not have been said expenses. Reliance on said lists is purely speculative x x x
categorical in ordering the suspension of the works, FSIs reply the list of equipments is a mere index or catalog of the
letter of December 18, 1997 indicated that it actually complied equipments, which may be utilized at the construction site. It is
with the notice to suspend, as it said, "We hope for the early not the best evidence to prove that said equipment were in fact
resolution of the new foundation plan and the resumption of rented and maintained at the construction site during the
work."59 Despite the suspension, FSI claimed that it could not suspension of the work. x x x [FSI] should have presented the
stop the delivery of the steel bars (nor found the need to do so) lease contracts or any similar documents such as receipts of
because (a) the steel bars were ordered as early as November payments x x x. Likewise, the list of employees does not in
1997 and were already loaded in Manila and expected to arrive anyway prove that those employees in the list were indeed at
in Legaspi City by December 23, 1997, and (b) it expected the construction site or were required to be on call should their
immediate resumption of work to meet the 90-day deadline.60 services be needed and were being paid their salaries during
the suspension of the project. Thus, in the absence of sufficient
Records, however, disclose that these claims are not entirely evidence, We deny the claim for equipment and labor standby
accurate. The memorandum of agreement and sale covering costs.65
the steel bars specifically stated that these would be withdrawn
from the Cagayan de Oro depot, not Manila61; indeed, the bill of The claim for unrealized profit
lading stated that the steel bars were loaded in Cagayan de
Oro on January 11, 1998, and arrived in Legaspi City within FSI contends that it is not barred from recovering unrealized
three days, on January 14, 1998.62 The loading and delivery of profit under GC-41(2), which states:
the steel bar thus happened after FSI received ESCAs
December 16, 1997 and January 6, 1998 letters days after
GC-41. LICOMCEN, INCORPORATEDs RIGHT TO
the instruction to suspend the works. Also, the same stipulation
SUSPEND WORK OR TERMINATE THE CONTRACT
that authorizes LICOMCEN to suspend the works allows the
extension of the period to complete the works. The relevant
portion of xxxx

GC-38 states: 2. For Convenience of the LICOMCEN, INCORPORATED

In case of total suspension x x x and the cause of which is not x x x. The Contractor [FSI] shall not claim damages for such
due to any fault of the Contractor [FSI], the elapsed time discontinuance or termination of the Contract, but the
between the effective order for suspending work and the order Contractor shall receive compensation for reasonable expenses
to resume work shall be allowed the Contractor by adjusting the incurred in good faith for the performance of the Contract and
time allowed for his execution of the Contract Works.63 for reasonable expenses associated with termination of the
Contract. The LICOMCEN, INCORPORATED will determine
the reasonableness of such expenses. The Contractor [FSI]
The above stipulation, coupled with the short period it took to
shall have no claim for anticipated profits on the work thus
ship the steel bars from Cagayan de Oro to Legaspi City, thus
terminated, nor any other claim, except for the work actually
negates both FSIs
performed at the time of complete discontinuance, including
any variations authorized by the LICOMCEN,
argument and the CIACs ruling64 that there was no necessity to INCORPORATED/Engineer to be done.
stop the shipment so as to meet the 90-day deadline. These
circumstances prove that FSI acted imprudently in proceeding
The prohibition, FSI posits, applies only where the contract was
with the delivery, contrary to LICOMCENs instructions. The CA
properly and lawfully terminated, which was not the case at bar.
was correct in holding LICOMCEN liable for only 50% of the
FSI also took pains in differentiating its claim for "unrealized
costs of the steel bars delivered.
profit" from the prohibited claim for "anticipated profits";
supposedly, unrealized profit is "one that is built-in in the
The claim for equipment andlabor standby costs contract price, while anticipated profit is not." We fail to see the
distinction, considering that the contract itself neither defined
The Court upholds the CAs ruling deleting the award for nor differentiated the two terms. [A] contract must be
ADR || First Batch 12
5
interpreted from the language of the contract itself, according to ARTURO D. BRION
its plain and ordinary meaning."66 If the terms of a contract are
clear and leave no doubt upon the intention of the contracting Associate Justice
parties, the literal meaning of the stipulations shall control.67
WE CONCUR:
Nonetheless, on account of our earlier discussion of
LICOMCENs failure to observe the proper procedure in
CONCHITA CARPIO MORALES
terminating the contract by declaring that it was merely
indefinitely suspended, we deem that FSI is entitled to the
payment of nominal damages. Nominal damages may be Associate Justice
awarded to a plaintiff whose right has been violated or invaded
by the defendant, for the purpose of vindicating or recognizing LUCAS P. BERSAMIN
that right, and not for indemnifying the plaintiff for any loss
suffered by him.68 Its award is, thus, not for the purpose of Associate Justice
indemnification for a loss but for the recognition and vindication MA. LOURDES P.A. SERENO
of a right. A violation of the plaintiffs right, even if only
technical, is sufficient to support an award of nominal Associate Justice
damages.69 FSI is entitled to recover the amount of
P100,000.00 as nominal damages.
ATTESTATION
The liability for costs of arbitration
I attest that the conclusions in the above Decision had been
reached in consultation before the case was assigned to the
Under the parties Terms of Reference, executed before the writer of the opinion of the Courts Division.
CIAC, the costs of arbitration shall be equally divided between
them, subject to the CIACs determination of which of the
CONCHITA CARPIO MORALES
parties shall eventually shoulder the amount.70 The CIAC
eventually ruled that since LICOMCEN was the party at fault, it
should bear the costs. As the CA did, we agree with this finding. Associate Justice
Ultimately, it was LICOMCENs imprudent declaration of
indefinitely suspending the works that caused the dispute Chairperson
between it and FSI. LICOMCEN should bear the costs of
arbitration. CERTIFICATION

WHEREFORE, premises considered, the petition for review on Pursuant to Section 13, Article VIII of the Constitution, and the
certiorari of LICOMCEN INCORPORATED, docketed as G.R. Division Chairpersons Attestation, it is hereby certified that the
No. 167022, and the petition for review on certiorari of conclusions in the above Decision had been reached in
FOUNDATION SPECIALISTS, INC., docketed as G.R. No. consultation before the case was assigned to the writer of the
169678, are DENIED. The November 23, 2004 Decision of the opinion of the Courts Division.
Court of Appeals in CA-G.R. SP No. 78218 is MODIFIED to
include the award of nominal damages in favor of RENATO C. CORONA
FOUNDATION SPECIALISTS, INC. Thus, LICOMCEN
INCORPORATED is ordered to pay FOUNDATION
SPECIALISTS, INC. the following amounts: Chief Justice

a. P1,264,404.12 for unpaid balance on FOUNDATION


SPECIALISTS, INC. billings;
Footnotes
b. P5,694,939.87 for material costs at site; and
1 Rollo (G.R. No. 167022, Vol. I), p. 63.
c. P100,000.00 for nominal damages.
2 Ibid.
LICOMCEN INCORPORATED is also ordered to pay the costs
of arbitration. No costs. 3 Id. at 96-105.

SO ORDERED. 4 Id. at 106-119.


ADR || First Batch 12
6
5 Id. at 120-156. 28 Rollo (G.R. No. 167022, Vol. I), p. 128.

6 Id. at 903. 29 Id. at 65.

7 Id. at 202-203. 30 Rollo (G.R. No. 167022, Vol. I), p. 76.

8 Id. at 260. 31 Id. at 147.

9 Bill of Lading; id. at 261. 32 Rollo (G.R. No. 167022, Vol. II), pp. 1938-1943.

10 Id. at 64. 33 Id. at 1944-1946.

11 Id. at 184. 34 Rollo (G.R. No. 167022, Vol. I), page 80.

12 Id. at 185. 35 Rollo (G.R. No. 167022, Vol. II), pp. 1948-1949.

13 Id. at 195. 36 Id. at 1981-1986.

14 Id. at 200. 37 Ibid.

15 Id. at 212. 38 Id. at 1987.

16 Id. at 214. 39 Id. at 2141-2145.

17 Id. at 215-217. 40 Id. at 2015-2016.

18In reply to FSIs March 24, 2001 demand letter, LICOMCEN 41 Id. at 1996.
simply stated that the matter would be referred to its finance
and legal department, in its March 24, 2001 letter, id. at 430. 42 Id. (G.R. No. 167022, Vol. I), p. 146.

19 Id. at 90-95. 43 E.O. 1008 (1985), Whereas clauses.

20 Id. at 224-229. 44BF Homes, Inc., et al. v. Manila Electric Company, G.R. No.
171624, December 6, 2010, citing Civil Service Commission v.
21 Id. at 1863-1869. Albao, G.R. No. 155784, October 13, 2005, 472 SCRA 548,
555.
22 Rollo (G.R. No. 167022, Vol. I), pp. 889-890.
45Municipality of Sogod v. Rosal, G.R. Nos. 38204 and 38205,
23 Id. at 894-908. September 24, 1991, 201 SCRA 632.

24 Id. at 62-85.
46"E.O. No. 1008 does not distinguish between claims involving
payment of money or not," Excellent Quality Apparel, Inc. v.
Win Multi-Rich Builders, Inc., G.R. No. 175048, February 10,
25LICOMCENs petition for review on certiorari is docketed as
2009, 578 SCRA 272, 280, citing C. Parlade, The Law and
G.R. No. 167022, while FSIs petition for review on certiorari is
Practice of Conciliation and Arbitration of Construction Disputes
docketed as G.R. No. 169678.
(2001 ed.), p. 89.
26 Rollo (G.R. No. 167022, Vol. I), p. 156. 47 G.R. No. 180640, April 24, 2009, 586 SCRA 746, 760-761.
27 LICOMCEN cites GC-1.14, GC-1.09 and GC-1.13 which 48 Id. at 763.
defined the terms "works," "permanent works," and "temporary
works," respectively; id. at 38, and rollo (G.R. No. 167022, Vol.
II), pp. 1926-1928.
49 E.O. 1008, Section 4.
ADR || First Batch 12
7
50 Rollo (G.R. No. 167022, Vol. I), p. 144. 69Almeda v. Cario, G.R. No. 152143, January 13, 2003,
395 SCRA 144.
51 Id. at 146.
70 Rollo (G.R. No. 167022, Vol. II), p. 1366.
52LICOMCEN cites OMB-ADM-1-98-2015, and Civil Case Nos.
10109 and 10093; id. at 20-22.

53 Id. at 745.

54 The Invitation to Bid was dated October 1, 2002; id. at 221.

55 Id. at 902.

56 Id. at 146-147.

57 Id. at 260.

58 Id. at 144.

59 Id. at 203.

60 Rollo (G.R. No. 167022, Vol. II), pp. 2137-2138.

61 Rollo (G.R. No. 167022, Vol. I), p. 732.

62 Id. at 261.

63 Supra note 58.

64 Rollo (G.R. No. 167022, Vol. I), p. 903, the CIACs decision
states:

According to [Licomcen], FSI acted unreasonably by allowing


the rebars to be shipped to Legaspi City notwithstanding the
suspension of the project. This argument holds no water. First
of all, since the project was supposedly simply suspended, FSI
had every reason to expect work thereon to be resumed after a
short time. There was, therefore, no necessity then for it to stop
the shipment of the rebars. Furthermore, the stipulated period
of construction is only ninety (90) days. Because said period is
quite short, FSI cannot be faulted in ordering the remaining
rebars needed for the project ahead of their scheduled use,
since these had to be shipped from Cagayan de Oro.

65 Id. at 77-78.

66Adriatico Consortium, Inc. v. Land Bank of the Philippines,


G.R. No. 187838, December 23, 2009, 609 SCRA 403, 418.

67 CIVIL CODE, Article 1370.

68 Id., Article 2221.


ADR || First Batch 12
8
Republic of the Philippines patents in order to practice the processes claimed in
SUPREME COURT those patents in the United States, the Philippines, and
Manila Indonesia, enforce those patents and collect royalties in
SECOND DIVISION conjunction with Licensor.

G.R. No. 185582 February 29, 2012 xxx

TUNA PROCESSING, INC., Petitioner, 4. Establishment of Tuna Processors, Inc. The parties hereto
agree to the establishment of Tuna Processors, Inc. ("TPI"), a
vs. corporation established in the State of California, in order to
implement the objectives of this Agreement.
PHILIPPINE KINGFORD, INC., Respondent.
5. Bank account. TPI shall open and maintain bank accounts
in the United States, which will be used exclusively to deposit
DECISION
funds that it will collect and to disburse cash it will be obligated
to spend in connection with the implementation of this
PEREZ, J.: Agreement.

Can a foreign corporation not licensed to do business in the 6. Ownership of TPI. TPI shall be owned by the Sponsors and
Philippines, but which collects royalties from entities in the Licensor. Licensor shall be assigned one share of TPI for the
Philippines, sue here to enforce a foreign arbitral award? purpose of being elected as member of the board of directors.
The remaining shares of TPI shall be held by the Sponsors
In this Petition for Review on Certiorari under Rule 45,1 according to their respective equity shares. 9
petitioner Tuna Processing, Inc. (TPI), a foreign corporation not
licensed to do business in the Philippines, prays that the xxx
Resolution2 dated 21 November 2008 of the Regional Trial
Court (RTC) of Makati City be declared void and the case be
The parties likewise executed a Supplemental Memorandum of
remanded to the RTC for further proceedings. In the assailed
Agreement10 dated 15 January 2003 and an Agreement to
Resolution, the RTC dismissed petitioners Petition for
Amend Memorandum of Agreement11 dated 14 July 2003.
Confirmation, Recognition, and Enforcement of Foreign Arbitral
Award3 against respondent Philippine Kingford, Inc. (Kingford),
a corporation duly organized and existing under the laws of the Due to a series of events not mentioned in the petition, the
Philippines,4 on the ground that petitioner lacked legal capacity licensees, including respondent Kingford, withdrew from
to sue.5 petitioner TPI and correspondingly reneged on their
obligations.12 Petitioner submitted the dispute for arbitration
before the International Centre for Dispute Resolution in the
The Antecedents
State of California, United States and won the case against
respondent.13 Pertinent portions of the award read:
On 14 January 2003, Kanemitsu Yamaoka (hereinafter referred
to as the "licensor"), co-patentee of U.S. Patent No. 5,484,619,
13.1 Within thirty (30) days from the date of transmittal of this
Philippine Letters Patent No. 31138, and Indonesian Patent No.
Award to the Parties, pursuant to the terms of this award, the
ID0003911 (collectively referred to as the "Yamaoka Patent"),6
total sum to be paid by RESPONDENT KINGFORD to
and five (5) Philippine tuna processors, namely, Angel Seafood
CLAIMANT TPI, is the sum of ONE MILLION SEVEN
Corporation, East Asia Fish Co., Inc., Mommy Gina Tuna
HUNDRED FIFTY THOUSAND EIGHT HUNDRED FORTY SIX
Resources, Santa Cruz Seafoods, Inc., and respondent
DOLLARS AND TEN CENTS ($1,750,846.10).
Kingford (collectively referred to as the "sponsors"/"licensees")7
entered into a Memorandum of Agreement (MOA),8 pertinent
provisions of which read: (A) For breach of the MOA by not paying past due
assessments, RESPONDENT KINGFORD shall pay
CLAIMANT the total sum of TWO HUNDRED TWENTY NINE
1. Background and objectives. The Licensor, co-owner of
THOUSAND THREE HUNDRED AND FIFTY FIVE DOLLARS
U.S.Patent No. 5,484,619, Philippine Patent No. 31138, and
AND NINETY CENTS ($229,355.90) which is 20% of MOA
Indonesian Patent No. ID0003911 xxx wishes to form an
assessments since September 1, 2005[;]
alliance with Sponsors for purposes of enforcing his three
aforementioned patents, granting licenses under those patents,
and collecting royalties. (B) For breach of the MOA in failing to cooperate with
CLAIMANT TPI in fulfilling the objectives of the MOA,
RESPONDENT KINGFORD shall pay CLAIMANT the total
The Sponsors wish to be licensed under the aforementioned
sum of TWO HUNDRED SEVENTY ONE THOUSAND FOUR
ADR || First Batch 12
9
HUNDRED NINETY DOLLARS AND TWENTY CENTS dismissed the petition. Thus:
($271,490.20)[;]14 and
Herein plaintiff TPIs "Petition, etc." acknowledges that it "is a
(C) For violation of THE LANHAM ACT and infringement of the foreign corporation established in the State of California" and
YAMAOKA 619 PATENT, RESPONDENT KINGFORD shall "was given the exclusive right to license or sublicense the
pay CLAIMANT the total sum of ONE MILLION TWO Yamaoka Patent" and "was assigned the exclusive right to
HUNDRED FIFTY THOUSAND DOLLARS AND NO CENTS enforce the said patent and collect corresponding royalties" in
($1,250,000.00). xxx the Philippines. TPI likewise admits that it does not have a
license to do business in the Philippines.
xxx15
There is no doubt, therefore, in the mind of this Court that TPI
To enforce the award, petitioner TPI filed on 10 October 2007 a has been doing business in the Philippines, but sans a license
Petition for Confirmation, Recognition, and Enforcement of to do so issued by the concerned government agency of the
Foreign Arbitral Award before the RTC of Makati City. The Republic of the Philippines, when it collected royalties from "five
petition was raffled to Branch 150 presided by Judge Elmo M. (5) Philippine tuna processors[,] namely[,] Angel Seafood
Alameda. Corporation, East Asia Fish Co., Inc., Mommy Gina Tuna
Resources, Santa Cruz Seafoods, Inc. and respondent
Philippine Kingford, Inc." This being the real situation, TPI
At Branch 150, respondent Kingford filed a Motion to Dismiss.16
cannot be permitted to maintain or intervene in any action, suit
After the court denied the motion for lack of merit,17 respondent
or proceedings in any court or administrative agency of the
sought for the inhibition of Judge Alameda and moved for the
Philippines." A priori, the "Petition, etc." extant of the plaintiff
reconsideration of the order denying the motion.18 Judge
TPI should be dismissed for it does not have the legal
Alameda inhibited himself notwithstanding "[t]he unfounded
personality to sue in the Philippines.21
allegations and unsubstantiated assertions in the motion."19
Judge Cedrick O. Ruiz of Branch 61, to which the case was re-
raffled, in turn, granted respondents Motion for The petitioner counters, however, that it is entitled to seek for
Reconsideration and dismissed the petition on the ground that the recognition and enforcement of the subject foreign arbitral
the petitioner lacked legal capacity to sue in the Philippines.20 award in accordance with Republic Act No. 9285 (Alternative
Dispute Resolution Act of 2004),22 the Convention on the
Recognition and Enforcement of Foreign Arbitral Awards
Petitioner TPI now seeks to nullify, in this instant Petition for
drafted during the United Nations Conference on International
Review on Certiorari under Rule 45, the order of the trial court
Commercial Arbitration in 1958 (New York Convention), and the
dismissing its Petition for Confirmation, Recognition, and
UNCITRAL Model Law on International Commercial Arbitration
Enforcement of Foreign Arbitral Award.
(Model Law),23 as none of these specifically requires that the
party seeking for the enforcement should have legal capacity to
Issue sue. It anchors its argument on the following:

The core issue in this case is whether or not the court a quo In the present case, enforcement has been effectively refused
was correct in so dismissing the petition on the ground of on a ground not found in the [Alternative Dispute Resolution Act
petitioners lack of legal capacity to sue. of 2004], New York Convention, or Model Law. It is for this
reason that TPI has brought this matter before this most
Our Ruling Honorable Court, as it [i]s imperative to clarify whether the
Philippines international obligations and State policy to
The petition is impressed with merit. strengthen arbitration as a means of dispute resolution may be
defeated by misplaced technical considerations not found in the
The Corporation Code of the Philippines expressly provides: relevant laws.24

Sec. 133. Doing business without a license. - No foreign Simply put, how do we reconcile the provisions of the
corporation transacting business in the Philippines without a Corporation Code of the Philippines on one hand, and the
license, or its successors or assigns, shall be permitted to Alternative Dispute Resolution Act of 2004, the New York
maintain or intervene in any action, suit or proceeding in any Convention and the Model Law on the other?
court or administrative agency of the Philippines; but such
corporation may be sued or proceeded against before In several cases, this Court had the occasion to discuss the
Philippine courts or administrative tribunals on any valid cause nature and applicability of the Corporation Code of the
of action recognized under Philippine laws. Philippines, a general law, viz-a-viz other special laws. Thus, in
Koruga v. Arcenas, Jr.,25 this Court rejected the application of
It is pursuant to the aforequoted provision that the court a quo the Corporation Code and applied the New Central Bank Act. It
ratiocinated:
ADR || First Batch 13
0
Korugas invocation of the provisions of the Corporation Code is It also expressly adopted the Model Law, to wit:
misplaced. In an earlier case with similar antecedents, we ruled
that: Sec. 19. Adoption of the Model Law on International
Commercial Arbitration. International commercial arbitration
"The Corporation Code, however, is a general law applying to shall be governed by the Model Law on International
all types of corporations, while the New Central Bank Act Commercial Arbitration (the "Model Law") adopted by the
regulates specifically banks and other financial institutions, United Nations Commission on International Trade Law on
including the dissolution and liquidation thereof. As between a June 21, 1985 xxx."
general and special law, the latter shall prevail generalia
specialibus non derogant." (Emphasis supplied)26 Now, does a foreign corporation not licensed to do business in
the Philippines have legal capacity to sue under the provisions
Further, in the recent case of Hacienda Luisita, Incorporated v. of the Alternative Dispute Resolution Act of 2004? We answer
Presidential Agrarian Reform Council,27 this Court held: in the affirmative.

Without doubt, the Corporation Code is the general law Sec. 45 of the Alternative Dispute Resolution Act of 2004
providing for the formation, organization and regulation of provides that the opposing party in an application for
private corporations. On the other hand, RA 6657 is the special recognition and enforcement of the arbitral award may raise
law on agrarian reform. As between a general and special law, only those grounds that were enumerated under Article V of the
the latter shall prevailgeneralia specialibus non derogant.28 New York Convention, to wit:

Following the same principle, the Alternative Dispute Resolution Article V


Act of 2004 shall apply in this case as the Act, as its title - An
Act to Institutionalize the Use of an Alternative Dispute 1. Recognition and enforcement of the award may be refused,
Resolution System in the Philippines and to Establish the Office at the request of the party against whom it is invoked, only if
for Alternative Dispute Resolution, and for Other Purposes - that party furnishes to the competent authority where the
would suggest, is a law especially enacted "to actively promote recognition and enforcement is sought, proof that:
party autonomy in the resolution of disputes or the freedom of
the party to make their own arrangements to resolve their
(a) The parties to the agreement referred to in article II were,
disputes."29 It specifically provides exclusive grounds available
under the law applicable to them, under some incapacity, or the
to the party opposing an application for recognition and said agreement is not valid under the law to which the parties
enforcement of the arbitral award.30
have subjected it or, failing any indication thereon, under the
law of the country where the award was made; or
Inasmuch as the Alternative Dispute Resolution Act of 2004, a
municipal law, applies in the instant petition, we do not see the
(b) The party against whom the award is invoked was not given
need to discuss compliance with international obligations under
proper notice of the appointment of the arbitrator or of the
the New York Convention and the Model Law. After all, both
arbitration proceedings or was otherwise unable to present his
already form part of the law.
case; or

In particular, the Alternative Dispute Resolution Act of 2004


(c) The award deals with a difference not contemplated by or
incorporated the New York Convention in the Act by specifically
not falling within the terms of the submission to arbitration, or it
providing: contains decisions on matters beyond the scope of the
submission to arbitration, provided that, if the decisions on
SEC. 42. Application of the New York Convention. - The New matters submitted to arbitration can be separated from those
York Convention shall govern the recognition and enforcement not so submitted, that part of the award which contains
of arbitral awards covered by the said Convention. decisions on matters submitted to arbitration may be
recognized and enforced; or
xxx
(d) The composition of the arbitral authority or the arbitral
SEC. 45. Rejection of a Foreign Arbitral Award. - A party to a procedure was not in accordance with the agreement of the
foreign arbitration proceeding may oppose an application for parties, or, failing such agreement, was not in accordance with
recognition and enforcement of the arbitral award in the law of the country where the arbitration took place; or
accordance with the procedural rules to be promulgated by the
Supreme Court only on those grounds enumerated under (e) The award has not yet become binding on the parties, or
Article V of the New York Convention. Any other ground raised has been set aside or suspended by a competent authority of
shall be disregarded by the regional trial court. the country in which, or under the law of which, that award was
made.
ADR || First Batch 13
1
2. Recognition and enforcement of an arbitral award may also beginning, it will destroy the very essence of mutuality
be refused if the competent authority in the country where inherent in consensual contracts.38
recognition and enforcement is sought finds that:
Clearly, on the matter of capacity to sue, a foreign arbitral
(a) The subject matter of the difference is not capable of award should be respected not because it is favored over
settlement by arbitration under the law of that country; or domestic laws and procedures, but because Republic Act No.
9285 has certainly erased any conflict of law question.
(b) The recognition or enforcement of the award would be
contrary to the public policy of that country. Finally, even assuming, only for the sake of argument, that the
court a quo correctly observed that the Model Law, not the New
Clearly, not one of these exclusive grounds touched on the York Convention, governs the subject arbitral award,39
capacity to sue of the party seeking the recognition and petitioner may still seek recognition and enforcement of the
enforcement of the award. award in Philippine court, since the Model Law prescribes
substantially identical exclusive grounds for refusing recognition
or enforcement.40
Pertinent provisions of the Special Rules of Court on Alternative
Dispute Resolution,31 which was promulgated by the Supreme
Court, likewise support this position. Premises considered, petitioner TPI, although not licensed to
do business in the Philippines, may seek recognition and
enforcement of the foreign arbitral award in accordance with the
Rule 13.1 of the Special Rules provides that "[a]ny party to a
provisions of the Alternative Dispute Resolution Act of 2004.
foreign arbitration may petition the court to recognize and
enforce a foreign arbitral award." The contents of such petition
are enumerated in Rule 13.5.32 Capacity to sue is not included. II
Oppositely, in the Rule on local arbitral awards or arbitrations in
instances where "the place of arbitration is in the Philippines,"33 The remaining arguments of respondent Kingford are likewise
it is specifically required that a petition "to determine any unmeritorious.
question concerning the existence, validity and enforceability of
such arbitration agreement"34 available to the parties before the First. There is no need to consider respondents contention that
commencement of arbitration and/or a petition for "judicial relief petitioner TPI improperly raised a question of fact when it
from the ruling of the arbitral tribunal on a preliminary question posited that its act of entering into a MOA should not be
upholding or declining its jurisdiction"35 after arbitration has considered "doing business" in the Philippines for the purpose
already commenced should state "[t]he facts showing that the of determining capacity to sue. We reiterate that the foreign
persons named as petitioner or respondent have legal capacity corporations capacity to sue in the Philippines is not material
to sue or be sued."36 insofar as the recognition and enforcement of a foreign arbitral
award is concerned.
Indeed, it is in the best interest of justice that in the
enforecement of a foreign arbitral award, we deny availment by Second. Respondent cannot fault petitioner for not filing a
the losing party of the rule that bars foreign corporations not motion for reconsideration of the assailed Resolution dated 21
licensed to do business in the Philippines from maintaining a November 2008 dismissing the case. We have, time and again,
suit in our courts. When a party enters into a contract ruled that the prior filing of a motion for reconsideration is not
containing a foreign arbitration clause and, as in this case, in required in certiorari under Rule 45.41
fact submits itself to arbitration, it becomes bound by the
contract, by the arbitration and by the result of arbitration,
Third. While we agree that petitioner failed to observe the
conceding thereby the capacity of the other party to enter into
principle of hierarchy of courts, which, under ordinary
the contract, participate in the arbitration and cause the
circumstances, warrants the outright dismissal of the case,42 we
implementation of the result. Although not on all fours with the
opt to relax the rules following the pronouncement in Chua v.
instant case, also worthy to consider is the
Ang,43 to wit:

wisdom of then Associate Justice Flerida Ruth P. Romero in


[I]t must be remembered that [the principle of hierarchy of
her Dissenting Opinion in Asset Privatization Trust v. Court of
courts] generally applies to cases involving conflicting factual
Appeals,37 to wit:
allegations. Cases which depend on disputed facts for decision
cannot be brought immediately before us as we are not triers of
xxx Arbitration, as an alternative mode of settlement, is gaining facts.44 A strict application of this rule may be excused when the
adherents in legal and judicial circles here and abroad. If its reason behind the rule is not present in a case, as in the
tested mechanism can simply be ignored by an aggrieved present case, where the issues are not factual but purely legal. 1wphi1

party, one who, it must be stressed, voluntarily and actively In these types of questions, this Court has the ultimate say so
participated in the arbitration proceedings from the very that we merely abbreviate the review process if we, because of
ADR || First Batch 13
2
the unique circumstances of a case, choose to hear and decide JOSE PORTUGAL PEREZ
the legal issues outright.45
Associate Justice
Moreover, the novelty and the paramount importance of the
issue herein raised should be seriously considered.46 Surely, WE CONCUR:
there is a need to take cognizance of the case not only to guide
the bench and the bar, but if only to strengthen arbitration as a
ANTONIO T. CARPIO
means of dispute resolution, and uphold the policy of the State
embodied in the Alternative Dispute Resolution Act of 2004, to
wit: Associate Justice

Sec. 2. Declaration of Policy. - It is hereby declared the policy Chairperson


of the State to actively promote party autonomy in the
resolution of disputes or the freedom of the party to make their ARTURO D. BRION
own arrangements to resolve their disputes. Towards this end,
the State shall encourage and actively promote the use of Associate Justice
Alternative Dispute Resolution (ADR) as an important means to BIENVENIDO L. REYES
achieve speedy and impartial justice and declog court dockets.
xxx Associate Justice

Fourth. As regards the issue on the validity and enforceability of ATTESTATION


the foreign arbitral award, we leave its determination to the
court a quo where its recognition and enforcement is being
I attest that the conclusions in the above Decision were
sought.
reached in consultation before the case was assigned to the
writer of the opinion of the Courts Division.
Fifth. Respondent claims that petitioner failed to furnish the
court of origin a copy of the motion for time to file petition for
ANTONIO T. CARPIO
review on certiorari before the petition was filed with this
Court.47 We, however, find petitioners reply in order. Thus:
Associate Justice
26. Admittedly, reference to "Branch 67" in petitioner TPIs
"Motion for Time to File a Petition for Review on Certiorari Chairperson, Second Division
under Rule 45" is a typographical error. As correctly pointed out
by respondent Kingford, the order sought to be assailed CERTIFICATION
originated from Regional Trial Court, Makati City, Branch 61.
Pursuant to Section 13, Article VIII of the Constitution, and the
27. xxx Upon confirmation with the Regional Trial Court, Makati Division Chairpersons Attestation, it is hereby certified that the
City, Branch 61, a copy of petitioner TPIs motion was received conclusions in the above Decision were reached in consultation
by the Metropolitan Trial Court, Makati City, Branch 67. On 8 before the case was assigned to the writer of the opinion of the
January 2009, the motion was forwarded to the Regional Trial Courts Division.
Court, Makati City, Branch 61.48
RENATO C. CORONA
All considered, petitioner TPI, although a foreign corporation
not licensed to do business in the Philippines, is not, for that Chief Justice
reason alone, precluded from filing the Petition for
Confirmation, Recognition, and Enforcement of Foreign Arbitral
Award before a Philippine court.
Footnotes
WHEREFORE, the Resolution dated 21 November 2008 of the
Regional Trial Court, Branch 61, Makati City in Special
Proceedings No. M-6533 is hereby REVERSED and SET
1 Rollo, pp. 36-59.
ASIDE. The case is REMANDED to Branch 61 for further
proceedings. 2Id. at 65-75. Penned by Judge Cedrick O. Ruiz, Regional Trial
Court, Branch 61, Makati City.
SO ORDERED.
3 Id. at 105-113.
ADR || First Batch 13
3
4 Id. at 41. Petition for Review on Certiorari under Rule 45. 25 G.R. No. 169053, 19 June 2009, 590 SCRA 49.

5 Id. at 72-75. Resolution dated 21 November 2008 of the RTC. 26Id. at 68 citing In re: Petition for Assistance in the Liquidation
of the Rural Bank of Bokod (Benguet), Inc., Philippine Deposit
6 The Yamaoka Patent pertains to "the extra-low temperature Insurance Corporation, v. Bureau of Internal Revenue, G.R. No.
smoking process using filtered smoke on fresh tuna which 158261, 18 December 2006, 511 SCRA 123, 141 further citing
prevents the discoloration of the tuna and ensures its freshness Laureano v. Court of Appeals, 381 Phil. 403, 411-412 (2000).
during the frozen state." Id. at 41. Petition for Review on
Certiorari under Rule 45. 27 G.R. No. 171101, 5 July 2011, 653 SCRA 154.

7 Id. at 40. Petition for Review on Certiorari under Rule 45. 28 Id. at 244 citing Koruga v. Arcenas, Jr., supra note 24.

8 Id. at 76-83. 29 Sec. 2, Republic Act No. 9285.

9 Id. at 76-77. 30Secs. 42 and 45, Republic Act No. 9285, which adopted the
New York Convention; and Sec. 19, Republic Act No. 9285,
10 Id. at 84-85. which adopted the entire provisions of the Model Law.

11 Id. at 87-89.
31 A.M. No. 07-11-08-SC dated 1 September 2009.

12 Id. at 42. Petition for Review on Certiorari under Rule 45.


32 RULE 13.5. Contents of petition. The petition shall state the
following:
13Id. at 93-99. Award of Arbitrator dated 26 July 2007. Id. at
103-104. Disposition of Application for Modification of Award of a. The addresses of the parties to arbitration;
Arbitrators dated 13 September 2007.
b. In the absence of any indication in the award, the country
14Id. at 103. Pursuant to the Disposition of Application for where the arbitral award was made and whether such country
Modification of Award of Arbitrators dated 13 September 2007, is a signatory to the New York Convention; and
which modified the Award of Arbitrator dated 26 July 2007.
c. The relief sought.
15 Id. at 97-98. Award of Arbitrator dated 26 July 2007.
Apart from other submissions, the petition shall have attached
16 Id. at 184-195. to it the following:

17 Id. at 294-302. Order dated 20 May 2008. a. An authentic copy of the arbitration agreement; and

18Id. at 303-326. Motion for Inhibition with Motion for b. An authentic copy of the arbitral award.
Reconsideration dated 30 May 2008.
If the foreign arbitral award or agreement to arbitrate or
19 Id. at 337-338. Order dated 11 June 2008. submission is not made in English, the petitioner shall also
attach to the petition a translation of these documents into
English. The translation shall be certified by an official or sworn
20 Id. at 65-75. Resolution dated 21 November 2008.
translator or by a diplomatic or consular agent. A.M. No. 07-11-
08-SC dated 1 September 2009.
21 Id. at 72-73. Resolution dated 21 November 2008.
33 Rule 3.1, A.M. No. 07-11-08-SC dated 1 September 2009.
22 Republic Act No. 9285 approved on 2 April 2004.
34 Rule 3.2, A.M. No. 07-11-08-SC dated 1 September 2009.
23 As adopted by the United Nations Commission on
International Trade Law on 21 June 1985, and as amended by 35 Rule 3.12, A.M. No. 07-11-08-SC dated 1 September 2009.
the United Nations Commission on International Trade Law on
7 July 2006.
36In relation to a petition "to determine any question concerning
the existence, validity and enforceability of such arbitration
24 Rollo, p. 38. Petition for Review on Certiorari under Rule 45.
agreement" available to the parties before the commencement
ADR || First Batch 13
4
of arbitration, Rule 3.6 provides: is a Commercial Arbitration Tribunal and hence, it is
engaged in commercial arbitration. Under the third sentence of
RULE 3.6. Contents of petition. The verified petition shall Section 40 of Republic Act No. 9285, [t]he recognition and
state the following: enforcement of an award in an international commercial
arbitration shall be governed by Article 35 of the Model Law [the
Model Law on International Commercial Arbitration adopted by
a. The facts showing that the persons named as petitioner or
the United Nations Commission on International Trade Law on
respondent have legal capacity to sue or be sued;
21 June 1985] and not the so-called New York Convention.
Rollo, p. 74.
b. The nature and substance of the dispute between the
parties; 40 Article 36 of the Model Law provides:
c. The grounds and the circumstances relied upon by the
Article 36. Grounds for refusing recognition or enforcement
petitioner to establish his position; and

(1) Recognition or enforcement of an arbitral award,


d. The relief/s sought.
irrespective of the country in which it was made, may be
refused only:
Apart from other submissions, the petitioner must attach to the
petition an authentic copy of the arbitration agreement.
(a) at the request of the party against whom it is invoked, if that
party furnishes to the competent court where recognition or
In relation to a petition for "judicial relief from the ruling of the enforcement is sought proof that:
arbitral tribunal on a preliminary question upholding or declining
its jurisdiction" after arbitration has already commenced, Rule
(i) a party to the arbitration agreement referred to in article 7
3.16 reads:
was under some incapacity; or the said agreement is not valid
under the law to which the parties have subjected it or, failing
RULE 3.16. Contents of petition. The petition shall state the any indication thereon, under the law of the country where the
following: award was made; or

a. The facts showing that the person named as petitioner or (ii) the party against whom the award is invoked was not given
respondent has legal capacity to sue or be sued; proper notice of the appointment of an arbitrator or of the
arbitral proceedings or was otherwise unable to present his
b. The nature and substance of the dispute between the case; or
parties;
(iii) the award deals with a dispute not contemplated by or not
c. The grounds and circumstances relied upon by the petitioner; falling within the terms of the submission to arbitration, or it
and contains decisions on matters beyond the scope of the
submission to arbitration, provided that, if the decisions on
d. The relief/s sought. matters submitted to arbitration can be separated from those
not so submitted, that part of the award which contains
In addition to the submissions, the petitioner shall attach to the decisions on matters submitted to arbitration may be
petition a copy of the request for arbitration and the ruling of the recognized and enforced; or
arbitral tribunal.
(iv) the composition of the arbitral tribunal or the arbitral
The arbitrators shall be impleaded as nominal parties to the procedure was not in accordance with the agreeement of the
case and shall be notified of the progress of the case. parties or, failing such agreement, was not in accordance with
the law of the country where the arbitration took place; or
37 G.R. No. 121171, 29 December 1998, 300 SCRA 579
(v) the award has not yet become binding on the parties or has
been set aside or suspended by a court of the country in which,
38 Id. at 631.
or under the law of which, that award was made; or
39In its Resolution dated 21 November 2008, the court a quo
(b) if the court finds that:
observed: "This reliance by TPI solely upon the New York
Convention in conjunction with Section 42 of Republic Act No.
9285 may not be correct. It is apparent from the Award of (i) the subject-matter of the dispute is not capable of settlement
Arbitrator that the International Centre [f]or Dispute Resolution by arbitration under the law of this State; or
ADR || First Batch 13
5
(ii) the recognition or enforcement of the award would be Republic of the Philippines
contrary to the public policy of this State. SUPREME COURT
Manila
(2) xxx SECOND DIVISION

41San Miguel Corporation v. Layoc, Jr., G.R. No. 149640, 19 G.R. No. 179628 January 16, 2013
October, 2007, 537 SCRA 77, 91; Bases Conversion and
Development Authority v. Uy, G.R. No. 144062, 2 November THE MANILA INSURANCE COMPANY, INC., Petitioner,
2006, 506 SCRA 524, 534; and Paa v. CA, G.R. No. 126560, 4
December 1997, 282 SCRA 448. vs.

42Catly v. Navarro, G.R. No. 167239, 5 May 2010, 620 SCRA SPOUSES ROBERTO and AIDA AMURAO, Respondents.
151, 193.
DECISION
43 G.R. No. 156164, 4 September 2009, 598 SCRA 229.
DEL CASTILLO, J.:
44Id. at 238 citing Mangaliag v. Catubig-Pastoral, G.R. No.
143951, 25 October 2005, 474 SCRA 153,161; Agan, Jr. v.
The jurisdiction of the Construction Industry Arbitration
Philippine International Air Terminals Co., Inc., G.R. Nos.
Commission (CIAC) is conferred by law. Section 41 of Executive
155001, 155547 and 155661, 21 January 2004, 420 SCRA Order (E.O.) No. I 008, otherwise known as the Construction
575, 584.
Industry Arbitration Law, "is broad enough to cover any dispute
arising from, or connected with construction contracts, whether
45 Id. these involve mere contractual money claims or execution of
the works."2
46La Bugal-B'laan Tribal Association, Inc. v. Ramos, G.R. No.
127882, 27 January 2004, 421 SCRA 148, 183. This Petition for Review on Certiorari3 under Rule 45 of the
Rules of Court assails the Decision4 dated June 7, 2007 and
47 Rollo, pp. 427-428. Comment/Opposition on the petition the Resolution5 dated September 7, 2007 of the Court of
dated 1 April 2009. Appeals (CA) in CA-G.R. SP No. 96815.

48Id. at 459. Reply to "COMMENT/OPPOSITION (Re: Petitoner Factual Antecedents


Tuna Processing, Inc.s Petition for Review on Certiorari Under
Rule 45 dated January 23, 2009)" dated 1 April 2009. On March 7, 2000, respondent-spouses Roberto and Aida
Amurao entered into a Construction Contract Agreement
(CCA)6 with Aegean Construction and Development
Corporation (Aegean) for the construction of a six-storey
commercial building in Tomas Morato corner E. Rodriguez
Avenue, Quezon City.7 To guarantee its full and faithful
compliance with the terms and conditions of the CCA, Aegean
posted performance bonds secured by petitioner The Manila
Insurance Company, Inc.8 (petitioner) and Intra Strata
Assurance Corporation (Intra Strata).9

On November 15, 2001, due to the failure of Aegean to


complete the project, respondent spouses filed with the
Regional Trial Court (RTC) of Quezon City, Branch 217, a
Complaint,10 docketed as Civil Case No. Q-01-45573, against
petitioner and Intra Strata to collect on the performance bonds
they issued in the amounts of P2,760,000.00 and
P4,440,000.00, respectively.11

Intra Strata, for its part, filed an Answer12 and later, a Motion to
Admit Third Party Complaint,13 with attached Third Party
Complaint14 against Aegean, Ronald D. Nicdao, and Arnel A.
Mariano.
ADR || First Batch 13
6
Petitioner, on the other hand, filed a Motion to Dismiss15 on the Petitioner moved for reconsideration but the CA denied
grounds that the Complaint states no cause of action16 and that the same in a Resolution33 dated September 7, 2007.
the filing of the Complaint is premature due to the failure of
respondent-spouses to implead the principal contractor, Issues
Aegean.17 The RTC, however, denied the motion in an Order18
dated May 8, 2002. Thus, petitioner filed an Answer with
Hence, this petition raising the following issues:
Counterclaim and Cross-claim,19 followed by a Third Party
Complaint20 against Aegean and spouses Ronald and Susana
Nicdao. A.

During the pre-trial, petitioner and Intra Strata discovered that THE HONORABLE CA ERRED WHEN IT HELD THAT IT IS
the CCA entered into by respondent-spouses and Aegean ONLY WHEN THERE ARE DIFFERENCES IN THE
contained an arbitration clause.21 INTERPRETATION OF ARTICLE I OF THE CONSTRUCTION
AGREEMENT THAT THE PARTIES MAY RESORT TO
ARBITRATION BY THE CIAC.
Hence, they filed separate Motions to Dismiss22 on the grounds
of lack of cause of action and lack of jurisdiction.
B.
Ruling of the Regional Trial Court
THE HONORABLE CA ERRED IN TREATING PETITIONER
AS A SOLIDARY DEBTOR INSTEAD OF A SOLIDARY
On May 5, 2006, the RTC denied both motions.23 Petitioner and
GUARANTOR.
Intra Strata separately moved for reconsideration but their
motions were denied by the RTC in its subsequent Order 24
dated September 11, 2006. C.

Aggrieved, petitioner elevated the case to the CA by way of THE HONORABLE [CA] OVERLOOKED AND FAILED TO
special civil action for certiorari.25 CONSIDER THE FACT THAT THERE WAS NO ACTUAL AND
EXISTING CONSTRUCTION AGREEMENT AT THE TIME
THE MANILA INSURANCE BOND NO. G (13) 2082 WAS
Ruling of the Court of Appeals
ISSUED ON FEBRUARY 29, 2000.34

On June 7, 2007, the CA rendered a Decision26 dismissing the


Petitioners Arguments
petition. The CA ruled that the presence of an arbitration clause
in the CCA does not merit a dismissal of the case because
under the CCA, it is only when there are differences in the Petitioner contends that the CA erred in ruling that the parties
interpretation of Article I of the construction agreement that the may resort to arbitration only when there is difference in the
parties can resort to arbitration.27 The CA also found no grave interpretation of the contract documents stated in Article I of the
abuse of discretion on the part of the RTC when it disregarded CCA.35 Petitioner insists that under Section 4 of E.O. No. 1008,
the fact that the CCA was not yet signed at the time petitioner it is the CIAC that has original and exclusive jurisdiction over
issued the performance bond on February 29, 2000.28 The CA construction disputes, such as the instant case.36
explained that the performance bond was intended to be
coterminous with the construction of the building.29 It pointed Petitioner likewise imputes error on the part of the CA in
out that "if the delivery of the original contract is treating petitioner as a solidary debtor instead of a solidary
contemporaneous with the delivery of the suretys obligation, guarantor.37 Petitioner argues that while a surety is bound
each contract becomes completed at the same time, and the solidarily with the obligor, this does not make the surety a
consideration which supports the principal contract likewise solidary co-debtor.38 A surety or guarantor is liable only if the
supports the subsidiary one."30 The CA likewise said that, debtor is himself liable.39 In this case, since respondent-
although the contract of surety is only an accessory to the spouses and Aegean agreed to submit any dispute for
principal contract, the suretys liability is direct, primary and arbitration before the CIAC, it is imperative that the dispute
absolute.31 Thus: between respondent-spouses and Aegean must first be
referred to arbitration in order to establish the liability of
WHEREFORE, we resolve to DISMISS the petition as we find Aegean.40 In other words, unless the liability of Aegean is
that no grave abuse of discretion attended the issuance of the determined, the filing of the instant case is premature.41
order of the public respondent denying the petitioners motion
to dismiss. Finally, petitioner puts in issue the fact that the performance
bond was issued prior to the execution of the CCA.42 Petitioner
IT IS SO ORDERED.32 claims that since there was no existing contract at the time the
performance bond was executed, respondent-spouses have no
ADR || First Batch 13
7
cause of action against petitioner.43 Thus, the complaint should A careful reading of the Performance Bond reveals that
be dismissed.44 the "bond is coterminous with the final acceptance of the
project."53 Thus, the fact that it was issued prior to the execution
Respondent spouses Arguments of the CCA does not affect its validity or effectivity.

Respondent-spouses, on the other hand, maintain that the But while there is a cause of action against petitioner, the
CIAC has no jurisdiction over the case because there is no complaint must still be dismissed for lack of jurisdiction.
ambiguity in the provisions of the CCA.45 Besides, petitioner is
not a party to the CCA.46 Hence, it cannot invoke Article XVII of The CIAC has jurisdiction over the case
the CCA, which provides for arbitration proceedings.47
Respondent-spouses also insist that petitioner as a surety is Section 4 of E.O. No. 1008 provides that:
directly and equally bound with the principal.48 The fact that the
performance bond was issued prior to the execution of the CCA
SEC. 4. Jurisdiction. The CIAC shall have original and
also does not affect the latters validity because the
exclusive jurisdiction over disputes arising from, or connected
performance bond is coterminous with the construction of the
with, contracts entered into by parties involved in construction
building.49
in the Philippines, whether the dispute arises before or after the
completion of the contract, or after the abandonment or breach
Our Ruling thereof. These disputes may involve government or private
contracts. For the Board to acquire jurisdiction, the parties to a
The petition has merit. dispute must agree to submit the same to voluntary arbitration.

Nature of the liability of the surety The jurisdiction of the CIAC may include but is not limited to
violation of specifications for materials and workmanship,
A contract of suretyship is defined as "an agreement whereby a violation of the terms of agreement, interpretation and/or
party, called the surety, guarantees the performance by another application of contractual time and delays, maintenance and
party, called the principal or obligor, of an obligation or defects, payment, default of employer or contractor, and
undertaking in favor of a third party, called the obligee. It changes in contract cost.
includes official recognizances, stipulations, bonds or
undertakings issued by any company by virtue of and under the Excluded from the coverage of the law are disputes arising from
provisions of Act No. 536, as amended by Act No. 2206."50 We employer-employee relationships which shall continue to be
have consistently held that a suretys liability is joint and covered by the Labor Code of the Philippines.
several, limited to the amount of the bond, and determined
strictly by the terms of contract of suretyship in relation to the Based on the foregoing, in order for the CIAC to acquire
principal contract between the obligor and the obligee.51 It jurisdiction two requisites must concur: "first, the dispute must
bears stressing, however, that although the contract of be somehow connected to a construction contract; and second,
suretyship is secondary to the principal contract, the suretys the parties must have agreed to submit the dispute to
liability to the obligee is nevertheless direct, primary, and arbitration proceedings."54
absolute.52
In this case, both requisites are present.
In this case, respondent-spouses (obligee) filed with the RTC a
Complaint against petitioner (surety) to collect on the
The parties agreed to submit to arbitration proceedings "any
performance bond it issued. Petitioner, however, seeks the
dispute arising in the course of the execution and performance
dismissal of the Complaint on the grounds of lack of cause of
of the CCA by reason of difference in interpretation of the
action and lack of jurisdiction.
Contract Documents x x x which the parties are unable to
resolve amicably between themselves."55 Article XVII of the
The respondent-spouses have cause of action against the CCA reads:
petitioner; the performance bond is coterminous with the CCA
ARTICLE XVII ARBITRATION
Petitioner claims that respondent-spouses have no cause of
action against it because at the time it issued the performance
17.1 Any dispute arising in the course of the execution and
bond, the CCA was not yet signed by respondent-spouses and
performance of this Agreement by reason of difference in
Aegean.
interpretation of the Contract Documents set forth in Article I
which the OWNER and the CONTRACTOR are unable to
We do not agree. resolve amicably between themselves shall be submitted by
either party to a board of arbitrators composed of Three (3)
ADR || First Batch 13
8
members chosen as follows: One (1) member shall be chosen jurisdiction.
by the CONTRACTOR AND One (1) member shall be chosen
by the OWNER. The said Two (2) members, in turn, shall select SO ORDERED.
a third member acceptable to both of them. The decision of the
Board of Arbitrators shall be rendered within Ten (10) days from
MARIANO C. DEL CASTILLO
the first meeting of the board, which decision when reached
through the affirmative vote of at least Two (2) members of the
board shall be final and binding upon the OWNER and Associate Justice
CONTRACTOR. 1wphi1

WE CONCUR:
17.2 Matters not otherwise provided for in this Contract or by
Special Agreement of the parties shall be governed by the ANTONIO T. CARPIO
provisions of the Arbitration Law, Executive Order No. 1008.56
Associate Justice
In William Golangco Construction Corporation v. Ray Burton
Development Corporation,57 we declared that monetary claims Chairperson
under a construction contract are disputes arising from
"differences in interpretation of the contract" because "the TERESITA J. LEONARDO-DE CASTRO*
matter of ascertaining the duties and obligations of the parties
under their contract all involve interpretation of the provisions of
Associate Justice
the contract."58 Following our reasoning in that case, we find
MARVIC MARIO VICTOR F. LEONEN**
that the issue of whether respondent-spouses are entitled to
collect on the performance bond issued by petitioner is a
"dispute arising in the course of the execution and performance Associate Justice
of the CCA by reason of difference in the interpretation of the
contract documents." ATTESTATION

The fact that petitioner is not a party to the CCA cannot remove I attest that the conclusions in the above Decision had been
the dispute from the jurisdiction of the CIAC because the issue reached in consultation before the case was assigned to the
of whether respondent-spouses are entitled to collect on the writer of the opinion of the Court's Division.
performance bond, as we have said, is a dispute arising from or
connected to the CCA. ANTONIO T. CARPIO

In fact, in Prudential Guarantee and Assurance, Inc. v. Anscor Associate Justice


Land, Inc.,59 we rejected the argument that the jurisdiction of
CIAC is limited to the construction industry, and thus, cannot Chairperson
extend to surety contracts. In that case, we declared that
"although not the construction contract itself, the performance
bond is deemed as an associate of the main construction CERTIFICATION
contract that it cannot be separated or severed from its
principal. The Performance Bond is significantly and Pursuant to Section 13, Article VIII of the Constitution and the
substantially connected to the construction contract that there Division Chairperson's Attestation, I certify that the conclusions
can be no doubt it is the CIAC, under Section 4 of E.O. No. in the above Decision had been reached in consultation before
1008, which has jurisdiction over any dispute arising from or the case was assigned to the writer of the opinion of the Court's
connected with it."60 Division.

In view of the foregoing, we agree with the petitioner that MARIA LOURDES P. A. SERENO
juriisdiction over the instant case lies with the CIAC, and not
with the RTC. Thus, the Complaint filed by respondent-spouses Chief Justice
with the RTC must be dismissed.

WHEREFORE, the petition is hereby GRANTED. The Decision


dated June 7, 2007 and the Resolution dated September 7, Footnotes
2007 of the Court of Appeals in CA-G.R. SP No. 96815 are
hereby ANNULLED and SET ASIDE. The Presiding Judge of * Per raffle dated January 14.2013.
the Regional Trial Court of Quezon City, Branch 217 1s
DIRECTED to dismiss Civil Case No. Q-01-45573 for lack of
ADR || First Batch 13
9
** Per Special Order No. 1408 dated January 15, 2013. 16 Id. at 26.

1 SEC. 4. Jurisdiction. -The ClAC shall have original and 17 Id. at 27.
exclusive jurisdiction over disputes arising from. or connected
with. contracts entered into by parties involved in construction 18 Id. at 49-50; penned by Judge Lydia Querubin Layosa.
in the Philippines. whether the dispute arises before or after the
completion of the contract, or after the abandonment or breach 19 Rollo, pp. 88-94.
thereof. These disputes may involve government or private
contracts. For the Board to acquire jurisdiction. the parties to a
dispute must agree to submit the same to voluntary arbitration.
20 Id. at 97-100.

The jurisdiction of the ClAC may include but is not limited to


21 Id. at 40.
violation of specifications for materials and workmanship.
violation of the terms of agreement, interpretation and/or 22 Id. at 117-124 and 110-116.
application of contractual time and delays. maintenance and
defects. payment. default of employer or contractor, and 23 Records, Volume II, pp. 544-546.
changes in contract cost.
24 Id. at 589.
Excluded from the coverage of this law are disputes arising
from employer-employee relationships which shall continue to 25 CA rollo, pp. 2-22.
be covered by the Labor Code of the Philippines.
26 Rollo, pp. 39-47.
2LICOMCEN, lncorporated v. Foundation Specialists, Inc., G.R.
Nos. 167022 and 169678. April 4, 2011, 647 SCRA 83, 91. 27 Id. at 42-44.
3 Rollo, pp. 13-37. 28 Id. at 45-46.
4 Id. at 39-47; penned by Associate Justice Apolinario D. 29 Id. at 46.
Bruselas, Jr. and concurred in by Associate Justices
Bienvenido L. Reyes (now a member of this Court) and Aurora
Santiago-Lagman.
30 Id.

5 Id. at 49.
31 Id. at 45.

6 Id. at 72-85.
32 Id. at 46-47.

7 Id. at 39-40.
33 Id. at 49.

8 Id. at 68-69.
34 Id. at 168-169.

9 Id. at 70-71.
35 Id. at 169.

10 Id. at 63-67.
36 Id. at 171.

11 Id. at 66.
37 Id. at 174.

12 Records, Volume I, pp. 29-32.


38 Id. at 175.

13 Id. at 38-39.
39 Id.

14 Id. at 40-42.
40 Id. at 180.

15 Id. at 26-28.
41 Id. at 182.
ADR || First Batch 14
0
42 Id. at 183. Republic of the Philippines
SUPREME COURT
43 Id. at 185. Manila
FIRST DIVISION
44 Id. at 186.
G.R. No. 199650 June 26, 2013
45 Id. at 192-193.
J PLUS ASIA DEVELOPMENT CORPORATION, Petitioner,
46 Id. at 193.
vs.
47 Id.
UTILITY ASSURANCE CORPORATION, Respondent.
48 Id. at 195.
DECISION
49 Id. at 196.
VILLARAMA, JR., J.:
50 INSURANCE CODE, Section 175.
Before the Court is a petition for review on certiorari under Rule
45 of the 1997 Rules of Civil Procedure, as amended, assailing
51Intra-Strata Assurance Corporation v. Republic, G.R. No.
the Decision1 dated January 27,2011 and Resolution2 dated
156571, July 9, 2008, 557 SCRA 363, 369.
December 8, 2011 of the Court of Appeals (CA) in CA-G.R. SP
No. 112808.
52Prudential Guarantee and Assurance, Inc. v. Equinox Land
Corporation, G.R. Nos. 152505-06, September 13, 2007, 533
The Facts
SCRA 257, 268.

On December 24, 2007, petitioner J Plus Asia Development


53 Rollo, p. 86.
Corporation represented by its Chairman, Joo Han Lee, and
Martin E. Mabunay, doing business under the name and style
54 Prudential Guarantee and Assurance, Inc. v. Anscor Land, of Seven Shades of Blue Trading and Services, entered into a
Inc., G.R. No. 177240, September 8, 2010, 630 SCRA 368, Construction Agreement3 whereby the latter undertook to build
376. the former's 72-room condominium/hotel (Condotel Building 25)
located at the Fairways & Bluewaters Golf & Resort in Boracay
55 Rollo, p. 83. Island, Malay, Aklan. The project, costing P42,000,000.00, was
to be completed within one year or 365 days reckoned from the
56 Id. first calendar day after signing of the Notice of Award and
Notice to Proceed and receipt of down payment (20% of
57 G.R. No. 163582, August 9, 2010, 627 SCRA 74. contract price). The P8,400,000.00 down payment was fully
paid on January 14, 2008.4 Payment of the balance of the
contract price will be based on actual work finished within 15
58 Id. at 85.
days from receipt of the monthly progress billings. Per the
agreed work schedule, the completion date of the project was
59 Supra note 54 at 373-379. December 2008.5 Mabuhay also submitted the required
Performance Bond6 issued by respondent Utility Assurance
60 Id. at 377. Corporation (UTASSCO) in the amount equivalent to 20% down
payment or P8.4 million.

Mabunay commenced work at the project site on January 7,


2008. Petitioner paid up to the 7th monthly progress billing sent
by Mabunay. As of September 16, 2008, petitioner had paid the
total amount of P15,979,472.03 inclusive of the 20% down
payment. However, as of said date, Mabunay had
accomplished only 27.5% of the project.7

In the Joint Construction Evaluation Result and Status Report8


signed by Mabunay assisted by Arch. Elwin Olavario, and Joo
ADR || First Batch 14
1
Han Lee assisted by Roy V. Movido, the following findings were In its Answer Ex Abundante Ad Cautelam With
accepted as true, accurate and correct: Compulsory Counterclaims and Cross-claims,14 respondent
argued that the performance bond merely guaranteed the 20%
III STATUS OF PROJECT AS OF 14 NOVEMBER 2008 down payment and not the entire obligation of Mabunay under
the Construction Agreement. Since the value of the projects
accomplishment already exceeded the said amount,
1) After conducting a joint inspection and evaluation of the
respondents obligation under the performance bond had been
project to determine the actual percentage of accomplishment,
fully extinguished. As to the claim for alleged overpayment to
the contracting parties, assisted by their respective technical
Mabunay, respondent contended that it should not be credited
groups, SSB assisted by Arch. Elwin Olavario and JPLUS
against the 20% down payment which was already exhausted
assisted by Engrs. Joey Rojas and Shiela Botardo, concluded
and such application by petitioner is tantamount to reviving an
and agreed that as of 14 November 2008, the project is only
obligation that had been legally extinguished by payment.
Thirty One point Thirty Nine Percent (31.39%) complete.
Respondent also set up a cross-claim against Mabunay who
executed in its favor an Indemnity Agreement whereby
2) Furthermore, the value of construction materials allocated for Mabunay undertook to indemnify respondent for whatever
the completion of the project and currently on site has been amounts it may be adjudged liable to pay petitioner under the
determined and agreed to be ONE MILLION FORTY NINE surety bond.
THOUSAND THREE HUNDRED SIXTY FOUR PESOS AND
FORTY FIVE CENTAVOS (P1,049,364.45)
Both petitioner and respondent submitted their respective
documentary and testimonial evidence. Mabunay failed to
3) The additional accomplishment of SSB, reflected in its appear in the scheduled hearings and to present his evidence
reconciled and consolidated 8th and 9th billings, is Three point despite due notice to his counsel of record. The CIAC thus
Eighty Five Percent (3.85%) with a gross value of declared that Mabunay is deemed to have waived his right to
P1,563,553.34 amount creditable to SSB after deducting the present evidence.15
withholding tax is P1,538,424.84
On February 2, 2010, the CIAC rendered its Decision16 and
4) The unrecouped amount of the down payment is made the following award:
P2,379,441.53 after deducting the cost of materials on site and
the net billable amount reflected in the reconciled and
Accordingly, in view of our foregoing discussions and
consolidated 8th and 9th billings. The uncompleted portion of
dispositions, the Tribunal hereby adjudges, orders and directs:
the project is 68.61% with an estimated value per construction
agreement signed is P27,880,419.52.9 (Emphasis supplied.)
1. Respondents Mabunay and Utassco to jointly and severally
pay claimant the following:
On November 19, 2008, petitioner terminated the contract and
sent demand letters to Mabunay and respondent surety. As its
demands went unheeded, petitioner filed a Request for a) P4,469,969.90, as liquidated damages, plus legal interest
Arbitration10 before the Construction Industry Arbitration thereon at the rate of 6% per annum computed from the date of
Commission (CIAC). Petitioner prayed that Mabunay and this decision up to the time this decision becomes final, and
respondent be ordered to pay the sums of P8,980,575.89 as 12% per annum computed from the date this decision becomes
liquidated damages and P2,379,441.53 corresponding to the final until fully paid, and
unrecouped down payment or overpayment petitioner made to
Mabunay.11 b) P2,379,441.53 as unrecouped down payment plus interest
thereon at the rate of 6% per annum computed from the date of
In his Answer,12 Mabunay claimed that the delay was caused by this decision up to the time this decision becomes final, and
retrofitting and other revision works ordered by Joo Han Lee. 12% per annum computed from the date this decision becomes
He asserted that he actually had until April 30, 2009 to finish final until fully paid.
the project since the 365 days period of completion started only
on May 2, 2008 after clearing the retrofitted old structure. It being understood that respondent Utasscos liability shall in
Hence, the termination of the contract by petitioner was no case exceed P8.4 million.
premature and the filing of the complaint against him was
baseless, malicious and in bad faith. 2. Respondent Mabunay to pay to claimant the amount of
P98,435.89, which is respondent Mabunays share in the
Respondent, on the other hand, filed a motion to dismiss on the arbitration cost claimant had advanced, with legal interest
ground that petitioner has no cause of action and the complaint thereon from January 8, 2010 until fully paid.
states no cause of action against it. The CIAC denied the
motion to dismiss. Respondents motion for reconsideration 3. Respondent Mabunay to indemnify respondent Utassco of
was likewise denied.13 the amounts respondent Utassco will have paid to claimant
ADR || First Batch 14
2
under this decision, plus interest thereon at the rate of 12% per Before this Court petitioner seeks to reverse the CA
annum computed from the date he is notified of such payment insofar as it denied petitioners claims under the Performance
made by respondent Utassco to claimant until fully paid, and to Bond and to reinstate in its entirety the February 2, 2010 CIAC
pay Utassco P100,000.00 as attorneys fees. Decision. Specifically, petitioner alleged that

SO ORDERED.17 A. THE COURT OF APPEALS SERIOUSLY ERRED IN NOT


HOLDING THAT THE ALTERNATIVE DISPUTE RESOLUTION
Dissatisfied, respondent filed in the CA a petition for review ACT AND THE SPECIAL RULES ON ALTERNATIVE
under Rule 43 of the 1997 Rules of Civil Procedure, as DISPUTE RESOLUTION HAVE STRIPPED THE COURT OF
amended. APPEALS OF JURISDICTION TO REVIEW ARBITRAL
AWARDS.
In the assailed decision, the CA agreed with the CIAC that the
specific condition in the Performance Bond did not clearly state B. THE COURT OF APPEALS SERIOUSLY ERRED IN
the limitation of the suretys liability. Pursuant to Article 137718 REVERSING THE ARBITRAL AWARD ON AN ISSUE THAT
of the Civil Code, the CA said that the provision should be WAS NOT RAISED IN THE ANSWER. NOT IDENTIFIED IN
construed in favor of petitioner considering that the obscurely THE TERMS OF REFERENCE, NOT ASSIGNED AS
phrased provision was drawn up by respondent and Mabunay. ANERROR, AND NOT ARGUED IN ANY OF THE PLEADINGS
Further, the appellate court stated that respondent could not FILED BEFORE THE COURT.
possibly guarantee the down payment because it is not
Mabunay who owed the down payment to petitioner but the C. THE COURT OF APPEALS SERIOUSLY ERRED IN
other way around. Consequently, the completion by Mabunay RELYING ON THE CASE OF AEROSPACE CHEMICAL
of 31.39% of the construction would not lead to the INDUSTRIES, INC. v. COURT OF APPEALS, 315 SCRA 94,
extinguishment of respondents liability. The P8.4 million was a WHICH HAS NOTHING TO DO WITH CONSTRUCTION
limit on the amount of respondents liability and not a limitation AGREEMENTS.21
as to the obligation or undertaking it guaranteed.
Our Ruling
However, the CA reversed the CIACs ruling that Mabunay had
incurred delay which entitled petitioner to the stipulated On the procedural issues raised, we find no merit in petitioners
liquidated damages and unrecouped down payment. Citing contention that with the institutionalization of alternative dispute
Aerospace Chemical Industries, Inc. v. Court of Appeals,19 the resolution under Republic Act (R.A.) No. 9285,22 otherwise
appellate court said that not all requisites in order to consider known as the Alternative Dispute Resolution Act of 2004, the
the obligor or debtor in default were present in this case. It held CA was divested of jurisdiction to review the decisions or
that it is only from December 24, 2008 (completion date) that awards of the CIAC. Petitioner erroneously relied on the
we should reckon default because the Construction Agreement provision in said law allowing any party to a domestic arbitration
provided only for delay in the completion of the project and not to file in the Regional Trial Court (RTC) a petition either to
delay on a monthly basis using the work schedule approved by confirm, correct or vacate a domestic arbitral award.
petitioner as the reference point. Hence, petitioners termination
of the contract was premature since the delay in this case was
We hold that R.A. No. 9285 did not confer on regional trial
merely speculative; the obligation was not yet demandable.
courts jurisdiction to review awards or decisions of the CIAC in
construction disputes. On the contrary, Section 40 thereof
The dispositive portion of the CA Decision reads: expressly declares that confirmation by the RTC is not required,
thus:
WHEREFORE, premises considered, the instant petition for
review is GRANTED. The assailed Decision dated 13 January SEC. 40. Confirmation of Award. The confirmation of a
2010 rendered by the CIAC Arbitral Tribunal in CIAC Case No. domestic arbitral award shall be governed by Section 23 of R.A.
03-2009 is hereby REVERSED and SET ASIDE. Accordingly, 876.
the Writ of Execution dated 24 November 2010 issued by the
same tribunal is hereby ANNULLED and SET ASIDE.
A domestic arbitral award when confirmed shall be enforced in
the same manner as final and executory decisions of the
SO ORDERED.20 Regional Trial Court.

Petitioner moved for reconsideration of the CA decision while The confirmation of a domestic award shall be made by the
respondent filed a motion for partial reconsideration. Both regional trial court in accordance with the Rules of Procedure to
motions were denied. be promulgated by the Supreme Court.

The Issues A CIAC arbitral award need not be confirmed by the regional
ADR || First Batch 14
3
trial court to be executory as provided under E.O. No. 1008. fulfillment of the prestation by reason of a cause
(Emphasis supplied.) imputable to the former. It is the non-fulfillment of an obligation
with respect to time.27
Executive Order (EO) No. 1008 vests upon the CIAC original
and exclusive jurisdiction over disputes arising from, or Article 1169 of the Civil Code provides:
connected with, contracts entered into by parties involved in
construction in the Philippines, whether the dispute arises ART. 1169. Those obliged to deliver or to do something incur in
before or after the completion of the contract, or after the delay from the time the obligee judicially or extrajudicially
abandonment or breach thereof. By express provision of demands from them the fulfillment of their obligation.
Section 19 thereof, the arbitral award of the CIAC is final and
unappealable, except on questions of law, which are
xxxx
appealable to the Supreme Court. With the amendments
introduced by R.A. No. 7902 and promulgation of the 1997
Rules of Civil Procedure, as amended, the CIAC was included It is a general rule that one who contracts to complete certain
in the enumeration of quasijudicial agencies whose decisions or work within a certain time is liable for the damage for not
awards may be appealed to the CA in a petition for review completing it within such time, unless the delay is excused or
under Rule 43. Such review of the CIAC award may involve waived.28
either questions of fact, of law, or of fact and law.23
The Construction Agreement provides in Article 10 thereof the
Petitioner misread the provisions of A.M. No. 07-11-08-SC following conditions as to completion time for the project
(Special ADR Rules) promulgated by this Court and which took
effect on October 30, 2009. Since R.A. No. 9285 explicitly 1. The CONTRACTOR shall complete the works called for
excluded CIAC awards from domestic arbitration awards that under this Agreement within ONE (1) YEAR or 365 Days
need to be confirmed to be executory, said awards are reckoned from the 1st calendar day after signing of the Notice
therefore not covered by Rule 11 of the Special ADR Rules,24 of Award and Notice to Proceed and receipt of down payment.
as they continue to be governed by EO No. 1008, as amended
and the rules of procedure of the CIAC. The CIAC Revised 2. In this regard the CONTRACTOR shall submit a detailed
Rules of Procedure Governing Construction Arbitration25 work schedule for approval by OWNER within Seven (7) days
provide for the manner and mode of appeal from CIAC after signing of this Agreement and full payment of 20% of the
decisions or awards in Section 18 thereof, which reads: agreed contract price. Said detailed work schedule shall follow
the general schedule of activities and shall serve as basis for
SECTION 18.2 Petition for review. A petition for review from a the evaluation of the progress of work by CONTRACTOR.29
final award may be taken by any of the parties within fifteen
(15) days from receipt thereof in accordance with the provisions In this jurisdiction, the following requisites must be present in
of Rule 43 of the Rules of Court. order that the debtor may be in default: (1) that the obligation
be demandable and already liquidated; (2) that the debtor
As to the alleged error committed by the CA in deciding the delays performance; and (3) that the creditor requires the
case upon an issue not raised or litigated before the CIAC, this performance judicially or extrajudicially.30
assertion has no basis. Whether or not Mabunay had incurred
delay in the performance of his obligations under the In holding that Mabunay has not at all incurred delay, the CA
Construction Agreement was the very first issue stipulated in pointed out that the obligation to perform or complete the
the Terms of Reference26 (TOR), which is distinct from the project was not yet demandable as of November 19, 2008
issue of the extent of respondents liability under the when petitioner terminated the contract, because the agreed
Performance Bond. completion date was still more than one month away
(December 24, 2008). Since the parties contemplated delay in
Indeed, resolution of the issue of delay was crucial upon which the completion of the entire project, the CA concluded that the
depends petitioners right to the liquidated damages pursuant to failure of the contractor to catch up with schedule of work
the Construction Agreement. Contrary to the CIACs findings, activities did not constitute delay giving rise to the contractors
the CA opined that delay should be reckoned only after the liability for damages.
lapse of the one-year contract period, and consequently
Mabunays liability for liquidated damages arises only upon the We cannot sustain the appellate courts interpretation as it is
happening of such condition. inconsistent with the terms of the Construction Agreement.
Article 1374 of the Civil Code requires that the various
We reverse the CA. stipulations of a contract shall be interpreted together,
attributing to the doubtful ones that sense which may result
Default or mora on the part of the debtor is the delay in the from all of them taken jointly. Here, the work schedule approved
by petitioner was intended, not only to serve as its basis for the
ADR || First Batch 14
4
payment of monthly progress billings, but also for evaluation of October 15, 2008
the progress of work by the contractor. Article 13.01 (g) (iii) of
the Construction Agreement provides that the contractor shall xxxx
be deemed in default if, among others, it had delayed without
justifiable cause the completion of the project "by more than
Dear Mr. Mabunay,
thirty (30) calendar days based on official work schedule duly
approved by the OWNER."31
We have noticed continuous absence of all the Engineers that
you have assigned on-site to administer and supervise your
Records showed that as early as April 2008, or within four
contracted work. For the past two (2) weeks, your company
months after Mabunay commenced work activities, the project
does not have a Technical Representative manning the jobsite
was already behind schedule for reasons not attributable to
considering the critical activities that are in progress and the
petitioner. In the succeeding months, Mabunay was still unable
delays in schedule that you have already incurred. In this
to catch up with his accomplishment even as petitioner
regard, we would highly recommend the immediate
constantly advised him of the delays, as can be gleaned from
replacement of your Project Engineer within the week.
the following notices of delay sent by petitioners engineer and
construction manager, Engr. Sheila N. Botardo:
We would highly appreciate your usual attention on this matter.
April 30, 2008
x x x x33
Seven Shades of Blue
November 5, 2008
Boracay Island
xxxx
Malay, Aklan
Dear Mr. Mabunay,
1wphi1

This is in reference to your discussion during the meeting with


Attention : Mr. Martin Mabunay Mr. Joohan Lee last October 30, 2008 regarding the
construction of the Field Office and Stock Room for Materials
General Manager intended for Villa Beatriz use only. We understand that you
Thru : Engr. Reynaldo Gapasin have committed to complete it November 5, 2008 but as of this
Project : Villa Beatriz date there is no improvement or any ongoing construction
Subject : Notice of Delay activity on the said field office and stockroom.
Dear Mr. Mabunay:
We are expecting deliveries of Owner Supplied Materials very
This is to formalize our discussion with your Engineers during soon, therefore, this stockroom is badly needed. We will highly
our meeting last April 23, 2008 regarding the delay in the appreciate if this matter will be given your immediate attention.
implementation of major activities based on your submitted
construction schedule. Substantial delay was noted in Thank you.
concreting works that affects your roof framing that should have
been 40% completed as of this date. This delay will create
x x x x34
major impact on your over-all schedule as the finishing works
will all be dependent on the enclosure of the building.
November 6, 2008
In this regard, we recommend that you prepare a catch-up
schedule and expedite the delivery of critical materials on site. xxxx
We would highly appreciate if you could attend our next regular
meeting so we could immediately address this matter. Thank Dear Mr. Mabunay,
you.
We would like to call your attention regarding the decrease in
Very truly yours, your manpower assigned on site. We have observed that for
the past three (3) weeks instead of increasing your manpower
Engr. Sheila N. Botardo to catch up with the delay it was reduced to only 8 workers
today from an average of 35 workers in the previous months.
Construction Manager LMI/FEPI32
Please note that based on your submitted revised schedule you
ADR || First Batch 14
5
are already delayed by approximately 57% and this will worsen 12.02 To give full force and effect to the foregoing, the
should you not address this matter properly. CONTRACTOR hereby, without necessity of any further act
and deed, authorizes the OWNER to deduct any amount that
We are looking forward for [sic] your cooperation and may be due under Item (a) above, from any and all money or
continuous commitment in delivering this project as per contract amounts due or which will become due to the CONTRACTOR
agreement. by virtue of this Agreement and/or to collect such amounts from
the Performance Bond filed by the CONTRACTOR in this
Agreement.36 (Emphasis supplied.)
x x x x35

Liability for liquidated damages is governed by Articles 2226 to


Subsequently, a joint inspection and evaluation was conducted
2228 of the Civil Code, which provide:
with the assistance of the architects and engineers of petitioner
and Mabunay and it was found that as of November 14, 2008,
the project was only 31.39% complete and that the ART. 2226. Liquidated damages are those agreed upon by the
uncompleted portion was 68.61% with an estimated value per parties to a contract, to be paid in case of breach thereof.
Construction Agreement as P27,880,419.52. Instead of
doubling his efforts as the scheduled completion date ART. 2227. Liquidated damages, whether intended as an
approached, Mabunay did nothing to remedy the delays and indemnity or a penalty, shall be equitably reduced if they are
even reduced the deployment of workers at the project site. iniquitous or unconscionable.
Neither did Mabunay, at anytime, ask for an extension to
complete the project. Thus, on November 19, 2008, petitioner ART. 2228. When the breach of the contract committed by the
advised Mabunay of its decision to terminate the contract on defendant is not the one contemplated by the parties in
account of the tremendous delay the latter incurred. This was agreeing upon the liquidated damages, the law shall determine
followed by the claim against the Performance Bond upon the the measure of damages, and not the stipulation.
respondent on December 18, 2008.
A stipulation for liquidated damages is attached to an obligation
Petitioners claim against the Performance Bond included the in order to ensure performance and has a double function: (1)
liquidated damages provided in the Construction Agreement, as to provide for liquidated damages, and (2) to strengthen the
follows: coercive force of the obligation by the threat of greater
responsibility in the event of breach.37 The amount agreed upon
ARTICLE 12 LIQUIDATED DAMAGES: answers for damages suffered by the owner due to delays in
the completion of the project.38 As a precondition to such
12.01 Time is of the essence in this Agreement. Should the award, however, there must be proof of the fact of delay in the
CONTRACTOR fail to complete the PROJECT within the period performance of the obligation.39
stipulated herein or within the period of extension granted by
the OWNER, plus One (1) Week grace period, without any Concededly, Article 12.01 of the Construction Agreement
justifiable reason, the CONTRACTOR hereby agrees mentioned only the failure of the contractor to complete the
project within the stipulated period or the extension granted by
a. The CONTRACTOR shall pay the OWNER liquidated the owner. However, this will not defeat petitioners claim for
damages equivalent to One Tenth of One Percent (1/10 of 1%) damages nor respondents liability under the Performance
of the Contract Amount for each day of delay after any and all Bond. Mabunay was clearly in default considering the dismal
extensions and the One (1) week Grace Period until completed percentage of his accomplishment (32.38%) of the work he
by the CONTRACTOR. contracted on account of delays in executing the scheduled
work activities and repeated failure to provide sufficient
manpower to expedite construction works. The events of
b. The CONTRACTOR, even after paying for the liquidated
default and remedies of the Owner are set forth in Article 13,
damages due to unexecuted works and/or delays shall not
which reads:
relieve it of the obligation to complete and finish the
construction.
ARTICLE 13 DEFAULT OF CONTRACTOR:
Any sum which maybe payable to the OWNER for such loss
may be deducted from the amounts retained under Article 9 or 13.01 Any of the following shall constitute an Event of Default
retained by the OWNER when the works called for under this on the part of the CONTRACTOR.
Agreement have been finished and completed.
xxxx
Liquidated Damage[s] payable to the OWNER shall be
automatically deducted from the contractors collectibles without g. In case the CONTRACTOR has done any of the following:
prior consent and concurrence by the CONTRACTOR.
ADR || First Batch 14
6
(i.) has abandoned the Project The plain and unambiguous terms of the Construction
Agreement authorize petitioner to confiscate the Performance
(ii.) without reasonable cause, has failed to commence the Bond to answer for all kinds of damages it may suffer as a
construction or has suspended the progress of the Project for result of the contractors failure to complete the building. Having
twenty-eight days elected to terminate the contract and expel the contractor from
the project site under Article 13 of the said Agreement,
petitioner is clearly entitled to the proceeds of the bond as
(iii.) without justifiable cause, has delayed the completion of the
indemnification for damages it sustained due to the breach
Project by more than thirty (30) calendar days based on official
committed by Mabunay. Such stipulation allowing the
work schedule duly approved by the OWNER
confiscation of the contractors performance bond partakes of
the nature of a penalty clause. A penalty clause, expressly
(iv.) despite previous written warning by the OWNER, is not recognized by law, is an accessory undertaking to assume
executing the construction works in accordance with the greater liability on the part of the obligor in case of breach of an
Agreement or is persistently or flagrantly neglecting to carry out obligation. It functions to strengthen the coercive force of
its obligations under the Agreement. obligation and to provide, in effect, for what could be the
liquidated damages resulting from such a breach. The obligor
(v.) has, to the detriment of good workmanship or in defiance of would then be bound to pay the stipulated indemnity without the
the Owners instructions to the contrary, sublet any part of the necessity of proof on the existence and on the measure of
Agreement. damages caused by the breach. It is well-settled that so long as
such stipulation does not contravene law, morals, or public
13.02 If the CONTRACTOR has committed any of the above order, it is strictly binding upon the obligor.42
reasons cited in Item 13.01, the OWNER may after giving
fourteen (14) calendar days notice in writing to the Respondent, however, insists that it is not liable for the breach
CONTRACTOR, enter upon the site and expel the committed by Mabunay because by the terms of the surety
CONTRACTOR therefrom without voiding this Agreement, or bond it issued, its liability is limited to the performance by said
releasing the CONTRACTOR from any of its obligations, and contractor to the extent equivalent to 20% of the down
liabilities under this Agreement. Also without diminishing or payment. It stresses that with the 32.38% completion of the
affecting the rights and powers conferred on the OWNER by project by Mabunay, its liability was extinguished because the
this Agreement and the OWNER may himself complete the value of such accomplishment already exceeded the sum
work or may employ any other contractor to complete the work. equivalent to 20% down payment (P8.4 million).
If the OWNER shall enter and expel the CONTRACTOR under
this clause, the OWNER shall be entitled to confiscate the The appellate court correctly rejected this theory of respondent
performance bond of the CONTRACTOR to compensate for all when it ruled that the Performance Bond guaranteed the full
kinds of damages the OWNER may suffer. All expenses and faithful compliance of Mabunays obligations under the
incurred to finish the Project shall be charged to the Construction Agreement, and that nowhere in law or
CONTRACTOR and/or his bond. Further, the OWNER shall not jurisprudence does it state that the obligation or undertaking by
be liable to pay the CONTRACTOR until the cost of execution, a surety may be apportioned.
damages for the delay in the completion, if any, and all; other
expenses incurred by the OWNER have been ascertained
The pertinent portions of the Performance Bond provide:
which amount shall be deducted from any money due to the
CONTRACTOR on account of this Agreement. The
CONTRACTOR will not be compensated for any loss of profit, The conditions of this obligation are as follows:
loss of goodwill, loss of use of any equipment or property, loss
of business opportunity, additional financing cost or overhead Whereas the JPLUS ASIA, requires the principal SEVEN
or opportunity losses related to the unaccomplished portions of SHADES OF BLUE CONSTRUCTION AND DEVELOPMENT,
the work.40 (Emphasis supplied.) INC. to post a bond of the abovestated sum to guarantee 20%
down payment for the construction of Building 25 (Villa Beatriz)
As already demonstrated, the contractors default in this case 72-Room Condotel, The Lodgings inside Fairways and
pertains to his failure to substantially perform the work on Bluewater, Boracay Island, Malay, Aklan.
account of tremendous delays in executing the scheduled work
activities. Where a party to a building construction contract fails Whereas, said contract required said Principal to give a good
to comply with the duty imposed by the terms of the contract, a and sufficient bond in the above-stated sum to secure the full
breach results for which an action may be maintained to and faithful performance on his part of said contract.
recover the damages sustained thereby, and of course, a
breach occurs where the contractor inexcusably fails to perform It is a special provision of this undertaking that the liability of the
substantially in accordance with the terms of the contract.41 surety under this bond shall in no case exceed the sum of
P8,400,000.00 Philippine Currency.
ADR || First Batch 14
7
Now, Therefore, if the Principal shall well and truly perform and CA-G.R. SP No. 112808 are hereby REVERSED and
fulfill all the undertakings, covenants, terms, conditions and SET ASIDE.
agreements stipulated in said contract, then this obligation shall
be null and void; otherwise to remain in full force and effect.43 The Award made in the Decision dated February 2, 2010 of the
(Emphasis supplied.) Construction Industry Arbitration Commission Is hereby
REINSTATED with the following MODIFICATIONS:
While the above condition or specific guarantee is unclear, the
rest of the recitals in the bond unequivocally declare that it "Accordingly, in view of our foregoing discussions and
secures the full and faithful performance of Mabunays dispositions, the Tribunal hereby adjudges, orders and directs:
obligations under the Construction Agreement with petitioner.
By its nature, a performance bond guarantees that the
1) Respondent Utassco to pay to petitioner J Plus Asia
contractor will perform the contract, and usually provides that if
Development Corporation the full amount of the Performance
the contractor defaults and fails to complete the contract, the
Bond, P8,400,000.00, pursuant to Art. 13 of the Construction
surety can itself complete the contract or pay damages up to
Agreement dated December 24, 2007, with interest at the rate
the limit of the bond.44 Moreover, the rule is that if the language
of 6% per annum computed from the date of the filing of the
of the bond is ambiguous or uncertain, it will be construed most
complaint until the finality of this decision, and 12% per annum
strongly against a compensated surety and in favor of the
computed from the date this decision becomes final until fully
obligees or beneficiaries under the bond, in this case petitioner
paid; and
as the Project Owner, for whose benefit it was ostensibly
executed.45
2) Respondent Mabunay to indemnify respondent Utassco of
the amounts respondent Utassco will have paid to claimant
The imposition of interest on the claims of petitioner is likewise
under this decision, plus interest thereon at the rate of 12% per
in order. As we held in Commonwealth Insurance Corporation
annum computed from the date he is notified of such payment
v. Court of Appeals46
made by respondent Utassco to claimant until fully paid, and to
pay Utassco P100,000.00 as attorney's fees.
Petitioner argues that it should not be made to pay interest
because its issuance of the surety bonds was made on the
SO ORDERED.
condition that its liability shall in no case exceed the amount of
the said bonds.
With the above modifications, the Writ of Execution dated
November 24, 2010 issued by the CIAC Arbitral Tribunal in
We are not persuaded. Petitioners argument is misplaced.
CIAC Case No. 03-2009 is hereby REINSTATED and
UPHELD.
Jurisprudence is clear on this matter. As early as Tagawa vs.
Aldanese and Union Gurantee Co. and reiterated in Plaridel
No pronouncement as to costs.
Surety & Insurance Co., Inc. vs. P.L. Galang Machinery Co.,
Inc., and more recently, in Republic vs. Court of Appeals and R
& B Surety and Insurance Company, Inc., we have sustained SO ORDERED.
the principle that if a surety upon demand fails to pay, he can
be held liable for interest, even if in thus paying, its liability MARTIN S. VILLARAMA, JR.
becomes more than the principal obligation. The increased
liability is not because of the contract but because of the default Associate Justice
and the necessity of judicial collection.
WE CONCUR:
Petitioners liability under the suretyship contract is different
from its liability under the law. There is no question that as a
1wphi1

MARIA LOURDES P. A. SERENO


surety, petitioner should not be made to pay more than its
assumed obligation under the surety bonds. However, it is clear
Chief Justice
from the above-cited jurisprudence that petitioners liability for
the payment of interest is not by reason of the suretyship
agreement itself but because of the delay in the payment of its Chairperson
obligation under the said agreement.47 (Emphasis supplied;
citations omitted.) TERESITA J. LEONARDO-DE CASTRO

WHEREFORE, the petition for review on certiorari is Associate Justice


GRANTED. The Decision dated January 27, 2011 and BIENVENIDO L. REYES
Resolution dated December 8, 2011 of the Court of Appeals in
ADR || First Batch 14
8
Associate Justice 18 ART. 1377. The interpretation of obscure words or
stipulations in a contract shall not favor the party who caused
CERTIFICATION the obscurity.

Pursuant to Section 13, Article VIII of the 1987 Constitution, I


19 G.R. No. 108129, September 23, 1999, 315 SCRA 92.
certify that the conclusions in the above Decision had been
reached in consultation before the case was assigned to the 20 Rollo, p. 67.
writer of the opinion of the Court's Division.
21 Id. at 23.
MARIA LOURDES P. A. SERENO
22 Approved on April 2, 2004.
Chief Justice
23Metro Construction, Inc. v. Chatham Properties, Inc., G.R.
No. 141897, September 24, 2001, 365 SCRA 697, 718-719 &
794.
Footnotes
24 A.M. No. 07-11-08-SC, effective October 30, 2009.
1 Rollo, pp. 57-68. Penned by Associate Justice Samuel H.
Gaerlan with Associate Justices Hakim S. Abdulwahid and 25As amended by CIAC Resolution Nos. 15-2006, 16-2006, 18-
Ricardo R. Rosario concurring. 2006, 19-2006, 02-2007, 07-2007, 13-2007, 02-2008, and 03-
2008, which took effect on December 15, 2005.
2 Id. at 69-73.
26 Rollo, pp. 202-210.
3 Id. at 87-99.
27 IV Arturo M. Tolentino, COMMENTARIES AND
4 Id. at 962-967. JURISPRUDENCE ON THE CIVIL CODE OF THE
PHILIPPINES, 101 (1987 ed.).
5 Id. at 101-103, 606.
28 17 Am Jur 2d 387, p. 832.
6 Id. at 184.
29 Rollo, p. 93.
7 Id. at 109.
30Santos Ventura Hocorma Foundation, Inc. v. Santos, 484
Phil. 447, 457 (2004), citing IV Arturo M. Tolentino,
8 Id. at 109-110.
COMMENTARIES AND JURISPRUDENCE ON THE CIVIL
CODE OF THE PHILIPPINES, 102 (1987 ed.). See also
9 Id. at 110. Philippine Export and Foreign Loan Guarantee Corporation v.
V.P. Eusebio Construction, Inc., G.R. No. 140047, July 13,
10 Id. at 76-86. 2004, 434 SCRA 202, 218-219.

11 Id. at 82. 31 Rollo, p. 94.

12 Id. at 189-197. 32 Id. at 104.

13 Id. at 115-121, 132-136, 163-164. 33 Id. at 106.

14 Id at 165-183. 34 Id. at 107.

15 Id. at 211-212. 35 Id. at 108.

16 Id. at 600-614. 36 Id. at 93-94.

17 Id. at 614 to 614-A. 37Atlantic Erectors, Inc. v. Court of Appeals, G.R. No. 170732,
October 11, 2012, 684 SCRA 55, 65, citing Philippine Charter
ADR || First Batch 14
9
Insurance Corporation v. Petroleum Distributors & Service
Corporation, G.R. No. 180898, April 18, 2012, 670 SCRA 166,
177 and Filinvest Land, Inc. v. Court of Appeals, G.R. No.
138980, September 20, 2005, 470 SCRA 260, 269.

38Id., citing H.L. Carlos Construction, Inc. v. Marina Properties


Corporation, 466 Phil. 182, 205 (2004).

39 Id., citing Empire East Land Holdings, Inc. v. Capitol


Industrial Construction Groups, Inc., G.R. No. 168074,
September 26, 2008, 566 SCRA 473, 489.

40 Rollo, pp. 94-95.

41 13 Am Jur 2d 72, p. 73.

42Suatengco v. Reyes, G.R. No. 162729, December 17, 2008,


574 SCRA 187, 194, citing Ligutan v. Court of Appeals, G.R.
No. 138677, February 12, 2002, 376 SCRA 560, 567-568.

43 Rollo, p. 100.

44 17 Am Jur 2d 1, p. 192.

45 17 Am Jur 2d 3, p. 193.

46 466 Phil. 104 (2004).

47 Id. at 112-113.

You might also like