Date Activity
Jun-17 Begin submission of project proposals
4/6/2017-
Week 1 10/6/2017 Submission of draft project proposals
11/6/2017- Assignment of supervisors
Week 2 17/6/2017
18/6/2017-
24/6/2017 Compulsory meeting 1
Week 3
Discussion on proposed project and
25/6/2017- implementation
Week 4 1/7/2017
2/7/2017-
Week 5 8/7/2017
9/7/2017-
Project implementation
Week 6 15/7/2017
16/7/2017-
Week 7 22/7/2017
23/7/2017-
Student updates to supervisor on progress
29/7/2017
Week 8
30/7/2017-
Week 9 5/8/2017
6/8/2017-
Week 10 12/8/2017
13/8/2017-
Project implementation
Week 11 19/8/2017
20/8/2017-
Week 12 26/8/2017
27/8/2017-
Week 13 2/9/2017
3/9/2017- Compulsory meeting 2
Week 14 9/9/2017 Discussion on progress and project report
10/9/2017-
Submit first draft of report to supervisor
Week 15 16/9/2017
17/9/2017-
Week 16 23/9/2017
Corrections, Edit and Binding
24/9/2017-
Week 17 30/9/2017
Submit report:
1/10/2017-
- Ring bound report (submit to supervisor)
7/10/2017
Week 18 - Meeting record (submit to EDGE Office)
8/10/2017-
14/10/2017
Week 19 Supervisor submit marks to EDGE office
15/10/2017-
21/10/2017
Week 20 Faculty Meeting (Marks Presentation)
Remarks