You are on page 1of 68

Blast design for underground

mining applications
1

R. HOLMBERG

R. Holmberg Lima Nov 2011


Contents
2

Contents:
1. Purpose - applications 11. Mining methods
2. Surface blasting 12. Ring layouts
3. Surface - underground 13. Design formula
4. Tunneling 14. Explosives
5. Function of cut 15. Decoupled charges
6. Design of parallel cut 16. Pointers
7. Tunnel rounds 17. Acknowledgements
8. Contour blasting
9. Divided faces
10. Shaft sinking
R. Holmberg Lima Nov 2011
Purpose & applications -1
3

The purpose is to:


Efficiently excavate rock so that the pieces removed
can be handled economically
Avoid ore losses and waste rock intrusion
Obtain the planned contour with no underbreak and
as little overbreak as possible
Leave the remaining rock stable for as long as the
operation requires.

R. Holmberg Lima Nov 2011


Purpose & applications -2
4

The main applications are


Mining; drifting and development work plus full
workings
Raise blasting and shaft sinking
Quarrying
Infrastructure; traffic tunnels, hydropower and water
tunnels, parking garages, shelters, power house
caverns etc
Other applications; well springing, seismic
operations etc.

R. Holmberg Lima Nov 2011


Surface blasting -1
5

Quarry; typically identical holes,


parallel, same diameter and
same burden and spacing, BS
pattern, same charging,
q = 0,5-0,9 kg/m3.
Road cut; like quarry but
contour holes , smaller hole
diameters, smaller charges and
on flatter angle

Foundations; essentially like


road cuts but vertical holes.

R. Holmberg Lima Nov 2011


Surface blasting -2
6

Open cast mine; like road cut but larger holes and
contour gets special emphasis, sometimes smaller
holes of different angles and depths.
1st row
7540

7520
production
7500 holes 17 m

7480
311 mm

7460
helper &
contour
7440
152 mm
7420

presplit 127 mm
15 m bench 7400
4480 4500 4520 4540 4560 4580 4600 4620 4640

R. Holmberg Lima Nov 2011


Surface vs underground - 1
7
Worldwide: OP >> UG, OP: ore < waste, UG: ore >> waste

R. Holmberg Lima Nov 2011


Surface vs underground - 2
8

Annually excavated volumes in Sweden


LKAB UG mines: 25 Mton Fe-ore, 20 Mton waste
Aitik open pit mine: 28 Mton Cu-ore, 30 Mton
waste.
Other mines and crushed stone, infrastructure
projects etc. ~80Mton
Makes about 180 Mton
or 6 m3 per capita
70 kton explosives makes
about 8 kg per capita

R. Holmberg Lima Nov 2011


Surface vs underground - 3
9

Underground blasting; often more complicated


Tunnelling: drilling patterns and combinations of blasting
methods

fire-in-the-hole!

blasting plan
charged & primed

R. Holmberg Lima Nov 2011


Tunnelling - 1
10

What has happened in tunnelling recent 25 years?

R. Holmberg Lima Nov 2011


Tunnelling - 2
11

blasting = (38% 2007), small part of total excavation work


but outcome often decisive for downstream operations
R. Holmberg Lima Nov 2011
Tunnelling - 3
12

look-out angle needed to make


room for drilling next round,
min 0.2-0.3 m, design burden
applied to hole bottom (toe)
and at face deduct look-out

Start- first one free


face - the tunnel face.
Blasting is confined
and specific charge is
high
q = 1,5-2 kg/m3

R. Holmberg Lima Nov 2011


Tunnelling - 4
13
enlargement
Tunnel round with parallel holes of cut part

larger empty
(void, reamer
or burn) holes
cut

blasting starts with cut = opening part of round


R. Holmberg Lima Nov 2011
Tunnelling - 5
14

Charge calculations for tunnelling can be made according to


Chapter 7 in Rock Blasting and Engineering by
Persson, Holmberg & Lee.

In these OHs simplified rules of thumbs by Finn Oucterlony at Swebrec is used.

R. Holmberg Lima Nov 2011


Design of parallell hole cut - 1
15

reamer hole = first swelling volume


#3

#1 #2

rock to be
broken
#4 - 100 ms

R. Holmberg Lima Nov 2011


Design of parallell hole cut - 2
16

In principle, choose
burden a according
to diagram but:
If burden a too large
breakage failure
(rifling) or choking of
flow of rock fragments
If burden a too small
burning of rock
fragments

Drilling accuracy is most essential!

R. Holmberg Lima Nov 2011


Design of parallell hole cut - 3
17

Geometric considerations for cartridged explosives:


1st quadrangle: 2nd quadrangle:
B1 = W1
a = 1,5 B1

a 0,5W1
+
W2 =1,5W12
W1= 2a W1

3rd quadrangle: 4th quadrangle:


B2 = W2 & W3 =1,5W22 B3 = W3 & W4 =1,5W32

R. Holmberg Lima Nov 2011


Design of parallell hole cut - 4
18

Charge concentration lb = lp in first quadrangle:


Advance;
0.95*(0.15+34.1 -
39.42)

In case of several (n)


empty holes (d) in the cut
use:
= dn
when estimating advance.

Use an uncharged
part at the collar of
h0 = a.
R. Holmberg Lima Nov 2011
Design of parallell hole cut - 5
19
Charge concentration lp for 2nd-4th quadrangles:
Charge concentration lp, kg/m

lp

Bi, i =1, 2, 3

Max burden B,
m
Stemming or uncharged length 10d or 0.5B.
Bottom part may need lb=2lp to height of 1.25B.
R. Holmberg Lima Nov 2011
Tunnel rounds - 1
20
1. Lifters; spacing should not exceed
Design of parts of round: design value S, e.g. width/S = 11,4
means round up to 12 and add 1
hole. Correct B for look-out of 0.2-
Roof or back holes 0.3 m
Downward 2. Wall+roof; same for spacing and
stoping subtract look-out distance 0,2-0,3
m from design burden B. If cautious
Wall or rib holes

blasting see below.


Side stoping

3. Cut; match size of cut to side stope,


Helper row

Cut if B3 > B0 (next OH) then decrease


holes B3. Place cut to minimize no. of
side stope rows.
4. Stoping; use same side stope
Floor holes or lifters burden < B in all rows, same for
downward stope and adjust to even
Spacing S Burden B breakage volumes.
5. Helpers; balance contour damage
R. Holmberg Lima Nov 2011
or lift cut position
Tunnel rounds - 2
21
Part of Burden Spacing Bottom Charge concentration Stemming
round B S charge length bottom lb column lp not charged
m m Lb, m kg/m kg/m h0, m
Floor /Lifter 1 x B0 1,1 x B 0 1/3 x H lb 1,0 x lb 0,2 x B 0
Contour:
Wall 0,9 x B 0 1,1 x B 0 1/6 x H lb 0,4 x lb 0,5 x B 0
Roof 0,9 x B 0 1,1 x B 0 1/6 x H lb 0,3 x lb 0,5 x B 0
Stoping:
Upwards 1 x B0 1,1 x B 0 1/3 x H lb 0,5 x lb 0,5 x B 0
Horiz./Side 1 x B0 1,1 x B 0 1/3 x H lb 0,5 x lb 0,5 x B 0
Downwards 1 x B0 1,2 x B 0 1/3 x H lb 0,5 x lb 0,5 x B 0
Note: The explosive chosen (density and charge diameter) determines the
charge concentration lb, kg/m. Calculate lp and use next larger cartridge or
pipe size for real column charge. Helpers may be designed as stoping holes
or with consideration for damage depth. Diagram in next OH gives B0.
R. Holmberg Lima Nov 2011
Tunnel rounds - 3
22
B0, burden at hole bottom or toe
vs equiv. charge con-centration lb
(kg/m) needed for breakage.
Deduct look-out for perimeter
B0 holes

lb cartridged emulsion with alu,


suitable for bottom charges

cartridge,mm dynamite, e.g. bottom


charge
cartridge,mm
same emulsion but in longer
pipes, used for column charges
pipe,mm
bulk ANFO like SSE fills hole,
and a proper primer is needed
blasthole,mm
shifted scales on lines because
R. Holmberg Lima Nov 2011 densities are different
Tunnel rounds 4
23
Priming and initiation sequence principles
Do not initiate
two holes on
same delay no.
in first two
quadrangles.

Detonator no:s #1-22 tell the initiation sequence. In practice it is not usual to
have the same delay time between all intervals, see Nonel LP series
R. Holmberg Lima Nov 2011
Tunnel rounds 5
24

Nonel plastic tube with 17 mg/m of explosive


VoD 2100 m/s Nonel LP detonators
suitable for UG work

New series Nonel LP detonators:


delays up to 6000 ms in steps of 50, 100,
200 and 400 ms
old series detonator no.18100 ms same as
new LP 1800 e.g.
LP 0 at 25 ms exception
dont use intervals shorter than 100 ms in
tunnel rounds without trials
R. Holmberg Lima Nov 2011
Tunnel rounds 6
25
Drilling and charging plan data:
Part of Holes Spacing Burden
from sp TASS tunnel, note look-out round no. m m
Cut 9 special list
Stoping 28 0,60 0,60
Lifter 10 0,50 0,45
Helper 17 0,60 0,55
Contour 28 0,45 0,60
Part of Bottom xL Column xL
round charge mm charge mm
Cut Dynomit 30380 Dynorex 251100
1m Stoping Dynomit 30380 Dynorex 251100
Lifter Dynomit 30380 Dynorex 251100
Helper Dynomit 30380 Dynotex 1 221000
1m Contour Dynomit 30190 Dynotex 1 17 460
Part of Charge Total Charge length Un-
round weight part bottom column charged
kg/hole kg m m m
Cut 2,8 25,2 0,38 3,92 0,3
Stoping 2,8 75,6 0,38 3,92 0,5
Lifter 2,9 29,0 0,38 4,02 0,2
Helper 1,8 32,4 0,38 3,92 0,2
Contour 1,1 30,8 0,19 4,21 0,2
4,3 m
R. Holmberg Lima Nov 2011
Tunnel rounds 7
26

In summary:
Only 1 free face to start with when cut fires, tight hole
burdens and spacings (high specific charge)
Cut design requires special considerations like avoidance
of sympathetic detonations and dead pressing
Long delays to avoid choking of flow of fragmented rock,
up to 6000 ms or more.
Parallel holes in good rock and small tunnels to achieve
long pull (parallel & burn hole cuts).

R. Holmberg Lima Nov 2011


Tunnel rounds 8
27

In summary, ctd:
Poor rock requires shorter rounds, angled holes, e.g.
fan and plow cuts possible to use if face wide enough
to angle booms
Depending on local conditions packaged or bulk
explosives may be used. With bulk there is no special
pipe charge, lp = lb, and primer should be used.
Contour and helper row holes are usually more lightly
charged than stoping holes; e.g. plastic pipe charges
or string emulsion.

R. Holmberg Lima Nov 2011


Contour blasting - 1
28
Why cautious blasting?
Extent of cautions blasting depends
on expected life time of tunnel
/cavern /drift etc
Less dilution, better ore recovery
Less support work, less bolting, less without
shotcrete or concrete to cast caution
Increased safety
Less rock to haul, saves time and
money
Smooth blasting method used UG
to reduce overbreak and blast
damage. with

R. Holmberg Lima Nov 2011


Contour blasting 2
29

Cautious and smooth blasting:


By cautious blasting is meant that the cracking in the
remaining rock due to blasting, shall be limited to the
damage zone depth Rc that has been prescribed for
the perimeter in question. perimeter
or contour
The cracking caused by the stoping
and helper holes inside the perimeter
helpers or
must not reach farther into the stoping holes
remaining rock than the cracking
from the perimeter/contour holes.
Smooth blasting uses light decoupled charges
in contour and helpers with balanced damage
damage
zone depths; holes fired last in round. zone radius
R. Holmberg Lima Nov 2011
Contour blasting 3
30
In Swedish tunneling:
Damage zone depth Rc, m
Rc < 0,3 m often required 2.5
Rc= 1,9*q
Damage zone table gives
charge concentration for 2.0
Swedish bedrock
conditions; 45-51 mm 1.5
holes.
Note: q is given in Dyna- 1.0
mite equivalents,
multiply real q by 0,73 0.5
for Gurit Rc = 1,9q; q < 0,5 kg/m
Contour and helper Rc = 0,95(q+0,5); q > 0,5 kg/m
0.0
damage zones can be 0.0 0.5 1.0 1.5 2.0
read off curve Charge concentration q, kg DxM/m
Holmberg-Persson
theory behind line.
R. Holmberg Lima Nov 2011
Damage zone

Contour blasting - 4
31

Recommended charging of countour holes

Notes: Connect charges and use small primer to initiate them


*: Damage zone e.g. from 17 mm Gurit Rc = 1,90,230,73 0,3 m
New Swebrec approach explicitly includes effect on Rc of= 0,17 eq kgDxM/m
Blast hole diameter and coupling factor
Water in blast hole and rock properties
Simultaneous initiation using e.g. electronic dets or cord.
R. Holmberg Lima Nov 2011
Contour blasting 5
32

If stoping holes too heavily charged


then the cracks will extend beyond
damage zone of contour holes.
normal Solution = more lightly charged
stoping holes helper row with adjusted burdens
and spacings!

When cracks from holes inside the


contour reach no further than the
cracks from the contour holes, the
damage zones are balanced.

stoping

R. Holmberg Lima Nov 2011


Contour blasting 6
33

Does it matter? Take 22 mm Gurit


Crack length in dry 64 mm hole 15-20 cm
Crack length in wet 64 mm hole 45-60 cm
Crack length with no decoupling 90-100 cm!

Crack lengths with electronic dets shorter than


for Nonel detonators if
Charge concentration q < 0.6 kg/m and
spacing S/B < 1
If decoupling is sufficient and holes are
proven dry
Initiation simultaneous well within 1 ms.

R. Holmberg Lima Nov 2011


Contour blasting - 7
Extremely cautious blast with
34 hybrid initiation plan
Nonel + electronic dets (EDD)
in contour and helpers
Lightly charged lifters and
helpers

Note half casts in floor!


R. Holmberg Lima Nov 2011
Contour blasting - 8
35

R. Holmberg Lima Nov 2011


Divided faces - 1
36

R. Holmberg Lima Nov 2011


Divided faces - 2
37

Reasons for dividing face:


Stability reasons
- cant otherwise maintain stability of and at face
- uncertain about geology, pilot gathers information
Productivity; access to many faces
Length of rounds
- the span is able to support the rock-load
- the support measures can be installed in due time.

R. Holmberg Lima Nov 2011


Divided faces - 3
38

West Ex. Lttinge traffic tunnel,


2-lane 1058 m Sthlm 2005-6
portal 188,5 m, 152 m2:
10 E & W access
Rd 1-3 Side pilot, leaving plug
to prevent noise coming out and
1:a verlapp ca 7m

10 winter cold in
Rd 4-7 Widen to full section
ca 5m

ca 5m
Rd 8-9 side pilots
Rd 10-123 side pilot and trailing
side stope in same round.
saved plug
6000

1
ca 3m

R. Holmberg Lima Nov 2011


Divided faces - 4
39

Drilling of pilot at East portal and side stopes (slashes).


R. Holmberg Lima Nov 2011
Divided faces 5
40

Excavation sequence for


hydro power house cavern
R. Holmberg Lima Nov 2011
Shaft sinking - 1
41

2 m bench
with confined
toe and
fanned rows

R. Holmberg Lima Nov 2011


Shaft sinking - 2
42
5 m full face
round with cut
and parallel
holes
easier drilling, pulls
deeper and produces
finer muck than bench
round

200 mm pilot (reamer)


hole drilled 0,3 m
deeper than rest of
round to ensure 100%
pull.
R. Holmberg Lima Nov 2011
Mining methods -1
43

Room and pillar; metal mines & underground quarries


drift heading
cross cut =
= tunnel round
tunnel round vertical
bench

upward stoping
=
horizontal bench

Depending on the mining method


a mine uses several blasting methods.
R. Holmberg Lima Nov 2011
Mining methods -2
44

Drift and (multiple)


benching, Zinkgruvan

Parallel drill holes


that follow the ore.

R. Holmberg Lima Nov 2011


Mining methods -3
45

Panel stoping, Zinkgruvan

2 1 2
rings or fans with
89 mm angled
1 2 1 2 1 2
holes of different
1 lengths
2 1 2 2 1 2 1
2
1 2 1 1 2 1 2

Panels 1 filled with paste fill


before # 2 between blasted.
R. Holmberg Lima Nov 2011
Mining methods -4
46
Sublevel caving or SLC at LKAB

SLC rings with angled


holes of different
blasting against lengths
confinement of
caving masses

high grade iron


ore 4500
kg/m3

R. Holmberg Lima Nov 2011


Ring layouts 1
47

Different SLC ring layouts at LKAB

water hydraulic ITH, 115 mm holes, 15-58 m long, 3 m


burden, typically opened at center, 2 holes every 100 ms.
R. Holmberg Lima Nov 2011
Ring layouts 2
48
Deck charging sometimes
used for
breakage sequence + flow
Vibrations. delay number =
initiation sequence

stemming

charge in hole separated


into decks by stemming and
detonated separately in
sequence 3, 4 etc

R. Holmberg Lima Nov 2011 flow


Explosives -1
49

Types of explosives used

R. Holmberg Lima Nov 2011


Explosives - 2
50

Anolit (ANFO) compressed air


charging equipm.

Anolit
Density 850 kg/m3
Weight strength 100 %
Volume strength 100 %
Expl. energy 4,0 MJ/kg
VOD 2400 m/s
Gas volume 970 l/kg
Water resistance poor
Use primer

Anolit A with 6-7% Al


expl. energy = 4,9 MJ/kg
volume strength = 125 %
R. Holmberg Lima Nov 2011
Explosives - 3
51

Emulsion matrix is not an explosive


which means safer, less restricted
transportation

R. Holmberg Lima Nov 2011


Explosives - 4
52

Reaction kinetics
Emulsion finer structure
rendering in higher VoD

R. Holmberg Lima Nov 2011


Explosives - 5
53

Site Sensitised Emulsion


Oxidizer Solution
Slurry Station Fuel and
Emulsifier

Gassing agents

Emulsion mixer Dosage pumps

Control - Emulsion matrix


panel

Pump

R. Holmberg Lima Nov 2011


Explosives - 6
54

Titan SSE system (site sensitized emulsion)

under ground in
45-51 mm holes

R. Holmberg Lima Nov 2011


Explosives - 7
55

Slurry Station Oxidizer Solution


Fuel and
Gassing agents Emulsifier

AN - Prills
Aluminum

Control -
panel

Blender

Pump

Emulsion mixer Dosage pumps

R. Holmberg Lima Nov 2011


Explosives - 8
56

Bore hole diameter :


Quarries : 2 - 6
Mining : 6 - 12
Max pump heigth : 40 m
Max hose length : 150 m

Slurry Station Oxidizer Solution


Fuel and
Gassing agents Emulsifier

AN - Prills
Aluminum

Control -
panel

Blender

Pump

Emulsion mixer Dosage pumps

above ground in
holes 64-320 mm
R. Holmberg Lima Nov 2011
Explosives - 9
57

Comparing ANFO and emulsion


explosives
Emulsion matrix less restricted in transportation
Pumped emulsions have higher charging capacity
Density regulated by gassing during pumping
Decoupled string emulsion in horizontal holes
Slurry Station Oxidizer Solution
Fuel and
Gassing agents Emulsifier

AN - Prills
Aluminum

Control -
panel

Blender

Pump

Emulsion mixer Dosage pumps

Emulsions have higher water resistance and AN


prills may be added to raise density
Energy content per m3 roughly the same
but
Lower price of ANFO ideal for dry hole conditions.

Roger
R. Holmberg Lima Nov 2011
YZ-snitt KI-28-849-o3030-19
6

40-50 m
-40

Explosives - 10 -35 5 7

58
Uphole ring charging at LKAB
-30
4 8

-25
9 8 8 8 9 10
2 3 9

KR0500 (Kimulux Repumpable


10 10
11 11

-20

0500), sensitized by glass micro-


balloons, contains aluminum -15
1 11

9 8

Water used to lubricate inside of -10


12
9
12

charging hose; mixed in at nozzle 11 11

Staying in place is a balance -5 10


8 10
8

between viscosity and adhesion 0


12 12

Emulsion is tixotropic and blast -10 -5 0 5 10

shock is too fast to cause


liquefaction
But, running water creates
problems.

R. Holmberg Lima Nov 2011


Explosives - 11
DynoRex 59

Dynamite with NG, nitro-


glycol, nitrocellulose and AN

used as bottom charge, primer & also available as


booster, in wet holes etc. 1100 mm pipe
R. Holmberg Lima Nov 2011 charges
59
Explosives - 12
60

Kemix A

used as bottom and column


charge (pipe) , primer &
booster, contour blasting.

R. Holmberg Lima Nov 2011


Decoupled charges - 1
61

R. Holmberg Lima Nov 2011


Decoupled charges - 2
62

Dynotex
pipe charges
17-32460/1000 mm

R. Holmberg Lima Nov 2011


Decoupled charges - 3
63
by balancing emulsion
String emulsion flow through nozzle and
hose retraction an even
string is deposited in hole

string 0,35 kg/m


mini SSE
R. Holmberg Lima Nov 2011
Decoupled charges - 4
64
Selmer Anlggning AB Strengladning SSE
Chalmers-tunnelen Ladeplan 4,2 m
4.steg . SSE emulsjon i hele salven

Strossehull oppe : 4,0 kg


1,1 kg/m
A 3,05 m
0,7m 0,45m
Innerkontur (hjelpekontur) : 3,0 kg
0,8 kg/m
B
0,7m 3,2m 0,3m
A B
Kutt m/hjelpehull : 4,5 kg
1,1 kg/m
C
0,3m 3,45m 0,45m
D Konturhull m/hjrneliggere : 1,7 kg
0,4 kg/m : 3,0 kg
Innerkontur (hjelpekontur)
C D
0,3m 3,9 m 0,15m
Liggerhull : 3,3 kg
0,8 kg/m
E
0,3m 3,6m 0,3m

Emulsjon Tennpatron

R. Holmberg Lima Nov 2011


Pointers - 1
65

Underground blasting:
Often more complicated drilling patterns and blasting
methods used than in surface blasting
Special considerations for cuts and openings; stability; rock
stress and water complicate work
Separation between fragmented rock (ore) and remaining
rock mass (waste) hard to maintain
Short life span of drifts and cavities in mining but long span in
infrastructure tunnels and cavern
Nitrate leakage from explosives is coming into focus; spillage
& non-detonating explosives are sources.

R. Holmberg Lima Nov 2011


Pointers - 2
66

Quality of blasting work:


Blasting never gets better than drilling and drill hole
deviations are frequently large
Water problem in charging also with emulsions - bad
charging practice mixes emulsion & water, may cause
detonation failure; water removes cushion effect for
decoupled charges; wet upholes cause emulsion to slip etc
Some cases black holes, e.g. SLC. One doesn't - see the
drilling quality, know how the ring fired or even which ring
the ore loaded comes from
High quality blast designs, drilling and charging work
needed to achieve good blasting results.
R. Holmberg Lima Nov 2011
Accknowledgements
67

The author wishes to acknowledge Prof Finn


Ouchterlony , Swebrec and LTU who provided a lot
of the sources for the material presented in this
lecture

R. Holmberg Lima Nov 2011


THANKS!
68

R. Holmberg Lima Nov 2011

You might also like