GENERAL DESCRIPTION
1. Annual Plan 2016-17: Under consideration is the letter received from JMD-III,
MSRDC, Mumbai MSRDC/JMD/D-1/NH-160/PR/6053/2016 from MSRDC,
Maharashtra dated 02.11.2016 submitted therewith estimate of amount Section of
Pune-Mangaon , Newly declared NH 753F has been included in the Annual Plan
2017-18. The work of DPR preparation has been entrusted with L. N. Malviya Infra
Projects Pvt. Ltd. The entire project has been divided in three construction packages.
Section-I(A) from 1+275 (Ex. Ch. 13.180) in Pune to km 31+400 (Ex. Ch. 43.420)
(Shende Patil), Section-I(B) from 31+400(Ex. Ch. 43.420) (Shende Patil) to km 69+000
(Ex. Ch. 81.300) (Pune-Raigad District Border) & Section I(C) From km 69+000 (Ex.
Ch. 81.300) (Pune-Raigad District Border) to km 103+775 (Ex. Ch. 116.124) (Mangaon)
is being submitted.
2. Background: The Project road is a newly declared National Highway No. 753F. The
road starts from Pune (at Paud Toll Plaza) and passes through Bhugaon, Pirangut,
Paud, Mulshi town portions in Pune District & Nizampur town portion in Raigad
District and terminates at Junction with NH-17 in Mangaon in the state of
Maharashtra. This whole length 103.775 km (Ex Length 102.944) is principally
declared National Highway. The present estimate is submitted for (Section-I), i.e.
Section from Pune to Shende Patil covering length 30.125 km. The present
carriageway of the project highway is Two Lane with Paved Shoulder, Two lane &
Intermediate Lane. The type of the existing pavement is flexible. Project road passes
through Plain terrain & Hilly Terrain. Forest land exist at many stretches. The
improvement as per IRC:SP-73-2015 is proposed. The details of improvement are
given in subsequent paras.
(Sanjay Gosavi)
Executive Engineer,
M.S.R.D.C, Mumbai
4. Following is the salient features of the project:
7. VUP Nil
5. Improvement Proposals:
Keeping in view the length of the project, the design parameters and likely facilities
to be provided in the project, the MSRDC had submitted the Estimate. It is proposed
to have rigid pavement for 2 lane carriageway including paved shoulders & 4 lane
carriageway for this project package. Based on Engineering Surveys, Investigations,
Traffic analysis and projections the following design standards have been adopted as
per Manual of specifications and standards for 2-laning of Highways with paved
shoulder (IRC:SP:73-2015)published by IRC.
(Sanjay Gosavi)
Executive Engineer,
M.S.R.D.C, Mumbai
Sr.
Item Standards for Plain / Rolling Terraig
No
1 Design Speed Desirable 100 kmph and Minimum 80 kmph,
Mostly Proposed Alignments has been proposed
2 Land width in Open / Built-up Area
within existing ROW ( 18m to 25m)
3 Width of Carriageway 2x7m
2.50% (Bituminous)
(i) Carriageway & Paved Shoulder
2.0% (Rigid)
8. NHDP Status/IAHE: -The DPR for the Section is being done by the MSRDC which is
under progress. The MSRDC has submitted that the most of the land required is
available.
(Sanjay Gosavi)
Executive Engineer,
M.S.R.D.C, Mumbai
9. Scope of work:
Broadly the Scope of work is defined as under
A. Main carriageway -
(i) Crust Composition (Rigid Pavement) (Length=30.125 km)
Design Life-30 years
(Length - 1.275 to 31.400 km)
a. GSB 150 mm thick
b. DLC - 150 mm
c. PQC - 300 mm thick (M-40)
B. Junction Improvements -
Major Junctions - 1 Nos.
o Major junction @ km 13+000
C. Culverts
Pipe culverts - 68 Nos.
- Reconstruction - 32 Nos.
- Widening - 36 Nos.
- Retained - Nil
- Abandoned - Nil
- New Construction - Nil
(Sanjay Gosavi)
Executive Engineer,
M.S.R.D.C, Mumbai
- Reconstruction - 9
D. Bridges
Major Bridges - Nil
- Reconstruction - Nil
- Retained - Nil
F. ROB - Nil
H. Traffic Control Devices, Road Safety Work and Road Furniture as per provision of
manual have also been taken.
I. Miscellaneous Work -
The provision of slope and shoulder protection, high embankment protection, utility ducts,
RCC cover drains with footpath in built up section have also been taken.
J. Project Facilities -
The provision of project facilities in accordance to requirement of manual such as
(i) Road Boundary, km and 200 m stones
(ii) Street lighting in habitation and structure approaches.
(Sanjay Gosavi)
Executive Engineer,
M.S.R.D.C, Mumbai
(iii) Bus Shelters (9 x 2 Nos).
K. Safety and Traffic Management during Construction-
The provision of traffic management as per clause 112 of Ministry specification during
construction have also been taken in cost estimates by providing diversion of 7.00m at Bridge
reconstruction locations.
L. Utility Shifting:
As Electricity poles at some places and water supply line at few point are found in between
ROW, suitable provisions have been considered in estimate for shifting of these utilities
S. AMOUNT AMOUNT
ITEM OF WORKS
No. (Rs.) (Cr.)
1 ROAD WORKS
i BILL No. 1 - SITE CLEARANCE AND DISMANTLING 14050257.03 1.41
BILL No. 2 - EARTH WORK, EROSION CONTROL AND
ii 108047057.32 10.80
DRAINAGE
BILL No. 3 - SUB-BASES, BASES (NON- BITUMINOUS) AND
iii 145967362.99 14.60
SHOULDERS
iv BILL No. 4 - BITUMINOUS PAVEMENT 8896300.00 0.89
V BILL No. 5 - CEMENT CONCRETE ROAD 852583424.65 85.26
vi BILL No. 6 - NEW JERSEY TYPE MEDIAN 60212764.44 6.02
vii BILL No. 7 - C.C. DRAIN 206721561.37 20.67
viii BILL No. 8 - PAVER BLOCK 164036005.00 16.40
BILL No. 9 - TRAFFIC SIGNS, ROAD MARKINGS AND OTHER
ix 129088061.67 12.91
APPURTENANCES
BILL No.10 - JUNCTION IMPROVEMENT & APPROCHES
x 112554877.68 11.26
IMPROVEMENT
xi BILL No.11 - PLANTATION (HORTICULTURE) WORK 7809400.25 0.78
xii BILL No.12 - PROTECTION WORK 103970347.80 10.40
xiii BILL No.13- BUS SHELTER 4599344.00 0.46
AMOUNT - I 1918536764.20 191.85
2 CD-STRUCTURES - BIIL No. 11
i RECONSTRUCTION OF CULVERT 52,754,760.25 5.28
ii WIDENING OF CULVERT 11,733,348.00 1.17
iv RECONSTRUCTION OF MINOR BRIDGE 71,570,138.90 7.16
v WIDENING & REPAIR OF MINOR BRIDGE 79,503,916.30 7.95
AMOUNT - II 215,562,163.45 21.56
(A) COST OF CIVIL WORKS (SUB TOTAL) BASE COST 2,134,098,927.65 213.41
MODIFICATIONS & DEVIATION , IF ANY
SUB TOTAL FOR CIVIL WORKS (A) 2,134,098,928 213.41
(Sanjay Gosavi)
Executive Engineer,
M.S.R.D.C, Mumbai
S. AMOUNT AMOUNT
ITEM OF WORKS
No. (Rs.) (Cr.)
COST PER KM FOR CIVIL WORKS 70,841,458 7.08
11. Rates: The estimate is based on rates of SOR Pune Circle and same is verified by MSRDC.
Necessary Rate Analysis wherever required has been prepared and attached to the estimates.
(Sanjay Gosavi)
Executive Engineer,
M.S.R.D.C, Mumbai