QUANTITY OF CONCOURSE PRECAST BEAM AT STATION

Rev : 0, November 03, 2016


Per Nos of Precast Total Precast
Location Type Mark Width Depth Length Nos Concrete Vol C. Weight Rebar Weight Rebar-Ratio Concrete Vol C. Weight Rebar Weight
(m3) (ton) (kg) (kg/m3 Conc) (m3) (ton) (kg)

Hj.Nawi Station Precast cba03 0.900 0.550 8.250 12 4.08 9.80 1,046 256 49.01 117.61 12,549
cba03a 0.900 0.550 8.250 2 4.08 9.80 1,040 255 8.17 19.60 2,080
cba07 0.900 0.550 8.250 10 4.08 9.80 1,458 357 40.84 98.01 14,579
cba09 0.900 0.550 8.250 2 4.08 9.80 1,458 357 8.17 19.60 2,916
cba17 0.900 0.725 8.250 6 5.38 12.92 1,141 212 32.30 77.52 6,848
cba05 1.200 0.725 8.250 10 7.18 17.23 1,890 263 71.78 172.26 18,902
cba05a 1.200 0.725 8.250 2 7.18 17.23 1,890 263 14.36 34.45 3,780
cba15 1.200 0.725 8.250 2 7.18 17.23 1,935 270 14.36 34.45 3,870

Precast troughs cba01 1.200 0.725 8.100 10 2.86 6.85 1,357 475 28.55 68.53 13,575
cba01a 1.200 0.725 8.100 2 2.86 6.85 1,357 475 5.71 13.71 2,715
cba11 1.200 0.725 8.100 2 2.86 6.85 1,357 475 5.71 13.71 2,715
cba13 1.200 0.725 8.100 2 2.86 6.85 1,357 475 5.71 13.71 2,715

Blok A Station Precast cba03 0.900 0.550 8.250 12 4.08 9.80 1,046 256 49.01 117.61 12,549
cba03a 0.900 0.550 8.250 2 4.08 9.80 1,040 255 8.17 19.60 2,080
cba07 0.900 0.550 8.250 10 4.08 9.80 1,458 357 40.84 98.01 14,579
cba09 0.900 0.550 8.250 2 4.08 9.80 1,458 357 8.17 19.60 2,916
cba17 0.900 0.725 8.250 6 5.38 12.92 1,141 212 32.30 77.52 6,848
cba05 1.200 0.725 8.250 10 7.18 17.23 1,890 263 71.78 172.26 18,902
cba05a 1.200 0.725 8.250 2 7.18 17.23 1,890 263 14.36 34.45 3,780
cba15 1.200 0.725 8.250 2 7.18 17.23 1,935 270 14.36 34.45 3,870

Precast troughs cba01 1.200 0.725 8.100 10 2.86 6.85 1,357 475 28.55 68.53 13,575
cba01a 1.200 0.725 8.100 2 2.86 6.85 1,357 475 5.71 13.71 2,715
cba11 1.200 0.725 8.100 2 2.86 6.85 1,357 475 5.71 13.71 2,715
cba13 1.200 0.725 8.100 2 2.86 6.85 1,357 475 5.71 13.71 2,715

Blok M Station Precast cb01 1.200 0.725 11.750 8 10.22 24.53 2,802 274 81.78 196.27 22,415
cb03 1.200 0.725 11.750 2 10.22 24.53 2,390 234 20.45 49.07 4,779
cb07 1.200 0.725 11.750 8 10.22 24.53 2,826 276 81.78 196.27 22,607
cb09 1.200 0.725 11.750 6 10.22 24.53 2,269 222 61.34 147.20 13,616
cb13 1.200 0.725 11.750 6 10.22 24.53 2,585 253 61.34 147.20 15,512
cb15 1.200 0.725 11.750 2 10.22 24.53 2,161 211 20.45 49.07 4,323
cb19 1.200 0.725 11.750 4 10.22 24.53 2,585 253 40.89 98.14 10,341
cb21 1.200 0.725 11.750 4 10.22 24.53 2,623 257 40.89 98.14 10,493
cb23 1.200 0.725 11.750 4 10.22 24.53 2,704 264 40.89 98.14 10,815
cb27 1.200 0.725 11.750 4 10.22 24.53 2,272 222 40.89 98.14 9,088

Precast troughs cb05 1.350 1.050 11.300 2 5.34 12.81 2,813 527 10.68 25.63 5,627
cb11 1.350 1.050 11.300 2 5.34 12.81 2,533 474 10.68 25.63 5,066
cb17 1.350 1.050 11.300 8 5.34 12.81 2,533 474 42.71 102.51 20,263
cb25 1.275 1.050 11.300 2 5.21 12.51 2,302 442 10.42 25.02 4,604
cb29 1.275 1.050 9.375 1 4.32 10.38 2,073 479 4.32 10.38 2,073

Sisingamangaraja St Precast cbs03 0.900 0.550 8.250 14 4.08 9.80 1,012 248 57.17 137.21 14,172
cbs03a 0.900 0.550 8.250 2 4.08 9.80 1,012 248 8.17 19.60 2,025
cbs07 0.900 0.550 8.250 8 4.08 9.80 1,161 284 32.67 78.41 9,291
cbs09 0.900 0.550 8.250 2 4.08 9.80 1,012 248 8.17 19.60 2,025
cbs17 0.900 0.725 8.250 6 5.38 12.92 1,325 246 32.30 77.52 7,952
cbs05 1.200 0.725 8.250 10 7.18 17.23 1,808 252 71.78 172.26 18,083
cbs05a 1.200 0.725 8.250 2 7.18 17.23 1,628 227 14.36 34.45 3,256
cbs15 1.200 0.725 8.250 2 7.18 17.23 1,848 257 14.36 34.45 3,695

Precast troughs cbs01 1.200 0.725 8.100 10 2.86 6.85 1,357 475 28.55 68.53 13,575
cbs01a 1.200 0.725 8.100 2 2.86 6.85 1,357 475 5.71 13.71 2,715
cbs11 1.200 0.725 8.100 2 2.86 6.85 1,357 475 5.71 13.71 2,715
cbs13 1.200 0.725 8.100 2 2.86 6.85 1,357 475 5.71 13.71 2,715

Note : Shop Drawing of Concourse Beam at Haji Nawi Station is not available ( use Blok A Station Drawing )