You are on page 1of 2

Page: 1 of 2

Job: Block 1
Job No:
Calculation Title:
Made By: Elevate Version 6.01 Demonstration Version
Check By:
File/Date: Sebel-Block 1.elv 26 Dec 2016 08:48:36

ANALYSIS DATA
Analysis Type Up peak calculation
Measurement system Metric
Losses (%) 5.00

BUILDING DATA
Floor Name Floor Height (m)
Level 1 4.80
Level 2 3.50
Level 3 3.50
Level 4 3.50
Level 5

ELEVATOR DATA
No of Elevators 2
Capacity (kg) 800
Door Pre-opening Time (s) 0.00
Door Open Time (s) 1.50
Door Close Time (s) 2.00
Speed (m/s) 1.00
Acceleration (m/s) 0.70
Jerk (m/s) 0.90
Start Delay (s) 0.50

PASSENGER DATA
Loading Time (s) 1.20
Unloading Time (s) 1.20
Passenger Mass (kg) 70
Capacity Factor (%) 80.00
Stair Factor (%) 10.00

Floor Name No of people Area (m) Area/person


Level 2 25
Level 3 25
Level 4 22
Level 5 19
Page: 2 of 2
Job: Block 1
Job No:
Calculation Title:
Made By: Elevate Version 6.01 Demonstration Version
Check By:
File/Date: Sebel-Block 1.elv 26 Dec 2016 08:48:36

UP PEAK CALCULATION RESULTS (2 No. 800 kg elevators @ 1.00 m/s)


Main Results
Interval (s) 41.9
5 Min Handling Capacity (% population) 71.4 %

Additional Results
Car Capacity (persons) 11
Average No of Passengers in Car 8.8
Effective Building Population (persons) 88
Number of Stops (above main terminal) 3.7
Highest Reversal Floor (floors above main terminal) 3.9
Average Passenger Transfer Time (s) 1.2
Distance to Reversal Floor, Excluding Express (m) 14.9
Express Zone Distance (m) 0.0
Time Consumed When Stopping (s) 6.2
Round Trip Time (s) 83.8
Handling Capacity (persons per 5 mins) 63.0
Performance Time (s) 10.0
Single Floor Flight Time (s) 6.0
Distance for Single Floor Flight Time (s) 3.8