Professional Documents
Culture Documents
large mirror surface and then reflecting it on a much smaller one. This way we Curved mirror
Parabolic troughs
Linear Fresnel reflector
1
ROYAL DECREE 661/2007 FEED--IN TARIFF: The way it works
FEED
Total tariff
Tariffs RD 661/2007 (c€/kWh)
1. Constant Premium
Reference
Fixed Tariff Top Bottom
Group Subgroup Power Period Premium
c€/kWh c€/kWh c€/kWh Total tariff
c€/kWh 2. Premium decreases
The first 25 years 44,0381 Cap
P< 100 kW
From then 35,2305
The first 25 years 41,7500
34,39
b.1.1. 100 kW < P < 10 MW
From then 33 4000
33,4000 3 No Premium
3.
b.1.
The first 25 years 22,9764 Fixed tariff Tariff equals pool prize
10 MW < P < 50 MW Premium
From then 18,3811
The first 25 years 26,9375 25,4000 26,93
b.1.2. 34,3976 25,4038
From then 21,5498 20,3200
25,40
FIRST ASIA SOLAR ENERGY FORUM FIRST ASIA SOLAR ENERGY FORUM
Manila, 5th July, 2010 Manila, 5th July, 2010
DMM1
X 10 !!!
•The National Comission of Energy (CNE) established an information Photovoltaic Capacity Installed (MW)
system through its web page, showing in each moment and for each
technology, the total power with the definitive registration in the 3000
administrative register of installations of energy production in
special regime. 2500
•This information system shows the degree of securing of the power 2000
objectives of Renewable Energy Plan 2005-2010: 371 MW for
1500
photovoltaic and 500 MW for thermoelectric, the monthly evolution, as
85% of the objective
well as the estimated time to achieve the aim. 1000
REP objective
• Once it is reached 85 per cent of the aim of power for a group or 500
subgroup, it is established the period, not lower than 12 months,
during which those installations that are registered in the 0
administrative register of installations of production in special September 2007 September 2008
regime will have right to the premium or fixed tariff.
2
Slide 9
DMM1 Encabezados
Daniel Morales Muñoz, 6/20/2007
Royal Decree-Law 6/2009: Conditions to enter
Other Renewables
the Pre-assignment Register
• In order to support the sustainable growth of • Have grid access and connection point for the facility’s rated
the rest of the renewable energies, the capacity
Government approved in 2009 Royal Decree‐ • Have government permits and building licenses
Law 6/2009: • Have own economic resources or sufficient financing to
– Establishes a register called pre‐assignment register undertake at least 50% of the facility investment
for all technologies except for photovoltaic
for all technologies except for photovoltaic. • Have reached a purchasing agreement signed by the
Have reached a purchasing agreement signed by the
– To get the feed‐in tariff it is necessary to be included promoter and equipment manufacturers for an amount equal
in the pre‐assignment register. to at least 50% of the total value of the installation as listed in
– Main aims: the project.
• Legal security for investors. • Have received a favorable report on use of water from the
• Sustained growth of the different technologies. competent authority
• Higher efficiency by gradually adjusting the premiums. • Have deposited a 100€/kW bank guarantee in the AGE
Government Depository.
13 14
2.500 2.471
ACUMULADO
CUMULATIVE (MW)
(MW)
ANNUAL
ANUAL(MW)
(MW) 2.028
• 338 projects (9.050,8 MW) have been registered under the 2.000
new system:
15 SOURCE: IDAE 16
3
First Power Tower in Spain: PS10
A supporting factor: the PLATAFORMA SOLAR DE ALMERÍA
Steam Turbine
PSA is one of the biggest and most complete existing facilities to the 11.0MWe
40 bar, 250ºC
≈
research, testing and development of solar technologies and applications Solar receiver Steam
»
Drum
SATURATED STEAM
•Conservative
approach
•Limited capacity Steam Storage System
factor
Condenser
0,06 bar, 50ºC
Heliostat Field
FIRST ASIA SOLAR ENERGY FORUM FIRST ASIA SOLAR ENERGY FORUM
Manila, 5th July, 2010 Manila, 5th July, 2010
PS 10
Experimental area PS20: Inaugurated on 23 September 2009
PS20
PS 20
FIRST ASIA SOLAR ENERGY FORUM FIRST ASIA SOLAR ENERGY FORUM
Manila, 5th July, 2010 Manila, 5th July, 2010
PROTERMO
S LAR ACS--COBRA STATUS
ACS
Cobra is building three plants and has the objective to operate eight CSP plants
with a total capacity of 400 MW within five years
ANDALUCIA EXTREMADURA
ANDASOL-1 EXTRESOL-1
ANDASOL-2 EXTRESOL-2
manchasol-1,2
manchasol 12 ANDASOL-4
ANDASOL 4 EXTRESOL-3
EXTRESOL 3
ANDASOL-3
extresol1,2,3
ANDASOL-5 CASTILLA-LA MANCHA
ANDASOL-6
ANDASOL-7 MANCHASOL-1
MANCHASOL-2
andasol-1,2,3,4,5,6,7
4
PROTERMO
ACS--COBRA STATUS
ACS S LAR
ANDASOL-1: In operation
ANDASOL-2: Commissioning
EXTRESOL-1: Inaugurated
EXTRESOL-2: in construction
MANCHASOL-1: in construction
(228
228 M€
M€)
EXTRESOL-1 plant
in Torre de Miguel
Sesmero (Badajoz)
PROTERMO
EXTRESOL 1
Slide 27
- 24 February, 2010
FIRST ASIA SOLAR ENERGY FORUM FIRST ASIA SOLAR ENERGY FORUM
Manila, 5th July, 2010 Manila, 5th July, 2010
5
ACS--COBRA STATUS
ACS ACCIONA STATUS
FIRST ASIA SOLAR ENERGY FORUM FIRST ASIA SOLAR ENERGY FORUM
Manila, 5th July, 2010 Manila, 5th July, 2010
PROTERMO
First hit in the US !! New CSP Plant after SEGS IX in 1991 S LAR
NEVADA SOLAR ONE, property of ACCIONA Solar
•64 Mwe
•El Dorado Valley,
Boulder City (NV)
• Thermal Oil
• No thermal storage
• June 2007
• 250 MUS$
La Risca / Alvarado
FIRST ASIA SOLAR ENERGY FORUM
Manila, 5th July, 2010
FIRST ASIA SOLAR ENERGY FORUM FIRST ASIA SOLAR ENERGY FORUM
Manila, 5th July, 2010 Manila, 5th July, 2010
6
PROTERMO
IBERDROLA STATUS (IBERSOL PLANT) …but not only PTC plants are under construction !!!!! S LAR
Collector type:
Inaugurated on 8th May, 2009 EUROTROUGH
Novatec-Biosol: Puerto Errado 1
FIRST ASIA SOLAR ENERGY FORUM
Manila, 5th July, 2010
PROTERMO
S LAR TORRESOL ENERGY (GEMASOLAR)
Heat Storage
System
Heliostats
(Concentrating system) Steam
Generator
Conventional Electricity
Generator
FIRST ASIA SOLAR ENERGY FORUM FIRST ASIA SOLAR ENERGY FORUM
Manila, 5th July, 2010 Manila, 5th July, 2010
7
TORRESOL ENERGY (GEMASOLAR) TORRESOL ENERGY (GEMASOLAR)
FIRST ASIA SOLAR ENERGY FORUM FIRST ASIA SOLAR ENERGY FORUM
Manila, 5th July, 2010 Manila, 5th July, 2010
Conclusions
• The future Spanish regulation, under negotiation
nowadays, will continue its support to
renewable energies based in five pillars:
1. Promote a sustainable development of the
different technologies to achieve the renewable
energy targets for 2020 (around 40% of electricity
energy targets for 2020 (around 40% of electricity
production). Th k ffor your attention
Thanks tt ti !!
2. Enhance technology development by adjusting
gradually the premiums.
3. Guarantee the necessary legal security for investors.
4. Simplify procedures for small installations (roofs).
5. Foster self‐consumption.
45 46