Chapter 7 - Capital Cost Estimation

Chemical Engineering Department


West Virginia University

Copyright - R.Turton and J.


Shaeiwitz 2008 1
Outline
Types of estimate
Adjusting costs for changes in capacity
Adjusting costs for changes in time
Total plant cost estimates
Direct, indirect, etc.
Lang Factors
Module cost approach
Effect of temperature and pressure
Capcost program
Copyright - R.Turton and J.
Shaeiwitz 2008 2
Types of Capital Cost Estimate
1. Order of Magnitude Estimate (Feasibility)
+ 40%, - 20%
BFD , Process Modification
2. Study Estimate / Major Equipment
+ 30%, - 20%
PFD , Cost Chart

Copyright - R.Turton and J.


Shaeiwitz 2008 3
Types of Capital Cost Estimate (contd)

3. Preliminary Design (Scope) Estimate


+ 25%, - 15%
PFD , vessel sketches , equip. diagrams
4. Definitive (Project Control) Estimate
+ 15%, - 7%
PFD , P&ID, all vessel sketches, equip. diagrams,
preliminary isometrics

Copyright - R.Turton and J.


Shaeiwitz 2008 4
Types of Capital Cost Estimates (contd)

Detailed (Firm or Contractors) Estimate


+ 6%, - 4%
Everything included ready to go to construction
phase
Estimate low so actual cost will be high (+)
Estimate high so actual cost will be low (-)

Why is + # > - #.?


Copyright - R.Turton and J.
Shaeiwitz 2008 5
Cost of Estimate See Also Table 7.2

Accuracy
1
2
3
4
5

Cost of Estimate (Time)


Copyright - R.Turton and J.
Shaeiwitz 2008 6
Estimating Purchased Equipment
Costs
Vendor quote
Most accurate
- based on specific information
- requires significant engineering
Use previous cost on similar equipment and scale for
time and size
Reasonably accurate
- beware of large extrapolation
- beware of foreign currency
Use cost estimating charts and scale for time
Less accurate
Convenient
Copyright - R.Turton and J.
Shaeiwitz 2008 7
Effect of Size (Capacity)
n
Ca Aa
(7.1)
Cb Ab Cost Exponent

Cost Equipment Cost


Attribute - Size

C a KA a n
(7.2)

where K
Cb
Ab n Copyright - R.Turton and J.
Shaeiwitz 2008 8
Effect of Size (Capacity) cont.
n = 0.4 0.8 Typically
Often n ~ 0.6 and we refer to Eq.(7.1)
as the (6/10)s Rule
Assume all equipment have n = 0.6 in a
process unit and scale-up using this
method for whole processes
Order-of-Magnitude estimate

Copyright - R.Turton and J.


Shaeiwitz 2008 9
Example 1
A New Plant Ordered a Set of
Floating Head Heat Exchangers
(Area = 100 m2) cost $92,000. What
Would Cost be for a Heat Exchanger
for Similar Service if Area = 50 m2
and n = 0.44 ?

Copyright - R.Turton and J.


Shaeiwitz 2008 10
Example 1 - Solution
n
Aa
n
C a Aa
Ca Cb
C b Ab Ab
0.44
50 Ca $67, 300
92 ,000
100
100 m2 Exchanger is not twice as expensive as a 50 m2 exchanger

Economy of Scale
Copyright - R.Turton and J.
Shaeiwitz 2008 11
Effect of Time
Time increases cost increases (inflation)
Inflation is measured by cost indexes - Figure
7.3
Chemical Engineering Plant Cost Index (CEPCI)
Marshall and Swift Process Industry Index
Numbers based on basket of goods typical
for construction of chemical plants - Table 7.5

Copyright - R.Turton and J.


Shaeiwitz 2008 12
Copyright - R.Turton and J.
Shaeiwitz 2008 13
Table 7.5: The Basis for the Chemical Engineering Plant Cost Index

Components of Index Weighting of Component (%)

Equipment, Machinery and Supports:

(a) Fabricated Equipment 37


(b) Process Machinery 14
(c) Pipe, Valves, and Fittings 20
(d) Process Instruments and Controls 7
(e) Pumps and Compressors 7
(f) Electrical Equipment and Materials 5
(g) Structural Supports, Insulation, and 10
Paint 100 61% of total
Erection and Installation Labor 22

Buildings, Materials, and Labor 7

Engineering and Supervision 10

Total 100
Copyright - R.Turton and J.
Shaeiwitz 2008 14
Equation for Time Effect
I2
C2 C1
I1
C = Cost
I = Value of cost index
1,2 = Represents points in time at
which costs required or known and
index values known
Copyright - R.Turton and J.
Shaeiwitz 2008 15
Example 2
Cost of vessel in 1993 was 25,000,
what is estimated cost today (Sept 2007
CEPCI = 500)?

Copyright - R.Turton and J.


Shaeiwitz 2008 16
Example 2 - Solution

I now 500
C now C1993 25 ,000 $34 ,820
I1993 359

Copyright - R.Turton and J.


Shaeiwitz 2008 17
Example 3 - Accounting for Time
and Size
2 heat exchangers, 1 bought in 1990
and the other in 1995 for the same
service
A B
Area = 70 m2 130 m2
Time= 1990 1995
Cost = 17 K 24 K
I = 358 381
Copyright - R.Turton and J.
Shaeiwitz 2008 18
Example 3 (contd)
What is the Cost of a 80 m2 Heat
Exchanger Today ? (I = 500)

Copyright - R.Turton and J.


Shaeiwitz 2008 19
Example 3 - Solution

Must First Bring Costs to a Common


Time 500
Ca (2007) 17 $23, 743
A = 70 358

500
Cb (2007) 24 $31, 496
A = 130 381

Copyright - R.Turton and J.


Shaeiwitz 2008 20
Example 3 - Solution (contd)
C KA n

$23, 743 K (70) n

$31, 496 K (130) n


log 31, 496 log(23, 743)
n 0.4565
log 130 log(70)
C 23, 743
K n
0.4565
$3, 414
A 70
C 3, 414 80
0.4565
$25, 235
Copyright - R.Turton and J.
Shaeiwitz 2008 21
Example 4
Date Vessel Purchased Cost Exchange
Capacity (pounds sterling = ) Rate
(m3)
1993 75 7,800 $ 1.40/
1998 155 13,800 $ 1.65/
2007 120 $ 2.00/

How much ($) would the new vessel cost?


Copyright - R.Turton and J.
Shaeiwitz 2008 22
Total Cost of Plant
Purchased cost equipment f.o.b.
Installed cost Often 3 to 8 times
larger than purchased cost

Copyright - R.Turton and J.


Shaeiwitz 2008 23
Installed Cost of Equipment (Table 7.6)
1. Direct Project Expenses
Equipment
Material for installation
Labor for installation

2. Indirect Project Expenses


Freight, insurance, and taxes
Construction overhead
Contractor engineering expenses

Copyright - R.Turton and J.


Shaeiwitz 2008 24
Installed Cost of Equipment Table 7.6 (contd)

Contingency and Fee


Contingency
Contractor fee

Auxiliary Facilities
Site development
Auxiliary buildings
Off-sites and utilities

Copyright - R.Turton and J.


Shaeiwitz 2008 25
Lang Factors
Table 7.7
Use multiplier depending on type of plant to
escalate equipment costs to installed costs
Flang = 4.74 Fluid processing plant
= 3.63 Solid-Fluid processing plant
= 3.10 Solid processing plant

Copyright - R.Turton and J.


Shaeiwitz 2008 26
Lang Factors (contd)
n
C TM FLang C pi
i 1

Total Module Cost Purchased Cost of Major Equipment


From Preliminary PFD
(Pumps, Compressors, vessels, etc.)

Copyright - R.Turton and J.


Shaeiwitz 2008 27
Module Factor Approach

Table 7.8
Direct, Indirect, Contingency and Fees are
expressed as functions (multipliers) of purchased
equipment cost C op at base conditions (1 bar and
CS)
Each equipment type has different multipliers
Details given in Appendix A

Copyright - R.Turton and J.


Shaeiwitz 2008 28
Module Factor Approach
C BM o
C p FBM Bare Module Factor
(sum of all multipliers)

Bare Module Purchased Equipment Cost for CS


Cost and 1 atm pressure - Appendix A

FBM = B1 + B2FpFM
o
FBM B1 B2

Fp = pressure factor (= 1 for 1 bar)


FM = material of construction factor (=1 for CS)

C p C op Fp FM
Copyright - R.Turton and J.
Shaeiwitz 2008 29
Module Factor Approach Pressure Factors

Figure 7.6 Pressure Factors for Carbon Steel Vessels


Copyright - R.Turton and J.
Shaeiwitz 2008 30
Module Factor Approach Pressure Factors

Copyright - R.Turton and J.


Shaeiwitz 2008 31
Illustrative Example
Compare Costs for
1. Shell-and-tube heat exchanger in
2001 with an area = 100 m2 for
Carbon Steel at 1 bar
Carbon Steel at 100 bar
Stainless Steel at 1 bar
Stainless Steel at 100 bar

Copyright - R.Turton and J.


Shaeiwitz 2008 32
Effect of Materials of Construction
and Pressure on Bare Module Cost
P MOC C op Cp o
C BM CBM

1 bar CS 25 K 25 K 82.3 K 82.3 K

1 bar SS 25 K 68.3 K 82.3 K 154 K

100 bar CS 25 K 34.6 K 82.3 K 98.1 K

100 bar SS 25 K 94.4 K 82.3 K 197.4 K


Copyright - R.Turton and J.
Shaeiwitz 2008 33
Bare-Module and Total-Module
Costs
BM Previously Covered
TM Includes Contingency and Fees at
15% and 3% of BM

CTM 1.18 C BM
all equip

Copyright - R.Turton and J.


Shaeiwitz 2008 34
Grass-Roots Costs
GR grass-roots cost includes costs for
auxiliary facilities

CGR 0.50 o
C BM CTM
all equip

Use base BM costs in GR cost (1 atm


and CS) since auxiliary facilities should
not depend on pressure or M.O.C.
Copyright - R.Turton and J.
Shaeiwitz 2008 35
Materials of Construction
Very important
Table 9.9 rough guide
Perrys good source

Copyright - R.Turton and J.


Shaeiwitz 2008 36
Capcost
Calculates costs based on input
CEPCI use current value of 500 or
latest from Chemical Engineering
Program automatically assigns
equipment numbers

Copyright - R.Turton and J.


Shaeiwitz 2008 37
Capcost

Copyright - R.Turton and J.


Shaeiwitz 2008 38
Copyright - R.Turton and J.
Shaeiwitz 2008 39
Copyright - R.Turton and J.
Shaeiwitz 2008 40
Copyright - R.Turton and J.
Shaeiwitz 2008 41
Summary

In general, information about costs must be scaled


for capacity and time using appropriate cost
exponents and indices
Total plant costs involve a variety of factors that vary
with equipment type, operating pressure, and
materials of construction.
For additions to existing facilities, the total module
cost should be used but for totally new projects grass
roots costs are appropriate.

Copyright - R.Turton and J.


Shaeiwitz 2008 42