1.

With the rates of works given below, prepare the abstract estimate for the items of work

Item Rate Per Unit Quantity

1. Earth work excavation Rs. 590/- 10m3 550.0 Cum

2. C.C bed in the foundation Rs. 3,500/- 1m3 55.0 Cum


3. R.R masonry in C.M. (1:6) Rs. 3,050/- 1m3 32.0 Cum

4. Brick Masonry with CM(1:5) Rs. 2050/- 1 Cum 255.0 Cum

5. Plastering in C.M. (1:6) 12 mm thick Rs. 680/- 10m2 1255.0 Sqm

6. Tiles Flooring Rs. 255/- 1 Sqm 1150.0 Sqm

7. Doors Rs 10500/- 1 No 4 Nos

8. Windows Rs. 4500/- 1 No 10 Nos

Note: Add building services as lumpsums in terms of percentages of total cost of building.
2. Prepare the Abstract estimate for the following items for the given drawing:

1. Earth work excavation


2. P C C Bed
3. Brick work for footings, basement and super structure wall
4. Sand filling
5. Platering inside and out side separatly
6. Flooring
7. RCC Items for lintels ( Size 300mm x 300mm) and slab ( Th. 125mm)

Note: Assume suitable specifications, if any data missing and take Super structure wall thickness is 300mm.