Professional Documents
Culture Documents
ADOPTION OF THE
AMENDMENTS TO RESOLUTION
NO. 10, SERIES OF 2012,
ENTITLED "A RESOLUTION
APPROVING THE FEED-IN
TARIFF (FIT) RATES" (FIT
RULES),. PARTICULARLY FOR
WIND. FIT RATES, AS
NECESSITATED BY THE REVIEW
AND RE-ADJUSTMENT OF THE
WIND FIT SINCE THE
INSTALLATION TARGET FOR
WIND TECHNOLOGY HAS
ALREADY BEEN ACHIEVED
DECISION
Nameplate
No. of
Name of Plant Location Rating
Units (MW)
LUZON GRID
1. EDC Burgos Wind Burgos,
50WTG 150
PQwer Corp. . , lIocos Norte
2. Northwind Power Bangui,
Development 6WTG 18.9
lIocos Norte
Corporation (Phase 3)
3. North Luzon
Renewable Energy Pagudpud,
27WTG 81
Corp. (Caparispisan lIocos Norte
Wind Farm Project)
4. Alternergy Wind One 54
27WTG Pililla, Rizal
Corp.
VISAYAS GRID
5. Trans Asia Renewable
Energy Corp. (San San Lorenzo,
27WTG 54
Lorenzo Wind Farm Guimaras
Project)
6. Petrowind Energy, Inc.
Nabas and
(Nabas Phase 1 Wind 18 WTG 36
Malay, Aklan
Project)
TOTAL
. 393.9
y
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 4 of 31
been certified by the DOE as eligible for the first round of FIT
implementation.
In the said letter, NREB averred that in computing for the WIND
FIT2, it adopted several common assumptions under the second FIT
rate for solar (SOLAR FIT2) approved by the Commission on April 28,
2015.
y
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 5 of 31
DISCUSSION
Capacity
RE Developer RE Plant Location
(MW)
Luzon Grid
EDC Burgos Wind Burgos Wind Power Burgos,
150
Power Corporation Project (Phase 1 & 2) lIocos Norte
Northwind Power
Bangui Wind Power Bangui,
Development 18.9
Project (Phase 3) lIocos Norte
Corporation
Northern Luzon UPC Caparispisan Wind Pagudpud,
81
Asia Corporation Energy Project lIocos Norte
Alternergy Wind One Pililla Wind Power
Pililla, Rizal 54
Corporation (AWOC) Project
Visayas Grid
Trans-Asia Renewable
San Lorenzo Wind San Lorenzo,
Energy Corporation 54
Power Project Guimaras
(TAREC)
Petro Wind Energy, Inc. Nabas Wind Energy Nabas and
36
(PWEI) Project Malay, Aklan
2Pursuant to NREB's Resolution No.4, Series of 2015, entitled "Resolution to Recommend Adoption of
Feed-In Tariff for the Second Batch of Wind Power Plants (WIND FIT2)" dated June 10, 2015 ~
r
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 9 of 31
3ERC Case No. 2014-004 RM, entitled "In the Matter of the Adoption of the Amendments to Resolution No.
10. Series of 2012. A Resolution Approving the Feed-In Tariff (Fin Rates, As Necessitated by the New
Installation Target for s~ergy Generation set by the Department of Energy (DOE)", Decision dated
March 27, 2015. /1/
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 10 of 31
. ';'
Commission . NREB-
Item -Approved .P.r6posed Remarks
WIND FIT 1 WIND FIT 2
Due to lower
Total Project Cost ($OOO/MW) 2,492 2,462
interest rate
Commission NREB.
Item -Approved Proposed Remarks
WIND FIT 1 WIND FIT2
Based on CAPM
',' 'J
formula updated as
of 2013 reflecting
project risk when
Equity IRR 16.44% 14.71% FIT2 eligible
projects committed
or started
construction
activities.
Due mainly to
lower Equity IRR
Feed-In-Tariff (PhP/kWh) 8.5300 7.9300 and lower interest
rate
4ERC
51bid
d
/1
Case No. 2011-006 RM, Decision dated July 27,2012
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 13 of 31
-
100m
'Om
''''''_;;1i I~"
1QCln
TI:r r.~.-.....
1QQol:. ~ '--'---~
n
2010 ~:;;;;:;J Source: Btoomberg New EMrgy
n
Finance
!!!~~g I I I I I I
6Based on the Generation Company Management Report (GCMR) submitted by Northwind in compliance
with the terms and conditions of its COC
7The Global Wind Energy Outlook Scenarios 2010. page 8
http://www.gwec.netlfileadmin/documents/Publications/GWEOo/o20201O%20final.pdf
8 Amy Grace, BNEF University, AprilS. 2012
http://www.bnef.com/free-publications/presentations/BNEF delivers the analysis, data and news for its
.,"" to ,"=,,"11, "",,,.Ie d'" ""9Y,,' ~,~ '" m.~,".~
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 14 of 31
Wind
RE Turbine IEC Hub Rotor
COD Capacity 10 swept
Developer Type Class Height Diameter
Area
June
Vestas 5,821 sq.
Northwind 20, 1.65 MW II-A 70m 82m
V82 m
2005
Siemens
Thai End of 8,000 sq.
SWT-2.3- 2.3MW 111-8 80m 101 m
Project12 2012 m
101
9ERC Case No. 2011-060 RC entitled "In the Matter of the Adoption of the Feed-In Tariff (FIT) Pursuant to
the Feed-In Tariff Rules Specific to the Existing Renewable Energy Plants, With Prayer for Provisional
Authority, Northwind Power Development Corporation (NORTHWIND), Applicant"
10 Turbine Class: I - High Wind; II - Medium Wind; III - Low Windl Turbulence: A - High; B - Low
A leading international engineering consultancy commissioned by WEDAP for a wind farm cost study in Sept. 2010
suggested that Class I WTG is the suitable type of turbines for sites with extreme wind speeds (mostly across
outer northern Luzon). It also noted that only one of the planned wind power projects can be considered a Class II
site based on a desktop study (Annex "G-3-d" of NREB Petition). According to a report published Nov.1, 2011,
General Electric (GE) "has pulled out of a number of opportunities in the Philippines where the company was not
confident its equipment would survive an extreme storm, while competitors have used their usual machines."
("Turbine Makers Ponder Risk and Reward in Asia-Pacific Wind", RECHARGE,
www.rechargenews.com/energylwind/article286217.ece). The report quoted GE's Asia-Pacific sales manager,
Peter Cowling, saying: "The islands have very good average wind speeds, but very nasty extremes, which are not
to be taken lightly."
11 Quotation dated Jan 18,2011 attached as Annex "G-3-b" of NREB's Petition docketed as ERC Case No. 2011-
006 RM
12207 MW wind power plant in Northeastern Thailand,
_.,;.m'",.rom"re'~."","",rel ,.n"""~/."",re",rel."",~0121eo.",,Iw;"d.powe"~P20120203~
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 15 of 31
Average
RE Developer RE Plant Capacity Period NCF13
The above tables show the actual capacity factors of the new
wind power plants during their initial operations, which lie between
14.81% and 32.27%.
13
romm."ood ~m;,,;o"t"' 0" tho mlddl. of tho mo"", '"' oom' t" tho "" ~.k
The first month of operations of the new power plants were excluded in computing for the capacity factor,
as they are assumed to be on commissioning phase and does not represent a full month operations (new
~~~t~'""
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 16 of 31
;FKWRl' A .12: CM'Af:;1f'f fAf:;TORS IIY moJECf mo MlGH'lEO AVf!!ACE$ fOR COt.t14$:S1ONED .NO I'IlOPOSW \WolD FAIlM$.
201Q.2014
Capacity factor
o \00
141RENAreport entitled "Renewable Power Generation Cost in 2014" published in January 2015
1~he International Renewable Energy Agency (IRENA) is an intergovernmental organisation that supports
countries in their transition to a sustainable energy future, and serves as the principal platform for international
co-operation, a centre of excellence, and a repository of policy, technology, resource and financial knowledge
on renewable energy. IRENA promotes the widespread adoption and sustainable use of all forms of renewable
energy, including bioenergy, geothermal, hydropower, ocean, solar and wind energy, in the pursuit of
sustainable development, energy access, energy security and low-carbon economic growth and prosperiY
~~ ~
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 17 of 31
Country .
;.',
~.:'}~"~/~
,.;iJq~jcF(%)
';1- ":," ", .',
Commission-
Actual EPC Difference
Capacity Approved EPC
RE Plant Cost (US$OOO/MW)
(MW) Cost
(US$/MW)
(US$OOO/MW)
San Lorenzo Wind 1,714
54
Power Project
Nabas Wind Energy 2,177
36
Project
Pillilla Wind Power 1,928
54
Project
Weighted Average EPC Cost 1,910 1,836 74
16
17
All of Asia excluding China and India
Page 33" IRENA report entitled "Renewable Power Generation Cost in 2014" published in January 201Y f
~
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 18 of 31
2010.2014
2010 2013 2014 ("0lAKGE)
NI."II'CUACm
AIlOfTIOIIS (GW)
._ .
ClIMULA11V! IImAWD
c.wcm(GW)
:.--~-~~~-.~- ..
_ . -~II ~ffi.!P~." fJeEP ~ ~W:> .~' ... ~..~ .....
- ..
!
I
I"
.
t
~ 002!) 00El OO!!) ~ ~ <W3 ~
..._111------' -- .- .
Noles: 2014 ~t data llI'C es:imates. n.a. = dala ~s ,not evaa.,bIc or not ~h dala 10 prclYIdc a robust estimlllc. Offshorc
I'oindcost ~ ere fOtll~ prOJects,Onshore wind cost rengcs are tOl regioneI teighted ~.
It can be gleaned from the above figure, that the reported global
average wind plant installed cost during 2013 ranges from a low of
US$1 ,340/kW and a maximum of US$2,330/kW.
NREB
Cost Component ERC Difference
Proposal
EPC Cost (US$/kW) 1,836 1,730 106
Total Plant Installed Cost
2,462 2,330 132
(US$/kW)
WIND FIT (PhP/kWh) 7.9300 7.4000 0.5300
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 19 of 31
rf + Setae x MRP
Where:
Particulars Values
Market Risk Premium 10.13%
Multiply by Relevered beta 1.03
Equals 10.43%
Plus Risk free rate 6.01%
Cost of Equity 16.44%
19Such
others. f
as ERC Case No. 2013-205 RC, ERC Case. No. 2014-129 RC, ERC Case No. 2014-102 RC, amon~
/
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015 .
Page 20 of 31
Date of Commercial
Capacity
RE Developer 'il RE Plant Conver- Operations
(IViWf'
sion Date
Total 249.9
To reflect the risk and fair price for their investment, the
Commission deems it appropriate to recalculate the cost of equity
using 2013 parameters/estimates since said updated data represent
the prevailing economic situation at the time the investment decision
was made.
Particulars Values
Market Risk Premium 9.40%
Multiply by Re-Ievered beta 1.03
Equals 9.68%
Plus Risk free rate 5.03%
Cost of Equity 14.71%
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 21 of 31
2013 PDST-F
January 5.6835%
February 5.0829%
March 4.5899%
April 4.0457%
May 4.1842%
June 5.3932%
July 5.3077%
August 5.0313%
September 5.4529%
October 5.3234%
November 4.9149%
December 5.3818%
Particulars Values
Market Risk Premium 9.40%
Multiply by Re-Ievered beta 1.03
Equals 9.68%
Plus Risk free rate 5.03%
Cost of Eq u ity 14.71%
TABLE 1.1: ASSUMPTIONS FOR THE CALCULATION OF THE LMUSED COST OF EtECTRICITY NOT 0Il1VED fROM PROJECT DATA
i Wind power 25
l_
: Solar PV 25
~ + ~ .__._. ._...~i
25
7.5'f, 10'f,
Hydropower
"
Geothermal 25 ,
Ie
Price
Particulars
In PhP In US$23
20/25 MVA, Power Transformer, Off-
18,800,000.00 423,518.81
load, 67/13.2 KV
Substation Steel Structures 800,000.00 .18,066.85
69KV Protection and Metering Equipment 5,965,000.00 134,377.11
15KV Protection Equipment 5,055,000.00 113,877.00
69KV/15KV METERING, Control and
1,800,000.00 40,549.67
Protection Panel
Station Battery, Battery Charger 670,000.00 15,093.49
Service Station Distribution Transformer 93,854.00 2,114.31
15KV Power Cable and Termination Kit 527,000.00 11,872.04
Civil And other Electrical Works 4,950,000.00 111,511.60
Total 38,660,854.00 870,936.11
The NEA Equipment and Materials Price Index along with other
Price Benchmark serves as a tool in the Commission's evaluation of
Capital Expenditures Projects applications.
22
1bid
) ~At2014
~mg' 10m,of PhP44.3QIU/{
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 24 of 31
FIGURE 4.15: FIlll-SERVtCE O&M PRICING 2008-2013 VS. WEIGHTED AVERAGE O&M REVENUES OF nvo MANUFAClUllERS
2014 USDIkWlyear
50
39 _
30
20
- 8NEF OIloM prla!
index
o Weighted average
-~::>~)-
23
25
"'V"',,,,,,
(2 mmulactu""'l
10
o I
, I I I I
It can be gleaned from the above figure that the BNEF reported
2013 level of Full-service O&M contract cost of US$28/kw per year or
US$840,000.00 is still lower than the adjusted US$1,200,000.00
annual O&M cost.
24
25
IRENA report entitled "Renewable
Ibid
Power Generation Cost in 2014"
published in January
/'1
2015 ~
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 25 of 31
NREB ERC
Component
US$/year US$/kWh US$/year US$/kWh
O&M Cost 1,500,000 0.0208 1,200,000 0.0166
. , .,
Spare parts, Tools,
750,000 0.0104 750,000 0.0104
& Equipment
General and
600,000 0.0083 600,000 0.0083
Administrative Cost
Total 0 & M 2,850,000 0.0394 2,550,000 0.0353
IRENA
Component ERC US
Min Max
EDP Renovaveis
Infigen US$/kWh US$/kWh
(EDPR)
supplies and services
Turbine O&M 0.0118 0.0142
(includes O&M costs)
Balance-of-plant 0.0028 personnel costs 0.0036
Asset management Other operating costs
0.0049 (mainly includes
and administration 0.0035
operating taxes, leases,
Other direct costs 0.0057 and rents)
Total 0 & M Cost 0.025229 0.0213
26
lbid
27 According to IRENA an average value of around USD 0.02 to USD 0.03/kWh would appear to be the norm,
but more systematic data collection is required to confirm these values.
282014 Wind Technologies Market Report dated August 2015, The report authored by Ryan Wiser and Mark
r
Bolinger of the Lawrence Berkeley National Laboratory is being disseminated by the U.S. Department of
Energy (DOE)
29 Infigen's total operating expenses may be higher than indicated here, given that reported costs .~~ no/
include certain capital expenditures related to the replacement of turbines and/or turbine component/"
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 26 of 31
Aust: I"af I.Dol. Dr A:UDUSO 0.77 0.75 O.?ll 0.7'1 0.70 0"'0
NeVlll'ZOatand NZOUSO 0.74 0.74 ,0.71 0.G8 0.67 0.66
fEN!
Ik'aZIllan
L.-t...-
Sc:Krth A'frI-c.1In
IReal
iAand USDZAR
USOBRL
12.04
3.06
c=__
._11.81
3.10
11.92
3.08
12.0-4
1l.OG
12.:1.2
3.05
12.16
3.,04
I ,
fIW'IIe:lidc:
Peso USONlXN 15.50 15.0 14.'9 14.8 14.7 ]:.4.5
3ODeveiopment Budget Coordination Committee (DBCC), 2015 Budget Briefer, Congressional pOlic:::vand
Budget Research Department ~ /
31 ERC Case No. 2014-004 RM, Decision dated March 27, 2015 ZJ
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 27 of 31
in order given that the WIND FIT2 would likely apply to the second
batch of FIT-eligible wind power projects that have commenced
commercial operations late 2014 and mid-2015, to wit:
Commercial
RE Developer RE Plant Location Operations Date
Trans-Asia Renewable San
San LorenzoWind December 27,
Energy Corporation Lorenzo,
Power Project 2014
(TAREC) Guimaras
AlternergyWind One PilillaWind Power
Pililla, Rizal June 9, 2015
Corporation(AWOC) Project
PetroWind Energy, Inc. NabasWind Nabas and
June 10, 2015
(PWEI) Energy Project Malay, Aklan
Considering that the WIND FIT2 will likely apply to the 2nd batch
of FIT eligible wind power projects whose FIT entitlement generally
commenced in 2015,36 the Commission updated the base local CPI
from the PhP160.00 2009 original level to PhP138.91. The
PhP138.91 is the average CPI during 2014 and consistent with the
Commission's approval under ERC Case No. 2014-004 RM.
32The policy target is set by the Development Budget Coordination Committee (DBCC) in consultation with
the BSP. The DBCC. created under Executive Order (E.O.) No. 232 dated 14 May 1970, is an inter-
agency committee tasked primarily to formulate the National Government's fiscal program. It is composed
of the Office of the President (OP), Department of Budget and Management (DBM), National Economic
and Development Authority (NEDA), and the Department of Finance (DOF). The BSP attends the
Committee meetings as a resource agency
33BSP Inflation Report 2nd Quarter 2015
~he inflation target range for 2015-2018 was announced thru DBCC Resolution No.2015-1 dated 27
January 2015
35NEDA, Philippine Medium Term Development Plan 2011-2016
36AlthoughTAREC's San Lorenzo Wind Power Project was commissioned on December 27,2014, the same~/
falls within the January 2015 billing month
?;!
rfl
ERC CASE NO. 2015-002 RM
DECISION/October 06, 2015
Page 28 of 31
NREB Difference
ERC WIND
Particulars PROPOSED Increase/
FIT2
WIND FIT2 (decrease)
Commercial
Capacity
RE Developer RE Plant Operations
(MW)
Date
WIND FIT2 Eligible Wind Projects
Trans-Asia San Lorenzo
Renewable Energy Wind Power 54 12/27/2014
Corporation Project
Petro Wind Energy, Nabas Wind
36 6/10/2015
Inc. Energy Project
Total 144.00
As for the FIT that will apply to whoever will take up the remaining 6.1
MW of the total WIND installation target, the Commission shall fix the
same at a later time.
SO ORDERED.
L~'~'~_Af~
GLpRIA VICTORIAlf.'VAP-TARUC
Commissioner
JOSEFIN~ICIA A. MAGPALE-ASIRIT
commissli~t~TR
Copy Furnished:
'1
Counsel for Alternergy Wind One Corporation (AWOC)
Unit 1912 Jollibee Plaza Building, F. Ortigas Jr. Road,
Ortigas Center, Pasig