”
TOP - DOWN CONSTRUCTION FOR DEEP BASEMENTS
by
V. S. Samathar
Abstract
“The top-down method is a method for construction of
deep basements, given in the BS: 8002 code of practice
for retaining structures. It was adopted in early 60's and
now itis used in various countriesas and when required
by site conditions
Unlike in traditional method, in the top-down method,
first the perimeter wall is constructed and usually the
piled foundation and columns are laid from the ground
level. The ground floor slab is laid and excavation for
basements carried out through openings left in the slab.
Construction of basements and super structure can be
done simultaneously.
In this paper the top-down method is discussed first.
Variations in the top-down method, and theadvantages
and disadvantages compared with traditional methods
are also discussed. A perimeter wall for a building with
three basements was analysed limiting its lateral
deflection. This enabled to outline design steps that
could be used in design of perimeter wall in top-down,
method. The Terzahgi and Peck method was used to
obtain strut loads in the permanent slabs and the
Rankine pressure distribution for the earth pressure on
the wall.
This method hasbeen found to be ofadvantage in highly
populated cities but economic viability would have to
be estimated for each individual project.
1.0 Introduction
In cities population density is increasing and so are the
land values. This has resulted in high-rise buildings in
the cities, for parking, storage, loading of goods and
services combined with the aesthetics of the building,
basements are required. Although construction of
basements are expensive, it has potential benefits and,
income. So it has become essential and must for
commercial high-rise buildings.
51
Unlike in bottom-up method, in the top-down method,
first a permanent perimetre wall is constructed, followed
by alll internal piles are constructed. Then the basements
are constructed downwards starting with the first
basement,
This paper describes the construction, advantages and,
disadvantages faced in the top-down method. New
technologies are being introduced to make this method
more economical and safe. Some of the techniques used,
in column construction are also given. Design procedure
that could be adopted for this purpose is briefly
discussed
2.0 Deep basement construction
methods
Deep basements are widely classified as construction
in Open excavation, Bottom-up construction, Top-down,
‘construction and a Combination of bottom-up and top-
down,
‘The BS8002:1994 on Earth retaining structures (c14.3.2.1)
gives the various construction methods for deep
basement construction. Two typesof top-down methods
of construction of deep basements are illustrated in the
code in Fig 28 and Fig 29 which are also included in the
Institution of the Structural Engineers’, ‘Design and
construction of deep basements’ published in 1975. They
are ‘concurrent upward and downward construction’
(Fig 1) and ‘Floors cast on ground with excavation
continuing below’ (Fig 2) are given in the appendix.
Ms. WS Sunuthor-B,Tch-Trmporary acre, Open University of LankaPlates for supporting floor stabs
Cylinder betled out
to form final
foundation base.
In-situ column cast in cylinder shat
First basement floor level wating stab
Line of berm
Foundations to
central area
Progress concurently
Note 1, Advantages. Good for deep excavation. Affords speedier construction on
superstructure.
Note 2. Disadvantages. Excavation and removal of spoil from enclosed area relatively
difficult
Note3. Source. Institution of Structural Engineers 1975. Design and construction of
deep basements.
Figure taken from. BS 8002: 1994
Fig 1: Concurrent upward and downward construction
52Waling. beam at first Sheet pile wall
Tor level
\ 6
: PRR +
Steet cylinder —2
-3
Steel tottice ———] Snes
a coluen ay
‘Small. temporary —H a a
tose
G
; fL. aoa
Viting sls
wierd 38 ui
excavation —3
proceeds: —st
downwards i
ea a
Lif? of retaining wall buil! with wating slab t
&
=1
=)
asc
he
15
E —6
Final column loads Iransmitted onto raft ten aft at si
‘basement floor level
NUTE 1, Advantayes, Gund method for deep excavations Temporary suiting eliminated
‘ Temporary beam imiated,
NOTE 2. Disudim tage. Excuvativn under ss and removal spl relatively dificult
NOTE A, Sain: INSTITUTION OF STRUCTUMAL ENGINEERS 1975. sign and vastrutin
1h deop basements,
a Figure 2. Floors cast on ground with excavation continuing below
,
) 53‘The Top-down method is being used in many countries.
Different ways of constructing the basement using,
top-down method are discussed in the following papers.
+ Headquarters of Hong Kong and Shanghai
Banking Corporation, Hong Kong (Archer et al
(1998), Humphenson, Fitzpatrick et al (1986)
+ The Galleries Shopping Center, Bristol. Peattie
(199)
+ Office block, Victoria Street, London. (Hodgson.
(1975), Tomlinson (1986)
* Queen Elizabeth Il Conference Centre,
Westminster. Kalra and Willows (1986)
3.0 Top-Down method
‘The construction sequence of Top-Down method for
deep basement is illustrated in Fig 3. It generally
includes the following sequence of operations:
1. The perimeter basement wall is constructed first.
This could be of cast-in-situ or Precast concrete
diaphragm walls constructed by bentonite slurry
method, secant piles, contiguous piles or stee!
sheet piles (Fig 3a).
2, Allinternal foundations are constructed from the
existing ground level, before carrying out any
excavation. Usually the internal structure
comprises steel stanchions on piled foundations.
Under-reamed piles and raft foundations too
could be used. It is also essential for top-down
construction to use only a single pile at each
column position and this technique will not
permit multi pile-cap arrangements. (Fig 3.b)
Since the columns would be loaded by the
superstructure prior to being restrained by the
sub-structure floors, it is necessary to provide
temporary lateral restraint tostee! stanchioas. Pile
casing could be back filled with peat shingle. The
steel liner above also could be braced to the steel
column (Marcand, 1993a)
3. The ground level floor is cast directly on the
ground, connecting it with the diaphragm wall
and the pre-founded columns. First, the ground
is levelled and blinding concrete is laid. On top
of this ply wood formwork is placed and then
the reinforcement, Since the slabs act as struts to
perimeter wall, slabs should be connected to
perimeter wall, The top section of perimeter wall
is broken and reinforcement is lapped to
reinforcement in theslab. (Fig 3.c). Opening is left
in the slab for the movement of materials and
machinery to construct the first basement slab.
(@) diaphragm walls;
(b) piles and steol stanchion;
(upper basement floor;
(d) first basement and superstructure;
(second basement;
(0) final basement raft
Fig 3 Sequence of top-down method
4. Then superstructure construction can be done as
usual. Basement construction is done
simultaneously below (Fig 3.d). Excavate
underneath the ground floor to the first basement
level, Level the first ground floor of the basement
and prepare the reinforcements. During
excavation, dewatering may be necessary, but
perimeter wall will act as a cut-off wall or reduce
the amount of seepage.
5. The procedure is repeated until the lowest
basement is reached. Final basement floor is
constructed with water proofing and drainage
system (Fig 3.¢g).
3.1 Advantages of top-down method
+ Intop-down method since the retaining structure
is permanent, it saves time and money spentona
temporary retaining structure. Recently steel
sheet piles with proper protection, were used as
permanent retaining wall in a Bristol, U-K.,
underground car park. In this method,
construction begins with the ground floor
propping the retaining wall. The deflections of
the wall are reduced as they are strutted by the
ground floor before any significant excav:
takes place (Katzenbach & Quick 1998). This
limits settlement of any adjacent buildings. This
would be necessary where shallow foundation*
buildings and historical buildings are present
close to the site.
In bottom up method steel is used for propping
the retaining wall. in the top-down method, the
perimeter wall is propped by permanent slabs at
different levels, According to Rowley, F.N. et al
(1988) a permanent concrete slab is perhaps the
best form of temporary prop. This is because it
fulfils in the permanent condition and also it is
very much stiffer than steel. Once in place there
is no need to remove heavy strutting with high
locked in loads.
Temporary props used in bottom up method,
makes the movement of material and equipment
difficult
Slabsare constructed, before any excavation starts
below. Ground is used as formwork and props
for the slab construction. This saves time and
money, in setting up slab formwork
The construction of the superstructure can be
started as soon as the ground floor is completed,
and well before the completion of the basements.
This can bring about several months of saving on
the total construction program. Early completion
will bring early income, loan interests are reduced
and contractor can start a new project. Even
though diaphragm walll may be costlier than other
methods, early completion saves a lot of money,
In the Aldersgate Street, London basement this
method enabled completion and use of 7 storey
superstructure while lowest of 14 split level
basement was in construction (Marchand, 1993b).
This method provides valuable storage room
during construction, since part of the ground level
area is available at all times and progressively,
the floors below.
This method minimizes noise and dirt nuisance
‘caused by the excavation of the deep pit as the
major part of the excavation is done under the
protection of the basement floors.
top-down method minimizes changes in load
through compensation of the excavated material's
weight with the gradually rising building’s load
and therefore reducing the deformations of the
new building and of the neighboring structures
(Katzenbach R et al 1998).
3.2 Problems in Top-Down method
* Excavation under the slab is difficult. It may bea
strain for the workers since working condition are
difficult.
* If any unexpected ground conditions such as
buried foundation or difficult soil layers to work
with are encountered, then excavation becomes
difficult.
* Earth moving operation is slower than the
conventional methods
+ Thereshould be very goad coordination between
management and workers. Construction material,
storage, handing, transport and all the other
activities should be planned ahead.
* After completing the concreting of floors,
excavation cannot be started immediately. Soil
cannot be removed before slab attains the
required strength
+ Rowley, FIN et al(1988) suggests that only. piled
foundations can be used for top-down
construction. Raft foundations are possible but
these are usually restricted to relatively narrow
structures. Under-reamed pile with raft
foundation was used in Queen Elizabeth Il centre
(Klara J.C. et all 1986). Hence decision to use the
top-down method, will restrict the selection on
foundation type and basement columns.
Some of these problems could be overcome having
larger slab openings. Two or more opening could be
designed so that separate paths could be used for
handing materials inside and outside. There will be more
ventilation and lighting inside basement during
excavation.
3.3 Columns construction in
top-down method
in all the case histories studied so far, steel stanchions
were used as columns in the basement. Warren Deen
(1996) suggests that large diameter piles can also be
installed in the pre-determnied positions before any
excavation takes place and are concreted up to ground
floor. This would become the permanent structural
columns for basement.
Marchand et al. (1994) describes two methods of
permanent column installation on the market. The two
methods are as follows :Bored pile is constructed first and permanent casing
placed in between cut-off level and ground level. This
casing would provide safe access to people. People
descend into the casing, prepare the pile head and place
steel stanchions.
‘The second method is plunging the column into the wet
concrete immediately after the pile had been poured.
This has the advantage of faster construction. Also there
in no requirement for a permanent casing and prepare
the pile cap and it is safe since the works are carried out
at ground level. Levels of accuracy of + 10mm
horizontally and 1 : 6000 verticaly can be achieved.
4.0 Design
building with three basement was considered for the
design. A sandy soil with angle of internal friction of
9=27° which corresponds to relatively loose sand was
assumed to simplify the calculation of earth pressure.
Analysis is carried out for a reinforced concrete
diaphragm wall. According to sheet pile wall design
shown in Fig 38 of BS8002: 1994 at strutting positions
the wall is assumed tobe pinned. A rigid wall cannot be
assumed tobe pinned thus, this makes the multi strutted
wall an indeterminate structure.
‘Acomputer package Microfeap was used to analyse this
type walll. Packages with finite element method could
be used to obtain soil settlements and wall movement
due to construction. This takes soil stffnessin to account.
Since Microfeap does not account for soil properties, this
‘was not possible.
Atypical diaphragm wall panel was analysed according
to BS 8002: 1994, code of practice for retaining wall
structure, In ultimate limit state design.
‘The wall has to resist active earth pressure, pore pressure
and surcharge loads. Passive pressure is developed to
resist these forces. The wall was analysed considering a
typical depth of panel. Allowable lateral deflection of
the wall was assumed to be 25mm. Since the assumed
depth of wall gave excessive wall movements, depth of
wall and thickness of wall were adjusted and the analysis,
repeated until an acceptable wall movement was
obtained. For allowable deflection, depth of panel,
amount of moment to be resisted, thickness of wall etc.
were calculated. Please refer the appendix for more
details.
Design steps of procedure
recommended for perimeter wall
1, Obtain borehole details and establish ground
conditions and surcharge loads
2 Obtain basement layout and dimensions.
3. Thickness of diaphragm wall is assumed. Select
relevant material, sizes and material properties.
4, Obtain relevant active and passive pressure
taking in to consideration all the variations along,
the depth of the wall
5. Establish critical stages of excavation.
6 Assume an embedment length of diaphragm
wall.
7. Analyse the wall for Rankine pressure
distribution
8. Obtain the inward movernent of the wall. If this,
is more than the allowable, increase the
embedment, and /or wall thickness analyse it, till
the deflection is within the allowable limit.
9. According to Terzhgi and Peck’s pressure
distribution, analyse the wall again to obtain strut
loads on the slab.
10. Maximum of strut load obtained in 7 & 9 should
bbe used in design of the slab.
11. Using these design values obtain the
reinforcement details for diaphragm wall and
slab.
5.1 Active pressure calculation in
braced Excavation
First the perimeter wall is constructed. Before any
excavation takes place the wall is fully supported by
the earth. Then struts (floors) are constructed as
excavation proceeds. As the excavation increases,
yielding of the soil becomes appreciable but the ground
evel slab prevents yielding near the surface.
Deformation of the wall is negligible at the top and
inereases with the depth. Thus deformation condition
of Rankine theory cannot be used for multiple row of
braced excavation (Craig, 1983). To determine strut loads
‘Terzaghi and Peck (1976) developed a pressure envelope
shown in Fig 4 from case histories (semi-empirical
method). This is Fig 37 of BS 6002:1994.
A retaining wall acts as a structural unit and fails as a
unit whereas a strutted excavation has some flexibility,
and local concentrations of earth pressure can cause high
Joads on individual bracing members. [fone strut fails
it will immediately throw increased loads on to theadjoining members, thus initiating a general collapse of
the system, hence the trapezoidal distribution of
Terzaghi and Peck envelope coversthe maximum strut
loads likely to occur at any level rather than representing
the average strut loads (Tomlinson, 1986).
‘The perimeter wall is designed according to BS
8002:1994. ‘For the strutted excavation, the pressure
distribution given in BS8002:cl.4.43. 1s used. Inbraced
excavation propping force are transferred to all the
struts. To determine strut forces this soil pressure
distribution is used to this
Note: Source : Soil Mechanics in Engineering Practice
(second edition). Terzghi & Peck (1967)
Ka - Coefficient of earth pressure
D = bulk density
H_ = Depth of excavation
Figure taken from BS 8002 : 1994
Figure 4. Active pressure diagram relating to maximum
strut loads in braced earth retaining structures
pore water pressure and surcharge pressure should be
added according to BS 8002:c.4.4.3.2. Itshould be noted
that active pressure, pore pressure and surcharge loads,
are considered only to the depth of excavation
Here both a trapezoidal pressure distribution and a
triangular pressure distribution was used separately to,
analyse the diaphragm wall. Triangular pressure
distribution to obtain bending momentsand trapezoidal
Pressure to obtain critical strut loads.
5.2 Critical stages of excavation
At critical stages of excavation maximum bending
moments, shear force and deflection were calculated.
Stage1 at theend excavation for I" basement (after
constructing ground floor)
Stage 2: at the end of excavation for 2” basement
(after constructing ground floor and 1*
basement floor)
7
at the end of excavation for 3" basement
(after constructing ground floor, ¥* and 2"
basement floors)
Stage 3
5.0 Conclusion
‘Top-down method has advantages of using the slabs as
temporary struts, using completed slabs as storage
space, concurrent construction of superstructure and
basement, deflection of wall is minimised without
obstruction the construction with large number of struts,
early completion of the building and super structurecan,
be utilised before the completing the basement
construction. Permanent perimeter retaining wall and
slabs serve as shoring and struts, as well as permanent
final elements in the structure. This saves time, resources,
and money on temporary works.
In top-down method, the basement walls are strutted at,
‘ground level using the permanent structure. and the wall
movements are reduced compared to traditional
method. These would save on extra care that need to be
taken on protecting the adjacent structures. Since the
construction is carried out simultaneously above as well
in the basement, ground heave is reduced. This method,
minimizes the pollutions during excavation.
In designing the perimeter wall in top - down method,
Rankine method should be used in obtaining the
moments and shear forces on the wall. Terzaghi and
Peck’s method should be used to obtain the strutting
slab loads. The outline steps that were discussed in the
paper would be most helpful to understand the design
procedure at design stage, construction stage and post
construction stage.
‘This method has been found tobe of advantage in highly
built-up areas. The economic viability would have to
estimated for the individual project before deciding on
this method.
Acknowledgement
I take this opportunity to thank my supervisor
Dr. Mrs. P.Sivaparakasapiliai without whose assistance
this project would not have been possible. She guided
and instructed me throughout this project. I also wish
to thank the consultants whom I met to get information.
‘The information they shared with me were a great help,
to this project. I also thank my uncle who found the
technical material. | thank my family forall the support
they gave me.Reference:
1
10,
nL.
12,
13.
Archer, FH. and Knight, DWM. (1988), Hong
Kong and Shanghai Banking Corporation
Headquarters Construction, Proc. Instn Civ.
Engrs, Part], 1988, 84, Feb. pp. 43-65.
CIRIA Report 139, Water-resisting basements,
1995,
Code of practice for Earth retaining structures BS
8002: 1994
Craig, R.F. (1983), Soil mechanics, 4" edition,
Workingham, Berks; Van Nostrand Reinhold.
Design and construction of Deep basements (Aug,
1975) institution of Structural Engineers, 11 Upper
Belgrave Street, London SWIX 8BH.
Hodgson, FT, (1975) Design and construction of
a diaphragm wall at Victoria Street, London.,
Diaphragm walis and anchorages, paper-7,
Institution of Civil Engineers, London, 1975,
pp5i-56
Humpheson, C,, Fitzpatrick, AJ. and Anderson,
J.M.D, (1986), The basements and substructure for
the new headquarters of the Hong Kong and
Shanghai Banking Corporation, Hong Kong, Proc.
Instn Civ. Engrs, Part 1, 1986, 80, Aug., pp. 851-
883, Thomas Telford Ltd.
Kalra, J.C. and Willows, KR. (1986), Queen
Elizabeth Il Conference Centre: Design and
- construction. proc. instn. Civ, Engrs, Part 1, 1986,
80, Dec,, pp. 1451-1477, Thomas Telford Ltd,
Katzenbach, R. and Quick H. (1998), A new
concept for the excavation of deep building pits
in inner urban areas combining top/down
method and piled raft foundation, 5.17, 7*
international conference and exhibitions on piling
and deep foundations, Austria.
Lee Hyun-Soo (1999), Nonshored forwork system
for top-down construction, Journal of
construction engineering and management,
November / December 1999
Marchand, S. (1993 a), A deep basement in
Aldersgate Street, London. Part 1: Contractor's
design and planning,, Proc. Instn Civ. Engrs., Civ.
Engng, 1993, 93, Feb., pp. 19-26
Marchand, S. (1993 b), A deep basement in
Aldersgate Street, London. part 2: Construction,
Proc. Instn Civ. Engrs. Civ. Engng, 1993,97, May,
pp. 67-76
Marchand, S., Wren G. and Lamb R. (1994), Top-
down construction and its implications, proc.
Instn Civ. Engrs. Geotech. Engng, 1994107, Apr.,
pp. 123-124
58
14. Microfeap II (1988), Analysis of 2Dtruss / frame/
wall) Micro Ace club, Asian Institute of
Technology.
15. Peattie, G.C. and Mojabi, MS. (1991), Design and
construction of the Galleries Shopping Centre
Bristol, Proc. Instn Civ. Engrs, Part 1, 1991, 90,
Dec., pp. 1225-1253, Thomas Telford Ltd.
16. Rowley, FN. and Yarwood, N.G.A. (1988),
Method on design, Proceedings of the conference
Economic construction techniques: temporary
works and their interaction with permanent
works, organized by the Institution of Civil
Engineers and held in London on 16 Nov. 1998.
17. Terzaghi, K. and Peck, R.B. (1967), Soil mechanics
in engineering practice. Wiley, New Yourk, 1967,
2 edition.
18, Tomlison, MJ. (1986), Foundation Design and
Construction 5* edition, Thomas Telford Ltd.
publication,
19, Warren Deen, R. (1996), Civil Engineering
Construction, Design and Management,
Macmillan.
Appendix
A building with three basements was considered for the
design. Since this is a strutted excavation the analysis,
becomes indeterminate. A computer package was used
for this analysis. Since basement diaphragm wall take
the soil pressures these triangular loads also need to be
inchided. Microfeap package used does not accept them.
This package not analyse structures using finite element,
method. Hence this package does not accept the
properties of soil. Settlement of adjacent buildings,
cannot be calculated using this package.
‘The figure 5 below shows the section of the building
analysed. It was assumed that the diaphragm walll does
not carry any vertical loads. Diaphragm wall was,
assumed to carry the soil pressure and strutting loads
of the slab.ut 15
Basement 3
ee
oer
Fig 5 Basement and diaphragm wall structure.
1to 16 - Node number (N)
1» 19 - Element number (E)
End condition F - Free
L ~ Locked
Element «7 - diaphragm wall
8tois - slab
419 = - column
39Table 1 gives the maximum bending moment in the wall,
‘maximum deflection and maximum axial force for 20m
and 186m deep diaphragm wall. For the 18.6m deep
diaphragm wall the deflections are found tobe excessive
0f25 mm. Then diaphragm wall was analysed again for
a 20m deep.
Table 2 gives the details of 20m deep diaphragm wall.
Maximum bending moment, deflection and axial force
at critical stages of excavation. From this it is evident
that the maximum axial force at the end of second
basement excavation is more in trapezoidal distribution
than the triangular distribution.
‘The package used has limited capability and this limits
the validity of the results obtained. In the basement
design shear wall action should be considered as the
shear wall carries the loads to the foundation. The 2-D
analysis of the Microfeap package does not take this in
to account,
Triangular active pressure distribution
thickness of wall 1000mm | 800mm.
Height of wall -20m
maximum bending moment on the
diaphragm wall KNm 932 932
NS NB
maximum deflection in mm towards
the excation 27 26
N6 N6
maximum axial force on the slab KN 8558 872
E10 E10
Height of wall -18.6 m
maximum bending moment on the
diaphragm wali KNm 1700 1700
Né Na
maximum deflection in mm towards
the exes 70 985
NB NB
maximum axial force on the slab KN 1086 1136
E10 E10
N- Node number
E- Element number
‘Tab 1 Results of deflection and bending moment for triangular active
pressure distribution
»
&
a
”Height of wall - 20 m
Triangular active pressure distribution
end of 1* | end of 2" | end of 3*
basement | basement | basement
excavation | excavation | excavation
maximum bending moment on the
diaphragm wall KNm 348 625 932
N7 NS NS
maximum deflection in mm towards
the excation 0.99 238 uz
N2 NB Nd
maximum axial force on the slab KN 849 48 855.8
EB BD E10
‘Trapezoidal active pressure distribution
‘maximum axial force on the slab KN end of | end of 2 | end of 34
basement } basement | basement
excavation | excavation lexcavation
1 st slab (E8) - 81 325
2st slab (E9) - 5058 231
3st slab (E10) 679
‘Tab 2 Results obtained for 20m deep diaphragm wall
maximum bending moment diaphragm wall
should be designed for
maximum axial force slab_—_1" and 2 nd slab
should be designedfor 3M slab
61
932 KNm.
505.8 KN
855.8 KN