Professional Documents
Culture Documents
Cost 20
Salvage Value 4
Selling Price 5
Gain On Sale 1
Tax 0.4
Salvage Value After Tax 4.6
d
REPLACEMENT ANALYSIS The Chang Company is considering the purchase of a new
machine to replace an obsolete one. The machine being used for the operation has a book
value and a market value of zero. However, the machine is in good working order and
will last at least another 10 years. The proposed replacement machine will perform the
operation so much more efficiently that Changs engineers estimate that it will produce
after-tax cash flows (labor savings and depreciation) of $9,000 per year. The new machine
will cost $40,000 delivered and installed, and its economic life is estimated to be 10 years.
It has zero salvage value. The firms WACC is 10%, and its marginal tax rate is 35%. Should
Chang buy the new machine? Explain.
0 1 2 3 4 5 6 7
-40000 9000 9000 9000 9000 9000 9000 9000
Tax 35%
NPV $55,301.10
EAA(A) $1,407.85
EAA(B) $1,174.62
$633,973.09 $665,927.19
NPV 166,026.91 134,072.81
NPV after Tax 66,410.76 53,629 (12,782)
NPV $12,781.64
Budget $ 2,500,000
Proect A,B,C,D $ 3,900,000
a. Should the firm operate the truck until the end of its 5-year physical life; if not, what is
the trucks optimal economic life?
b. Would the introduction of abandonment values, in addition to operating cash flows,
ever reduce the expected NPV and/or IRR of a project? Explain.
0
Hampton Manufacturing estimates that its WACC is 12% if
equity comes from retained earnings However, if the company issues new stock to raise
new equity, it estimates that its WACC will rise to 12.5%. The company believes that it will
exhaust its retained earnings at $3,250,000 of capital due to the number of highly profitable
projects available to the firm and its limited earnings. The company is considering the
following seven investment projects:
Projects Sixe IRR
A $ 750,000 14
B $ 1,250,000 13.5
C $ 1,250,000 13.2
D $ 1,250,000 13
E $ 750,000 12.7
F $ 750,000 12.3
G $ 750,000 12.2
a. Assume that each of these projects is independent and that each is just as risky as the
firms existing assets. Which set of projects should be accepted, and what is the firms
optimal capital budget?
b. Now assume that Projects C and D are mutually exclusive. Project D has an NPV of
$400,000, whereas Project C has an NPV of $350,000. Which set of projects should be
accepted, and what is the firms optimal capital budget?
c. Ignore Part b and assume that each of the projects is independent but that management
decides to incorporate project risk differentials. Management judges Projects B, C, D,
and E to have average risk; Project A to have high risk; and Projects F and G to have
low risk. The company adds 2% to the WACC of those projects that are significantly
more risky than average, and it subtracts 2% from the WACC of those projects that are
substantially less risky than average. Which set of projects should be accepted, and
what is the firms optimal capital budget?
Budget $ 3,250,000
$ 16,250.00
a. Assume that each of these projects is independent and that each is just as risky as the
firms existing assets. Which set of projects should be accepted, and what is the firms
optimal capital budget?
b. Now assume that Projects C and D are mutually exclusive. Project D has an NPV of
$400,000, whereas Project C has an NPV of $350,000. Which set of projects should be
accepted, and what is the firms optimal capital budget?
PRO D $ 400,000
PRO C $ 350,000
If Projects C and D are mutually exclusive, the firm will select Project D rather
than Project C, because Project Ds NPV is greater than Project Cs NPV. So, the
optimal capital budget is now $4 million, and consists of Projects A, B, D, and E.
If Projects C and D are mutually exclusive, the firm will select Project D rather
than Project C, because Project Ds NPV is greater than Project Cs NPV. So, the
optimal capital budget is now $4 million, and consists of Projects A, B, D, and E.
c. Ignore Part b and assume that each of the projects is independent but that management
decides to incorporate project risk differentials. Management judges Projects B, C, D,
and E to have average risk; Project A to have high risk; and Projects F and G to have
low risk. The company adds 2% to the WACC of those projects that are significantly
more risky than average, and it subtracts 2% from the WACC of those projects that are
substantially less risky than average. Which set of projects should be accepted, and
what is the firms optimal capital budget?
Projects WACC
High Risk A 14.5 Reject
Avg Risk B,C,D,E 12.5 Accept
Low Risk F,G 10.2 Accept