Petrol & Gas Construction co.

Safety ,Accuracy & Vision

Date: Tue 21-Feb-2017

MINUTES OF MEETING

UI61917 Kick-off Meeting - Provision of Goods and


Purpose Doc. No. UI61917-MOM-001-Rev 1
Services for GRP Equipment Contract

QSGTL-Ras Laffan-Central Control Room (CCR) -Al


Meeting Held At Wasael Prepared By JEC Perez
On 16th of FEB, 2017.

ACTION
ITEM DESCRIPTION OF DISCUSSION
By
Swinging barriers (GRVE materials) can be included on the Non-defined scope. Mr. Patrick De Bot
1 As cited by Ms. Shoaa, this shall be internally discussed in order to conclude how / Ms. Shoaa
this scope can be managed in/out of the service contract. Heedan
Area for storage facility ( Laydown Area + 20ft Container + Small
2 workshop+Shell spec. ) including power supply and other necessary items to be Mr. Patrick De Bot
provided
Mr. Said Ali / Mr.
3 Lay-out plan for the proposed storage facility to be submitted
Moustafa Elshemy
Contract risk (QSGTL Observation): No QA/QC on goods/materials: Level 4D
4
Mitigation response: Implementation of PGCC QA/QC system Mr. Said Ali
Contract risk (QSGTL Observation): No QA/QC on competent personnel: Level
4D
5 Mitigation response: CV copies to be submitted to Mr. Patrick De Bot Mr. Said Ali
Mitigation response: Personnels to be interviewed Mr. Patrick De Bot
Contract risk (QSGTL Observation): Untimely mobilization of personnel to
support major unplanned works resulting to not being able to quickly restart unit
6
Mitigation response: Additional manpower shall be scheduled to undergo safety Mr. Said Ali / Mr.
induction & gate pass activation Patrick De Bot
Normal working hours during the holy month of Ramadan: 8 hours to be
7 divided into two 4-hour shift. Ramdan coverage for service can be managed Mr. Said Ali
through having 2 shifts to comply with Qatar Labor law.
Service payment entry to be finalized; (System-based time sheet approval
8
or the hand-written timesheet to be submitted to the Contract Ms. Shoaa Heedan
Owner/Holder for approval). / Mr. Patrick De
Payement Process to be finalized Such as-Who enters the data to SAP Bot
(Contractor or Company)
Mr. Patrick De Bot
Date of commencement for the mobilization plan to be provided by
9 / Ms. Shoaa
Contract Owner & incorporated on the actual plan Heedan
10 Clarification on the TIR: Shell to clarify which party will provide TIR Mr. Patrick De Bot
Shell itself (Shanjoy Malkani? Which will keep it consistant) or by
contractor (not included in contract)

Page 1 of 3
Petrol & Gas Construction co.
Safety ,Accuracy & Vision

Date: Tue 21-Feb-2017


All job shall only proceed once the Technical Investigation Report (TIR)
has been issued. Mr. Moustafa
PGCC focal person for TIR & technical concerns shall be Mr. Moustafa Elshemy
Elshemy.
As per the latest information from Mr. Patrick De Bot thru email - it has
previously been agreed that the area inspectors themselves will be setting
up and issuing the TIRs

Variation order to be raised concerning the previous undisclosed status of the


contract ( previously believed to be Call-off basis, but eventually become Service
Mr. Said Ali / Ms.
11 provision)
Shoaa Heedan
As advised by Ms. Shoaa, it should be on a reasonable value and the
breakdown shall be included)
HDPE, Dual laminates, rubber linings , PVC /UPVC/CPVC and any other
12 nonmetallic scopes are not included on the previous bid. Any job request
concerning the mentioned scopes can also be executed by PGCC and shall be on
quotation-based scope.
Site Office desk (2 Office space), Computer workstation (Max 2 GID), Mr. Patrick De Bot
13 meals shall be provided by QSGTL. Preparations and arrangement to be / Ms. Shoaa
executed by QSGTL Heedan
Standard Invoice period is 60-days as mentioned by Ms. Shoaa, contrary
to the 30-day period indicated on the signed contract. This is implemented
14 Ms. Shuaa Heedan
for all contractors working under QSGTL, and shall overrule the indicated
terms on the Non-metallic contract.
Mr. Patrick De Bot
15 Company (QSGTL) to create Clarity around emergencies after office hours / Ms. Shuaa
Heedan

Attendees [Position] Company

Page 2 of 3
Petrol & Gas Construction co.
Safety ,Accuracy & Vision

Date: Tue 21-Feb-2017

Shoaa Heedan Contract Engineer QSGTL.

Patrick de Bot FGP Field Engineer QSGTL

Said Ali Excutive Manager PGCC

Moustafa Elshemy Non Metallic division Manager PGCC

Joseph Perez QC Inspector PGCC

Page 3 of 3