Experiences And Future Trends In Design And
Construction Of Bridges
by
Pryush Agarwal*
SYNOPSIS
The history of bridge building, right from the inception of human civilization to the modem era, has been
the history of humankind’s endeavours and achievements. To an engineer, bridges are a challenge to
successfully surmount the obstacles in construction. A bridge may be defined as a structure
‘surmounting an obstacle such as a river, road, valley, depression or Railway and used asa passage for
‘people or vehicular traffic. A bridge is designed to satisfy the functional, economic, strategic and
aesthetic requirements. The varieties of bridges demonstrate the combination of art and technology.
1.1 Bridges existed in nature, say in the form of a wooden
log across a stream or an arch of stone formed by the
erosion of soll in a stream. The first known bridge
constructed is said to be an arch bridge built in Babylon in
2200BC, The concept of building bridges has taken roots,
probably through the observations of these natural
Phenomena. Timber was the first material used for bridge
‘construction followed by bricks and stones which imparted
greater durability. Numerous arch bridges have been
constructed, some of them with elegant and graceful
aesthetics, including two and three-tiered arch viaducts.
‘Old masonry arch bridges built more than 150 years ago
are still found in service.
1.2 With the development of technology of wrought iron
and steel, the bridge construction technology took a
‘quantum jump and the era of long-span bridges started. In
1815, Henry Jessop of Jessop & Co of Kolkata built the first
iron bridge in India for the Nawab of Oudh and this stil
spans the Gomati river at Lucknow. The first plate girder
bridge was built in 1847. Number of wrought iron and ste!
bridges, built more than 100 years ago, are still in service,
notable amongst which is ald Yamuna Bridge in Delhi and
Howrah bridge at Kolkata on river Hoogly.
1.3 With the advent of concrete, construction of concrete
bridges started in the country. The advantages of concrete
such as low relative cost, easy availabilty of ingredients,
versatility, adaptability and adequate engineering
properties were soon realized and the later half of 20th
century witnessed a boom in concrete bridge construction.
The concrete bridge design evolved through many forms,
ranging from the plain concrete to reinforced concrete and
from beam and girder type to the bow-string girders.
Meanwhile composite bridges were also built utilizing the
{ull strength potential of steel and concrete both. However,
it was the advent of pre-casting and_pre-stressing
technologies that enabled the real potential of concrete in
bridge construction to be realised. Today, techniques
ranging from simple pre casting to segmental construction
Executive DrectorB&S, ROSO, Lucknow
combined with the use of high-strength and very recently
high performance concretes have opened a vista for bridge
engineers to conceive and construct bridge structures
which were undreamt of earlier. The limits of the technology
have by no means been reached, even with the concept of
the cable-stayed structures.
4.4. The chronological development of bridges are as
below:
1854] FirstBridge | “Dapoorie” viaduch of GIP Railway
with 22 stone arches across the
‘reek to link Bombay island with the
mainland of Thane.
Historie breakthrough by EIR after 7
years of construction near Arran in
Bihar with 28 piers spanning almost
114 km. Later upper Sone bridge
madein 1900,
“Twin Rall-cum-Road deck bridges of
‘Tonse NearAlahabad & Old Jamuna
near Delhi. Duke of Edinburgh fixed
asilverrivorin"Tonse" in 1870.
BBECI's crossing across Bassein
‘reek 20 miles from Bombay.
Madras City connection
Sirsawa across Yamuna near
Ambala, Sutle), Beas (it colapsed:
with a passenger train) & Alexandra
‘across Chenab. More bridges acrass
Sutle) &Beasin 1914.
“Dufferin" Rail-cum-Road deck
bridge near Kashi. Re-named as
Malviya bridge after independence,
Balawali bridge near Moradabad
Later, Garmuketshwar bridge made
in 1901. “Curzon” Rail-cum-Road
deck bridge near Allahabad made in
1905
1863 | Sone Bridges
"1864 | Yamuna bridges|
1864 | Bassein Creek
1870
7870
Pennair Greek
Punjab Bridges
11887 | Ganga bridges
{IRICEN JOURNAL OF CIVIL ENGINEER1887] Hooghly bridges) Calcutta city connections through
“Jubilee” bridge-24 miles. north.
"Wilingadon” bridge near Bally made
in 1929. Howrah Bridge opened to
traffic on 1943. 1900 Godavri
bridges Earliest of Rajamundry
triplets each spanning 3 kms. 2nd &
3rd in 1964 & 1998 respectively
Last of these is a unique bowstring
arch girder concrete bridge,
Jor 4 ter viaducts Roman style with
4-618/10 arches.
Rameshwaram link reducing the
distance to Colombo and spanning
‘ver 2 kms including a two leat
"Scherzer" roling lit bridge (span
200 feet to lift and allow ships to
pass. Restored after cycione in 1964,
4927 | Kangra crossing) Unique steel arch spanning 200 feet
across Reyond Nullah of Kangra
Valley hil Railway
Rall-cum-Road deck bridge near
‘Guwahati spanning 1.3 kms. Later, 3
km near Tezpore in 1987 &
2.3km ral-cum-Road crossing near
Jogighopa in 1998,
+1998 | Konkan Railway) Tallest viaduct on Panvel Nadi (64m)
bridges and Shravati river crossing in
Honnavar (over 2 kms) apart from
other 175 majorbridges.
7903) Sima Viaducts|
1913 | Pamban bridge
7962 Brahmputra
bridges
2.0 TYPE OF RAILWAY BRIDGES
2.1 There are about 1,27,768 bridges on Indian Railways.
(Out of which, 42% are more than 100 years old, 62% are
more than 80 years and 75% are more than 80 years old.
The details areas below:
Important Br
Major Br
MinorBr
Arch Br
‘Steel/Composite Br
RCC box
RCCIPSC slab
PSC girder
Pipes
Others
37
0,437
16,678
= 19,647
Bridges have been constructed across major rivers, small
nallahs, large lakes, deep valleys and across irrigation
fields. The span of these bridges vary from small pipe
culverts of less than 30 cm diameter to more than 120
metre. During early period, naturally available stone was,
used for constructing piers, abutments and the arches.
Later brick masonry and concrete masonry were used as
the technology of producing these material improved. Steel
was mainly used for construction of superstructures. The
steel girders were manufactured mostly in England and
shipped to India initially Plate girders of different spans and
types of that era still existing. For larger spans, open web
girders of different types have been used both for railway
bridges and rail-cum-road bridges. Concrete girders for
railway bridges are of recent origin, Wherever used,
concrete girders are heavier than steel girders of similar
span.
2.2 __In India, modem bridge building emerged during
the British rule, when many major bridges were built,
mostly with steel decks to carry the railway tracks across
the mighty rivers of Ganga, Jamuna, Godavari,
Brahmaputra, Mahanadi and many others. Masonry arch
and stee! trussed bridges were also built. Modem concrete
bridges emerged on the indian scene during the twenties of
the last century. Plain and reinforced conerete bridge:
categories, namely, simply supported bridges with s
slabs or ‘slab-and-beam, balanced cantilever with
suspended spans and plain and reinforced concrete and
bow-string girders were built during the second half of this,
century.
2.3. Bridge building in India got a real boost only in the
post-independent period. During the last six decades
femarkable strides have been made, both in design
concepts and construction techniques. While the
construction of Palar Bridge in 1955 heralded the era of
prestressed concrete bridges in India, On Indian Railways
PSC girder bridges of 80' span were constructed in 1965 on
Singraull-Obra Section. The first application of cantilever
construction technique for the Barak Bridge at Silchar in
1961 opened up new vistas for long-span concrete bridges,
Indian’ engineering expertise crossed yet another
milestone with the construction of two cable-stayed
structures on roadways, first the Akkar Bridge in Sikkim in
1988 and then the second Hoogly Bridge in 1993, Indian
Railways have also adopted the technology for
construction of road over bridge at Chiraiyatand, Patna in
2006.
2.4 — During recent years, innovative application of
design and construction techniques has led to the
construction of a number of outstanding bridges, such as
the 5.575-km long Ganga Bridge at Patna which
incidentally is the longest river bridge in Asia, Brahmaputra
Bridge at Tezpur, rail-cum-road bridge at Jogigappa,
Pamban Bridge in the Palk Strait, and bridges across the
‘Thane Creek near Bombay - tomention only a few. Mention
also needs to be made of the notable achievements of the
‘engineers and builders of the Konkan Railway who have
built 143 major bridgesiviaducts having a total linear
waterway of more than 19 km in a short span of 5 years.
‘The credit for this achievement goes mainly to the adoption
of innovative design methods, standardisation of
procedures, extensive pre-casting, use of slip-formwork for
tall piers and abutments, and adoption of suitable
launching methods for superstructure. Incidentally, the
incremental launching technique which is popular in
Europe and elsewhere had been adopted for the first time
in India for the Panval Nadi viaduct on the Konkan Railway,
With the recent advancements in welding technology,
increased emphasis has been given to design welded
girders instead of vetted. Even open web girder members
are now welded type. In new constructions, the field
‘connections are also proposed to be welded.3.0 BRIDGE DESIGN PRACTICES
Key elements to be considered at the preliminary phase of
design of a bridge are loads, soll conditions for foundations,
waterway requirements, vertical clearance requirements
with respect to the designed discharge level, initial
construction and maintenance costs, safely and materials.
For major and important bridges, other considerations like
development of the area served by the railway line,
aesthetic considerations also are to be considered.
3.1 The Indian rivers, especially in North India, are still
unstable and changing courses frequently, The flood levels
and the extent of floods are also changing, Based on the
experience in the pastin India and abroad, corrective action
canbe taken for the assessment of waterway requirement,
vertical clearance, scour depth. River training and
protection works are very costly and should be carefully
applied. For smaller bridges, the waterway requirement
can be reviewed by adopting realistic methods based on
past experience and actual field conditions existing now,
This will be helpful in planning rebuilding of bridges in
‘gauge conversion works with reduced costs and time.
3.2 Another area which requires more consideration is the
‘subsoil investigation and deciding the type of foundations.
‘The type and extent of investigation has to be decided for
individual bridges and should be followed to avoid failures
and unsatisfactory features during their service life. The
techniques of geotechnical investigations have developed
to a high degree of accuracy and these techniques should
be adopted to the advantage of Bridge Engineering,
3.3 Traditionally, well foundations are preferred by Bridge
Engineers and these foundations are functioning well in
majority of cases. But they are more labour intensive and
the progress of work can be slow in difficult situations. With
availabilty of precast piles and pile driving equipments, pile
foundations can be cheaper and construction can be faster.
Pile driving rigs are now-a-days available for bores upto to
2.5m dia therefore pile foundations can be used as an
alternative to well foundations. The relative cost of these
two types of foundations in a particular project can be
worked out taking into consideration the ground conditions
and cost can be optimised. An overall view of river flow
pattern, subsoil conditions, construction facilities, time of
construction, maintenance efforts required in future ete,
hhas tobe taken by the designers,
3.4 The selection of material for superstructure has to be
made, based on considerations like initial cost,
maintenance cost, service life, speed of construction,
environmental conditions etc. Concrete bridges are likely to
increase the load on the substructure and consequently
their cost. Concrete structures require quality construction
to reduce the maintenance costs. Steel structures are light,
easy for replacement and renewal but require intensive
maintenance programme. The salvage value of steel
structures is often large enough to justify their adoption in
long span bridges. Maintenance requirement of the track
con the bridge should be considered including restoration
during accidents.
20
3.5 Any structure in service requires maintenance and
inspection of a bridge is the starting point of maintenance.
Railway bridges are inspected manually by a well
organised inspection organisation. Historically the
inspection is done with safety in mind, The entire service life
behaviour of the structure depends on the type of
construction, Steel has been a time tested material for
bridges. Most of the long span bridges on Indian Railways
have been constructed with steel for which fabrication has
been done in Central Workshops of railways. However,
steel bridges require frequent maintenance attention like
painting, testing of rivets, greasing of bearings etc. Since
steel is produced under factory conditions, there is not
much change in material properties except due to
3.6 Masonry bridges on the other hand have served with
almost no maintenance for a long period. Their reserve
strength is being utilized today by increasing the
permissible stresses. But this cannot be extended for too
long a period. Procedures for testing the masonry
structures based on visual inspection and minor repairs has
to be adopted for railway bridges like being followed for
highway bridges in U.K. and other countries. These
countries have developed dynamic response techniques
also for masonry bridges to predict their residual life,
3.7 Concrete bridges are considered as maintenance-free
structures provided the initial construction is good and
without any defects. Concrete being a heterogeneous
Material, there are various parameters to be controlled
during construction, Some of these are good cement,
aggregate, water cement ratio, detailing of reinforcement,
leak proof shuttering, workable concrete mix, good
vibration, proper curing, adequate time interval for removal
of shuttering, proper handling of members after removal of
shuttering, adequate drainage arrangements for water,
provision of wearing course etc. The quality control is
extremely important and everything has to be controlled
during construction itself. It is almost impossible to make
corrective action later. Corrosion of steel reinforcement and
bad concreting are the main factors which have to be taken
care of, if maintenance free structures are to be produced
3.8 Technological advancement have also taken place in
the field of bridge bearings. From conventional fat sliding
bearings and rocker cum roller bearings, Indian Railway
has already moved to Pot-PTFE bearings which are
considered maintenance free. Further advancements
such as Spherical bearing with PTFE is stillto be adopted in
future
4.0 _TECHNOLOGICALLY ADVANCED BRIDGES
CONSTRUCTED/UNDER CONSTRUCTION ON INDIAN
RAILWAYS
4.4 Sarai Ghat Bridge
First bridge constructed across Brahmaputra. Rail cum
road bridge is situated close to Guwahati and Provide road
connectivity to NH-31 from NH-37.
+ Length of bridge-1.296 Km.
+ Span- (33.20m + 10x122.95m + 33.20m) steel trussgirder
+ Double Warren type girder with sub-verticals 18.30
mhigh and 8.90 mwide
+ rollerand rockerbearings
+ Rail:TwoMGML or Single BEML
+ Road: 2Class'A’ or Single Class 'AA
+ Design Discharge - 63,720 cumec
+ Design Scour-40.84 m below HFL
+ Foundation - Double D' type wells (16.30mx9.75m)
+ Steining- 0.90 mthick concrete steining
+ Depth of well -60.65m below HFL
+ Shore Pier Twin circular well of 6.0m dia each
having depth of 27.50m below HEL.
4.2 Nara- Narayan Setu at Jogigoppa
Rail-cum-road bridge constructed over river Brahmaputra.
Length of bridge-2.284 km,
+ Span-1x32.60m+14x125m_+1x94.60m+3x125m+
1x32,.60m
+ Length of Road Viaducts- 1.082 kms
+ Main spans-Double Warren type open web steel
girders, 18.50m high and 11.50m wide with steel
floor system for railway and composite roadway
deck.
+ Foundation-Double 'D' Type wells (14mx17m) for P1
to P16 and P19, circular wells for P-17 and P-18
(18m diameter) Twin-circular wells (6m diameter) for
both abutments,
+ Design discharge: 90,400 cumecs,
43° Kallabhomora Road Bridge Near Tezpur-
Road bridge constructed by Railway on river Brahmaputra
at the request of North Eastern Council. Main bridge gitders
are of 120 m span PSC box girder which have been
constructed by segmental construction method.
? Length ofbridge-3.015 km
2 Spans - 1x67.5m + 24x120m + 1x67.5m, PSC
cantilever box girder with RCC suspended span
2 Foundations Circularwells of 12m dia;
2 Thickness of well steining -2m
2 Depth of well -62.5m below HFL ( 56m below LWL)
? Design Discharge : 92,000 cumec
4.4. Bogibeo! Rail Cum Road Bridge Near
‘Assam (Under Gonstruction)-
ibrugarh,
Design ofs land mark in the history of Railway bridges. Itis
atwo tier Rail cum Road Bridge composite truss bridge with
2BG Tracks & 2 Lane Road on the top deck. Itconceives a
steel truss floor system for railway with composite
reinforced concrete road deck. First time welded truss
joints have been proposed. Provisions from international
codes have been taken wherever not available.Incremental launching method is proposed to be adopted.
+ Length of Main Bridge: 4.315kms
+ Length of Road Viaducts: 1.815 kms
+ Span-1x32.5m+34x125m+ 1x32.5m
+ Warren type Welded High Strength Steel Truss
(13.50mhigh, 11.60m wide)
+ Twin circular hollow RCC piers on Double
Shaped wells (16.2mx 10.5m)
4.8 Pamban Bridge -
Pamban Bridge across Palk Strait in the Bay of Bengal is
2.06 km long with 146 spans of 40’ and one Scherzer lift
span (navigational span) of 214’ and is 95 years old. Itwas
modified from MG to BG & was commissioned for
passenger train services on 12” Aug,2007. The navigated
span with its lifting arrangements has been modified to
cater to the needs of Broad Gauge. The bridge being
located in one of the severest corrosive zone in the world,
was severely affected by corrosion. Conversion involved,
apart from execution problems, many analysis/design
challenges suchas
+ Severe limitation in providing additional plates for
extra counter weight
+ Design of coupling for Mid span connection
between two cantilever portions.
+ Actual cross sectional properties were
considered in view of corrosion.
4.6 ROB at Chiralyatand
Cable Stayed Rallway over bridge at Chiraiyatand, Patna
constructed recently. It was Constructed in two stages to
allow the traffic during the construction. Innovative load
transfer devices (steel out riggers) to transfer load from
bridge deck to cables was used
+ Overallspan-110m.
+ ROC pylons -40m height (3No)
4.7 Kosi Bridge Under Construction -
This is on river Kosi, most notorious river, considered to be
the sorrow of Bihar. Ithas changed its course 100 times in
past 100 years. Bridge falls in seismic zone V & Seismic
design is based on site specific spectrum.
2 Span-39X45.7m, Steel OWG girder.
2 Overall Length-1.875km.
2 Diaofcircularwell 8.0m,
2 Steining thickness 2.2m
2 Depth of well 39.0m
2 Design discharge 26900 cum/sec
4.8 Rall Cum Road Bridge Over River Ganga At Digha
Ghat, Patna (Under Construction) -
This connect Danapur station of Patna- New Delhi Main
Line (Danapur Divsision) to Sonpur station of Hajipur-
CChhhapra section (Sonpur Division) of East Central Railway.
Thus connect North & South Bihar near Patna. After the
construction of Bridge, the distance between Patna andChhapra will reduce to 70 Km from 250 Km and 120 Km via
rail route (Rajendra Bridge) and road route respectively.
After the construction of bridge, Chhapra, Sonpur, Hajipur,
Vaisalitowns etc. of north Bihar willbe directly connected to
the capital city of Bihar through raillink
Span - 1x64m+36x 123m+1x64m,
Foundation , 39 Nos, well Double D shape of size
18,0mx9,5m, Depth 51.5m
Height ofpier- 15m
Maximum depth of water- 9m.
‘Sheet Pile was used for wells in water
Weight of each girder - 1980 MT (Superstructure
total stee! 73260 MT)
4,9 Munger Bridge (Under Construction)
‘A rail-cum-road bridge having length 3.69 km on river
Ganga. Warren type welded stee! truss having single track
at bottom level and 12m road deck at intermediate!
4.40
el.
‘Span- 1X32.6 m+29X125m-+ 1X32.6m
Foundations - Double D well, 18.0mx 1.0m
Well depth 55.2m
Nooffoundation 32
Design discharge 90,000 cumisec
Mahanadi Bridge
This is a 2” rail bridge over river Mahanadi and located
between Kendrapara Road and Cuttack Station Ithas been
planned in such a way that its spans shall match with the
existing Bridge without causing any obstructions in river
flow due to Sub-structure. The superstructure is launched
element by element with cantilever method of erection. The
‘Super-structure and Sub-structure have been designed for
Heavy Mineral Loading.The Girders are provided with
POT/PTFE Bearings
Design discharge - 18,000 Cumecs
Length of Bridge -2.106km.
Number of Spans -32x64.6m
Type of Girder- Steel Open Web
Design discharge - 18,000 cumecs
4.11 Sone Bridge Under Construction
This is a 3.06 km long rail bridge connecting Dehri on Sone
to
‘Sone Nagar Station of MGS Division and first mega bridge
on pile foundation
NoofTracks 3+1 (future track)
Total length of bridge 3.06 km
Span - 30.8m PSC box, (Total 93 x 3=279 for
three tracks)
Type - Pre-cast PSC Box-girder
concrete
Foundation - Bored cast in situ end bearing pile,
M-30 grade
Diaofppile 1.25m, total 2304 no
Max depth ofpile 39.55m
Design discharge 37,400 cum/sec
» M-45 grade
4.12 Mandovi Bridge
Mandovi is an Esturian river of Arabian Sea, Thisis bridge
No.1 on Mandovi
Span - 1922.8 m+1x124.2m+6x535m+4x
28.8m,
PSC girder except 1 span of 124.2 m, which is a
through type, triangulated steel girder bridge.
‘Adoption of steel girder for the longest span has
helped to reduce the height of embankment.
Sub structures of smaller spans are of pile
foundation varying from 1.5 to 1 mdiabored piles.
For main span, well foundations have been
provided of the dia of 11 mand 9.5m,
M-25 grade of concrete had been used with
steining thickness of 600 mm.
Pneumatic sinking was required for well
foundation due to rocky strata, which took average
of about3 months time for 22 to 25 mofsinking.
4.13 Zuari Bridge
Zuari Bridge is also one of the Esturian river of Arabian Sea.
Railway alignment is crossing the same at about 10 km
Upstream of the sea,
Navigational requirement at this
”bridge site was the same as that was for Mandovi Bridge
and hence a clearance of at least 96 m by 13 m was
required tobe provided.
+ Span- 25x22.8m+4x53.5m+1x124.2m+3x
13.5m+5x22.8m+1x12m.
+ Allthe spans of PSC girders except larger span i.e.
fone of 124.2 m, which is of through type of
triangulated stee! girder.
+ Here also, sub structures are bored concrete type
of piles having varying diameters except for the
larger span where well foundation have been
provided.
4.13 Godavari Bridge-
‘The third Godavari Bridge is another feather in the cap of.
Indian engineers. This architecturally-clegant structure has
an innovative bowstring arch gitder superstructure
constructed in concrete.
+ 28 no bow-string arch girders having spans of
95.55 mlong,
+ Total length is 2.730 KM.
414 2° Godavari Bridg
Itis a Rail Cum Road Bridge.
+ Spans-7x45.7m+27x91.4m
+ Type of Bridge - Through Open Web Girder
+ Material of Super Structure Mild/High Tensile
Steel
+ Loading Standard -BGML
+ Bearing Rockerand Roller
+ Sub-structure Mass Concrete Solid Piers and
Abutments
+ Foundation Well Foundation
4.15 Chenab bridge
It consists longest steel! arch bridge in the world being
constructed on Udhampur Baramula rail link project with
Liber eerie rirtreeerr esr
ey al
total span length of 485m. The National codes (IRS, IRC,
IS) have been augmented with International standards (8S,
UIC and Euro). For estimation of wind load, actual site data
has been generated by way of wind tunnel modeling. Snow
load and blast oad have also been considered in the design
of the bridge in addition to normal loads.
+ Total length of the bridge : 1315 m
+ Height of bridge 359m
+ Main arch span 485m
+ Total no. of spans 17 Nos.
+ Deck width
Viaduct Portion 13.0m
‘Arch portion 17.00m
+ Max. ht ofstes! pier: 133.734m
+ Max ht ofconerete pier :49.343m
(Hollow rectangular)
+ Max. size offoundation
Viaduct portion 18x15x4.15m
‘Arch portion 50x30 m
+ Total steel fabrication: 25000 MT
+ Seismic zone Zone V
+ Wind velocity
level)
220 kmph (at deck4.16 Anji Khad Bridge-
The aesthetic merit of the bridges has been considered,
The number of bearings have been minimized. The
National codes have been augmented with International
standards (BS, UIC and Euro). Utmost care has been
taken in dealing with wind and seismic actions considering
the height and seismicity of the area, Wind tunnel testing
was carried outto assess the topographic effects of the site
on the reference wind speed. Ductilty detailing of hollow
piers have been taken from Euro Code. LWR has been
provided over these bridges using international codes i.e,
UIC 774-3R. Fatigue design has been done as per BS
5400. The dynamic pressure history for blast load
calculation has been taken according to the specialist
advice.
+ Total length of the Bridge: 657m
+ Height of Bridge 189m
+ Arch Span 265m
+ Viaduct Span on Kalra side = 80m (2x 28.41 +
23,18)
+ Viaduct Span on Reasi side : 312 m
(8x 30+3x 24)
+ Total Stee! Fabrication 7000 MT
+ Deck Width 13.50 m
+ Seismic zone Zone V
Wind Velocity(at Deck Level) :189 kmph
4.17 Sardan Bridge
The longest bridge of Jammu-Udhampur project, having
total length of 620 m. Consists of tall piers with maximum
height of about 40 m above bed level. The approach spans
are on 3-degree reverse curves having no straight in
between, This bridge is having 9 spans of 45,2 m PSC
girders for the viaduct on both ends with central spans of 2x
45.2 m + 2 x 63 m constructed by cantilever method of
construction. Tall hollow pier shafts of 20 to 40 m heights
have been cast using slipform-shuttering technique,
4.18 Gambhir Khad Bridge
This is an important high level single line railway bridge on
Jammu-Udhampur Project which was initially proposed as
PSC continuous girders to be constructed by cantilever
construction method. Two piers were already completed,
however, due to some geo-technical problem at the
location of one of the abutments steel super structures was
proposed with spans arrangement of 2x 102m +1x80m.
+ Total length of the bridge : 284m
Mumbai Gets Asia's Tallest Monument
i he ae eT
Global Vipassana Pagoda, the tallest pillarless dor
the world, ‘world mounment of peace and harmony
eee Maes aed
State rue ca Ee
Got
Pee eee Cm)
ic une Matta
eee Olan
Raa
+ Span 80m+2x102m
+ Pierheight : 71mirs, Highest IR, higher than
Qutab Minar.
+ Foundation: : open,
4.19 _ Br. No. 20 Over Jhajjar River On Udhampur-
Katra Section -
This is open web type though girder bridge & tallest bridge
on Indian Railway. The launching of the bridge has been
done by cantilever technique using pull & push method
+ Span - 2X154.0 meters, single longest simply
supported span in India,
+ Pierheight-94,633 meters
+ Bearing -POT-PTFE
4.20 Tawi Bridge-
Continuous PSC Box Girder having a max. span of 102 mir
whichis the longest on Indian Railways.
2 Total length of the bridge
2 Span
2 Open Foundation
Well Foundation
2 Bearing
249.15 Mrs
71.4+102471.4m
2Nos. (P3 & At),
2.Nos.(P1 & P2)
POT-PTFE
5.0 CONCLUSION
Although notable advances have already been made in the
field of bridge engineering in India, there is no room for
‘complacency. The present liberalized economic scenario in
the country with emphasis on development of
infrastructure, particularly highways, bypasses and
superhighways, offers a tremendous challenge to Indian
Railway Bridge Engineers. Railway bridges are mostly with
simply supported girders resting on gravity type piers and
abutments. Special type of construction like continuous
bridges, integral piers with RCC or PSC, curved girders,
bridges on gradients, multiple cel box girders, earthquake
resistant design of substructures and superstructures are
some of the areas where Bridge Engineering has to
develop. Adoption of seismic isolation devices for the
bridge is yet another area where studies have been taken
up. In certain situations, some of these concepts can be
used to reduce the cost of the bridge and improve
maintenance. But this requires sound analysis procedures
and special construction methods. Railway Engineers must
be equipped to tackle these problems and produce well
constructed bridges.
oe
ee MCC
PES cies,
Ties uce rede aR Curom OT as
Ses ivan eV EL ater)
etn rans ee rete ta are
‘mediation hail which can accommodate 8,000 people at
erry
Ronee)
Cera ae tT)