You are on page 1of 17

SewerApprovedMethodStatement

MittonRoad,
Whalley

ExistingSewerNetwork
Thereare3existingsewercrossthesite;

150mmcombinedsewerservingpropertiesfacingontoMittonRoad.

450mmcombinedsewercrossingthesitefromnorthtosouth.

675mmcombinedsewerfollowingRidingLane

ProposedScheme;
Theproposedschemeistoconstruct137residentialunitswithassociatedinfrastructure.See
appendixA.Thereareanumberofinteractionsbetweentheexistingsewernetworkandthe
proposedscheme,therisksarehighlightedbelow;

150mmSewerShallow,closetofoundationsandshareddrive,groundlevelsneedtobe
reviewed.Proposedlevelsareelevatedabovecurrentlevelsbycirca300mm.Highriskof
contact.
450mmCombinedSewerCirca2.5mbelowexistinggroundlevel,multiplepointsof
connectionfornewsewernetwork.Proposedlevelsareelevatedabovecurrentlevelsby
circa300mm.Moderateriskofcontact.
675mmCombinedSewerDeepandremotefromallproposedconstruction.Lowriskof
contact.

DiscussionandMitigationofrisks;
Priortocommencementonsitethedepthandlocationofallexistingsewerswillbeconfirmedand
theirlocationclearlymarkedonthesurfaceat20mcentresandaCCTVsurveywillbeundertakento
recordthecurrentcondition.

Allfoundationswilldesigntopreventloadstransferringontothesewers,duetotheproximityofthe
150mmsewertotheproposedhousingitisatrisk.Asproposedplotsarelocated65mawayforthe
sewerandthefoundingdepthsareatasimilarleveltotheinvertofthesewer,thereisnoriskof
loadingthesewer.SeefoundationscheduleinAppendixB.

The450mmsewersitsdirectlybeneaththesiteaccessroadsotheconstructionoftheroadneedsto
beconsidered.SeeAppendixCLongsectionshowingproposedroadandsewersalongwithexisting
sewer.ThesectionofsewertohavearoadconstructedaboveitrunsfromUU6508(EGL46.10,
ProposedCL46.40,IL43.40)toUU6401(EGL45.034,PCL45.76,IL43.13),alongthisentirelengththe
proposedfinishedroadlevelisabovethecurrentgroundlevelthusincreasingcovertothepipeand
ensuringthatexcavationabovethepipeislimited.

Theproposedroadconstructionisgenerally600mmbutthiscouldincreaseto900mm,sothis
excavationfortheroadcappinglayerwillbeinexcessof2.5mabovethesewer.Intermofprocess
thetopsoilwillberemovedandtheroadfootprintexcavatedtoformationlevelwhereuponitwill
bebackfilledwithsuitablecrushedstoneorconcrete,thusprotectingtheexistingsewer.

Installationofproposedsewerstheproposedsewersdonotunderminetheexistingnetworkand
thereforeriskoflateralmovementislimited,irrespectivethiscorrectuseoftrenchsupportsand
shoringwouldpreventthisforoccurring.

Methodstatementandriskassessmentforinstallationofnewsewersandcrossingof
theexistingsewers;
AppendixDcontainsthecontractorsriskassessmentfortheinstallationofnewsewersdiscussing
themethodsforconnectingontoandcrossingtheexistingnetwork.

WithregardtotheexistingnetworkUnitedUtilitiesstandardmethodswillbeadopted,theseareas
follows:

Demolition,piling,tunnelingoranyotherconstructiontechniquewhichinducessignificantvibration
(notexceedingapeakparticlevelocityof5mm/s)shallbepermittedupto10metresawayfromthe
Pipeline(s).PermissionwillbegrantedbyUUprovidedthatthePromoterhasaccuratelyestablished
thepositionofthePipeline(s)andthishasbeenverifiedbyUUandawrittenstatementofthe
precautionstobetakentoensurethesafetyofthePipeline(s)hasbeensubmittedbythePromoter
andreceivedandconsentedtobyUUpriortoworksbeingundertaken.

Shoulddemolition,piling,tunnelingoranyotherconstructiontechniquewhichinducessignificant
vibrationbeproposedwithin3.510metresofthePipeline(s)thisshallbesubjecttoseismic
monitoringinordertopreventdamagetothePipeline(s).ThePromotershallaccuratelyestablishthe
positionofthePipeline(s).SeismographreadingsshallbetakenbythePromoter'sspecialist
organisationonthelineofthePipelineatlocationstobeagreedwithUU.Vibrationmonitoringshall
bedoneunderthesupervisionofaspecialistorganisationwhichhassignificantexperienceofsimilar
monitoringwork.TheidentityofthespecialistorganisationshallbeproposedbythePromoterand
approvedbyUU.Thisapprovalshouldnotbeunreasonablywithheldordelayed.Thecostofthe
seismicmonitoringshallbebornebythePromoter.Vibrationshallbemeasuredintermsofpeak
particlevelocity(PPV)andthePromotershallemploysuitablemethodsofconstructionincarrying
outitsworkssuchthatthePPVdoesnotexceed5mm/s.IfthemeasuredPPVdoesexceed5mm/s
thenworkshallceaseimmediatelyandareviewofthemonitoringdatashallbeundertakenbetween
thePromoterandUUEngineeringstaff.IfnecessaryUUshallnotifythePromoterofanyreasonable
mitigationmeasurestoprotectthePipeline(s)thatitrequiresthePromotertocarryout.The
Promotershallcomplywiththesereasonablemitigationmeasuresincarryingoutitsworks.Awritten
statementoftheprecautionstobetakentoensurethesafetyofthePipeline(s)shallbesubmittedby
thePromoterandreceivedandapprovedbyUUpriortoworksbeingundertaken.

Movementofvehiclesandplantwithatotalweightexceeding6tonnesacrosstheunprotected
Pipelineisforbidden.Therepetitivemovementofvehiclesorplantofanyweightoverthe
unprotectedPipelineinthesamepositionisforbidden.Wheretemporaryorpermanentaccessis
required,thePromotermustconsultwithUUpriortogainingaccess.

EachproposedtemporarycrossingpointofaPipelineshallbeconsideredonanindividualbasis.The
PromotershallsubmitthedesignoftheproposedcrossingpointtoUUforacceptance.Workto
constructthetemporarycrossingpointshallnotcommencewithoutpriorwrittenconsentfromUU.

ThePromotershalldesignanytemporarycrossingpointsuchthattheloadfromanyvehicleorany
itemofconstructionplantthatwillusethecrossingpointcreatesasuitablyfactoredbearingpressure
ofnotmorethan8.5kN/m2atthecrownoftheUUPipeline.(N.B.Thisloadisapproximately
equivalenttotheloadingonaPipelinewith900mmofcoverwhena6tonneexcavatorcrossesabove
it.)Inordertoachievethis,thePromotermayusesubstantialtimberbaulks,reinforcedconcrete
slabsorproprietarygroundprotectionsystems(e.g.EveTrakway).Whereitisnotpossibleto
distributethesurchargeloadfromtheplanttolessthan8.5kN/m2atthecrownofthePipeline,then
thedesignofthetemporarycrossingpointshallconsistofasuspendedcrossingwhichbridgesover
thePipeline.

TemporarycrossingpointsshallonlybeusedtoallowvehiclesandplanttotraverseacrossaPipeline.
Temporarycrossingpointsarenottobeusedasworkingplatformsforconstructionplant.Plantshall
notbeallowedtooperateaboveaUUPipelineunlessspecificwrittenconsentisgivenbyUU.Any
requestbyaPromoterforthemtositeworkingplantaboveaUUPipelinemustdemonstratethatthe
platformwhichtheirplantistobesitedonhasbeendesignedasaworkingplatformandwillensure
thatthemaximumsurchargeloadfromthatplantisdistributedtolessthan8.5kN/m2atthecrown
ofthePipeline,orbridgesoverthePipeline.

Allpartsofatemporarycrossingpointmustberemovedwhentheworkiscomplete,unlesswritten
consentisobtainedfromUUforthecrossingtobeleftinplace.Thedesignandconstructionofthe
temporarycrossingpointshallbesuchthatitpermitsforitsremoval(andthereinstatementofthe
groundbeneathit)withoutexposingthePipelinetoundueloading,vibrationorrisk

PondConstruction;
Theproposedpondistobeconstructedadjacenttotheexisting450mmcombinedsewer,thepond
islocatedoutsideoftheUnitedUtilitiessewereasementandisgenerallybetween5m(minimum)
and10mtotheeastofthesewer.Thebedlevelofthepondisbetween41.863mAODand42.163m
AOD,theinvertofthesewer42.51mAOD(worstcase).Theedgeofthepondwillbesituatedsome
5mfromthesewer,thedeepestbedpointwillbesome11mfromthesewer,themaximumlevel
differenceis0.68mgivingagradientof1:16whichisstableisallsoilconditions.

Thepondwillbeformerbyremovingthetopsoil,excavatingthesubsoilandthenliningthebasin
withpuddleclaytoformanimpermeablelining.Thesidesofthepondsaretobebatteredat1:3to
ensureslopestability.

Uponreviewingtheproximityofthepondtothesewerandtherelativeinvertlevels,itisclearthat
thesewerhighlyunlikelytobeimpactedbytheconstructionofthepond.Howevertoensurethat
thereisnochanceofthesewerbeingimpactedduringtheconstructionphase,insitugeotechnical
testingwouldbeundertakentoensureslopestabilitycanbeensuredandifnecessarysheetpiling
willbeinstalled.GeotechnicalreviewanddetaileddesigntobeagreedwithUnitedUtilitiespriorto
construction.

AppendixA
MainDrainagePlanDWH133101_DRAINAGE_LAYOUT_P3

DO NOT SCALE
Notes
NOTE 1. Drainage design and construction is in accordance with Sewers for Adoption 6th
The use of any other flow control device not associated with the Hydro International Edition and the requirements of the statutory undertaker.
Hydro-Brake Optimum reference SHE-0245-3320-1050-3320 may constitute a flood
N 2. Tolerances in pipe laying to be in accordance with Sewers for Adoption 6th
risk. Should an alternative device be considered, the Betts Associates Engineer Edition clause 4.5.9
shall be contacted to check if it is compatible with the design model and discharge
3. For pipes 150-450mm dia. all rocker pipes to be in accordance with Sewers for
W E
constraint. Betts Associates will not accept any liability from flooding caused by the Adoption 6th Edition.
Existing stone wall to be
use of an alternative flow control product.
4. Engineering bricks shall not contain frogs or holes.
retained. Openings to be
S cut and made good. New THE ADOPTABLE DRAINAGE WORKS ARE SUBJECT TO TECHNICAL
stone pillar to terminate
5. Brickwork to manholes to be english bond.

WORKS TO EXISTING PUBLIC wall (see detail) APPROVAL BY UNITED UTILITIES AND MAY THEREFORE CHANGE

1
ROAD
W 6. Where pipes are surrounded in concrete, flexibility is to be maintained at pipe
SEWER MANHOLE UU6508 joints by the use of a suitable compressible material eg. "flexcell" or
Cover to be raised to proposed finished road level FFL 47.50 "fibreboard".
S1 CY16FFL 48.1
W W
CL46.406 CY17 CY7
CY16 5
W

CY16 7. All manhole covers and frames must comply with BS EN124. Covers in roads to
be grade D400 and be 150mm deep. Manhole covers in car parking areas and

45.056
UU6508 45.12
5
exg sewer drives to be grade B125, whilst landscaped areas may be grade A15.
il 43.40 (450) 5 4 3
5
2
UU7504 8. Clayware pipes to be 65 extra strength quality "hepseal" or similar approved.
1

W
exg sewer

W
6
CY7 il 45.36 (150)
9. Granolithic benching to manholes to be 40mm minimum thickness.

6.25
6 1

FFL 4
6 1
CY7 10. Precast concrete chamber rings to be reinforced.
2

Type C 1:100
7

W
11. The slope of benching in all cases should be 1 in 30.

LAY

AS
2

W
GSL 46.1

150m1m.000
@
0 9 3

CY15 3 12. Manholes shall not incorporate double square or double oblique channel
GSL 46.1 E
4 junctions in their inverts.
0 8 4
8 9

W
7
13. All incoming pipes shall be surrounded with 150mm of concrete to the face of

W
7

CY7 the collar of the first flexible joint and the outgoing pipe shall also be surrounded

5
16

FFL 46.2
9 14 16 to within 50mm of the first flexible joint and a compressible filler used as a
UU8501 former between the concrete surround and downstream pipe collar.
15 15 14
exg sewer
F5 CY7
14 il 47.55 (150)
CL46.184 44.86 10 15
16 14. All underground services to be confirmed by contractor prior to commencement

W
10

W
13

44.434
10

11 CY16 17 on site. Any discrepancies to be reported to engineer.


WORKS TO EXISTING PUBLIC GSL 46.2

.575
E 75
CYG1 CY1675 W
6.5

44.543
SEWER MANHOLE UU6401

L 46
CEG1 15. Private sewers not located in roads to be Class F granular bed and surround as
CY16 FL 4 FFL

OPP
11 CY16 E

GS
18

GS
F 46.7 per standard details.

FFL 46.42
44.47

Type C 1:80
Cover to be raised to proposed finished road level

L
W
S2 25

LAY
CY16

46.
CYG1 13

150mm2.000
@

225mm .001 44.468

425
and chamber modified with proposed incoming CL46.251 17
CY10 E 19
W 18
16. Sewers located under adopted roads to be Class S granular bed and surround

Type CL 51
150mm connection GS
L 46

@ 1:1
FFL

AY
13

5
W
F2 43.91 .425
CEG2 (more than 1.2m cover.)
12 12 1.001 CL46.581
17
46.7 E

1
SEWER CROSSING F3 S7 150mm @ 1:150 44.31 18 OPP CE5 25 E
CL46.393 CL46.436 Type CLAY 43.870 FFL
CE5 20

FFL
Levels of existing sewer to be 46. 17. Sewers located under private roads and car parking bays to be Class F

.275
752

OPP
CY8SP 43. 725 19
granular bed and surround as per standard details unless adopted, then provide

46.

L 46
checked on site before site 43.910 AS
F6 S3 02 150
2.002 43. 20 CEG1
842

50
985

GS
CL46.107 CL46.135 1.0 @ 1: Y 43. 300mmV @ 1:245 E Class S (if more than 1.2m cover).
start and Betts Associates m CLA
V
Type CONC
S6 FFL 21
m

44.3
150 Type CL46.621 19
Engineer notified immediately 43.64 46.5
CE6

225 pe CLA
20

70
43.83 OPP 75 18. Private sewers with less than 0.6m of cover to be concrete surrounded as class

mm
Ty

1.00@ 1:28
03 243 44.34 21
22
FLOW CONTROL CHAMBER MH S31 2.0 @ 1: C

2.001 1:24
z on standard details.

150m e CLAY
F4

2
OPP OPP AS 53
m m CON
CL46.103 300 Type

m@
Hydro International HydroBrake Optimum

Y
CE5

.575
55
03 49 FFL

Typ
1.0 @ 1:1 Y 67 56 46.500 CY7
CY7FFLCY7
52 21
OPP
46.4 19. Adopted sewers with less than 1.2m cover, provide class z concrete bed and

L 46
SHE-0245-3320-1050-3320 m m CLA 43.5 E
25

.275
150 Type
56
FFL 150 1.

GS
Design head = 1.05m E CY13 OPP
225 2.0 m 00 CE5 23 surround. Concrete haunching may be suitable for large diamater storage
46 Typ m @ 10

L 46
43.7
mm 01 CEG1
690
52.725
53
eC
Restricted discharge max. = 33.2 l/sec 43. Typ @ 1 LAY :135 AS E sewers, guidance must be sought from adopting authority prior to use.
AS
35

GS
6
46. e C :170

6
2 5 SL LAY
5 .49 3.61 S8 43.63 E GCEG5 51
14 43 4 FFL
04 1 : CL46.038 46.5
1.0m @ LAY 200 55 54 53 20. Road gullies to be trapped.

CE
S37 (node) 44.37 24
23 325 46. CE4 75
C 22 OPP
CL44.100 0m e D
A .00 1: C GS
15 Typ
FFL

4
O
R 1 @ ON 54 50 FF L 4CEG3
6.42
m 51 L4 E 5 21. No deep or wide routed trees to be planted within close proximity of the
5m e C CY2 6.4 44.68
S32 9 37 Typ 50
2
.36 5 GS proposed and existing public sewer system.
POND OUTLET 42.37
4 CL44.023 UU6401 43
56
54
V
44.
336 FFL E L 46
.35

25
46.5

0
CL45.736 51
CY7 25

5.6
44.

43.565
Headwall with pipe safety grille S9 23

AS
6.4
V
CE4

AS
50 49 4 11 OPP 0

L4
1.010 :301 CL45.767 CYG1
57 S5 23
E 22. All existing public sewer levels and indicative pipe/chamber locations have been

L4
E

GS
1 CL46.353
m@

FF
S38 (node) 375m
UU6401 CY7 F1 24
taken from sewer records. A drainage survey should be carried out to before a
FFL

OPP
CL43.200 C CL46.366 44.52 24

375
CON CE2 46. site start to confirm pipe sizes, invert levels and pipe locations.
Type exg sewer 44.4 25

mm
1.0 1:3
57 GS 65 89

Typ
il 43.13 (450) 49
150 2.00

09 00
GS L4 FFL

@
24
L4 CEG1 6.2 CE1 m 0

eC
S33 5.6
CEG3 75 Typ m @ 1 24
CE746.5
6

FFL E 58 OPP
.27

0 S4

ON
CL43.896 49 e C :10 0

E
44.87 25
45.
42

LAY 0

C
40
CE9 44. CL46.272
00

57
S39 (node) 75 CE1
.23 5mm 011

V
720
1:3

CL43.150
OPP 59 39 CE3
1.

42.
44.55
@

S31 59 FFL

442
58 38
NC

S41 (node)
41
46.6
CO

58

5
CL44.213
Legend
37

OPP
48

46.6
CE1
2

CL42.652
pe

V 44.60

3
CE1
Ty

s) FFL

:40
42

1.014
ord

mm 1.008
47
12

FFL

.50
FFL
@1
600mm @ 1:127 rec 45. E
1.0

S40 (node)

C
S34 (new headwall) 39
46.3

L 46
AS CE4 75 38 CY2

ON
m

Type C 1:96
46
(fro
42 CYG2
CL42.450 CL43.300 FFL 137 50

eC

GS
ONC
2 40
Type CONC 1:9

600

375mm.004
1.013 45.9

@
S35 (node)

Typ
45
@ CE7 75 CE1 GS27LCYP2
CL43.470 er OPP 45.9 26

1
41 GSL
sew S30 39-48 & 137 37 CY2 75

AS
27 46G2
exg
44
S36 (node) CL44.061 E CE .350

466
43 43 42

5
CL43.550
OUTFALL TO EXISTING STONE WALLED 42.
44

6.27
CY12 E

25
AS
CE2 Proposed adoptable SW sewer and manhole

OPP
45
CY14 35

46.1
36

4
DITCH FFL

AS

FFL
FFL 46
48 37
CY12 27 26
V146.5

FFL
CE1
46.6 35
00

AS
Proposed 375mm outlet pipe to discharge to existing ditch via CE1

0
5 CY2 37

45.3
28

5
new headwall CE15 34 Proposed adoptable FW sewer and manhole

46.6

AS
CE1

25
30 28 28

45.8
FFL

OPP
47 CYP1
FFL

FFL

GSL
30
CE1 36
29
V2
46.5 Proposed SW dragout chamber and lateral
UU6402 34
00

AS
29
exg sewer 36 Turning Area
33

AS
il 42.51 assumed (450)
134 134
CY12 Proposed FW dragout chamber and lateral

5
135 44.40

7
il 42.36 (600) FFL FFL

AS
135

45.9
AS

5
134
CE11

45.1
45. 29 V246.3
CEG4 15 33
5 0

GSL

FFL
F8 CY2 Proposed road gully and 150mm connection
OPP

GS E
32

AS
S10 L4 CL45.769

46
CEG4 44.01
5.0

43.9
CL44.945 0 FFL
9 0

136 44.35
30
5.00
43.0

V246.3

40
GSL

44.2
CE4 136 S11 32
5 0
FFL 4

CL45.714

44.7
AS
31 Proposed public sewer easement

AS
CEG3

AS
E0
OPP
133 135 FFL
76
46.2

5.00
FFL 45.60
CE9 V3
FFLCE9

FFL
133 CE15 45.45 E 31 00
E

FFL 4
2 74
GSL 45.300
4.85

CE4
e CO 11

44.8
G

AS
133 CEG5 CE
Typ @ 1:1

44.70
CEG3 GSL 45.450
GSL 4
NC
mm 5

73
E
375 1.00

5
76 E

OPP
AS CY4 136
GSL

FFL

e C 1:80
44.85 124 77

e C :135
E 126 EGSL Existing public sewer easement

Typ m @ 0
OPP

LAY
m 0
225 3.0
126 44.63

LAY
mm 0
4.63

Typ @ 1
150 1.00
CEG1
4 43.07 76 76 75 FFL V
GSL 74
FFL 44.85

E
130 CYG1 43.41 45.
CE7 AS
129
45

OPP
CE4 126
77
DETENTION BASIN 132 128
124
FFL

AS
V
S28 73 CY2
45.5
15

No infiltration - lined with clay or 128 CY10 CY6 75


25 Existing combined public sewer

OPP
127
42.7

42.463 CL44.598

AS

AS
E

RO

00
impermeable membrane 42.491 78

FFL
127

44.78
125 80
79 CY7 72

45.3
AD2
Bed level = 41.863 to 42.163m S29 1 06
600mm .0 43.01

25
V
127

44.7
@ 1:3 42.96

OPP
42.4

43.71
Type CO 93

45.5
79
GSL

CY7

FFL
87
E

FFL
F13

OPP
Permanent water level = 42.463m NC CY4
91

128 78

8
CEG4 CL44.656 GSL 87
F9 71
44

GSL
CY7

FFL
132
Top water level (100yr+30%) = 43.455m 43.29
E45.15 GSL Development boundary
.70

129 CY10 .63 CL45.176

OPP
CYG1
131 74 4 0
44.6
AS
Top of bank level = 43.755 132
42.8 SL4
CYP2
CY12
44.02 87 CY345.3 65

75
G
86 FFL 0
3

45.0
Freeboard depth = 0.30m S12 44.05 45.3
CY7 70 E
CY7 OPP
AD2
600

21
21 80 79 CL45.131 75

OPP
130 8 RO 42.9

43.6
68

FFL
Side slopes = 1:5 44.7
3.00 @ 1:40

CY12
mm

FF

61
Typ

OPP

UU5302 CY7

82
FFL
125
S18
L4

60
8

43.6
Earthworks batters = 1:3 CE11 43.81
e CO

68
exg sewer

.925
OPP CL44.710
CY7 85 69 65

AS
4.8

60

FFL
CY7

AS
AS
il 41.54 (600) 5 0 81 CYP1 86

L 44
1.00@ 1:15
NC

OPP

e CL 50
mm e CLAY

GS
FFL

45.0
POND INLET GSL 85 86 CY12

Typ @ 1:1

5
44.7 50

AY
1 Typ 45.7

7
OPP
mm 1
CEG4 AS
0 V3

150 1.00

45.0
E 69

75
FFL 44.78 CY7 85
0

OPP
Adoptable headwall with pipe safety grille

e C :76
CY10 84 CY12 68 61

m 01
Typ m @ 1
CY12

LAY
69

FFL

OPP
AS 67

225 3.0
5 9

45.0
3.00@ 1:39 82
42.5

81

GSL
S27 AS

150 ype C
m ONC 115 FCY10 70

OPP
42.49 131 42.58 0 m FL 44 66 67
FFL
63

45 ype C

FFL
CYP1 82 CY12

mm

25
CL44.398 F15 131 .78

44.9
1.00@ 1:15
UU5301 81
45.5

T
43.14 T 83 V2

44.9
AS 70 62
CL44.511 F14 66 CYP1 67 5

25
4
exg sewer 1.006 FFCY10
L 45.
V
82

GSL
CL44.664

AS
S14

AS
08 62

LAY
il 41.55 (675) 84 71
150mm @ 1:150

OPP
GSL

GSL
E

0
600 3. 42. CL44.893

72
Type CLAY 44.02
600 FFL

OPP
mm 00

450 ype CO

OPP
42.403 CYG1

43.3
Typ @ 17 8 CYG1 FFL 4 84 71

44.7 F10
44.6

44.7
116
CY11 5.075 45.0
CY2 FFL

mm
42.496

3.00@ 1:4
e C :396 42.750 L CL44.893 43.3
CY10 75 45.4
3

F 114 E 43.76

75
ON F FFL 4
72 72 63
V2

4 01
C 0

Typm @ 1: .147
AY 50
3.006 42.780
RO 42.403

115
GSL
42.60
4.925 66

1
CL 1:1
Ty m @.002

.43
114
42.900

NC
72
450mm @ 1:395 CYP1 63

2 3
LEAP
AD3

5 CY10

OPP
AS 116

43

e C 401
450 3.00 4
44.8
44.9

0m 1
117
S19 F11

ONC
Type CONC 83
43.12 L
CY8 114
3

pe
CL44.621 F CL44.800 225 4.00 43.71
FFL
AS RO

15
S26 AD4 m
Typ m @
0
45.2
64
V2
OPP
CL44.480 CY7

m
e C 1:17 5
FFL

V
GSL

E 116 3.36
8 LAY 0
GS

E 3 4
CYG1 1.00 1:150
L 44

44.6

OPP
CYG1 24
300mm @ 1:251

@ Y
43.1
43.46
150mm @ 1:150

m
5.08
CONC

m
150 ype CLA
92 43.5 64
FFL

.70

113
Type CLAY
6.005

CY7 S15 43.71


92 38
AS

T
AS

118 117
1.007

CL44.794 FFL
44.

V1
Type

CE13 CY6
FFL
OPP
S13 45.2

43.2
78

.78 3
3.00 1:403 45 CL44.914 5
L 44

01
111GSCY4 112 .15 AS
42.981

OPP
E @
F12 5 0 mm CONC 91
4
43.0
1.008 S25 GS CL44.895
Typ
e CY7 89
L4
.15

E
41.935 150mm @ 1:150 CL44.677 E 4.6 E
45 5CE1 90

FL 4
CEG4
3 119 111 OPP
OPP

F23
113
CY7 F GS
UU6301 S17 92
CY3L90
88

E
43.
UU6301CL44.611 Type CLAY 42.242 CL44.703
112
CE1 45.0 OPP
FFL

CL44.968 270
93
111
0
WORKS TO EXISTING PUBLIC exg sewer 118
109 CY7 CE2
AS
45.1

il 41.65 (675) FF 91 CYP2


GS

94
30 118
L4 RO 95
89 FFL
SEWER MANHOLE UU6301 15 2
L4

0 6 CEG4
E

AS
Ty mm @.004 4.7
5

0m .00 CE11 AD3 45.1


4.6

Ty m @ 6 pe 8
108 91 V1 50
3

Chamber to be modified with proposed incoming 1


CO :2 CY1
AS

pe 1: 109 89
108
225 ype C

CL 150 NC 45 107 96 V

FFL
119 110 V
AY
T

90
mm LAY

AS
5.0 @ 1:1

150mm connection AS CE1 V 88


00 7
GSL

119 107 106 V


S24 E

45.1
CL44.696
119
120 CYP1 V
88 FFL V3
45.0

43 E 44.78
107 106 V 93-102 45.1

5
0

.10 43.30 119


0

6
42.58
110GSCY3
L V 50
42 V

AS
OPP

CY12
FF

FFL

43.

102
OPP

.5 27 CE4 V
S16
L4

415

43.53 CE3 V
45.1

CL45.154
4.7

F22 110 106 101


AS
8

CY12
225 ype C

CL44.673 CE1
5

105
mm LAY

100
6.00@ 1:1
T

GS
150 ype CLA

43.54 97
P3 05.05.16 SD MINOR LEVEL AMENDMENTS, ISSUED FOR
L

43.40
121 CE1
3 70

CEG3
E

44

105 104
mm
T

2.00@ 1:15

5.15 APPROVAL RA
.63

105 CE1
99
4
5

120
104
98
FF
CE1L P2 22.04.16 SD CLIENT COMMENTS INCORPORATED, AMENDED RA
GS
Y

FF L TO SUIT SITE LAYOUT REV F AND INCLUSION OF


0

V
S23 120 L4 E 44
CEG4
43.

.8 104 CE1
42.6

FFL
CL44.734
OPP
CE45.0 5 EXISTING CULVERT FOR EA APPROVAL PURPOSES
292

UU6302 0 CY6
36

225 6.0
122 P1 08.02.16 SD FIRST ISSUE RA
45.1
mm 02 CE2
4.925

exg sewer
F21 Typ @ 1:1
il 41.71 (675) e CL 70 121
5

CL44.663 AY 123 103 F16


OPP

121
FFL 4

CL44.993
89

150 2.0 43.3 S22


2

mm 04
43.

80 CL44.862 42.82 121


Typ @ 1:
e C 150
LAY 42.7 22 1 12
FFL CY6 FOR APPROVAL
AS

64 5m 6. 45.0
Ty m @001 CE9 GSL
0 44.85
e C :135

pe CEG2 103
CL 1:17 AS E
Typ @ 10
LAY

AY 0
mm .00

F20 E 44.78
FFLCE8
150 2

1 43.21
CL44.886 50m 2.
Ty m 003 OPP 103 F17
pe @
CL 1:1
AY 50 43
S21 122
CL44.771 50.000
.50 CL44.982 123 1
2.00 1:150
42 1 225mm6.000
.88 m@ Y 57
0 @
Type C 1:171
43.72 150mype CLA 43.1
LAY T
43.602
F19
CL44.969 150m 2.002 43.00
7
m
Type @ 1:150 S20
CLAY CL44.821
F18
CL44.811

45.000

MITTON ROAD
WHALLEY
DATUM 40.000

RD1 SECTION 104


ADOPTABLE DRAINAGE LAYOUT
CHAINAGE

EXISTING GROUND LEVEL

DWH133 101 P3
AppendixB
FoundationScheduleDWH133MittonRoad,Whalley,Lancashire1001FoundationTable1REVP2

DO NOT SCALE
Notes
1. This drawing is to be read in conjunction with the standard details, the layouts,
RAISED CARRIAGEWAY schedules and specifications for the development.

RD4

RD2
2. A +1% gradient represents a rise of 1m in 100m.

3. Left and right hand channels are on the left and right hand side respectively, when
standing at zero chainage and looking along the road.

S28

S29
S14

S15

S17

S18
F10

F11

F12

F13

FUU6301
4. A level at any point 'x' m from the start of a vertical curve is given by the formula:-

F23
AX (A - B) x
Level @ 'x' = level @ start of the curve + ------- - -----------
100 200L

where 'a' and 'b' are the gradients at the start and end of the curve respectively and
having the algebraic signs +/,- .

5. Pipe sizes are stated in millimetres and levels are shown in metres A.O.D.
45.000

6. All pipes to have flexible joints with granular bedding (Class S) unless stated otherwise.
45.000 Where 150mm concrete bed and surround is specified the concrete must be broken at
the joint positions by the insertion of a 'flexcell' collar.
RAMP Attenuation Pond
IL 42.463
7. Connections to existing sewers are to be SOFFIT TO SOFFIT unless noted otherwise.
45.000 Dia 375
IL 42.715 Dia 600
IL 42.491 8. All vitrified clay pipes to be EXTRA STRENGTH to B.S. 65. 1991.
Dia 150
IL 42.336
Dia 225 Dia 225 Dia 150 9. 'MV' is equal to the rate of change of gradient and is calculated from the formula:-
IL 43.372 IL 42.242
IL 43.270 (A-B)
MV = 100 * ----------
40.000 L

40.000 where A and B are as in Note 4 above.

10. Existing levels to be confirmed on site prior to commencement of works.


DATUM 38.000 DATUM 39.000
40.000
S28 to S29 F23 to FUU6301 11. All concrete pipes to be CLASS 'M'.

44.161
44.598

44.572

44.670

44.703

44.094

44.087

44.062

44.033

44.094

44.320

44.442

44.547
12. Refer to Betts Associates drainage layout drawing DWH133-101 for further drainage
GROUND LEVEL GROUND LEVEL notes.
DATUM 38.000
484.176 483.901

512.102
512.222
475.000 475.129
475.537 477.686

485.611 487.507

558.816
560.774

43.704

44.612
44.598

44.703
RD2
529.113 HP
495.000 LP
465.000

470.000

480.000
482.458

485.000

490.000
491.012
493.009

495.369

500.000

503.868
504.176
505.000

510.000

515.000

519.183
520.000
521.387

525.000

530.000

535.000

540.000
541.387

545.000

550.000

555.000

560.000
560.193

565.000

570.000
571.630
571.640
STORMWATER COVER LEVEL FOULWATER COVER LEVEL

CHAINAGE

42.491

42.242
42.463

41.935
44.041

43.981
44.043

44.048

44.060

44.103

44.122

44.120

44.134

44.136

44.104

44.067

44.039

44.017

44.004

43.944

43.890

43.777

43.717

43.656

43.600
43.587
43.835
STORMWATER INVERT FOULWATER INVERT

EXISTING GROUND LEVEL


Pipe 1.006 Pipe 1.008
Dia 600 Dia 150
Circular CONC Circular CLAY
44.901

44.731
44.790

44.812

44.960
45.025

44.975

44.925

44.875

44.833
44.825

44.777
44.777

44.787

44.818

44.858

44.897

44.936
44.947

44.969

44.978
44.977

44.917

44.856

44.793

44.668

44.606

44.543
44.523
STORMWATER DETAILS 1 in 393 FOULWATER DETAILS 1 in 150
Class S bed & surround Class S bed & surround
ALIGNMENT LEVEL Crush. Load Min. 72 kN/m Crush. Load Min. 40 kN/m

11.015 46.117
STORMWATER LENGTHS FOULWATER LENGTHS
G= -1.000% KF= 11.19335 G= 0.787% L= 20.000 G= -1.250%
VERTICAL ALIGNMENT
1: -100.0 L= 20.000 1: 127.1 KF= -9.81944 1: -80.0

HORIZONTAL ALIGNMENT R= R= 9.750


5.000

S30

S31

S32

S33

S34
42.921
44.771

44.951
44.956

44.906

44.856

44.806

44.757

44.717

44.769

44.778

44.810

44.849

44.888

44.928

44.960

44.969

44.909

44.847

44.785

44.722

44.660

44.597

44.535
44.514

LEFT HAND CHANNEL


44.791
44.786
44.840
44.837

44.847

44.878

44.918

44.957

44.996

45.029

45.037

45.020

44.977

44.916

44.853

44.728

44.666

44.603
44.583
45.025

44.975

44.925

44.875

44.825

CENTRE LINE

Existing 450mm dia. public combined sewer


44.771

44.951
44.956

44.906

44.856

44.806

44.757

44.717

44.810

44.960

44.847

44.722

44.660

44.597

44.514
44.769

44.778

44.849

44.888

44.928

44.969

44.909

44.785

44.535

IL circa 42.83m AOD - crossing to be


45.000 checked on site and appropriate concrete
RIGHT HAND CHANNEL surround of crossing provided

CROSSFALLS
Attenuation Pond
IL 42.462
Exg Ditch
IL 42.232
44.893

44.794

44.968

44.710

P3 06.05.16 SD EXG PUBLIC SEWER CROSSING SHOWN ON


STORMWATER COVER LEVEL
SECTION S30 TO S34 RA
P2 05.05.16 SD ISSUED FOR APPROVAL RA
P1 08.02.16 SD FIRST ISSUE RA
42.921
43.372
43.147

43.124
43.124

43.045
43.045

40.000

STORMWATER INVERT

Pipe 3.001 Pipe 3.002 Pipe 3.003 Pipe 3.004


FOR APPROVAL
Dia 225 Dia 450 Dia 450 Dia 450 DATUM 38.000
Circular CLAY Circular CONC Circular CONC Circular CONC
STORMWATER DETAILS 1 in 76 1 in 401 1 in 403 1 in 401
Class S bed & surround Class S bed & surround Class S bed & surround Class S bed & surround S30 to S34
Crush. Load Min. 45 kN/m Crush. Load Min. 54 kN/m Crush. Load Min. 54 kN/m Crush. Load Min. 54 kN/m

44.061

44.231

44.011

43.931
44.212
44.137

44.215

43.930

43.944

43.919

43.897

43.756

43.958

43.677

43.156
GROUND LEVEL
23.497 9.228 31.828 49.688
STORMWATER LENGTHS

44.061

44.213

44.023

43.896

43.300
44.800
44.893

44.895

44.656

STORMWATER COVER LEVEL


FOULWATER COVER LEVEL

42.462

42.438

42.438

42.372
42.372

42.274
42.274

42.232
43.431
43.431

43.201
43.201
43.368
43.368

42.874

STORMWATER INVERT
FOULWATER INVERT

Pipe 1.008 Pipe 1.009 Pipe 1.010 Pipe 1.011


Pipe 1.001 Pipe 1.002 Pipe 1.003 Pipe 1.004 Dia 600 Dia 375 Dia 375 Dia 375
Dia 150 Dia 150 Dia 150 Dia 150 Circular CONC Circular CONC Circular CONC Circular CONC
STORMWATER DETAILS 1 in 403 1 in 302 1 in 301 1 in 298
Circular CLAY Circular CLAY Circular CLAY Circular CLAY
FOULWATER DETAILS Class S bed & surround Class S bed & surround Class S bed & surround Class S bed & surround
1 in 150 1 in 150 1 in 150 1 in 150
Class S bed & surround Class S bed & surround Class S bed & surround Class S bed & surround Crush. Load Min. 72 kN/m Crush. Load Min. 45 kN/m Crush. Load Min. 45 kN/m Crush. Load Min. 45 kN/m
Crush. Load Min. 40 kN/m Crush. Load Min. 40 kN/m Crush. Load Min. 40 kN/m Crush. Load Min. 40 kN/m

9.667 19.904 29.494 12.510


STORMWATER LENGTHS
FOULWATER LENGTHS
28.551 9.360 25.028 49.022 MITTON ROAD
WHALLEY

ROAD & SEWER LONG SECTIONS


ROAD 2 (ch.465.00 to end)
& DRAINAGE SECTIONS

THE ADOPTABLE DRAINAGE AND HIGHWAY WORKS ARE SUBJECT TO TECHNICAL APPROVAL
BY UNITED UTILITIES AND LANCS CC RESPECTIVELY AND MAY THEREFORE CHANGE
DWH133 104 P3
AppendixC
LongSectionDWH133102_LONGSECTIONS_P3

Westbourne Civil Eng. Ltd. RISK ASSESMENT & METHOD STATEMENT


Sheet 1 of 4

Site Name: Mitton Rd, Whalley Date: 1/12/2015 SSW No. WBCE

Written By: A Gallagher Site Approval:

Client Review: D.W.HOMES Signature: *


* If this Safe System of Work is issued to several persons each should sign overleaf

Activity: Drainage 1.5m- 3.2m installation depth alongside existing Sewer


Examples of Common Hazards: Put x by the ones that apply
Fall from height x Trip on level x Falling objects x Fragile material Electrocution x Manual Handling X
Explosion x Noise Dust Striking object Asbestos Struck by traffic
COSHH Fire Lighting Cutting accident X Eye injury Struck by plant x
Collapse of x Contact hot Collapse of X Lifting Equipment x Drowning or x Confined Spaces x
excavation or cold surface structure failure flooding
Using this list and your knowledge of the activity, select the SIGNIFICANT hazards
Significant Hazards: Persons at Risk Likelihood Severity Risk
(Section A) (Number, Staff, L,M or H L,M or H L,M or H
Public, Children)
Striking underground electricity cables Operative(s) M H H
Collapse of unsupported excavations Operative(s) H H H
Falling into unfenced excavations Operative(s) M H H
Materials or plant falling into the excavation Operative(s) M H H
Breaking into gas or water main/existing sewer Operative(s) M H H
Operative being struck by the excavator Operative(s) M H H
Give priority to hazards where the persons at risk, likelihood or severity are high. Include any controls that reduce the risks from
the significant hazards
Control Measures: (For example, Work at height = Full scaffold instead of ladders, Electrocution = Battery powered drill
instead of 110V or mains electric, Confined spaces = Forced air ventilation instead of BA)
Accurate location of underground services by operatives trained in the use of locating equipment.
Planned provision of and use of excavation support equipment, trench support is to extend to 250mm from the bottom of
the dig. This is to be reviewed after every movement of the trench box, so ground conditions can be assessed by WBCE
Supervisor.
If ground conditions are that of solid state works may progress but any changes e.g. Water ingress, loose ground the works
must stop and be re assessed.
Excavations to be always backfilled as soon as practicable, if not warning signage, inspections & adequate fencing used.
Spoil and pipes, not to be placed at the edge of the excavation so as to surcharge it.
Proper tied ladder access extending 1.05m above top of excavation, and placed into the supported area of the excavation.
Only certified operators & lifting equipment to be used..SWL is not to be exceeded for the Excavator being used.
Excavator is banked during excavation work, and stops used on dumpers to prevent vehicles over running the excavation.
Operatives to be confined space trained medium risk and supervisor confined space trained high risk.
Control measures using PPE - Only select PPE where you cannot control or remove the hazard another way
Remember PPE is the last resort
Put x by the ones that apply: Head protection x Eye Protection x Dust mask x
Toe Protection x Ear Protection x Respirator
High-vis clothing x Harness or line Escape BA x
Details / other PPE required: Gloves x Gas Detector x Full BA
Gloves & good washing/personal hygiene to be adopted due to the increased risk of Weils disease. Gas detector to be used before
entry in to the trench, and remain within the trench either attached to the operative or by line into the trench.

The right supervision will help ensure a quality product at a fair price
Arrangements for Work:
Name of work Supervisor for this method statement WBCE Supervisor TBC
Level of supervision required (e.g. full time / part time / hourly) Full Time
Permits required (e.g. permit-to-dig / permit-to-enter etc.) Permit to Dig/Permit to enter
Level of competence / training standard required by operatives CSCS, CPCS, confined space
Other arrangements: A Permit to Dig to be in place before this work begins, and the
required trench support already on site
Jan 14 Rev 1 W/HS/71
Westbourne Civil Eng. Ltd. RISK ASSESMENT & METHOD STATEMENT
Sheet 2 of 4

Resources Sketch or diagram


Plant & tools required: Excavation depths;
Cat & Genny , Full escape set & gas detector, Minimum 1.5 m.
13-20 tonne 360 degree Excavators & associated Maximum 3.2 m.
lifting gear. compactor.
Proprietary trench system 5metre Drag box and
2.4-4.5 metre Man-Hole box. Edge protection.
Wooden ladder, (trench sheets and frames if
required). Pipe laser. Bowmag 120 roller.9tonne
dumper. Poker drive unit. Disc cutter & dust
suppression bottle.
Materials:
Clay pipe 150mm : foul drainage
Concrete pipe 300mm :surface water
Pipe bedding, Concrete Manhole Rings &Cover
slabs Gen3 concrete (builds manholes, bed and
surrounds pipes when applicable). Trench fill
Crushed hard-core/excavated material.
Labour:
Operatives (confined space trained).

Safety Method Statement


(Section : B):
Listing your sequence of work will help you, and your operatives,
carry out the task safely and cost effectively. It can reduce
errors and cut downtime due to lack of planning.

1 Underground services on site will be known, and have


been located through a cat & genny survey and marked
out on the ground. Working area to be fenced off at all
times .Gas detector to be lowered in to excavation
before operative enters and to remain within
excavation to monitor gas levels.
Escape BA also to remain within excavation for easy
access for operative if required.
2 A Permit to Dig and Permit to enter will have been
issued to the Westbourne team for the drainage work.
3 Manholes & excavations once they are excavated will
be supported by using a drag boxs/ manhole box
support system lifted into situ by 360 excavator.

Jan 14 Rev 1 W/HS/71


Westbourne Civil Eng. Ltd. RISK ASSESMENT & METHOD STATEMENT
Sheet 3 of 4

4 Foul line will be excavated first after trial holes have


been excavated to establish depth and position of
existing sewer.
Existing sewer is approx. 1.8m below ground so Hand
Dig will be used for final 0.8 to expose existing sewer
within trial holes.
Surface water line will be excavated after installation
of foul line has been completed. At two points the
surface water will cross the existing sewer at these
points operatives are to Hand dig to expose the existing
sewer so as not to damage the sewer with the 360
machine as there is only 300mm between the two at
this point
Works will progress from shallowest point adjacent to
Mitton Rd. Excavator will load arising into 9 tonne
dumper, once dumper has been filled operator will
mount dumper fit seat belt, start dumper and travel
across site to stockpile/tipping area (to be loaded off
site at later date) or stockpiled and sealed.

5 Once manhole excavation has reached a depth of 1


metre deep excavator will lift and lower Manhole
box in-situ. Excavator will carry on digging until
required depth has been reached. Then the Drag
box will be placed and abutted to manhole box to
provide all round excavation support and
protection prior to placement and securing of
ladder into excavation. Excavation will be
reviewed by supervisor prior to entry. This process
will be repeated and temporary support will be
adapted according to depth of dig. Gas monitor
used to establish safe atmosphere prior to entry.
The above process and sequence will be repeated
for the surface water drainage run. All safe
systems of work will be adopted as required.

Jan 14 Rev 1 W/HS/71


Westbourne Civil Eng. Ltd. RISK ASSESMENT & METHOD STATEMENT
Sheet 4 of 4

6 Operatives will hand dig around existing pipe to


accommodate concrete base to construct manhole.
Excavator will place concrete into excavation
where operative will level concrete to
accommodate clay channels/boxing out base to
accommodate Manhole ring. Manhole rings are to
be lifted in-situ by means of manhole lifting pins
and 4 leg chains attached to excavator by means of
a bow shackle (all lifting gear to have a valid test
certificate). Once Manhole has been built
Excavator will lift in-situ 1200mm-3m dia Manhole
shutter. Once Manhole shutter in place excavator
will place concrete on cover slab to enable
operative to shovel concrete around shutter ready
for 2poker drive unit to vibrate concrete.

7. Once manhole construction completed excavation


will be backfilled by means of excavated material
placed by excavator in 300mm layers and compacted.
Once backfilled excavator will lift manhole box and
place safely away from excavation so as remaining
drainage run can continue. The excavator digs the
trench (for pipe work) to level (with a banks man
present) the trench support will be placed by excavator
as the excavation progresses. Excavator will place into
excavation 10mm-20mm pipe bedding. Operative will
level pipe bedding with shovel to accommodate
clay/concrete pipe. Excavator will lower clay/concrete
pipe into trench box using certificated strap fixed to
excavator by means of 9 tonne certificated alloy bow
shackle .
7. A tied off ladder will be placed into the excavation,
(5 rungs of the ladder above trench box) so as to
provide a safe means of access/egress for ops,.
The trench support system will extend 1m above the
top of the excavation with edge protection so as to
prevent falls.
8. Backfilling will progress as manholes and pipe work
are constructed/placed to avoid open excavations.
Where this is not possible 0pen excavations will be
fenced as required.
9. Compaction of crushed hard-core/excavated
material to be compacted with compactor where
applicable . Once backfill material is 600mm from top
of excavation a Bowmag 1200 roller and operator will
be used to compact material. Clay pipe will have to be
cut by means of Disc cutter, suppression bottle and
Diamond blade, operatives abrasive wheel trained and
all JSP fpp3 dust mask approved Face fit trained.
Drainage less than a metre deep will be individually
assessed may not need any trench support systems.

Details to make the risk assessment site specific

Residual risk for significant hazards, is low, but control measures and safety method statement must be followed
by operatives on site

Jan 14 Rev 1 W/HS/71


WESTBOURNE CIVIL ENG. LTD. RISK ASSESMENT & METHOD STATEMENT
Sheet 1 of 3

Site Name: Mitten Rd, Whalley Date: 2/12/2015 SSW No. WBCE

Written By: A Gallagher Site Approval:

Client Review: D.W.H. Signature: *


* If this Safe System of Work is issued to several persons each should sign overleaf

Activity: Manhole Connection for 150mm Rising Main


Examples of Common Hazards: Put x by the ones that apply
Fall from height x Trip on level x Falling objects x Fragile material Electrocution x Manual Handling x
Explosion x Noise x Dust x Striking object Asbestos Struck by traffic
COSHH Fire Lighting Cutting accident Eye injury x Struck by plant x
Collapse of x Contact hot Collapse of x Lifting Equipment x Drowning or x Confined Spaces x
excavation or cold surface structure failure flooding Gas exceedance l
Using this list and your knowledge of the activity, select the SIGNIFICANT hazards
Significant Hazards: Persons at Risk Likelihood Severity Risk
(Section A) (Number, Staff, L,M or H L,M or H L,M or H
Public, Children)
Striking underground electricity cables Operative(s) M H H
Collapse of unsupported excavations Operative(s) H H H
Falling into unfenced excavations Operative(s) M H H
Materials or plant falling into the excavation Operative(s) M H H
Breaking into gas or water main/Toxic enviroment Operative(s) M H H
Operative being struck by the excavator Operative(s) M H H
Give priority to hazards where the persons at risk, likelihood or severity are high. Include any controls that reduce the risks from
the significant hazards
Control Measures: (For example, Work at height = Full scaffold instead of ladders, Electrocution = Battery powered drill
instead of 110V or mains electric, Confined spaces = Forced air ventilation instead of BA)
Accurate location of underground services by operatives trained in the use of locating equipment
Planned provision of and use of excavation support equipment, trench support is to extend to the bottom of the dig
Excavations to be always backfilled as soon as practicable, if not warning signage, inspections & adequate fencing used
Spoil and pipes, not to be placed at the edge of the excavation so as to surcharge it
Proper tied ladder access extending 1.05m above top of excavation, and placed into the supported area of the excavation
Only certified operators & lifting equipment to be used..SWL is not to be exceeded for the Excavator being used
Excavator is banked during excavation work, and stops used on dumpers to prevent vehicles over running the excavation.
All operatives to be confined space trained. Gas detector to be used, Emergency BA and Escape Kit

Control measures using PPE - Only select PPE where you cannot control or remove the hazard another way
Remember PPE is the last resort
Put x by the ones that apply: Head protection x Eye Protection x Dust mask x
Toe Protection x Ear Protection x Respirator
High-vis clothing x Harness or line x Escape BA x
Details / other PPE required: Gloves x Safety torch Full BA
Gloves to be used in excavations & good washing/personal hygiene to be adopted due to the increased risk of Weills disease.

The right supervision will help ensure a quality product at a fair price
Arrangements for Work:
Name of work Supervisor for this method statement
Level of supervision required (e.g. full time / part time / hourly) Full Time
Permits required (e.g. permit-to-dig / permit-to-enter etc.) Permit to Dig/ Confined Space Permit
Level of competence / training standard required by operatives CSCS & CPCS/NPORS
Other arrangements: A Permit to Dig to be in place before this work begins, and the required trench
support already on site, Emergency escape kit and tripod, Gas detector and BA

AUG 12 Rev 1 W/HS/71


WESTBOURNE CIVIL ENG. LTD. RISK ASSESMENT & METHOD STATEMENT
Sheet 2 of 3

Resources Sketch or diagram


Plant & tools required: Manhole & Sewer Construction Schedule:
Cat & Genny
360o Excavator & associated lifting gear, dumper,
Sewers 600mm Concrete
Proprietary trench support system and Man-Hole 150mm pipe (rising main)
trench sheets and frames, Gas detector, harness,
tripod and winch, LOLER Lifting Equipment. Disc All sewer/manhole design drawings to be
cutter and dust suppression kit, compressor and reviewed to ensure construction issue design
medium duty breaker ( low vibration ). drawing is used.
Materials:
Brick, sand, cement, Sika jointing compound Methodology Amendment:

Labour:
Operative(s), Supervisor

Safety Method Statement


(Section : B):
Listing your sequence of work will help you, and your operatives,
carry out the task safely and cost effectively. It can reduce
errors and cut downtime due to lack of planning.

1 Set up Working area to be fenced off with Heras


fencing and signage.
2 Service Information to be reviewed and Cat
Scanned A permit to dig will be implemented by
WBCE and issued to the WBCE Construction team
3 Existing work environment will be mechanically
civilised to provide flat working area. Designated
bucket change area will be established close to
work area.
4 Underground services on site will be known
(service drawings to be supplied by DWH), and
have been located through a cat & genny survey.
5 Excavator will break up existing ground and load
into dumper and taken to spoil stockpile (stockpile
to be removed from site at later date).
6 excavator will commence dig for MH connection.
Operatives will construct the ( MGF ) temporary
works system using LOLER certificated Lifting
Equipment and Excavator if a reduced dig is not
achievable to. Prior to entry into formed
excavation the GTU (gas detection unit) will be
placed at bottom/middle and top to gain air
clearance. Operative will implement a wooden
pole ladder will be lashed to extended to
accommodate access and egress.
7 Once required depth has been reached Supervisor
will complete confined space permit (confined
space trained) will enter excavation review and
commence the connection of the 150mm rising
main.
8 Once chamber prepared with gas readings taken
to record safe levels, operatives wearing
appropriate PPE will break out with CP9 medium
breaker, an opening for 150mm-pipe
connection.(with a top man present)
AUG 12 Rev 1 W/HS/71
WESTBOURNE CIVIL ENG. LTD. RISK ASSESMENT & METHOD STATEMENT
Sheet 3 of 3

9 The excavator and lifting equipment will then lift into


excavation 150mm pipe. Operatives will be positioned
within the temporary works protected areas while pipe
is lowered. Pipe will then be manoeuvred manually in to
correct position, operatives will then make good
manhole to UU Standards.
10 Backfilling will progress as manholes and pipe work are
in place to avoid open excavations. Where this is not
possible Open excavations will be fenced as required.
11 Banksman/top man will be in attendance at all times
and only confined space trained operatives will enter
the manholes/excavations.
12 Works area will be monitored to ensure area is made
safe, temporary covers placed on open chambers and
this will be monitored as required.
13

Details to make the risk assessment site specific

Residual risk for significant hazards, is low, but control measures and safety method statement must be followed
by operatives on site

AUG 12 Rev 1 W/HS/71

You might also like