No. DGM (Co-ordi)/2012/PR-3/Part-| Date. 13/11/2013
To,
(1) The Chief Engineer (Dam & vadodara), SSNNL, Vadodara
(2) The Chief Engineer (SBC),SSNNL, Rajkot.
(3) The Chief Engineer (Amdavad), SSNNL,Gandhinagar.
(4) The Chief Engineer (Mehsana),SSNNL, Mehsana.
(6) The Chief Engineer (Patan),SSNNL, Patan.
(6) The Chief Engineer (KBC),SSNNL, Gandhidham.
Sub: Guide lines for Network planning, Designing and preparation of
estimates of minors and sub minors as underground Pipe Line
(UGPL) in SSP Command.
With reference to above subject and SSNNL's letter no. DGM
(Co-ordi) /2012/PR-3/Part-I. dtd. 25/10/2013, clarification is _ as follow:-
The Para 2 in the above referred letter i.e. "Further, | am directed
to requested you to take up implementation of 1(one) UGPL project
covering (the minor along with it's sub minors) in each ‘Division under
their jurisdiction on pilot basis and based on it's result / performance
feedback remaining area can be taken up accordingly. It is also
requested to verify adoptability of the technical criteria/suggestions
proposed by WAPCOS, region wise/branch wise for your jurisdiction."
The above Paragraph in the said letter is. meant for
implementation of sub-minor i.e. for tendering & construction purpose.
With this clarification, it is requested not to stop the survey work/
design work of UGPL, being carried-out by WAPCOS. *
This letter issues with the approval of the competent authority of
SSNNL obtained on even no. of file.
Dy. General Manager (Co-ordi.)
SSNNL, Gandhinagar.