Professional Documents
Culture Documents
INDUS MOTOR
CORPORATION
INTERNSHIP REPORT
MUHAMMAD YASIR ABBAS
[2017]
0
1
2
UNIVERSITY COLLEGE OF ENGINEERING TECHNOLOGY
DEPARTMENT OF TECHNICAL EDUCATION
Learning objective
Bachelor of Engineering Internship Objectives fall under two major categories, namely, program
objectives defined by the College of Engineering as general conditions which all internships must meet,
and personal objectives defined by the intern for an internship. Personal objectives should be consistent
with program objectives. It is intended to establish that this experience meets the objectives of the
Bachelor of Engineering Technology internship. Following an examination of the internship objectives,
IMC organizational structure, approach, and management philosophy are overviewed. The major project
undertaken during the internship is introduced and its technological basis briefly discussed. The author's
specific work assignments and contributions in Maintenance Department, all in project control
engineering, are then presented. The work assignments include process instrument diagram of the Utility
department including Chiller, Cooling Towers, Compressors, Hot Water generation, Fire Fighting
System in Paint shop on a segment of this project assignment the internship was involved with; and
manpower utilization and productivity studies. Finally, aspects of project management to which the
intern was exposed through association and observation during the internship are discussed. It is thus
demonstrated that both the program and personal objectives are met.
Signature:
Student name; Muhammad yasir abbas
Registration No: BSMTF13E028
Signature:
Supervisor Name:
Dated:
Counted signature:
Head of department:
3
Acknowledgement:
All the praises for the Almighty, Allah who bestowed us with the ability and potential to complete this
internship. I also pay my gratitude to the Almighty for enabling me to complete this Internship report
within due course of time.
The internship opportunity I had with INDUS MOTOR COMPANY Ltd was a great chance for
learning and professional development. Therefore, I consider myself as a very lucky individual as I was
provided with an opportunity to be a part of it. I am also grateful for having a chance to meet so many
wonderful people and professionals who led me though this internship period.
Bearing in mind previous I am using this opportunity to express my deepest gratitude and special thanks
to the Mr. JAMSHED KHAN, Mr. SHOAIB and MR. HANEEF of INDUS MOTOR COMPANY
Ltd who despite being extraordinarily busy with their duties, took time out to hear, guide and keep me
on the correct path and allowing me to carry out my internship at their esteemed organization.
I express my deepest thanks to Mr. Islam ud din (GM Administration) for providing me requisite
information and arranged all facilities to make life easier. I choose this moment to acknowledge his
contribution gratefully.
I perceive as this opportunity as a big milestone in my career development. I will strive to use gained
skills and knowledge in the best possible way, and I will continue to work on their improvement, to
attain desired career objectives. Hope to continue cooperation with all of you in the future.
4
SUMMERY
This report documents my internship experience with INDUS MOTOR COMPANY Ltd., during the
period March 9, 2017 through April 8, 2017. It is intended to establish that this experience meets the
objectives of the Bachelor of Engineering Technology internship. Following an examination of the
internship objectives, IMC organizational structure, approach, and management philosophy are
overviewed. The major project undertaken during the internship is introduced and its technological basis
briefly discussed. The author's specific work assignments and contributions in Maintenance Department,
all in project control engineering, are then presented. The work assignments include process instrument
diagram of the Utility department including Chiller, Cooling Towers, Compressors, Hot Water
generation, Fire Fighting System in Paint shop on a segment of this project assignment the internship
was involved with; and manpower utilization and productivity studies. Finally, aspects of project
management to which the intern was exposed through association and observation during the internship
are discussed. It is thus demonstrated that both the program and personal objectives are met.
5
Chapter #01
1.1
Introduction--------------------------------------------------------------------------------------------------------- 01
1.4Vision----------------------------------------------------------------03
1.5 Mission--------------------------------------------------------------04
1.6 Slogan---------------------------------------------------------------04
1.9Organization chart----------------------------------------------------05
chapter #02
chapter #03
REFERNCE-------------------------------------------------------------------------------14 6
7
Figures title pages
1 structure 01
2 organization chart 05
3 unity is strength 05
4 PID symbols 08
7 PID of compressor 10
8
Chapter #01
1.1 Introduction
PURPOSE
This report relates the author's one month internship experience with
Indus Motor Company, Ltd. to establish that the objectives of the
internship have been met.
POSITION
The internship was served in the Maintenance Utility Department, with
the formal designation of Associate Engineer, under the direct
supervision of Engr Mr. Shoaib as Control Team Manager. Appendix A
contains brief descriptions of process and instrument diagram. Mr.
Jamshed Khan, Manager of Maintenance., was the intern supervisor
through much of the one-month life of the the internship. He was
subsequently assigned projects in my internship.
1
Program Objectives
Personal Objectives
Program objectives above emphasize contribution and broad exposure, respectively. Accordingly, the
following final objectives were defined to reflect the general guidelines.
Become familiar with the Process Industry Technology.
Take responsibility for cost engineering on one aspect of a
project.
Develop a manual of major cost reports.
Learn the essence of scheduling engineering.
Observe management practices at the project level.
The Company has played a major role in the development of the entire value chain of the local auto
industry and is proud to have contributed in poverty alleviation at the grass root level by nurturing
localization that, in turn, has directly created thousands of job opportunities and transferred technology
to over 60 vendors supplying parts. IMC is also a major tax payer and significant contributor to the GOP
exchequer.
Figure 1
1.4 Vision
To be the most respected and successful enterprise, delight customers with a wide range of products
and solutions in the automobile industry with the best people and best technology.
1.5 Mission
Mission of Toyota is to provide safe & sound journey. Toyota is developing various new technologies
from the perspective of energy saving and diversifying energy sources. Environment has been first and
most important issue in priorities of Toyota and working toward c
1.6 Slogan
Indus Motor Company Ltd is committed to provide a safe workplace to all its employees and to ensure,
so far as is reasonably practicable, the safety of its contractors, suppliers, vendors and all members of the
public that may be affected by its business operations.
The company will strive to prevent all accidents and injuries through the active participation of every
employee as well as the commitment to put in continuous efforts to identify, eliminate or manage safety
risks associated with its actions.
Our Philosophy:
Figure 2
Unity the strength
figure 3
Chapter #02
The project assign to me during my internship was process and instrument diagram of different sections
in maintenance utility section I have worked on cooling towers, chiller, oil free, oil injected
compressors, hot water generation and Firefighting system of the paint shop. First have a look at process
and instrument what is it what are symbols related to it and how they work in my drawing
content. A sidebar is a
Practice (PIP) - a consortium of process industry owners and
standalone
engineering construction contractors who serve the industry.
supplement to the
A P&ID Should Include:
Instrumentation and designations; main document. It is
Mechanical equipment with names and numbers;
often aligned on the
All valves and their identifications;
Process piping, sizes and identification; left or right of the
Miscellaneous - vents, drains, special fittings, sampling lines,
reducers, increasers and swaggers; page, or located at the
Permanent start-up and flush lines;
Flow directions; top or bottom. Use the
Interconnections references;
Drawing Tools tab to
Control inputs and outputs, interlocks;
Seismic category; change the formatting
Interfaces for class changes;
Quality level; of the sidebar text
Annunciation inputs;
Computer control system input; box.]
Vendor and contractor interfaces;
Identification of components and subsystems delivered by
others;
Intended physical sequence of the equipment;
Equipment rating or capacity.
Chiller section
Chiller in IMC provided chilled water to the paint shop because its necessary for the paint these chillers
are outside the paint shop I made their rough drawing and then draw it on the software.
Figure 5
2.4.3 Compressor
There are two types of compressors used in the IMC maintenance utility department
Oil free compressor for the paint shop and oil injected compressors for the the welding shop in
compressor there are also some dryer which are used to dry the air and control the humidity at the
control temperature oil free compressor having two compressed air reservoirs for compressed air before
the dryer and compress air after the dryer and three compressed air reservoir foot oil injected compressor
one before dryer and two for after the dryer
Figure 7
Chapter #03
Piping & Instrumentation Diagram (P&ID) is one of the important basic engineering documents in the
form of drawing , which truly represents the process plant It shows pipelines interconnecting all
equipment , instruments , control systems, valves , etc. for the completeness of the process plant .Since
detailed engineering work for any process plant depends more on the P & ID , its correctness and
completeness is very much essential .Any wrong information provided in the P&ID at the initial stage
may to a big disaster or may entail heavy expenses later .Hence , great attention is required for
the preparation of error free P&ID .Good quality P& ID may deistically cut the engineering man hour
requirement for the successful completion of a project .
Normally process plants have static equipment like storage tanks, columns, heat exchangers, etc. and
rotating equipment like pumps, blowers, etc. This equipment is connected to each other by a
complicated pipeline network for the completeness of the process. Measuring instruments like
thermocouple for temperature measurement, and controlling devices like temperature control valve, are
mounted on the equipment or pipelines for operating the plant at desired conditions. Although a single
step process like blending of two compounds can be represented in a single Piping & Instrumentation
Design (P & ID) , a process having a large number of processing steps like reaction , filtration , drying ,
etc. would need to have many P & IDs for the complete representation of the process plants .For ease of
understanding , the complete process plant is functionally divided into various units .For example a
reactor with the other related equipment , pipelines and instruments required for carrying out a reaction
process may be covered in one unit while filtration operation may be specified with another unit number
accordingly the individual units.
In a big process industry, the processing units are spread over a large area. Although two different units
may be far away from each other they are connected by pipelines or the continuous flow of fluid from
one unit to another Interconnection between two units is represented by Interconnecting P & IDs
Similarly, another engineering document, Utility P & IDs, provides information regarding the
distribution of utilities like water, steam fuel etc. in the required locations. This article deals only with
preparation of Process P & ID.
Process P & ID provides detailed information of the process plant like type of equipment, the details of
pipelines, i.e., size material, identification number, types of instruments and controlling devices etc.
Operation, start-up, maintenance, safety and aesthetic aspects are mainly considered during the
preparation of process P & ID.
3.1.1 Maintenance
Maintenance is an important aspect to be considered during the preparation of Process P & ID. For
example, Bypass line with regulating valve for control valve is provided for talking it out for
maintenance without affecting the running plant. Sometimes it is marked in the P & ID to provide
sufficient room for cutout in the floor above the vertical tube bundle from the heat exchanger body. If
such type of information is not provided initially, it may be missed out in the various engineering stages
and may lead to problems at the later stages. To avoid such possibilities, Process P &ID, should be
critically examined from the maintenance point of view during preparation stage.
3.1.2 Safety
For the safe operation of any process plant , safety measures cannot be overlooked .Hence, the
preparation of Process P & ID needs the attention of safety aspects also .HAZOP study is carried out
keeping in view each and every safety and operation step .For example , the exhaust of obnoxious gases
near the plant operators is harmful to their health .Such gases are diffused in the atmosphere at a higher
elevation .These safe elevations are normally marked in the process P & ID Safety interlocks are
provided to ensure safe operation of the process plant .For example, failure of a running pump for a
critical operation may disturb the complete process plant . To avoid this situation, the stand -by pump
should be started without any time lag. - Necessary interlock is shown in the process P & ID. Some
metallic pipelines and equipment handling hot fluids are insulated for body protection. Here heat saving
may not be an important criterion for the selection of insulating, but it is essential for the operators
safety.
Such safety requirements are clearly marked in the P & ID. Requirement of safety valves in pressurized
system, minimum flow lines for centrifugal pumps, high and low alarms etc., are to be critically seen
during the preparation of Process P & ID.
REFERNCEs:
www.toyota-indus.com
www.edrawsoft.com
www.pipingguide.net
Dear Sir,
Muhammad Yasir Abbas completed his one-month internship at INDUS MOTOR COMPANY Ltd on
April 8, 2017. His internship was a success and in my opinion he
achieved his internship objectives. He was assigned to a task force set up to engineer. For your
information, a task force within IMC is a group of professionals dedicated to a specific project. As such,
there is a lot of intermingling of various aspects and types of tasks required to achieve a common goal,
His role on the task force was that of an engineer having primary responsibility for drawing the process
instrument Diagram. In his primary responsibility his work involved interface with process engineers,
mechanical engineers, design engineers, and project management, which basically covers the whole
gamut of the project task force concept. This responsibility gave him a clear insight on how all task force
operations work and are managed.
The experience gained will serve him well. In addition to his primary responsibility, Muhammad Yasir
Abbas also worked directly under my supervision.
These special studies challenged Muhammad Yasir Abbas abilities to solve unique problems on the job
and he did an outstanding job in this regard. Muhammad Yasir Abbas demonstrated a strong ability to
communicate his work plan and
methods concisely and precisely to management. In all cases he met his deadlines on various
assignments and displayed a consciousness for proper planning and efficient use of time, which is very
important in our business.
In summary, I have no hesitation in stating that Muhammad Yasir Abbas met his internship objectives. I
also believe that he has demonstrated the technical ability required from a practicing engineer as well as
a good awareness of the multitude of variables that bear on project management.
I appreciate the opportunity to serve on Muhammad Yasir Abbas internship committee and look forward
to meeting you again at his final examination.
Sincerely,