SLAB THICKNESS BEAM THICKNESS TOP OF PILE CAP PILE CAP PILE EMBEEDED
BUILDING No. BUILDING SECTION Area Discription Level (m) TOP OF PILE (m)
(mm) (mm) (m) THICKNESS (mm) IN PILECAP (mm)
SECTION 1-1
Foundation Area Support For Tunnel Access To Building -8.500 m 1000 -9.500 1500 100 -10.900
01 GRIDLINE A to D, Q to T
Drawing No. S-01-B1-0-SEC-0001 SECTION 1-1
Micro-Vibration & Seismic Isolation Zone -4.500 m 300 -4.800 2200 100 -6.900
GRIDLINE E to P
SECTION 2-2
Foundation Area Support For Tunnel Access To Building -8.500 m 1000 -9.500 1500 100 -10.900
GRIDLINE A to C
01 SECTION 2-2
Micro-Vibration & Seismic Isolation Zone -4.500 m 300 -4.800 2200 100 -6.900
Drawing No. S-01-B1-0-SEC-0002 GRIDLINE D to F, O to T
SECTION 2-2
Micro-Vibration & Seismic Isolation Zone -4.500 m -4.500 4000 100 -8.400
GRIDLINE G to N
SECTION 1-1
Basement Level -6.500 m 300 900 -7.700 1300 100 -8.900
GRIDLINE H to F
02 SECTION 1-1
Ground Level -0.200 m 300 1000 -1.500 1500 100 -2.900
Drawing No. S-02-B1-0-SEC-0001 GRIDLINE E to C
SECTION 1-1
Foundation at Area close to External Paving -2.500 m 1200 -3.700 1300 100 -4.900
GRIDLINE B to A, I to J
SECTION 2-2
Foundation at Area close to External Paving -2.500 m 1200 -3.700 1300 100 -4.900
GRIDLINE 1 to 2, 25 to 26
SECTION 2-2
Basement Level -6.500 m 300 900 -7.700 1300 100 -8.900
02 GRIDLINE 3 to 13
Drawing No. S-02-B1-0-SEC-0002 SECTION 2-2
Foundation Area Support For Emergency Exit Tunnel -4.000 m 1200 -5.200 1300 100 -6.400
GRIDLINE 14 to 15, 18 to 19, 20 to 23
SECTION 2-2
Foundation at Area close to External Paving -2.500 m 1200 -3.700 1300 100 -4.900
GRIDLINE 16 to 17, 20 to 21
SECTION 1-1 Foundation Area Support For Tunnel Running Underneath the
-8.500 m 1000 -9.500 1050 100 -10.450
GRIDLINE 1 to 4 Building
03 SECTION 1-1
Foundation at Basement Area Underneath Micro Vibration Zone -8.500 m 300 700 -9.500 1500 100 -10.900
Drawing No. S-03-B1-0-SEC-0001 GRIDLINE 4 to 8
SECTION 1-1 Pile Raft Foundation of Draw Tower with Micro-Vibration & Seismic
-8.500 m -8.500 2500 100 -10.900
GRIDLINE 8 to 12 Isolation Zone
SECTION 1-1
Basement Level -6.500 m 300 1200 -8.000 1000 100 -8.900
05 GRIDLINE 1 to 2
Drawing No. S-05-B1-0-SEC-0001 SECTION 1-1
Foundation at Area close to External Paving -2.500 m 1000 -3.500 1500 100 -4.900
GRIDLINE 3 to 8
06 SECTION 1-1
Foundation at Area close to External Paving -1.500 m 1000 -2.500 1500 100 -3.900
Drawing No. S-06-B1-0-SEC-0001 GRIDLINE A to B
SECTION 1-1
Foundation Area Support For Emergency Stair for Utility Tunnel -12.120 m -12.120 1500 100 -13.520
GRIDLINE 1 to 2
SECTION 1-1
Foundation at Area close to External Paving -2.500 m 1000 -3.500 1500 100 -4.900
07 GRIDLINE 3 to 4
Drawing No. S-07-B1-0-SEC-0001 SECTION 1-1
Basement Level -6.500 m 300 700 -7.500 1500 100 -8.900
GRIDLINE 5 to 13
SECTION 1-1
Setdown Floor At Electric Cable Room -3.100 m 400 1000 -4.500 1500 100 -5.900
GRIDLINE 14 to 16
07 SECTION 2-2
Basement Level -6.500 m 300 700 -7.500 1500 100 -8.900
Drawing No. S-07-B1-0-SEC-0002 GRIDLINE A to D
10&11
SECTION 1-1
Drawing No. S-10-B1-0-SEC-0001 Ground Level -0.100 m 300 1100 -1.500 1500 100 -2.900
GRIDLINE 10.1 to 11.2
Drawing No. S-11-B1-0-SEC-0001