PROJECT STARTED : July 17, 2017

PROJECT NAME TARGET COMPLETION : November 13, 2017

PROJECT SCHEDULE
DATE OF REPORT:
CONTRACTTOR
JULY AUGUST SEPTEMBER OCTOBER NOVEMBER
DATE DATE
ITEM SCOPE OF WORKS QTY UNIT WT% WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12 WEEK 13 WEEK 14 WEEK 15 WEEK 16 WEEK 17
STARTED FINISHED

I GENERAL REQUIREMENTS 1.00 lot 4.44%


I FOUNDATION
Trimming 17-Jul-17 20-Jul-17 1,803.46 m3 4.76%
Gravel Bedding 19-Jul-17 21-Jul-17 58.71 m3 0.99%
Reinforcement 21-Jul-17 01-Aug-17 33,577.60 kg 2.42%
Formworks 29-Jul-17 03-Aug-17 1,797.63 m2 5.40%
Concrete 02-Aug-17 07-Aug-17 325.04 m3 1.95%
Backfilling and Compaction 07-Aug-17 09-Aug-17 2,024.73 m3 11.36%
II SOIL TREATMENT 12-Aug-17 15-Aug-17 4,288.04 m2 9.27%
III GROUND FLOOR / S.O.G
Gravel Bedding 10-Aug-17 12-Aug-17 63.47 m3 1.07%
Reinforcement 13-Aug-17 16-Aug-17 4,236.35 kg 0.31%
Concrete 17-Aug-17 18-Aug-17 69.35 m3 0.42%
IV GROUND FLOOR - 2ND FLOOR
Reinforcement 19-Aug-17 28-Aug-17 20,985.09 kg 1.51%
Formworks 27-Aug-17 05-Sep-17 2,924.44 m2 8.78%
Concrete 06-Sep-17 07-Sep-17 188.07 m3 1.13%
V 2ND FLOOR - 3RD FLOOR
Reinforcement 03-Sep-17 12-Sep-17 20,985.09 kg 1.51%
Formworks 11-Sep-17 20-Sep-17 2,924.44 m2 8.78%
Concrete 21-Sep-17 22-Sep-17 188.07 m3 1.13%
VI 3RD FLOOR - 4TH FLOOR
Reinforcement 18-Sep-17 27-Sep-17 20,985.09 kg 1.51%
Formworks 26-Sep-17 05-Oct-17 2,924.44 m2 8.78%
Concrete 06-Oct-17 07-Oct-17 188.07 m3 1.13%
VII 4TH FLOOR - 5TH FLOOR
Reinforcement 03-Oct-17 12-Oct-17 20,985.09 kg 1.51%
Formworks 11-Oct-17 20-Oct-17 2,924.44 m2 8.78%
Concrete 21-Oct-17 22-Oct-17 188.07 m3 1.13%
VIII 5TH FLOOR - 6TH FLOOR
Reinforcement 18-Oct-17 27-Oct-17 20,985.09 kg 1.51%
Formworks 26-Oct-17 03-Nov-17 2,924.44 m2 8.78%
Concrete 06-Nov-17 07-Nov-17 188.07 m3 1.13%
IX 6TH FLOOR - ROOFDECK
Reinforcement 06-Nov-17 08-Nov-17 594.00 kg 0.04%
Formworks 09-Nov-17 11-Nov-17 145.63 m2 0.44%
Concrete 12-Nov-17 13-Nov-17 8.24 m3 0.05%

TARGET ACCOMPLISHMENT 6.61% 3.47% 5.89% 17.72% 5.84% 2.20% 6.71% 4.20% 6.71% 5.08% 5.98% 5.81% 5.25% 6.53% 4.53% 6.09% 1.33% 0.06%

COMMULATIVE ACCOMPLISHMENT 6.61% 10.08% 15.97% 33.69% 39.53% 41.73% 48.44% 52.64% 59.35% 64.43% 70.41% 76.22% 81.47% 88.00% 92.53% 98.62% 99.94% 100.00%

ACTUAL ACCOMPLISHMENT

COMMULATIVE ACCOMPLISHMENT

PREPARED BY : CHECKED BY: APPROVED BY: