SECTION 04860
PART 1 GENERAL
A. The work of this section includes, but shall not be limited to, a unitized
(panelised) cladding system consisting of the following:
1.3 REFERENCES
1. ASTM C67 - Standard Test Methods for Sampling and Testing Brick and
Structural Clay Tile.
5. ASTM E 283 - Standard Test Method for Rate of Air Leakage Through
Exterior Windows, Curtain Walls, and Doors.
D- Design Criteria: Clay panel wall cladding system shall be based on sizes,
profiles, finishes, and dimensional requirements of the exterior clay panel wall
cladding system specified types/models of approved manufacturer's.
1.The replacement of panels shall be possible using simple methods
tools and shall not damage the surrounding panels.
1. The system shall resist a design load of positive and negative pressures
to a maximum of 45 psf (2.15 kPa) when tested in accordance with ASTM
E330.
2. Deflections within the system shall be limited to L/175 of their clear span
or 5/8 inch (16 mm), whichever is less when tested in accordance with
ASTM E 330.
1. Air Infiltration: ASTM E 283. Allowable air infiltration shall be 0.06 cfm (28
cu cm/sec) or less per square foot when tested under a constant pressure
of 6.24 psf (10 Pa).
1.6 SUMITALS
1. Submit under provisions of Section 01300.
2. Shop Drawings shall be submitted for approval prior to fabrication
including:
a. One drawing for each panel, baguette, louver or other terra cotta
unit type indicating profile, schedule of lengths, thickness, finish,
color, texture and size, profile and color of any adjacent, visible
gasket.
b. Elevations for each condition indicating clay panel and vertical
track locations.
c. Section drawings to illustrate proper fabrication/installation for
terra cotta unit types (panel, baguette, louver, etc.).
3. Verification Samples: 3 sets of the following samples in the selected
finishes and color.
a. Initial color, texture selection, if custom, will be submitted as per
actual tile dimensions. Standard colors shall be selected from
manufacturer's color board.
b. full size profile of each type of panel. Samples shall represent
the full range of color and texture proposed for the Work.
c. full profile sample of each type sheet metal trim and closure
piece.
4. Product Data: Manufacturer's latest published literature describing each
product selection.
5. Tests:
a. Manufacturer and fabricator shall certify that performance tests
specified have been performed and that products or systems,
including finishes, comply with specified requirements.
b. Submit 2 copies of updated test reports, prepared by the testing
authority as directed by Engineer, for each specified test
showing required performance criteria and test results. Include
reports of failures and remedial actions taken in test reports.
in-service performance.
4. Single responsibility:
a. The clay panel wall cladding system, including panels, vertical
track, clips, related gaskets/isolators, shall be provided by a
single company.
b. The clay panel wall cladding system, with all its components,
shall have been in use for at least 5 years.
5. Mock Up: Provide one completely assembled wall area, as directed by
the Architect/Owner, installed with all related accessories, in composite
configurations designed to fulfill the performance criteria, and
representative of the design as indicated on the Drawings.
a. Extent of mock-up shall be the same as that which will be
provided in the final work.
b. Mock-up shall be installed simulating actual construction
conditions, including actual structural supports and connections.
Use means, methods and techniques proposed for final
installation.
c. Locate mock-up in location as directed by the Architect.
d. Personnel assembling mock-up shall be the same personnel that
will perform the actual work at the project site.
e. Mock-up shall be subjected to testing criteria specified for final
installation.
6. Pre-Construction Compatibility and Adhesion Testing: Submit to joint
sealant manufacturers samples of material that will contact or affect joint
sealants for compatibility and adhesion testing as indicated below:
a. Use test methods standard with manufacturer to determine if
priming and other specific joint preparation techniques are
required to obtain rapid, optimum adhesion of joint sealants to
joint substrates.
b. Perform tests under normal environmental conditions that will
exist during actual installation.
7. Pre-Installation Inspection. Installer to contact manufacturer of clay
panel wall cladding system, Owner and Architect, prior to installation of
clay panel wall cladding system shall proceed on a visit to the
manufacturer.
2. Storage:
a. Store components on platforms or pallets, covered with
tarpaulins or other suitable weather-tight ventilated covering.
Store components so that water accumulations will drain freely.
b. Do not store clay panels in contact with other materials that
might cause staining, surface damage, or other deleterious
effect.
c. Do not stack platforms or pallets one on top of another.
3. Store products in manufacturer's unopened packaging until ready for
installation.
4. Store and dispose of solvent-based materials, and materials used with
solvent-based materials, in accordance with requirements of local
authorities having jurisdiction.
1.9.1 PROJECT CONDITIONS
Maintain environmental conditions (temperature, humidity, and ventilation)
within limits recommended by manufacturer for optimum results. Do not
install products under environmental conditions outside manufacturer's
absolute limits.
1.9.2 COORDINATION
Building structure to support clay panel wall cladding system shall be
coordinated with clay panel wall cladding system shop drawings.
1.9.3 WARRANTY
1. Manufacturer shall warrant the material for a period of 20 years from
date of Substantial Completion against material defects.
2. Installer shall warrant the workmanship for a period of 5 years from
date of Substantial Completion against defects in Workmanship.
3. The installation warranty shall provide that the exterior wall system will
remain weather tight during the warranty period and that if any leaks
occur due to faulty installation practices, that the system will be
repaired or replaced as required to render the system weather-tight, at
no cost to the Owner. The warranty shall cover labor and materials
PART 2 PRODUCTS
MANUFACTURERS
1. Ceramica Mayor S.A. Espana
2. Dynamic Faade-Europe
3. Palagio Engineering -Europe
FIXING SYSTEM
1. Domus Facades System
2. Allface Smart Fixing Sysytems
3. Fisher accessories in Nautural Stone Facade
2.2 INSTALLER
Subject to compliance with requirements, installers offering exterior wall
system installation that may incorporate the clay panel wall cladding
system specified into the work include in the Contract documents.
2.3 MATERIALS
1. Material Properties
a.. Absorption (ASTM C67): 4.2 to 6.5 percent.
b. Modulus of Rupture (ASTM C99): 2231 to 3717 lbs/in2 (15382 to
25628 kPa).
c. Flexural Strength (ASTM C880): 2280 to 3457 lbs/in2 (15720 to
23835 kPa).
d. Weight (ASTM C67): 130 to 135 lbs/ft3 (2083 to 2162 kgs/c m).
e. Weight per Unit Area: 13 to 16 lbs/ft2 (0.62 to 0.77 kPa).
f. Linear Coefficient of Thermal Expansion: 3.5 x 10-4 percent
(0.035 percent).
2. Fabrication Tolerances:
a. Dimensional Tolerance: .06 inch (1.5 mm) for any cut length up
to 60 inches (1524 mm).
b. Height:
(plus or minus 1/16) plus or minus (1.6 mm) up to 10
inches (254 mm).
(plus or minus 3/32) plus or minus (2.4 mm) up to 15
inches (381 mm).
(plus or minus 1/8) plus or minus (3 mm) up to 20 inches
(508 mm).
c. Thickness: (cross section of panel) (plus or minus 1/16) plus or
minus (1.6 mm).
d. Straightness ("sweep"): plus or minus 0.2 percent of length.
e. Diagonal Flatness: plus or minus 0.2 percent of diagonal.
f. Vertical Flatness: plus or minus 1.0 percent of height.
g. Torsion: plus or minus 0.2 percent of diagonal.
5. Vertical track:
Aluminium alloy 6105 T5, mill finished.
5. Flashing,
Trim and other Accessories: Shop-fabricated, corrosion-resistant type
capable of complying with the performance criteria specified and
designed to allow adjustments of system prior to being permanently
fastened.
PART 3 EXECUTION
3.1 EXAMINATION
1. Do not begin installation until substrates have been properly prepared.
2. If substrate preparation is the responsibility of another installer, notify
Architect of unsatisfactory preparation before proceeding.
3.2 PREPARATION
1. Clean surfaces thoroughly prior to installation.
2. Prepare surfaces using the methods recommended by the
manufacturer for achieving the best result for the substrate under the
project conditions.
3.3 EXAMINATION
1. Clay Panel Wall Cladding installer to examine conditions affecting the
work at site. If any conditions exist that would be detrimental to proper
installation of clay panel wall cladding system, installer is to notify
Contractor in writing.
2. Correct conditions detrimental to the proper and timely completion of
this work before proceeding with installation.
3.4 INSTALLATION
1. Do no install broken, chipped or cracked units.
2. Apply coat of bituminous paint on concealed aluminum surfaces to be
in contact with steel, cementitious, and dissimilar materials.
3. Install clay panel cladding system to wall assembly specified in
3.5 CLEANING
1. Clean soiled surfaces using materials which will not harm clay panel
units or adjacent materials, as recommended by the clay panel
manufacturer (clean with mild detergent using a natural bristle brush,
starting from top of building to the bottom). Use non-metallic tools in
cleaning operations.
2. Upon completion of installation, remove protective coatings or
coverings and clean aluminum surfaces, exercising care to avoid
damage of finish.
END OF SECTION