HOJA DE METRADOS

OBRA: HECHO POR : J.M.B.


PROPIETARIO: REVISADO POR :
FECHA : JULIO 2017
PART. DENOMINACION CANT. LARGO ANCHO ALTURA SUBTOTAL TOTAL UNID.
1.00.00 OBRAS PROVISIONALES
1.01.00 CARTEL DE OBRA 1 3.60 2.40 8.64 8.64 M2
1.02.00 ALMACEN DE OBRA 1 4.00 3.00 12.00 12.00 M2

2.00.00 OBRAS PRELIMINARES


2.01.00 LIMPIEZA PRELIMINAR CANALETA 1 74.87 1.00 74.87 74.87 M2
2.02.00 TRAZO NIVEL Y REPLANTEO PRELIMINAR 1 74.87 1.00 74.87 74.87 M2

3.00.00 MOVIMIENTO DE TIERRA


3.01.00 EXCAVACION MANUAL EN T.N. C. PLUVIAL 1 74.87 0.50 0.50 18.72 18.72 M3
3.02.00 EXCAVACION MANUAL EN T.N. ZAPATA 1 1.25 1.25 1.30 2.03 2.03 M3
3.03.00 ACARREO MATERIAL DE EXCAVACIONES 1 20.75 24.90 24.90 M3

4.00.00 OBRAS DE CONCRETO SIMPLE


4.01.00 CONCRETO 110 Fc' Kg/cm2
SOLADO ZAPATA TANQUE ELEVADO 1 1.25 1.25 0.10 0.16 0.16 M3

5.00.00 OBRAS DE CONCRETO ARMADO


5.01.00 SOBRECIMIENTO REFORZADO
5.01.01 CONCRETO F'c=175 Kg/cm2 SOBRECIMIENTO
EJES A y J 2 45.00 0.15 0.35 4.73
EJE 15 1 25.00 0.15 0.35 1.31
EJE 1 1 20.60 0.15 0.35 1.08 7.12 M3
5.01.02 ACERO DE REFUERZO F'y=4200 Kg/cm2
3/8" EJES A y J 4 45.60 94.85
3/8" EJE 15 2 25.60 26.62
3/8" EJE 1 2 21.20 44.10
1/4" ESTRIBOS 692 0.50 89.96 255.53 Kg
5.01.03 ENCOFRADO Y DESENCOFRADO SOBRECIMIENTO
EJES A y J 4 45.00 0.35 63.00
EJE 15 2 25.00 0.35 17.50
EJE 1 2 20.60 0.35 14.42 94.92 M2
5.02.00 COLUMNAS
5.02.01 CONCRETO F'c=175 Kg/cm2 COLUMNAS
COLUMNA C1 3 0.40 0.25 2.35 0.71
COLUMNA C2 40 0.40 0.15 2.35 5.64
COLUMNA C3 3 0.40 0.15 2.35 0.42
3 0.25 0.15 2.35 0.26 7.03 M3
5.02.02 ACERO DE REFUERZO F'y=4200 Kg/cm2
1/2" COLUMNA C1 12 3.85 48.51
3/8" COLUMNA C1 6 3.85 12.01
1/4" ESTRIBOS 60 1.25 19.50
1/2" COLUMNA C2 160 3.85 646.80
1/4" ESTRIBOS 760 1.05 207.48
1/2" COLUMNA C3 12 3.85 48.51
3/8" COLUMNA C3 12 3.85 24.02
1/4" ESTRIBOS 114 1.05 31.12 1037.96 Kg
5.02.03 ENCOFRADO Y DESENCOFRADO COLUMNAS
COLUMNA C1 3 1.30 2.00 7.80
COLUMNA C2 40 0.80 2.00 64.00
COLUMNA C3 3 1.30 2.00 7.80 79.60 M2
5.03.00 VIGAS
5.03.01 CONCRETO F'c=175 Kg/cm2 VIGAS
VIGA VS, EJES A y J 2 45.00 0.15 0.20 2.70
VIGA VS, EJE 15 1 25.70 0.15 0.20 0.77
VIGA VS, EJE 1 1 20.95 0.15 0.20 0.63 4.10 M3
5.03.02 ACERO DE REFUERZO F'y=4200 Kg/cm2
3/8" VIGA V-S, EJES A y J 8 45.60 189.70
HOJA DE METRADOS
OBRA: HECHO POR : J.M.B.
PROPIETARIO: REVISADO POR :
FECHA : JULIO 2017
PART. DENOMINACION CANT. LARGO ANCHO ALTURA SUBTOTAL TOTAL UNID.
1/4" ESTRIBOS 262 0.40 27.25
3/8" VIGA V-S, EJE 15 4 26.70 55.54
1/4" ESTRIBOS 158 0.40 16.43
3/8" VIGA V-S, EJE 1 4 21.80 45.34
1/4" ESTRIBOS 126 0.40 13.10 347.36 Kg
5.03.03 ENCOFRADO Y DESENCOFRADO VIGAS
VIGA VS, EJES A y J 4 45.00 0.20 36.00
VIGA VS, EJE 15 2 26.00 0.20 10.40
VIGA VS, EJE 1 2 21.10 0.20 8.44 54.84 M2

6.00.00 MUROS Y TABIQUES


6.01.00 MURO LADRILLO ARCILLA KK SOGA, 2CV Mo.Co. 1:5
EJE A 1 39.00 2.00 78.00
EJE 15 1 22.00 2.00 44.00
EJE 1 1 18.10 2.00 36.20 158.20 M2
6.02.00 MURO LADRILLO ARCILLA KK SOGA, 1CV Mo.Co. 1:5
EJE J 1 39.00 2.00 78.00 78.00 M2

7.00.00 REVOQUES Y ENLUCIDOS


7.01.00 TARRAJEO Co. FROTACHADO SOBRECIMIENTO
EJE A 2 45.00 0.15 13.50
EJE J 1 45.00 0.15 6.75
EJE 15 2 26.00 0.15 7.80
EJE 1 2 21.10 0.15 6.33 34.38 M2
7.02.00 TARRAJEO Co. FROTACHADO COLUMNAS
COLUMNA C1 3 1.30 2.00 7.80
COLUMNA C2 (AMBAS CARAS) 27 0.80 2.00 43.20
COLUMNA C2 (UNA CARA) 13 0.40 2.00 10.40
COLUMNA C3 3 1.30 2.00 7.80 69.20 M2
7.03.00 TARRAJEO Co. FROTACHADO VIGAS
VIGA VS, EJE A 2 45.00 0.20 18.00
VIGA VS, EJE J 1 45.00 0.20 9.00
VIGA VS, EJE 15 2 26.00 0.20 10.40
VIGA VS, EJE 1 2 21.10 0.20 8.44 45.84 M2

8.00.00 CARPINTERIA METALICA


8.01.00 PUERTA PERFIL Fe. PL. Ao. CONTRAPLACADA
PUERTA DE ACCESO VEHICULAR 1 3.00 2.35 7.05
PUERTA DE ACCESO PEATONAL 1 1.20 2.35 2.82 9.87 M2

9.00.00 PINTURA
9.01.00 PINTURA LATEX SOBRECIMIENTO
EJE A 2 45.00 0.15 13.50
EJE J 1 45.00 0.15 6.75
EJE 15 2 26.00 0.15 7.80
EJE 1 2 21.10 0.15 6.33 34.38 M2
9.02.00 PINTURA LATEX COLUMNAS
COLUMNA C1 3 1.30 2.00 7.80
COLUMNA C2 (AMBAS CARAS) 27 0.80 2.00 43.20
COLUMNA C2 (UNA CARA) 13 0.40 2.00 10.40
COLUMNA C3 3 1.30 2.00 7.80 69.20 M2
9.03.00 PINTURA LATEX VIGAS
VIGA VS, EJE A 2 45.00 0.20 18.00
VIGA VS, EJE J 1 45.00 0.20 9.00
VIGA VS, EJE 15 2 26.00 0.20 10.40
VIGA VS, EJE 1 2 21.10 0.20 8.44 45.84 M2
9.04.00 PINTURA ESMALTE CARPINTERIA METALICA
PUERTA DE ACCESO VEHICULAR 2 3.00 2.35 14.10
HOJA DE METRADOS
OBRA: HECHO POR : J.M.B.
PROPIETARIO: REVISADO POR :
FECHA : JULIO 2017
PART. DENOMINACION CANT. LARGO ANCHO ALTURA SUBTOTAL TOTAL UNID.
PUERTA DE ACCESO PEATONAL 2 1.20 2.35 5.64 28.18 M2

10.00.00 VARIOS
10.01.00 TRANSPORTE 1 1.00 1.00 UND
10.02.00 JUNTA DE CONSTRUCCION 6 2.35 14.10 14.10 ML
10.03.00 LIMPIEZA FINAL DE OBRA MANUAL 1 142.00 1.00 142.00 142.00 M2
HOJA DE METRADOS
OBRA: HECHO POR : J.M.B.
PROPIETARIO: REVISADO POR :
FECHA : JULIO 2017
PART. DENOMINACION CANT. LARGO ANCHO ALTURA SUBTOTAL TOTAL UNID.
1.00.00 OBRAS PROVISIONALES
1.01.00 CARTEL DE OBRA 1 3.60 2.40 8.64 8.64 M2
1.02.00 ALMACEN DE OBRA 1 4.00 3.00 12.00 12.00 M2

2.00.00 OBRAS PRELIMINARES


2.01.00 LIMPIEZA PRELIMINAR DE OBRA MANUAL 1 142.00 1.00 142.00 142.00 M2
2.02.00 TRAZO NIVEL Y REPLANTEO PRELIMINAR 1 142.00 1.00 142.00 142.00 M2

3.00.00 MOVIMIENTO DE TIERRA


3.01.00 EXCAVACION MANUAL EN ROCA SUELTA
EJES A y J 2 45.00 0.50 1.10 49.50
EJES 1 y 15 2 25.00 0.50 1.10 27.50 77.00 M3
3.02.00 RELLENO Y COMPACT. MATERIAL PROPIO MANUAL
EJES A y J 2 45.00 0.35 0.20 6.30
EJE 15 1 25.00 0.35 0.20 1.75
EJE 1 1 20.60 0.35 0.20 1.44 9.49 M3
3.03.00 ACARREO MATERIAL DE EXCAVACIONES 1 9.49 11.39 11.39 M3

4.00.00 OBRAS DE CONCRETO SIMPLE


4.01.00 CONCRETO 1:10+30%P.G. CIMIENTO CORRIDO
EJES A y J 2 45.00 0.50 0.90 40.50
EJES 1 y 15 2 25.00 0.50 0.90 22.50 63.00 M3

5.00.00 OBRAS DE CONCRETO ARMADO


5.01.00 SOBRECIMIENTO REFORZADO
5.01.01 CONCRETO F'c=175 Kg/cm2 SOBRECIMIENTO
EJES A y J 2 45.00 0.15 0.35 4.73
EJE 15 1 25.00 0.15 0.35 1.31
EJE 1 1 20.60 0.15 0.35 1.08 7.12 M3
5.01.02 ACERO DE REFUERZO F'y=4200 Kg/cm2
3/8" EJES A y J 4 45.60 94.85
3/8" EJE 15 2 25.60 26.62
3/8" EJE 1 2 21.20 44.10
1/4" ESTRIBOS 692 0.50 89.96 255.53 Kg
5.01.03 ENCOFRADO Y DESENCOFRADO SOBRECIMIENTO
EJES A y J 4 45.00 0.35 63.00
EJE 15 2 25.00 0.35 17.50
EJE 1 2 20.60 0.35 14.42 94.92 M2
5.02.00 COLUMNAS
5.02.01 CONCRETO F'c=175 Kg/cm2 COLUMNAS
COLUMNA C1 3 0.40 0.25 2.35 0.71
COLUMNA C2 40 0.40 0.15 2.35 5.64
COLUMNA C3 3 0.40 0.15 2.35 0.42
3 0.25 0.15 2.35 0.26 7.03 M3
5.02.02 ACERO DE REFUERZO F'y=4200 Kg/cm2
1/2" COLUMNA C1 12 3.85 48.51
3/8" COLUMNA C1 6 3.85 12.01
1/4" ESTRIBOS 60 1.25 19.50
1/2" COLUMNA C2 160 3.85 646.80
1/4" ESTRIBOS 760 1.05 207.48
1/2" COLUMNA C3 12 3.85 48.51
3/8" COLUMNA C3 12 3.85 24.02
1/4" ESTRIBOS 114 1.05 31.12 1037.96 Kg
5.02.03 ENCOFRADO Y DESENCOFRADO COLUMNAS
COLUMNA C1 3 1.30 2.00 7.80
COLUMNA C2 40 0.80 2.00 64.00
COLUMNA C3 3 1.30 2.00 7.80 79.60 M2
5.03.00 VIGAS
HOJA DE METRADOS
OBRA: HECHO POR : J.M.B.
PROPIETARIO: REVISADO POR :
FECHA : JULIO 2017
PART. DENOMINACION CANT. LARGO ANCHO ALTURA SUBTOTAL TOTAL UNID.
5.03.01 CONCRETO F'c=175 Kg/cm2 VIGAS
VIGA VS, EJES A y J 2 45.00 0.15 0.20 2.70
VIGA VS, EJE 15 1 25.70 0.15 0.20 0.77
VIGA VS, EJE 1 1 20.95 0.15 0.20 0.63 4.10 M3
5.03.02 ACERO DE REFUERZO F'y=4200 Kg/cm2
3/8" VIGA V-S, EJES A y J 8 45.60 189.70
1/4" ESTRIBOS 262 0.40 27.25
3/8" VIGA V-S, EJE 15 4 26.70 55.54
1/4" ESTRIBOS 158 0.40 16.43
3/8" VIGA V-S, EJE 1 4 21.80 45.34
1/4" ESTRIBOS 126 0.40 13.10 347.36 Kg
5.03.03 ENCOFRADO Y DESENCOFRADO VIGAS
VIGA VS, EJES A y J 4 45.00 0.20 36.00
VIGA VS, EJE 15 2 26.00 0.20 10.40
VIGA VS, EJE 1 2 21.10 0.20 8.44 54.84 M2

6.00.00 MUROS Y TABIQUES


6.01.00 MURO LADRILLO ARCILLA KK SOGA, 2CV Mo.Co. 1:5
EJE A 1 39.00 2.00 78.00
EJE 15 1 22.00 2.00 44.00
EJE 1 1 18.10 2.00 36.20 158.20 M2
6.02.00 MURO LADRILLO ARCILLA KK SOGA, 1CV Mo.Co. 1:5
EJE J 1 39.00 2.00 78.00 78.00 M2

7.00.00 REVOQUES Y ENLUCIDOS


7.01.00 TARRAJEO Co. FROTACHADO SOBRECIMIENTO
EJE A 2 45.00 0.15 13.50
EJE J 1 45.00 0.15 6.75
EJE 15 2 26.00 0.15 7.80
EJE 1 2 21.10 0.15 6.33 34.38 M2
7.02.00 TARRAJEO Co. FROTACHADO COLUMNAS
COLUMNA C1 3 1.30 2.00 7.80
COLUMNA C2 (AMBAS CARAS) 27 0.80 2.00 43.20
COLUMNA C2 (UNA CARA) 13 0.40 2.00 10.40
COLUMNA C3 3 1.30 2.00 7.80 69.20 M2
7.03.00 TARRAJEO Co. FROTACHADO VIGAS
VIGA VS, EJE A 2 45.00 0.20 18.00
VIGA VS, EJE J 1 45.00 0.20 9.00
VIGA VS, EJE 15 2 26.00 0.20 10.40
VIGA VS, EJE 1 2 21.10 0.20 8.44 45.84 M2

8.00.00 CARPINTERIA METALICA


8.01.00 PUERTA PERFIL Fe. PL. Ao. CONTRAPLACADA
PUERTA DE ACCESO VEHICULAR 1 3.00 2.35 7.05
PUERTA DE ACCESO PEATONAL 1 1.20 2.35 2.82 9.87 M2

9.00.00 PINTURA
9.01.00 PINTURA LATEX SOBRECIMIENTO
EJE A 2 45.00 0.15 13.50
EJE J 1 45.00 0.15 6.75
EJE 15 2 26.00 0.15 7.80
EJE 1 2 21.10 0.15 6.33 34.38 M2
9.02.00 PINTURA LATEX COLUMNAS
COLUMNA C1 3 1.30 2.00 7.80
COLUMNA C2 (AMBAS CARAS) 27 0.80 2.00 43.20
COLUMNA C2 (UNA CARA) 13 0.40 2.00 10.40
COLUMNA C3 3 1.30 2.00 7.80 69.20 M2
9.03.00 PINTURA LATEX VIGAS
HOJA DE METRADOS
OBRA: HECHO POR : J.M.B.
PROPIETARIO: REVISADO POR :
FECHA : JULIO 2017
PART. DENOMINACION CANT. LARGO ANCHO ALTURA SUBTOTAL TOTAL UNID.
VIGA VS, EJE A 2 45.00 0.20 18.00
VIGA VS, EJE J 1 45.00 0.20 9.00
VIGA VS, EJE 15 2 26.00 0.20 10.40
VIGA VS, EJE 1 2 21.10 0.20 8.44 45.84 M2
9.04.00 PINTURA ESMALTE CARPINTERIA METALICA
PUERTA DE ACCESO VEHICULAR 2 3.00 2.35 14.10
PUERTA DE ACCESO PEATONAL 2 1.20 2.35 5.64 28.18 M2

10.00.00 VARIOS
10.01.00 TRANSPORTE 1 1.00 1.00 UND
10.02.00 JUNTA DE CONSTRUCCION 6 2.35 14.10 14.10 ML
10.03.00 LIMPIEZA FINAL DE OBRA MANUAL 1 142.00 1.00 142.00 142.00 M2
HOJA DE METRADOS
OBRA: HECHO POR : J.M.B.
PROPIETARIO: REVISADO POR :
FECHA : JULIO 2017
PART. DENOMINACION CANT. LARGO ANCHO ALTURA SUBTOTAL TOTAL UNID.
1.00.00 OBRAS PROVISIONALES
1.01.00 CARTEL DE OBRA 1 3.60 2.40 8.64 8.64 M2
1.02.00 ALMACEN DE OBRA 1 4.00 3.00 12.00 12.00 M2

2.00.00 OBRAS PRELIMINARES


2.01.00 LIMPIEZA PRELIMINAR DE OBRA MANUAL 1 142.00 1.00 142.00 142.00 M2
2.02.00 TRAZO NIVEL Y REPLANTEO PRELIMINAR 1 142.00 1.00 142.00 142.00 M2

3.00.00 MOVIMIENTO DE TIERRA


3.01.00 EXCAVACION MANUAL EN ROCA SUELTA
EJES A y J 2 45.00 0.50 1.10 49.50
EJES 1 y 15 2 25.00 0.50 1.10 27.50 77.00 M3
3.02.00 RELLENO Y COMPACT. MATERIAL PROPIO MANUAL
EJES A y J 2 45.00 0.35 0.20 6.30
EJE 15 1 25.00 0.35 0.20 1.75
EJE 1 1 20.60 0.35 0.20 1.44 9.49 M3
3.03.00 ACARREO MATERIAL DE EXCAVACIONES 1 9.49 11.39 11.39 M3

4.00.00 OBRAS DE CONCRETO SIMPLE


4.01.00 CONCRETO 1:10+30%P.G. CIMIENTO CORRIDO
EJES A y J 2 45.00 0.50 0.90 40.50
EJES 1 y 15 2 25.00 0.50 0.90 22.50 63.00 M3

5.00.00 OBRAS DE CONCRETO ARMADO


5.01.00 SOBRECIMIENTO REFORZADO
5.01.01 CONCRETO F'c=175 Kg/cm2 SOBRECIMIENTO
EJES A y J 2 45.00 0.15 0.35 4.73
EJE 15 1 25.00 0.15 0.35 1.31
EJE 1 1 20.60 0.15 0.35 1.08 7.12 M3
5.01.02 ACERO DE REFUERZO F'y=4200 Kg/cm2
3/8" EJES A y J 4 45.60 94.85
3/8" EJE 15 2 25.60 26.62
3/8" EJE 1 2 21.20 44.10
1/4" ESTRIBOS 692 0.50 89.96 255.53 Kg
5.01.03 ENCOFRADO Y DESENCOFRADO SOBRECIMIENTO
EJES A y J 4 45.00 0.35 63.00
EJE 15 2 25.00 0.35 17.50
EJE 1 2 20.60 0.35 14.42 94.92 M2
5.02.00 COLUMNAS
5.02.01 CONCRETO F'c=175 Kg/cm2 COLUMNAS
COLUMNA C1 3 0.40 0.25 2.35 0.71
COLUMNA C2 40 0.40 0.15 2.35 5.64
COLUMNA C3 3 0.40 0.15 2.35 0.42
3 0.25 0.15 2.35 0.26 7.03 M3
5.02.02 ACERO DE REFUERZO F'y=4200 Kg/cm2
1/2" COLUMNA C1 12 3.85 48.51
3/8" COLUMNA C1 6 3.85 12.01
1/4" ESTRIBOS 60 1.25 19.50
1/2" COLUMNA C2 160 3.85 646.80
1/4" ESTRIBOS 760 1.05 207.48
1/2" COLUMNA C3 12 3.85 48.51
3/8" COLUMNA C3 12 3.85 24.02
1/4" ESTRIBOS 114 1.05 31.12 1037.96 Kg
5.02.03 ENCOFRADO Y DESENCOFRADO COLUMNAS
COLUMNA C1 3 1.30 2.00 7.80
COLUMNA C2 40 0.80 2.00 64.00
COLUMNA C3 3 1.30 2.00 7.80 79.60 M2
5.03.00 VIGAS
HOJA DE METRADOS
OBRA: HECHO POR : J.M.B.
PROPIETARIO: REVISADO POR :
FECHA : JULIO 2017
PART. DENOMINACION CANT. LARGO ANCHO ALTURA SUBTOTAL TOTAL UNID.
5.03.01 CONCRETO F'c=175 Kg/cm2 VIGAS
VIGA VS, EJES A y J 2 45.00 0.15 0.20 2.70
VIGA VS, EJE 15 1 25.70 0.15 0.20 0.77
VIGA VS, EJE 1 1 20.95 0.15 0.20 0.63 4.10 M3
5.03.02 ACERO DE REFUERZO F'y=4200 Kg/cm2
3/8" VIGA V-S, EJES A y J 8 45.60 189.70
1/4" ESTRIBOS 262 0.40 27.25
3/8" VIGA V-S, EJE 15 4 26.70 55.54
1/4" ESTRIBOS 158 0.40 16.43
3/8" VIGA V-S, EJE 1 4 21.80 45.34
1/4" ESTRIBOS 126 0.40 13.10 347.36 Kg
5.03.03 ENCOFRADO Y DESENCOFRADO VIGAS
VIGA VS, EJES A y J 4 45.00 0.20 36.00
VIGA VS, EJE 15 2 26.00 0.20 10.40
VIGA VS, EJE 1 2 21.10 0.20 8.44 54.84 M2

6.00.00 MUROS Y TABIQUES


6.01.00 MURO LADRILLO ARCILLA KK SOGA, 2CV Mo.Co. 1:5
EJE A 1 39.00 2.00 78.00
EJE 15 1 22.00 2.00 44.00
EJE 1 1 18.10 2.00 36.20 158.20 M2
6.02.00 MURO LADRILLO ARCILLA KK SOGA, 1CV Mo.Co. 1:5
EJE J 1 39.00 2.00 78.00 78.00 M2

7.00.00 REVOQUES Y ENLUCIDOS


7.01.00 TARRAJEO Co. FROTACHADO SOBRECIMIENTO
EJE A 2 45.00 0.15 13.50
EJE J 1 45.00 0.15 6.75
EJE 15 2 26.00 0.15 7.80
EJE 1 2 21.10 0.15 6.33 34.38 M2
7.02.00 TARRAJEO Co. FROTACHADO COLUMNAS
COLUMNA C1 3 1.30 2.00 7.80
COLUMNA C2 (AMBAS CARAS) 27 0.80 2.00 43.20
COLUMNA C2 (UNA CARA) 13 0.40 2.00 10.40
COLUMNA C3 3 1.30 2.00 7.80 69.20 M2
7.03.00 TARRAJEO Co. FROTACHADO VIGAS
VIGA VS, EJE A 2 45.00 0.20 18.00
VIGA VS, EJE J 1 45.00 0.20 9.00
VIGA VS, EJE 15 2 26.00 0.20 10.40
VIGA VS, EJE 1 2 21.10 0.20 8.44 45.84 M2

8.00.00 CARPINTERIA METALICA


8.01.00 PUERTA PERFIL Fe. PL. Ao. CONTRAPLACADA
PUERTA DE ACCESO VEHICULAR 1 3.00 2.35 7.05
PUERTA DE ACCESO PEATONAL 1 1.20 2.35 2.82 9.87 M2

9.00.00 PINTURA
9.01.00 PINTURA LATEX SOBRECIMIENTO
EJE A 2 45.00 0.15 13.50
EJE J 1 45.00 0.15 6.75
EJE 15 2 26.00 0.15 7.80
EJE 1 2 21.10 0.15 6.33 34.38 M2
9.02.00 PINTURA LATEX COLUMNAS
COLUMNA C1 3 1.30 2.00 7.80
COLUMNA C2 (AMBAS CARAS) 27 0.80 2.00 43.20
COLUMNA C2 (UNA CARA) 13 0.40 2.00 10.40
COLUMNA C3 3 1.30 2.00 7.80 69.20 M2
9.03.00 PINTURA LATEX VIGAS
HOJA DE METRADOS
OBRA: HECHO POR : J.M.B.
PROPIETARIO: REVISADO POR :
FECHA : JULIO 2017
PART. DENOMINACION CANT. LARGO ANCHO ALTURA SUBTOTAL TOTAL UNID.
VIGA VS, EJE A 2 45.00 0.20 18.00
VIGA VS, EJE J 1 45.00 0.20 9.00
VIGA VS, EJE 15 2 26.00 0.20 10.40
VIGA VS, EJE 1 2 21.10 0.20 8.44 45.84 M2
9.04.00 PINTURA ESMALTE CARPINTERIA METALICA
PUERTA DE ACCESO VEHICULAR 2 3.00 2.35 14.10
PUERTA DE ACCESO PEATONAL 2 1.20 2.35 5.64 28.18 M2

10.00.00 VARIOS
10.01.00 TRANSPORTE 1 1.00 1.00 UND
10.02.00 JUNTA DE CONSTRUCCION 6 2.35 14.10 14.10 ML
10.03.00 LIMPIEZA FINAL DE OBRA MANUAL 1 142.00 1.00 142.00 142.00 M2
HOJA DE METRADOS
OBRA: HECHO POR : J.M.B.
PROPIETARIO: REVISADO POR :
FECHA : JULIO 2017
PART. DENOMINACION CANT. LARGO ANCHO ALTURA SUBTOTAL TOTAL UNID.
1.00.00 OBRAS PROVISIONALES
1.01.00 CARTEL DE OBRA 1 3.60 2.40 8.64 8.64 M2
1.02.00 ALMACEN DE OBRA 1 4.00 3.00 12.00 12.00 M2

2.00.00 OBRAS PRELIMINARES


2.01.00 LIMPIEZA PRELIMINAR DE OBRA MANUAL 1 142.00 1.00 142.00 142.00 M2
2.02.00 TRAZO NIVEL Y REPLANTEO PRELIMINAR 1 142.00 1.00 142.00 142.00 M2

3.00.00 MOVIMIENTO DE TIERRA


3.01.00 EXCAVACION MANUAL EN ROCA SUELTA
EJES A y J 2 45.00 0.50 1.10 49.50
EJES 1 y 15 2 25.00 0.50 1.10 27.50 77.00 M3
3.02.00 RELLENO Y COMPACT. MATERIAL PROPIO MANUAL
EJES A y J 2 45.00 0.35 0.20 6.30
EJE 15 1 25.00 0.35 0.20 1.75
EJE 1 1 20.60 0.35 0.20 1.44 9.49 M3
3.03.00 ACARREO MATERIAL DE EXCAVACIONES 1 9.49 11.39 11.39 M3

4.00.00 OBRAS DE CONCRETO SIMPLE


4.01.00 CONCRETO 1:10+30%P.G. CIMIENTO CORRIDO
EJES A y J 2 45.00 0.50 0.90 40.50
EJES 1 y 15 2 25.00 0.50 0.90 22.50 63.00 M3

5.00.00 OBRAS DE CONCRETO ARMADO


5.01.00 SOBRECIMIENTO REFORZADO
5.01.01 CONCRETO F'c=175 Kg/cm2 SOBRECIMIENTO
EJES A y J 2 45.00 0.15 0.35 4.73
EJE 15 1 25.00 0.15 0.35 1.31
EJE 1 1 20.60 0.15 0.35 1.08 7.12 M3
5.01.02 ACERO DE REFUERZO F'y=4200 Kg/cm2
3/8" EJES A y J 4 45.60 94.85
3/8" EJE 15 2 25.60 26.62
3/8" EJE 1 2 21.20 44.10
1/4" ESTRIBOS 692 0.50 89.96 255.53 Kg
5.01.03 ENCOFRADO Y DESENCOFRADO SOBRECIMIENTO
EJES A y J 4 45.00 0.35 63.00
EJE 15 2 25.00 0.35 17.50
EJE 1 2 20.60 0.35 14.42 94.92 M2
5.02.00 COLUMNAS
5.02.01 CONCRETO F'c=175 Kg/cm2 COLUMNAS
COLUMNA C1 3 0.40 0.25 2.35 0.71
COLUMNA C2 40 0.40 0.15 2.35 5.64
COLUMNA C3 3 0.40 0.15 2.35 0.42
3 0.25 0.15 2.35 0.26 7.03 M3
5.02.02 ACERO DE REFUERZO F'y=4200 Kg/cm2
1/2" COLUMNA C1 12 3.85 48.51
3/8" COLUMNA C1 6 3.85 12.01
1/4" ESTRIBOS 60 1.25 19.50
1/2" COLUMNA C2 160 3.85 646.80
1/4" ESTRIBOS 760 1.05 207.48
1/2" COLUMNA C3 12 3.85 48.51
3/8" COLUMNA C3 12 3.85 24.02
1/4" ESTRIBOS 114 1.05 31.12 1037.96 Kg
5.02.03 ENCOFRADO Y DESENCOFRADO COLUMNAS
COLUMNA C1 3 1.30 2.00 7.80
COLUMNA C2 40 0.80 2.00 64.00
COLUMNA C3 3 1.30 2.00 7.80 79.60 M2
5.03.00 VIGAS
HOJA DE METRADOS
OBRA: HECHO POR : J.M.B.
PROPIETARIO: REVISADO POR :
FECHA : JULIO 2017
PART. DENOMINACION CANT. LARGO ANCHO ALTURA SUBTOTAL TOTAL UNID.
5.03.01 CONCRETO F'c=175 Kg/cm2 VIGAS
VIGA VS, EJES A y J 2 45.00 0.15 0.20 2.70
VIGA VS, EJE 15 1 25.70 0.15 0.20 0.77
VIGA VS, EJE 1 1 20.95 0.15 0.20 0.63 4.10 M3
5.03.02 ACERO DE REFUERZO F'y=4200 Kg/cm2
3/8" VIGA V-S, EJES A y J 8 45.60 189.70
1/4" ESTRIBOS 262 0.40 27.25
3/8" VIGA V-S, EJE 15 4 26.70 55.54
1/4" ESTRIBOS 158 0.40 16.43
3/8" VIGA V-S, EJE 1 4 21.80 45.34
1/4" ESTRIBOS 126 0.40 13.10 347.36 Kg
5.03.03 ENCOFRADO Y DESENCOFRADO VIGAS
VIGA VS, EJES A y J 4 45.00 0.20 36.00
VIGA VS, EJE 15 2 26.00 0.20 10.40
VIGA VS, EJE 1 2 21.10 0.20 8.44 54.84 M2

6.00.00 MUROS Y TABIQUES


6.01.00 MURO LADRILLO ARCILLA KK SOGA, 2CV Mo.Co. 1:5
EJE A 1 39.00 2.00 78.00
EJE 15 1 22.00 2.00 44.00
EJE 1 1 18.10 2.00 36.20 158.20 M2
6.02.00 MURO LADRILLO ARCILLA KK SOGA, 1CV Mo.Co. 1:5
EJE J 1 39.00 2.00 78.00 78.00 M2

7.00.00 REVOQUES Y ENLUCIDOS


7.01.00 TARRAJEO Co. FROTACHADO SOBRECIMIENTO
EJE A 2 45.00 0.15 13.50
EJE J 1 45.00 0.15 6.75
EJE 15 2 26.00 0.15 7.80
EJE 1 2 21.10 0.15 6.33 34.38 M2
7.02.00 TARRAJEO Co. FROTACHADO COLUMNAS
COLUMNA C1 3 1.30 2.00 7.80
COLUMNA C2 (AMBAS CARAS) 27 0.80 2.00 43.20
COLUMNA C2 (UNA CARA) 13 0.40 2.00 10.40
COLUMNA C3 3 1.30 2.00 7.80 69.20 M2
7.03.00 TARRAJEO Co. FROTACHADO VIGAS
VIGA VS, EJE A 2 45.00 0.20 18.00
VIGA VS, EJE J 1 45.00 0.20 9.00
VIGA VS, EJE 15 2 26.00 0.20 10.40
VIGA VS, EJE 1 2 21.10 0.20 8.44 45.84 M2

8.00.00 CARPINTERIA METALICA


8.01.00 PUERTA PERFIL Fe. PL. Ao. CONTRAPLACADA
PUERTA DE ACCESO VEHICULAR 1 3.00 2.35 7.05
PUERTA DE ACCESO PEATONAL 1 1.20 2.35 2.82 9.87 M2

9.00.00 PINTURA
9.01.00 PINTURA LATEX SOBRECIMIENTO
EJE A 2 45.00 0.15 13.50
EJE J 1 45.00 0.15 6.75
EJE 15 2 26.00 0.15 7.80
EJE 1 2 21.10 0.15 6.33 34.38 M2
9.02.00 PINTURA LATEX COLUMNAS
COLUMNA C1 3 1.30 2.00 7.80
COLUMNA C2 (AMBAS CARAS) 27 0.80 2.00 43.20
COLUMNA C2 (UNA CARA) 13 0.40 2.00 10.40
COLUMNA C3 3 1.30 2.00 7.80 69.20 M2
9.03.00 PINTURA LATEX VIGAS
HOJA DE METRADOS
OBRA: HECHO POR : J.M.B.
PROPIETARIO: REVISADO POR :
FECHA : JULIO 2017
PART. DENOMINACION CANT. LARGO ANCHO ALTURA SUBTOTAL TOTAL UNID.
VIGA VS, EJE A 2 45.00 0.20 18.00
VIGA VS, EJE J 1 45.00 0.20 9.00
VIGA VS, EJE 15 2 26.00 0.20 10.40
VIGA VS, EJE 1 2 21.10 0.20 8.44 45.84 M2
9.04.00 PINTURA ESMALTE CARPINTERIA METALICA
PUERTA DE ACCESO VEHICULAR 2 3.00 2.35 14.10
PUERTA DE ACCESO PEATONAL 2 1.20 2.35 5.64 28.18 M2

10.00.00 VARIOS
10.01.00 TRANSPORTE 1 1.00 1.00 UND
10.02.00 JUNTA DE CONSTRUCCION 6 2.35 14.10 14.10 ML
10.03.00 LIMPIEZA FINAL DE OBRA MANUAL 1 142.00 1.00 142.00 142.00 M2