You are on page 1of 20

LNG focus

LNG battles the deep freeze


Industry hopeful that commodity price slump will eventually be beaten

Photo: SEIC
20       
focus
 
LNG   29January2016

global outlook

LNG industry
faces an
uphill battle
International Energy Agency says new liquefaction
projects will struggle to get off the ground unless
commodity prices recover

AmAndA BAttErsBy
singapore

T he global liquefied natu-


ral gas industry faces an
uphill battle due to its
capital intensive nature
against the backdrop of the con-
tinuing commodity price slump.
Projects currently under con-
investment decisions taken in the
next two years will determine the
amount of incremental LNG avail-
able early in the next decade.
If the current low prices persist,
LNG markets could start to tight-
en up substantially by 2020, says
account for some 90% of the new
LNG volumes entering the market
through 2020.
Large quantities of flexible
supplies from the US are on the
way, says IeA executive director
Maria van der hoeven.
which are currently in front-end
engineering and design are strug-
gling to make economic sense in
the low price environment.
Adeosun says that the advent of
the US as a major LNG exporter is
likely to be slower than originally
1.4 billion cubic feet per day as
Sabine Pass ramps up its capacity.
Cheniere now envisages the
first commissioning cargo from
Sabine Pass to leave in late Febru-
ary or March rather than this
month as was earlier expected.
struction are likely to come into the IeA in 2015 Medium Term Gas But from a consumer stand- envisaged. Of the 20 US terminals however, interim chief execu-
operation as planned because sub- Market Report. In the shorter point, the economic attractive- proposed in the US, 11 were tive Neal Shear says the partners
stantial upfront capital expendi- term however, the global LNG ness of the henry hub-linked planned for start-up between 2016 anticipate no issues in meeting
ture has already been incurred. market will have to cope with a model has narrowed substantially and 2020. all contractual targets and guar-
however, new liquefaction flood of new supplies. relative to the traditional oil- however, DW reckons that only anteed completion dates.
projects will struggle to get off the Global LNG export capacity based one. What the impacts will six of these will now be up and Additionally, construction for
ground, according to the Paris- additions through 2020 will be on the next generation of LNG running by the end of the decade. trains two to five continues to be
based International energy Agen- amount to more than 40% of last projects remains to be seen. The approval process for US on- on an accelerated schedule and
cy (IeA). years existing infrastructure, shore liquefaction projects re- these trains are expected to come
Today LNG prices simply do not with almost half of the incremen- Increased expenditure Doug- mains slow and this will limit the on line on a staggered basis, says
cover the capital costs of new tal supply due to come on line in las-Westwood (DW) forecasts cap- increase in regional LNG expendi- Shear.
plants. Several projects have al- 2016 and 2017. ital expenditure on global LNG ture through the rest of the dec- The LNG markets need a further
ready been scrapped or postponed, Conventional and coal seam gas facilities will total $241 billion be- ade, according to DW. 65 million tonnes per annum-plus
and the number of casualties will (coalbed methane) LNG projects tween 2016 and 2020, which repre- The energy Intelligence Agency capacity to take final investment
rise if prices do not recover, are coming into operation in Aus- sents a 34% increase versus the (eIA) expects gross US LNG exports decisions this decade to avoid a
claims the IeA. tralia, which will overtake Qatar preceding five-year period. will this year increase to an average tight market by the mid-2020s, ac-
Proposed LNG projects are soft as the number one producer, and however, Mark Adeosun, author of 700 million cubic feet per day cording to McKinseys energy In-
targets for investment reductions also from the US, which not so of DWs 10th LNG World Market with the start-up of Cheniere en- sights.
and several of them are likely to be long ago was being touted as a Forecast, admits with commodity ergys Sabine Pass facility. Despite low oil prices and a
delayed or even cancelled, major LNG importer. prices depressed, future LNG The US eIA projects gross US weak medium-term outlook, the
according to the agency. Final Australia and the US will projects are uncertain, as those LNG exports in 2017 will average LNG market has a bright future.
29 January 2016
focus LNG 21

Impacts: International Energy


Global demand slows gradually
Agency executive director Global liquefied natural gas imports to approximately double
Maria van der Hoeven
Photo: WGC
demand is forecast to reach 400.6
million tonnes in 2020, up from risk of between 2014 and 2020.
The global lNG market is
238.2 million tonnes last year,
writes Amanda Battersby.
oversupply shifting in the buyers favour
after being tight for a few years,
However, this could still say sources, who add that
translate to 20 million tonnes of Increase expected to be customers are increasingly
overcapacity come the end of the looking to renegotiate existing
decade, says market research 2% per annum until 2020 deals.
agency ReportsnReports. We expect the market to shift
Global lNG demand is now Korea are looking to reduce the completely in buyers favour
seen increasing by 2% per annum amount of lNG that they from 2017 with the foray of US
to 2020, slower than the 2.3% purchase on long-term contracts, and australian lNG supplies.
projected a year ago, according to while China has been scaling lower than expected demand
the International Energy agency back on its spot purchases of growth rates coupled with
(IEa). late. commencement of new projects
a significant reason for the The latest devaluation of the is forcing the shift in global lNG
downward revision in global gas yuan by China has reportedly markets, says ReportsnReports.
demand is weaker than expected dampened Chinas independent There might be a shift in
growth in asia, where buyers enthusiasm for US contractual models and buyers
persistently high prices had dollar-denominated lNG might soon have the upper hand
until recently caused consumers imports, at least for the time but the longer-term market
to switch to less expensive being. However, the falling lNG outlook remains buoyant,
options such as coal. prices are expected to translate according to French major Total,
The belief that asia will take into increasing shipments into which sees annual lNG demand
whatever quantity of gas at Europe through the rest of the growth of 4% from 2015 through
whatever price is no longer a decade. 2030.
given, says Maria van der Europes growing import The global market will be
Hoeven, the IEas executive needs might well offer a driven by asia, where demand
director. welcome outlet to lNG exports for lNG will double between now
North asian stalwart struggling to find a home, and and 2030, Totals gas president
customers Japan and South the IEa expects European lNG laurent Vivier said last year.

There is the need for around 15


new LNG trains by 2025 and over
From a
double that by 2030, the McKin- consumer
sey report says.
Players should look past the standpoint,
structural loose market in the me-
dium term and push ahead with the economic
final investment decisions for this
growing market.
attractiveness
of the Henry
Positive outlook LNG markets
have a much more positive longer- Hub-linked
term outlook. Demand is forecast
to increase on average between 4%
model has
and 6% annually until 2030, so the narrowed
market needs to take a final in-
vestment decision on a further 20 substantially
million tpa or so by late 2017 or
early 2018 to bring it to market by
relative to the
2030. traditional
A final investment decision will
need to be taken on another 45 oil-based one.
million tpa by the end of the dec-
ade so that these volumes are International Energy
ready to enter the market in 2025. Agency executive
Otherwise from 2023, we qui- director Maria van
etly enter a very tight global LNG der Hoeven
market, says Energy Insights.
22      
focus
  
LNG   29January2016

Double us

blow for
Trinidad Consolidation likely befor
Predicting the future of the US industry beyond the current downturn is
ATlAnTic lnG difficult but long-term global LNG demand should create a fresh need
projecT for exports and US players are already jostling for position
Caribbean scheme NOAH BRENNER
Houston
faces volatile future
THE future of the US liquefied
THE near-term future of lique- natural gas business is likely to
fied natural gas supply from look significantly different than it
long-time producer Trinidad & does today as the sector matures
Tobago is as volatile as it has over the next decade.
ever been, as producer Atlantic The sector is likely to see sig-
LNG grapples with low supply, nificant consolidation, or at least
increased government scruti- changes in ownership, as projects
ny and a drastic change in move from speculation to con-
ownership, writes Noah Brenner. struction and eventually produc-
Natural gas production off tion, says Erik Codrington, project
Trinidad has fallen from a high finance managing director at the
of 4.2 billion cubic feet per day Bank of Tokyo-Mitsubishi.
to 3.8 Bcfd due to low upstream The bank is the lead lender for US
investment and ongoing main- projects such as Cheniere Energys
tenence programmes. Sabine Pass and Corpus Christi
Atlantic LNG has been oper- projects as well as Freeport LNG
ating below its nameplate and Cameron LNG.
capacity of 15 million tonnes Once these projects are up and
per annum and is likely to see running it would not surprise me
production crimped by 13% to if maybe some of them changed
15% through late 2017, when UK hands, he says. Or some of the
supermajor BP is expected to original investors changed out be-
bring on additional supply of cause you are going from a kind of
up to 590 million cubic feet risky developmentstage project
per day from its offshore to a more mature almost utility-
Juniper platform, says Atlantic type asset.
chief operating officer Arlene The dynamic may be similar to
Chow. what has already been seen in the
It is like we have a double US onshore midstream space.
whammy here in Trinidad We find smaller developers
these days, we have the lower that construct pipelines, once
oil prices and we also have the they are constructed they will of-
gas shortfalls, Chow says. ten sell out to larger companies
To further complicate mat- who have lower cost of capital and
ters, newly-appointed Trinidad lower return expectations, and
& Tobago Energy Minister are maybe better at being low-cost
Nicole Olivierre has questioned operators, Codrington says.
whether Atlantics member
companies are adhering to Thinning the herd The master
their various contracts. limited partnership (MLP) struc-
Those contracts were set up ture that many midstream com-
under the assumption that panies embraced is being sorely
Atlantics output would go to tested during the downturn but
the US, but most cargoes are the regular fees paid by compa-
now diverted to customers in nies to lease liquefaction capacity
South America. at US facilities would fit well into
With many of our commer- that business model.
cial pricing arrangements tied It wouldnt surprise me if a lot
to a US destination, this coun- of these either converted to an
try is realising netbacks well MLP structure of their own or
below the actual market price were acquired by MLP players,
applicable to the true destina- Codrington says.
tion of our cargoes, Olivierre Long-term, he sees the need for demand and they are tailoring Decade was founded with the idea for their LNG. However, Codring-
says. the development of an additional their projects for just that scenario. of leading the second wave of US ton does not believe the industry
The only conclusion that three to four trains of LNG capacity I think that these conditions LNG exports, and we are still on is in danger of over-building in
can be drawn is that the con- per year to meet growing world will thin the herd, and the strong track to achieve this, she says. the way that plagued the US LNG
tractual arrangements for the demand, and of that capacity, US projects with strong companies import industry.
marketing of LNG are not now players might win contracts for behind them are going to be the Appetite Yet, if the global mar- From a financing perspective I
working in the best interest of one to two trains. ones that benefit and move for- ket only has appetite for an addi- dont see that as a danger, he says.
Trinidad & Tobago. Many in industry believe the ward, says Kathleen Eisbrenner, tional train or two per year from The liquefaction projects are not
Olivierre has pledged to re- current pause in contracting will chief executive of NextDecade, the US, there is no way that many financed unless they already have
visit the various contracts un- give way to a second wave of which is pursuing a pair of facili- of the facilities being proposed to long-term fixed offtake.
derpinning Atlantics opera- projects meeting this incremental ties on the US Gulf Coast. Next- US regulators will find offtakers But there is some danger of over-
tions but has given little detail
of which contracts those are
and whether she would seek to US LNG ExPORT TERmiNALS APPROvEd ANd UNdER cONSTRUcTiON
reopen them before they come
due. Project Location company capacity
Dealing with these un- sabine Pass sabine, Louisiana Cheniere Energy 2.76 Bcfd
certainties will fall in large Cameron LNG Hackberry, Louisiana sempra 1.7 Bcfd
part to Atlantics new majority Freeport LNG Freeport, Texas Freeport LNG Development 1.8 Bcfd
shareholder, Shell, which Cove Point LNG Cove Point, Maryland Dominion 820 MMcfd
bought out Repsols stake in the Corpus Christi LNG Corpus Christi, Texas Cheniere Energy 2.14 Bcfd
project in a deal announced in sabine Pass LNG (expansion) sabine, Louisiana Cheniere Energy 1.4 Bcfd
2013 and will control a majority
Total capacity: 10.62 Bcfd
shareholding in each of Atlan-
tics trains when its takeover of us LNG EXPORT TERMINAL APPROVED BuT NOT uNDER CONsTRuCTION
BG Group is complete. Lake Charles LNG Lake Charles, Louisiana southern union 2.2 Bcfd
Shell declined to comment
as Upstream went to press.
29 January 2016
focus LNG 23

Trends in
re new contracting wave tech hard
to predict
Buyers wary of investing
in new technology
THE role of technology in the
LNG business both in the US and
abroad is a bit of a paradox,
writes Noah Brenner.
The industry has touted its
Maturing significant innovations but
sector: buyers, and therefore
workers at developers, are not always
Freeport LNG comfortable being the first one
in Texas to put the new designs into
practice, and instead return
time and again to decades-old
technologies.
Erik Codrington, project
finance managing director at
the Bank of Tokyo-Mitsubishi,
says he is seeing significant
interest in smaller-scale
technologies that can add
incremental volumes without
huge up-front investment.
Buyers are intrigued that
they could make smaller
commitments and help to
bootstrap a lower-cost
technology, he says. We
havent seen any of those move
forward yet but its out there.
At the same time, many
buyers are loath to take a
chance on new technology
when signing long-term,
multi-billion dollar offtake
agreements that depend on the
reliable operation of the plant.
Developers who push into
unfamiliar territory may have a
harder time lining up contracts.
A motto that I have is no
novelty is the new novelty,
meaning that our projects are
safe, reliable and use technology
proven and understood,
NextDecade chief executive
Kathleen Eisbrenner says.
Innovation for NextDecade lies
in how we do business and how
we work with our customers to
supply their LNG needs,
including the contract strategy.
Floating liquefaction has
garnered a lot of media
attention but it is still being
scrutinised by many in the
Photo: marketplace.
BLOOMBERG The banks are cautiously
interested in floating LNG,
Codrington says. There is a
building from large portfolio LNG its pretty difficult. You are likely open to offering a variety of sort of vertically integrate all the desire to see more track record
players such as ExxonMobil, BP to have overshoot and undershoot contract structures, whether its way back to the wellhead, he ex- around that but it makes
and Shell, which may not need given the very long lead times for taking a Henry Hub pricing or plains. They can buy reserves, facilities potentially reusable
such contracts because they are new LNG capacity. something totally different. they can contract for reserves, and allows access to places
keeping rights to their production. Here again, however, the flex- Even without such creative they can buy E&P players which where building out onshore
They might contract for more ibility of US offtake contracts contracting, US LNG projects fill a is something they dont have the infrastructure is not feasible or
than the market might bear but its could provide a much needed unique space in the industry be- ability to do in places like Qatar or is expensive.
their judgment, Codrington says. buffer, allowing the US to act as a cause the remainder of the US gas Algeria or Indonesia so they All of these potentially new
We are trying to forecast where true swing producer within the industry is also open to invest- have a lot of flexibility in access- schemes will face stiff
Asian and European LNG demand market. ment, Codrington says. ing different parts of the value competition from existing
is going to be five years from now Eisbrenner says NextDecade is If they choose to do so they can chain and hedging their risks. projects that are already trying
to grab larger market share.
Projects like Sabine Pass and
peNdiNG appLicaTioNs beFore Us FederaL eNerGy reGULaTory coMMissioN Cameron LNG already have
plans in the works to add
project Location company capacity incremental trains and such
Jordan Cove LNG Coos Bay, Oregon Jordan Cove Energy Project 900 MMcfd developments have the
Oregon LNG Astoria, Oregon Leucadia National 1.25 Bcfd advantage of having financially
Elba Island Elba Island, Georgia Southern LNG Company 350 MMcfd strong partners and
Magnolia LNG Lake Charles, Louisiana Liquefied Natural Gas Ltd 1.07 Bcfd construction contractors in
Golden Pass Sabine Pass, Texas ExxonMobil 2.1 Bcfd place.
Gulf LNG Pascagoula, Massachusetts Kinder Morgan 1.5 Bcfd Its either high-volume
Freeport LNG (expansion) Freeport, Texas Freeport LNG Development 340 MMcfd low-cost incumbents or new
Calcasieu Pass Cameron Parish, Louisiana Venture Global 1.41 Bcfd technologies that are pushing a
Cameron LNG (expansion) Hackberry, Louisiana Sempra 1.41 Bcfd low-cost lower-volume
technology where they can add
Total capacity: 10.33 Bcfd
smaller increments,
Codrington says.
24       
focus
 
lng   29January2016

us

Open for business: Cheniere Energys Sabine Pass LNG terminal Photo: BLOOMBERG

Spectre of supply glut looms


Increased Australian output and falling demand in parts of Asia
means new US export projects face near-term problems
CAROLINE EVANS
Houston

W ITHIN weeks, work-


ers at Cheniere En-
ergys Sabine Pass
liquefied natural
gas terminal in Louisiana will be-
gin to load the first US LNG car-
goes flagged for export.
with Sabine Pass, which is expect-
ed to load its first cargo in Febru-
ary or March.
This new capacity coincides
with increased output from Aus-
tralia, a continued slump in oil
prices, and weak demand in
LNG exports and the considerable
difference in market depth be-
tween Europe and Asia, we expect
north-west Europe to receive a
significant share of US LNG ex-
ports, she wrote in a recent
report.
final investment decisions in the
next two or three years for new
capacity in 2020, 2021, that gets
pushed out, Slaughter says.

Long-term hopes However,


Slaughter does foresee players
ed to benefit from increased
trade.
The DOE found that increasing
LNG exports from 12 billion cubic
feet per day to 20 Bcfd by 2040
could add an additional $7 billion
to $20 billion to the US gross do-
However, the US is entering the north-eastern Asia, which puts In addition, Brevik expects to continuing the regulatory process mestic product annually.
international LNG market at a downward pressure on spot pric- see an increase in short-term con- in the low price environment so Increased exports will also have
challenging time. The market es, according to Anne Kat Brevik, tracts as traders ride out the low they can have permits in hand a huge impact in Asia long-term.
faces a looming supply glut, a director of LNG forecasts and re- prices. when prices improve. As US LNG exports rise to 20 Bcfd,
volatile commodity price envi- search at Thomson Reuters. The projected downward trend These are long-term projects, Henry Hub prices are expected to
ronment and flagging Asian Brevik expects Asian LNG spot in spot prices has another conse- he said. increase slightly but Asian LNG
demand. prices to trade between $4.50 per quence delayed construction on You dont judge a projects prof- prices are expected to decline sig-
Some fear a fresh infusion of million British thermal units and new LNG export terminals. itability over one particular mar- nificantly.
supply from the US could upset an $6 million Btu for most of 2016, Brevik expects projects already ket condition. These in 20 to 25 It really confirms that the sup-
already depressed market. On the compared to an average of $7.50 under construction to go through, years will be good projects, I ply curve in the US is quite long
other hand, the US entry offers million Btu in 2015. but those awaiting a final invest- expect. and flat and can produce at eco-
flexibility of supply in terms of ment decision will sit out the Beyond 2025, prices are expect- nomic levels and grow production
both destination and volume. Eye on Europe Although Asia is downturn. ed to stabilise, leading to a robust rates, Slaughter says. Its not like
A recent study commissioned by thought to yield the best return These projects would need an LNG market. youre straining the capacity of
the US Department of Energy (DoE) for US exporters, Brevik expects offtaker on the other side in order Many peoples concerns about the supply system by throwing
forecasts US exports will have a Europe to be an attractive destina- to go ahead with financing this were about disruption of sup- more demand at it inordinately.
marginally positive impact on tion in the near term because it is and construction, Brevik tells ply or disruption of price, and I Brevik said prices could im-
the market long-term. Shorter better able to absorb excess car- Upstream. think that this goes to say that prove long-term, but it depends
term, however, is less rosy. goes without moving the price, Andrew Slaughter, executive even at higher levels, thats an un- largely on oil prices.
The US currently has five LNG and it offers access to liquid trad- director of Deloittes Center for En- likely outcome, Slaughter says. I dont see a sharp revival in
export projects that are expected ing hubs. ergy Solutions, agrees. Instead, both US LNG sellers LNG prices unless oil prices come
to come online by 2020, starting Due to the flexible nature of US Instead of seeing people take and their customers are expect- up, she tells Upstream.
29 January 2016
focus lng 25

canada

Turning fantasy into reality


With more than
20 projects in the
proposal stage,
Canadas young
LNG industry has
hit the ground
running
TONYA ZELINSKY
Calgary

O NCE upon a time, in


boardrooms across
western Canada, execu-
tives used to tell stories
about liquefying natural gas and
exporting it to the Asian Pacific.
Today those same stories are
still being told but billions of dol-
lars in investment is helping
dreams come true.
In the past five years, LNG has
become one of Canadas fastest-
growing industries without any-
thing actually happening. Many
projects have been proposed on
both the countrys west and east
coasts but none have been offi-
cially sanctioned or federally ap-
proved. Proposal: the LNG Canada site model displayed in Kitimat, British Columbia Photo: BLOOMBERG
More than 20 LNG projects are
proposed along British Columbias PrOPOSEd LNG PrOjECTS IN CANAdA
Pacific coast for export to Asian
markets, while another four are NOVA SCOTIA LnG, Haisla First nation) LNG Canada Stewart Energy LNG
proposed in Nova Scotia targeting Location: douglas channel Proponents: Shell canada, Proponents: canada Stewart
markets in India and Europe. Goldboro LNG Kogas, Mitsubishi, Petrochina Energy Group
BC LNG Alliance president Proponent: Pieridae Energy discovery LNG Location: Kitimat Location: near Stewart
David Keane is optimistic that at canada Proponent: Quicksilver
least two the proposed major Location: Guysborough Resources canada NewTimes Energy Triton LNG Limited
projects in British Columbia will county Location: campbell River Proponents: newTimes Partnership
begin exporting by 2020, while Energy Proponents: altaGas and
another three could come online Bear Head LNG douglas Channel Energy Location: Prince Rupert area Idemitsu
between 2021 and 2024. Proponent: LnGL Project Location: TBd
Its not unrealistic to suppose Location: Port Hawkesbury, Proponents: altaGas and Nisgaa LNG
that we could see three large LNG cape Breton Idemitsu Kosan, EdFT Proponents: nisgaa nation WCC LNG
export projects on the west coast, Trading, and Exmar Location: nasoga Gulf Proponents: ExxonMobil
with probably one or two small AC LNG Location: Kitimat (floating canada and Imperial Oil
ones as well. The governments Proponent: H-Energy facility) Orca LNG Location: Tuck Island, Prince
working and were working hard Location: Guysborough Proponents: Orca LnG Rupert
to reduce our costs both our fis- county Grassy Point LNG Location: Prince Rupert
cal competitiveness as well as the Proponents: Woodside Watson Island LNG
cost of construction, says Keane. LNG Nova Scotia Energy Pacific NorthWest LNG Proponents: Watson Island LnG
One of the countrys biggest Proponent: Unknown Location: Grassy Point, north Proponents: Petronas, Japex, Location: Watson Island, near
hurdles is that the LNG industry Location: TBd of Prince Rupert PetroleumBrunei, Indian Oil, Prince Rupert
is still in its infancy, with all the Sinopec, Huadian
proposed projects being built from BrITISH COLUMBIA Kitimat LNG Location: Prince Rupert WesPac LNG
the ground up. Proponents: chevron canada Proponents: WesPac Midstream
In comparison, global competi- Aurora LNG and Woodside Energy Prince rupert LNG Vancouver LLc
tors such as Australia, East Africa Proponent: nexen Energy, Location: Kitimat Proponents: BG Group Location: delta
and the US are working with Inpex, JGc Location: Prince Rupert
brownfield operations. Location: digby Island Kitsault Energy Woodfibre LNG
Proponents: Kitsault Energy Steelhead LNG (Sarita LnG Proponents: Woodfibre LnG
Optimistic But Canada definitely Cedar LNG Location: Kitsault and Malahat LnG) Location: Squamish
has some advantages. Proponent: cedar LnG Proponents: Steelhead LnG
Canada has a tremendous Export development (Golar Location: Vancouver Island
amount going for it an enor-
mous supply base, supportive pro-
vincial and federal government, a Coleman, is optimistic that those project development agreements meantime, what they can do is this year. Every single one of our
highly-educated workforce, and advantages will make a big differ- with the proposed Pacific North- make sure theyve got all of the members is working very hard to
its an OECD country. ence when filling global demand. West LNG and LNG Canada pieces they need to proceed to get to a final investment decision.
Last but not least, because of Not only does western Canada projects. project sanction and move on, he Theyre reducing costs to the
our colder climate we get a rough- boast cooler temperatures ideal for says. extent they possibly can with con-
ly 25% increase in the production LNG but it offers a long-term sup- Long-term planning The big- On the flipside, British Colum- tractors and with the EPC
capacity of our plants for the same ply of gas from major plays such as gest hurdle for proponents right bias projects are still moving (engineering, procurement and
amount of investment in British the Montney tight gas formation now is the rapidly declining price ahead. construction) companies, says
Columbia that you would get in and Duvernay shale. of crude. It has forced many pro- The proponents of the Petro- Keane.
the US Gulf Coast, Australia or the My job has been to focus on ponents to cut capital, potentially nas-led PNW LNG conditionally These are projects that are go-
Middle East, says Keane. this opportunity for British Co- delaying the pace at which LNG sanctioned the C$36 billion ing to be long-term they might
The big buyers are going to be lumbia to make sure were global- projects are sanctioned. (US$25 billion) project in June have an economic life of 25 years
looking to diversify their supply ly competitive, to make sure we In Nova Scotia, there has been a 2015 pending federal approval, but theyll have a physical life
portfolios they arent going to get all of our work as government shift in activity, said natural gas and the C$40 billion Shell well beyond that.
want to buy all their gas from one done legislation, taxation, and engineering specialist for the Canada-led LNG Canada is wait- As long as the market and sup-
particular country. those things we are globally com- provinces Department of Energy, ing on its federal environmental ply is there, theres no reason why
British Columbias Minister of petitive on, says Keane. Bill OHalloran. Many are waiting approval before a final invest- these plants wont continue to op-
Natural Gas Development, Rich To date, the province has signed for prices to rebound. In the ment decision is made sometime erate.
26       
focus
 
LNG   29January2016

australia
Bad time
for surge
in supply
The much-anticipated flood of
new Australian LNG supply is
under way thanks to three
recent project start-ups, but the
timing could not have been
worse for the producers, writes
Russell Searancke.
The LNG market is widely held
to be over-supplied due to lower
demand in Asia, which is
Australias primary customer.
In addition, the price of LNG is
linked to the price of oil, so the
producers are earning
substantially less revenue than
planned. LNG spot prices have
also hit a low level.
To illustrate the LNG price
devaluation, Woodside
Petroleum earned US$3 billion in
LNG revenue in 2015 compared to
US$4.5 billion in 2014, according
to its latest quarterly results.
Three projects have started
exporting cargoes in the past
year.
BGs Queensland Curtis LNG
project has started exporting
Big hitter: Chevrons Gorgon project will supply 15.6 million tonnes per annum Photo: CHEVrON from two trains, Santos
Gladstone LNG has started
exports from the first of two

Future projects hit the


trains, and ConocoPhillips
Australia Pacific LNG has started
exports from one of two trains.
Two more trains are due on
line this year from Queensland

wall of low LNG prices


and, at full capacity, the three
projects will have combined
capacity of more than 25 million
tonnes per annum of LNG, says
the government.
The LNG is currently being
absorbed by buyers, according
There are nine trains and one FLNG vessel in the to market observers, although
prices are not known.
works but the outlook beyond these is unclear There is some concern about
Sinopecs ability to handle its 7.6
RusseLL seaRaNCke million tpa of offtake from
Wellington Australia Pacific LNG, given its
lack of import capacity in China.

A
The challenge for all the LNG
ustralia has nine liq- pensive place on earth to build an opment, with one market-watcher and Pluto had been seen as ration- producers was highlighted by
uefied natural gas trains lNG project, the economics of lNG labelling it dead in the water. Or al next investments for australian BG when it said last October
and one giant floating in australia have been further im- should that be dead under the lNG. ConocoPhillips has for years that it had already delivered
lNG vessel at various perilled by the low lNG price. water? expressed its eagerness to build a QCLNG cargos to 10 different
stages of construction that, once Watchers say that, even though as part of a retention lease re- second train at Darwin, as has countries around the world.
on line, will cement its position as australia has several major green- newal last November, the operator Woodside at Pluto. So its a challenging
a global lNG powerhouse, but it is field lNG developments in the de- and its joint venture partner BHP Finding the offshore feedstock environment, but its an
difficult to know when the next sign and planning stages, it will be Billiton pledged to the australian resource has been the main chal- environment in which were
greenfield or brownfield lNG surprising if any make meaningful government to spend a$250 mil- lenge for both companies, and working hard to maintain our
project will occur. progress this year due to the com- lion ($174 million) in the next five they have invested heavily in ex- competitive advantage, says BG.
Bechtel is building one train bined effects of the low price, over- years on moving scarborough to- ploration and appraisal drilling The flood of new Australian
each for the santos-led Gladstone supply and cost challenges. ward a final investment decision. for reserves. LNG by no means ends there.
lNG project and ConocoPhillips there is also no optimism about PttEP applied the brakes at its ConocoPhillips has had more Four more groundbreaking
australia Pacific lNG (aPlNG), brownfield expansions at the Dar- Cash-Maple development a couple success than Woodside by finding projects are due on stream by
and two for Chevrons Wheatstone win lNG and Pluto lNG locations. of years ago, and says it is con- the Greater Poseidon and Caldita- 2018 the 15.6 million tpa
scheme, while the Kellogg Joint tinuing to work through concept Barossa resources. Gorgon scheme, the 8.9 million
Venture Group is building three Greenfield projects the pro- selection, with all commerciali- However, Poseidon is an enor- tpa Wheatstone project, the 3.6
trains for Chevrons Gorgon posed greenfield projects are the sation options still under consid- mous distance from Darwin, even million tpa project and the 8.9
project, the JKC joint venture is Woodside-led Browse scheme, the eration, including FlNG and farther than the ichthys fields, million tpa Ichthys scheme.
building two for inpexs ichthys, ExxonMobil-led scarborough re- pipeline options. presenting economic challenges. each project has long-term
and technip and samsung Heavy source, PttEPs Cash-Maple project a company spokesman says Pt- Caldita-Barossa is much closer, contracts with LNG buyers, but
industries are working on the and GDF suezs (now Engie) Bona- tEP is focussed on concluding about 270 kilometres from Dar- the enormous profitability that
Prelude FlNG vessel for shell. parte development, all of which this work prior to the retention win, but the gas has a high carbon was expected two years ago will
Gorgon will supply 15.6 million were linked to FlNG concepts. lease renewal in 2016. dioxide content of between 12% be seriously undermined as long
tonnes per annum, Wheatstone regarding Browse, Woodside the Bonaparte project has gone and 19%, making it costly to de- as the current market
8.9 million tpa, ichthys 8.9 mil- says in a January 2016 update that into hibernation since Engie sur- velop. conditions are in place.
lion tpa and Prelude 3.6 million work continues on a range of ac- rendered on the FlNG concept it is understood ConocoPhillips
tpa, while the new trains at Glad- tivities related to the commer- the capital costs of FlNG were current thinking is to use either
stone and aPlNG will add 3.9 mil- cialisation, timing and sequenc- considered too high and the re- Poseidon or Caldita-Barossa as Cost over-
lion tpa and 4.5 million tpa, re- ing of FlNG development required serves not large enough. backfill for its existing lNG train
spectively. to support a final investment deci- it is understood that alternative in Darwin. runs and
By 2019 to 2020 there will be a sion in the second half of 2016. concepts are being studied, in- the expansion of the Pluto plant
projected combined lNG export However, the majority of mar- cluding a near-shore lNG solution, also hinges on finding gas that schedule
volume of just over 76 million tpa,
according to the australian gas
ket watchers do not believe Wood-
side and its joint venture partners
third-party supplies, or the do-
mestic gas market in australia.
can be developed at a reasonable
cost, which Woodside has failed to
delays have
industry. will sanction Browse this year Engie and co-owner santos are do so far. characterised
However, cost overruns and given all the commercial chal- said to have turned their focus Woodside has other lNG
schedule delays have character- lenges. elsewhere in their portfolios. projects to pursue in its portfolio, the Australian
ised the australian lNG boom.
already defined as the most ex-
there is even less optimism for
ExxonMobils scarborough devel-
Prior to the lNG price crash,
brownfield expansions at Darwin
and is exploring in other coun-
tries.
LNG boom.
29 January 2016
focus lng 27

russia

Novatek has
Upbeat: Novatek
chief executive
Leonid Mikhelson
Photo: BLOOMBErG

Yamal LNG
on track for
start-up
Russian gas independent reports that
LNG project in Siberia is on track with
$12.6 billion in financing so far and
construction of the first train at 56%

VLADIMIR AFANASIEV
Moscow

N ovatek chairman Leo-


nid Mikhelson has giv-
en Russian President
vladimir Putin an opti-
mistic update on the Yamal lique-
fied natural gas project headed up
by his company, the countrys
the larger part of the 730 mil-
lion ($800 million) loan that Silk
Road extended to Novatek for a
period of 15 years to finance Yamal
LNG.
Following completion of the
deal, Novatek will hold a 50.1%
berths are operating year-round
and accepting deliveries, despite
the difficult ice conditions that
usually last in the area for half a
year or more, while a dedicated
airport has already transferred
about 130,000 passengers since
largest independent gas producer. stake in Yamal LNG, which is being opened in February 2015.
at a meeting in Moscow last currently aiming to produce first the construction of the founda-
week after international oil prices LNG by the end of 2017, despite the tion in the southern part of
dropped to $30 per barrel, Mikhel- worsening energy price environ- Sabetta for the future LNG loading
son told Putin that Yamal LNG, on ment. jetties is under way, he added,
the remote Yamal Peninsula in However, in his meeting with with Russian contractor tekhno-
West Siberia, has been success- Putin, Mikhelson opted out of promexport working on the
fully financed by its shareholders providing an update on the com- power plant for the project.
which have now invested about panys lengthy talks with Chinese Mikhelson added that the engi-
$12.6 billion. banks and asian and european neering, procurement and con-
according to Mikhelson, minor- export credit agencies over struction contract for the plants Delivering innovative solutions through
ity shareholders in the project arranging project finance loans of first train has passed the 56% com-
China National Petroleum Corpo-
ration and Frances total, each
up to $12 billion to Yamal LNG.
these loans are essential for
pletion mark, against 44% report-
ed at the end of September last
leading-edge expertise globally
holding 20% stakes paid $5 bil- Novatek to be able to cover esti- year. We deal with all aspects and phases of Our involvement at the earliest possible
lion and $3.7 billion for Yamal LNG, mated investments of $27 billion liquefied natural gas (LNG) and floating phase of major projects liaising with
respectively. in the first train of the LNG plant Ice-class carrier earlier in Jan- liquefied natural gas (FLNG) developments. potential stakeholders including
in the port of Sabetta and the uary, South koreas Daewoo Ship- Our global LNG capabilities and governments, developers, lenders and
Excess oil revenues the Rus- South tambeyskoye gas field. building & Marine engineering experience, when combined with in-house major gas field owners means we often
ports, shipping, power, environmental and influence investment decisions.
sian government provided $2.3 over the past year, Mikhelson floated an arc 7 ice-class LNG car-
project management offerings, puts Mott Following project sanction we can design
billion of financing to the project has reiterated deadlines at the end rier for the Yamal LNG project, and engineer all aspects of LNG and FLNG
MacDonald in a unique position.
by purchasing Novateks bonds in of June and later the end of classed for breaking through two developments.
two instalments last year, with December for binding agreements metres of ice. Our ports and coastal experts have
extensive experience in the planning,
money coming from the National on Chinese financing to be signed. the SCF Yamal was launched at design, procurement and construction
Welfare Fund created by Russia in Because of US and european Daewoos okpo shipyard in Geoje supervision of marine facilities associated
2008 to accumulate excess oil rev- sanctions against Russia and and is the first of 15 LNG new- with LNG import and export terminals.
enues. Novatek, introduced in 2014 in builds contracted to Daewoo to
Mikhelson added that further response to the annexation of the serve Yamal LNG.
financing for Yamal LNG is expect- Crimean Peninsula from Ukraine, Russias Sovcomflot, Japans
ed within the next few weeks the company cannot raise alterna- oSk Lines, Greeces Dynagas and
after the ratification of amend- tive long-term financing from Bermuda-registered teekay will
PIPELINES | ONSHORE AND OFFSHORE FACILITIES | REFINERY SERVICES
ments to an agreement between western banks. operate one, three, five and six
China and Russia in the Duma, the Dismissing last years concerns vessels, respectively. LNG SERVICES | TERMINALS AND STORAGE | ENHANCED OIL RECOVERY
lower house of parliament. about a possible delay to the all remaining vessels are sched-
the amendments are required project because of slow delivery of uled for delivery over the next
in order for Novateks deal with modules for the LNG plant four years at a total estimated cost
Chinas state-run Silk Road Fund from China, Mikhelson told Putin of about $5 billion.
to sell its 9.9% shareholding in that Yamal LNG will take delivery the three-train LNG plant is ex- oilandgas@mottmac.com
Yamal LNG to become binding. of 72 modules via Sabetta this pected to produce 16.5 million www.mottmac.com/oilandgas
earlier in January, Novatek year. tonnes per annum of LNG once it
revealed it had already received Mikhelson said the ports four reaches full capacity.
28      
focus
  
LNG   29January2016

africa

Mozambiques time is now


Final investment decisions from Anadarko and Eni on their
liquefaction projects should herald the arrival of the
country as a global LNG player
IAIN ESAU
London

MOZAMBIQUE has supplanted the US player and Eni, operator of tary Fund forecast that Mozam- years the International Mone- ward, pointing out that ensur-
Nigeria as the go-to place for lique- adjacent Area 4. The Rovuma biques annual LNG output will tary Fund (IMF) expects addi- ing LNG production materialises
fied natural gas export projects in basin was transformed into one of reach 89 million tonnes in 2028, tional capital gain taxes associ- remains important to underpin
Sub-Saharan Africa on the back of the worlds biggest gas plays, comprising more than 50% of the ated with transactions involving Mozambiques long-run debt sus-
huge offshore gas discoveries made which the government now reck- countrys gross domestic product transfers of ownership stakes in tainability.
by Eni and Anadarko Petroleum. ons holds about 200 trillion cubic at that time. large natural resource projects It predicts that, all being well,
Nigeria was the regions origi- feet of resources. Furthermore, the IMF predicts might occur. final investment decisions for
nal liquefaction heartland when that by 2045, total government This statement while applica- Coral FLNG and Afungi onshore
Nigeria LNGs Bonny Island com- Transformation Assuming gas revenues from LNG projects will ble to coal and mineral assets will be taken about mid-2016.
plex in the Delta began producing prices hold up, the two companies have reached about $500 billion. also supports market suggestions Anadarko is in the final stages
in the late 1990s, the first such fa- are closing in on taking final in- The IMF assumes that construc- that Eni may reduce its stake in of EPCC negotiations, says the
cility in sub-Saharan Africa. vestment decisions on two major tion work on Anadarkos initial Area 4 and Anadarko could reduce IMF, based on preliminary agree-
That plant subsequently ex- liquefaction schemes, one onshore two, 5.5 million tonnes per an- or sell its stake in Area 1. ment on how state oil company
panded to six trains but proposals and the other offshore. num onshore trains at Afungi and It is unclear when Anadarko ENH can pay its share of project
for a seventh train have been on Anadarko awarded a joint ven- Enis 3 million tpa Coral floating Petroleum and Eni will make final funds, on the amount of gas
hold for years now due to the ture of CB&I, Chiyoda and Saipem LNG project will start in the sec- investment decisions on their two reserved for domestic use and on
quagmire that is Nigerian politics, a turnkey contract to build its two ond half of this year, with first liquefaction projects in Mozam- the structure of marketing
fiscal issues and militancy in the onshore trains at Afungi in May cargos from both being exported bique. activities.
Delta. last year, since when the trio have in 2021. A unitisation agreement cover-
In the early years of this cen- been treading water. In its latest staff report, the Crucial decisions These have ing Mamba-Prosperidade has also
tury, multiple LNG projects were On Enis Coral South FLNG fund expects these facilities to be been delayed as the two propo- been reached.
touted for the Niger Delta, but the scheme, Upstream understands the precursors to no less than 11 nents have awaited clarity on In neighbouring Tanzania,
likes of Brass and certainly Ola- that a consortium of Technip, JGC additional onshore LNG trains and legislation, completion of nego- groups led by BG and Statoil have
kola have drifted into investment and Samsung Heavy Industries is three more FLNG units, all due on tiations on the terms and condi- plans to construct a three-train
backwaters despite hints of a pos- frontrunner for this order, which line by 2028. tions of their exploration, pro- onshore LNG facility with a to-
sible revival at Brass. is expected to be worth about $5.3 Total investment in Mozam- duction and concession contracts tal capacity of 15 million tpa at
But in 2010, industrys attention billion. biques LNG sector from this year for Areas 1 and 4, plus unitisation Lindi.
had already begun to shift from This project duo is set to herald to 2028 is projected to be about of the Mamba-Prosperidade gas The schedule for this proposed
West Africa to East Africa after the eventual transformation of $110 billion. field which straddles the two plant has fallen behind that of
Anadarko made its ground-break- Mozambique into a global LNG Due to cost-recovery mecha- licences. Mozambique, hampered by elec-
ing Windjammer gas discovery in player on a par with the likes of nisms, LNG revenues will not The IMF says it is crucial that tions, land acquisition and fiscal
Area 1 off northern Mozambique. Qatar and Australia. start accruing to Mozambiques jointly satisfactory agreements issues, capacity constraints in
That huge discovery triggered a In a report published this government until the mid-2020s. are reached soon to ensure that government, and BGs ongoing ac-
multi-year exploration effort by month, the International Mone- However, in the next few LNG investment can move for- quisition by Shell.
29 January 2016
focus LNG 29

New horizon:
Perenco and Ophir go
fishing boats
in the
Mozambican
for FLNG solutions
capital, Two independents are entering the Sub-Saharan Africas liquefied
Maputo natural gas arena in Equatorial Guinea and Cameroon, writes Iain
Esau.
Both Paris-based Perenco and ophir Energy will use novel
floating LNG technology from GolarLNG to tap small gas deposits
that would likely have been otherwise uneconomic.
Perenco will deploy a 1.2 million tonnes per annum unit to tap
less than 1 trillion cubic feet of gas off Cameroon, while ophir aims
to use a 2.2 million tpa unit off Equatorial Guinea and could deploy a
second vessel in the coming years.
Golars technical solution could be an economic game changer for
exploiting small fields, particularly in benign environments such
as the Gulf of Guinea.
Also in Cameroon, privately-owned NewAge is assessing the
possibility of using a barge-based LNG solution on its Etinde acreage
if it can establish sufficient resource base.
Engie formerly GDF Suez is after many years still studying
the possibility of constructing an onshore train near Kribi.
Meanwhile, in Congo-Brazzaville, Eni appears to be evaluating a
barge-based liquefaction plant to exploit a few trillion cubic feet of
shallow water gas resources in Marine XII.
The Italian major is cagey about discussing this project but its
partner, NewAge, is less reticent, with a recent presentation
highlighting a simple FLNG solution in graphic form.
off Mauritania, Dallas-based Kosmos Energy has a 15 Tcf deep-
water discovery on its hands with the most viable development
solution being based on LNG.
However, the find also extends into Senegalese waters and could
be complicated by the need for bi-lateral government
negotiations.
The two countries are also likely to press their cases to host an
onshore LNG plant so perhaps the simplest solution would be an
FLNG vessel.
Plans by Shell for a mini-FLNG vessel in Gabon have amounted to
little, as have proposals for an FLNG unit to tap some deepwater gas
finds off northern Mauritania.
In Angola, a Chevron-led consortium finally brought online a 5.2
million tpa, single-train plant in Soyo in 2013.
Photo: However, smiles soon turned to grimaces when the facility was
REUTERS/ partly destroyed by fire. Major concerns abide, but the facility is
SCANPIX now in the process of being recommissioned.

1618 March, scow

Organised by: Supported by:

LNG projects presented at the Congress:

+44 207 394 30 90 (London), +7 (499) 505 1 505 (scow)


www.lngrussiacongress.com
events@vostockcapital.com

Sponsors:
Special partner:
30       
focus
 
LNG   29January2016

india

Emblem: the Indian national flag near the India Gate in in New Delhi Photo: aFP/SCanPiX

Demand still strong in India


Countrys regasification capacity set to more than
double to 45 million tonnes per annum by 2020
NIShaNt UGal
New Delhi

I ndias appetite for liquefied


natural gas remains robust,
led by the weakening in glo-
bal LnG prices and strong de-
mand from core consumers such as
the power and fertiliser industries.
The nations regasification ca-
times the actual supply, demand
for imported LnG remains fairly
price-sensitive, industry experts
suggest.
Over the past year, spot LnG
prices have more than halved to
between $7 and $8 per million Brit-
er for longer, claims a recent re-
port by broker Kotak institutional
Equities. india and Qatar have re-
cently renegotiated their long-
term LnG contract, which is likely
to improve the fundamentals for
LnG players in india, experts
companies, the Kotak report adds.
The fertiliser sector has been at the
forefront of LnG activity, as the
power sector historically had sel-
dom been able to afford to burn
costly imported LnG that earlier
cost more than $14 per million Btu.
remains flat, while output from
Reliance industries Block KG-d6
continues to decline due to reser-
voir issues. analysts believe that
lower than expected domestic gas
production is likely to further in-
crease indias LnG appetite across
pacity is expected to more than ish thermal units, leading to a fa- believe. However, a recent policy inter- various sectors.
double to at least 45 million tonnes vourable environment for the LnG The countrys largest LnG player, vention led by Prime Minister Higher LnG demand is also ex-
per annum by 2020, as key LnG sector in the country. Petronet, stands to benefit most narendra Modi to revive stranded pected from city gas distribution
players embark on an expansion from the reworked deal, as the gas-based power plants, coupled and other industrial sectors, say
drive, in the hopes of higher de- Spot prices Experts suggest that company has a 7.5 million tpa long- with lower global LnG prices, is sources.
mand for the imported gas. spot LnG prices are expected to term contract with Qatars RasGas likely to increase acceptability of The majority of indias existing
LnG last year accounted for al- soften further, which could help to for a 25-year period. the imported gas for the power sec- and upcoming LnG regasification
most 40% of indias gas supply, ramp up demand for imported gas starting this year, Petronet is tor, experts say. facilities are located off the west
which stood at about 117 million in the country. sourcing Qatari LnG at about $6.5 coast, which has a reasonable pipe-
cubic metres per day. significant additions to global per million Btu, which is half the Government policy initial re- line infrastructure.
However, actual gas demand LnG liquefaction capacity over the price of what it paid last year to ports suggest that the new govern- However, limited pipeline
was much higher at more than 400 next few years are expected to pro- RasGas for gas imports. ment policy is generating an over- connectivity on the east coast
MMcmd, according to the Ministry vide opportunities for favourable The favourable amendment of whelming response from the and other parts of the country
of Petroleum & natural Gas. negotiations as well as renegotia- the long-term contract between power sector, which could further remains one of the biggest
While indias gas demand was tions of long-term contracts, and Petronet LnG and RasGas removes boost LnG demand. challenges for the expansion of the
believed to be more than three will also keep spot LnG prices low- a key overhang on gas sector indias domestic gas production LnG market in india.
29 January 2016
focus LNG 31

china

Effects of the economic


slowdown felt in sector
Demand for LNG
declined in 2015
after several
years of growth,
with industry
officials painting
gloomy picture Together with
for current year Kentz, we offer
Xu Yihe
Singapore
Proven
LNG
C hinas slowdown in eco-
nomic development has
affected demand for liq-
uefied natural gas, which
saw its first decline in 2015 after
years of double-digit growth.
The country last year witnessed
Capabilities

LnG demand drop by almost 2%,


snclavalin.com
according to consultants Wood
Mackenzie.
China had signed contracts
with overseas suppliers to import
38 million tonnes of LnG last year,
but through the first 11 months
the country only imported 17.5
million tonnes, in part due to lack
of demand. The majority of the
imports came from australia and
Qatar.
Chinese industry officials paint
a gloomy demand scenario for
2016, saying the bearish trend will
continue for a few more years
before a new stimulus package
from the government might boost
the economy.
The supply overhang last year
prompted China national Offshore
Oil Corporation (CnOOC) to offer
for sale in the asia market some of
the LnG it had committed to buy
from australia.
To cope with the glut in
supply, sources say that Chinese
national oil companies will this
year likely negotiate with term
suppliers to reduce their import
volumes.

Short-term effect however, in-


dustry officials say the waning
demand for LnG imports is a just
a short-term dip rather than a
long-lasting trend.
in the long run, LnG imports to
China are expected to increase to
60 million tonnes per annum by
2025, according to a government
forecast. Pluto LNG,
China has been trying to pro- image courtesy of Woodside
mote LnG consumption to replace
coal and has built 12 LnG termi-
nals to accommodate importa-
tion. These terminals have
combined regasification capacity
of 40 million tpa.
sources say some of CnOOCs Cargo: and LNG carrier at Chinas second LNG terminal in Fujian province Photo: Fujian
new LnG terminals are being
forced to delay operations as weak flood the market in the year gling with the sale of their term Beijing-based industry officials
demand does not justify the op- ahead. cargoes against cheap spot car- say that smaller plants with a to-
erational start-up now. sources say some term buyers goes. tal gasification capacity gauged at
industry officials in China in China already reviewed their Most of Chinas term cargoes 76 million cubic metres per day
have warned LnG project develop- prices last year in line with the are locked in take-or-pay con- will see their unit utilisation rate
ers to watch their margins for fall of the crude price and to com- tracts priced above $10 per million continue to drop to well below 50%
their contracted term imports pete with the spot cargoes. British thermal units, a sharp in 2016. Last year, these plants
from asia and Europe, as more Chinese LnG project developers contrast to the current spot price supplied only about 9.6 million
and more cheap spot cargoes will led by CnOOC are already strug- of less than $7 per million Btu. tonnes of LnG.
32      
focus
  
LNG   29January2016

south-east asia

Nations face change as domes


Key South-East Asian producers Indonesia, Malaysia and Brunei
work to boost output with multiple projects in the offing
AMAndA BAttErsBy
singapore

SOUTH-East Asia is home to three rying out the $500 million engi- the complex, which comprises the floater will be deployed on the is under construction at Johor.
of the worlds key liquefied natural neering, procurement, construc- Malaysia LNG Satu, Dua and Tiga Kanowit field off Sarawak. Construction of the 5 million tpa
gas producers Indonesia, Ma- tion and commissioning contract facilities. Meanwhile, PFLNG2, which is Johor terminal is expected to be
laysia and Brunei Darussalam. for the 3.6 million tpa Train 9. While Malaysia is boosting its being built at compatriot Sam- completed by April 2018.
In 2014, Malaysia was the A joint venture of Saipem and onshore liquefaction capacity, na- sung Heavy Industries yard, is
worlds number two LNG exporter, Chiyoda performed the front-end tional oil company Petronas also destined for the Rotan field off Exports down Indonesia, once
with exports hitting an all-time engineering and design work for has two landmark domestic float- Sabah. This vessel, with a produc- the worlds number one LNG ex-
high of 25.1 million tonnes per an- the latest train, which will boost ing LNG projects under construc- tion capacity of 1.5 million tpa of porter, has lost some of its lustre
num. Work is already under way output at the liquefaction complex tion. LNG, is expected to be commis- in the global marketplace, with
to add a ninth train at the Petro- to a nameplate capacity of 29.3 PFLNG1, which was constructed sioned in 2018. exports in 2014 down 1 million
nas LNG Complex in Bintulu, million tpa. by Daewoo Shipbuilding & Marine Malaysia is also an importer of tonnes on the previous year.
Sarawak. JGC is also undertaking rejuve- Engineering, is on track for start- LNG via the 3.8 million tpa Melaka The slide was due in part to
Japans JGC Corporation is car- nation work on trains 4, 4 and 6 at up this year. The 1.2 million tpa terminal and another such facility shortages in feedstock gas at the

Low costs boost reputation of Papua New Guinea


THE growth of Papua New Guineas LNG on Train 3 is provisionally planned for while InterOil believes the resource will per million British thermal units, while
industry is set to continue, with at least late 2017, according to co-owner Oil underpin two trains. Papua LNG is a little higher, according to
two new trains planned to be built in the Search. Total will decide this year about train Wood MacKenzie.
coming years, writes Russell Searancke. Project owners are operator dimensions as part of finalising its Both are superior to East Africa and the
An ExxonMobil-led joint venture ExxonMobil on 33.2%, Oil Search on 29%, development concept, and is currently in US Gulf Coast, and a cut above Canada
aspires to building a third train at the national oil company Kumul Petroleum the basis of design phase with front-end and Australia.
renowned PNG LNG project, while the on 16.6%, Santos on 13.5%, JX Nippon Oil engineering and design to follow. Oil Search says there are several
Total-led owners of the proposed Papua & Gas on 4.7%, PNGs Mineral Resources The optimistic attitude about PNGs reasons behind the PNG advantage
LNG project will construct one or two Development Company on 2.8% and potential for continued LNG investment conventional LNG projects with no new
trains. PNGs Petromin on 0.2%. is not limited to the LNG proponents and technology utilised in development,
Currently, there are two trains The Total-led owners of the Papua LNG the government. substantial reserves base with high
producing in PNG both at the PNG LNG project are also absorbed in appraisal PNG Prime Minister Peter ONeill heating value, suitable for Asian
project which in the quarter ending on drilling at the Elk-Antelope field recently pointed to analysis by Facts reticulation networks, high liquids that
31 December 2015 exported 7.6 million complex. Global Energy that said there will be four enhance economics, close proximity to
tonnes per annum, far in excess of the The joint venture comprises Total on or five trains operating in PNG by Asian LNG markets, a stable fiscal regime
nameplate capacity of 6.9 million tpa. 40.1%, InterOil on 36.5%, Oil Search on mid-2022, and potentially six or seven with strong government suppor, and
The size of the third train is still to be 22.8% and minority interests on 0.5%, trains by 2030. aligned joint ventures with highly-
determined, and current activities are although these stakes will dilute after Wood MacKenzie, meanwhile, has respected operators.
focused on drilling one and possibly two the PNG governments 22.5% back-in. identified PNG as having the lowest It is no wonder that PNGs growth
appraisal wells on the Pnyang field, Oil Search says the Elk-Antelope project break-even costs in the region. potential as an LNG destination has
which will be the feedstock source for resource is large enough to support at The third train at PNG LNG has an made both Oil Search and InterOil
train three. A final investment decision least one train of 5 million tpa capacity, estimated break-even price of about $7.50 prospective takeover targets.
29 January 2016
focus LNG 33

On track:
Japan turning to nuclear power
PFLNG1, seen
here under
construction
and renewables to reduce need
last year, is JAPAN is still the worlds largest it purchases under long-term
nearing importer of liquefied natural gas contracts, which currently
start-up although the nations imports largest lNg account for about 80% of its
are expected to decrease by 6.4%
year-on-year in the 2016-2017 importer imports.
More than 10 million tpa of
fiscal year as more nuclear the joint ventures LNG
reactors are brought back into Jera Company eyes end volumes are on long-term
operation, writes Amanda contracts that are due to expire
Battersby. to long-term contracts around 2020 and these will not
Japans Institute of Energy necessarily be renewed,
Economics reckons that LNG they secure LNG in future according to president Yuji
imports in the current financial against the backdrop of Asian Kakimi.
year, which ends on 31 March, spot prices falling by more than Looking ahead, Jera will only
will already be more than 4% 50% in the past two years. contract sufficient LNG on
down on last years levels. Japans Jera Company is set to long-term contracts to cover its
The nation is also increasing this year become the worlds minimum requirements based
its use of other renewable largest buyer of LNG, overtaking on expected scenarios of Japan
energy sources such as solar and South Koreas Kogas. restarting more nuclear
hydropower for power Jera, the 50:50 joint venture capability and increasing its use
generation that will contribute between Tokyo Electric of renewable energy.
to the falling demand for Power Company and Chubu Last year, Jera signed
imported LNG. Electric Power Company memoranda of understanding
Japans LNG demand is formed last year, agreed in with Singapores Pavilion Gas
forecast to be 77 million tonnes December to bring under one and the Electricity Generating
in 2020, down from the record umbrella their existing LNG Authority of Thailand, under
86 million tonnes of 2014, contracts, which account for which the companies will look
according to Platts analytical almost a combined 40 million for collaboration opportunities
unit, Eclipse Energy. tonnes. on LNG operations, including
Japanese customers are also However, Jera plans to cut the possible joint procurement
reviewing the way in which back on the amount of LNG that of LNG.

Photo:
PETRONAS

stic use rises


COMPLETE SOLUTIONS
THROUGHOUT THE
Bontang LNG plant, while more have agreed to commit more of ENTIRE LNG LIFE CYCLE
gas volumes are now being com- the proposed future trains pro-
mitted to the domestic market to duction in the same direction, al- From engineering and construction to
meet growing demand. though the take-up to date has not commissioning, initial operations and ongoing
The former Arun liquefaction been as high as originally expect- maintenance, CB&I helps customers get their gas
project in Nanggroe Aceh Darus- ed.
salam has been converted into a Indonesia is also home to the to market. Our expansive range of technology
land-based LNG receiving and re- 2 million tpa Donggi Senoro and EPC capabilities spans the entire life cycle
gas facility. project onshore Sulawesi, which of a projectdelivering consistent results
Indonesia currently has two last August shipped its first cargo. regardless of the project location.
LNG floating storage and regasifi- In 2014, Brunei also saw its LNG
cation units and at least two more exports dip, down by 800,000
are planned by 2019. tonnes to 6.2 million tonnes on With recent awards and on-going projects
Indonesian upstream regulator the back of lower contracted vol- in the U.S. and around the world, CB&I
SKK Migas has earmarked 39% of umes, according to the Interna- continues to build on its legacy of leadership
this years gas production for ex- tional Gas Union. in the LNG industry. Contact CB&I to learn
port, with the lions share intend- The country has been hit by a how our complete solutions can benefit your
ed for domestic use. lack of recent exploration success
The trend for domestic absorp- that translates into insufficient next LNG project.
tion is increasing. However, not new gas reserves to currently un-
all gas that has been produced is derpin a new train at the Brunei ONSHORE BASELOAD LIQUEFACTION
absorbed. Our LNG absorption is LNG (BLNG) facility, which has ca- OFFSHORE LIQUEFACTION
only 4%, partly because domestic pacity of more than 7.2 million tpa ONSHORE REGASIFICATION
infrastructure cannot support de- from its existing five trains.
liveries, says SKK Migas chief However, the project has em- ONSHORE PEAK SHAVING
Amien Sunaryadi. barked on a major rejuvenation LNG STORAGE
Photo Courtesy of Freeport LNG Development, L.P.

investment that is intended to


Expansion BP has deferred to un- sustain reliable LNG production
til at least this year the final in- beyond 2033.
vestment decision on its proposed BLNG is also carrying out an en-
multi-billion dollar expansion of ergy efficiency programme, in-
the Tangguh liquefaction project cluding phased co-generation
in West Papua, Indonesia. projects, that is due to run 2015 MEDAL RECIPIENT
This expansion includes adding through 2016 and will free up
a third 3.8 million tpa train that
would boost capacity to 11.4 mil-
300,000 tpa of LNG and reduce car-
bon dioxide emissions by 1.3 mil-
A World of Solutions
lion tpa. lion tpa. Visit www.CBI.com
Some of the Tangguh volumes BLNG is a joint venture between 13M012016H
are already committed to the do- the government of Brunei, Shell
mestic market and the partners and Mitsubishi.
34       
focus
 
LNG   29January2016

Egypt in middle east & north africa

play with
Zohr find
a yEaR ago there was a deep sense
of despair in Egypt about finding
enough gas supplies to meet
increasing domestic energy needs
at a time when international oil
companies baulked at investment
in a country grappling with finan-
cial problems, writes Nassir
Shirkhani.
Then in august, italys Eni
announced the discovery of the
giant deep-water Zohr field in the
Mediterranean Sea.
Zohr, with recoverable reserves
of 22 trillion cubic feet, dramati-
cally changed the dynamics of the
gas industry in the eastern Medi-
terranean, opening the way to gas
imports for resale from neigh-
bouring israel and Cyprus and
acting as a catalyst for renewed
exploration efforts by internation-
al oil companies.
Eni is now fast-tracking the
development of Zohr, which is
expected to supply 2.7 billion
cubic feet per day of gas in 2019.
Other deep-water develop-
ments, led by BP, are scheduled to
add a further 1.2 Bcfd before the
end of the decade, thus enabling
Egypt to stop imports of liquefied
natural gas.
The Zohr discovery has prompt-
ed both regional governments and
private companies in the eastern
Mediterranean to turn their focus
to Lng plants in Egypt, which Leading light: LNG vessels at Ras Laffan port in Qatar Photo: QatarGas
were forced to close following the
2011 revolution as the government

Qatar determined to
diverted supplies to the domestic
market.
The Bg group-led idku Lng
facilities, and the Damietta plant
led by Eni and its Spanish partner
Union Fenosa, are naturally ideal

defend its LNG crown


destinations for the significant
gas discoveries made off israel and
Cyprus in recent years.
With international oil compa-
nies unwilling to pour billions of
dollars into building new Lng
facilities at a time of weak gas
prices, the Egyptian plants offer Worlds largest exporter forced to renegotiate long-term
the most cost-effective solution to
monetising the israeli and contracts as it seeks to outmanouevre Australian and US rivals
Cypriot gas, while helping Egypt
to once again earn revenues from NASSiR SHiRkHANi
its idle Lng plants. London
Last month, israel gave the go-

H
ahead to allow gas exports to
Egypt. aving established it- redirect cargoes between conti- price. The new formula between Trafigura to sell to new markets
israel will be able to initially self as the worlds larg- nents to take advantage of better the two companies is... a win-win. like Egypt and Jordan.
sell 5 billion cubic meters (176.5 est liquefied natural prices. Where the previous contract Trading houses allow Qatars
billion cubic feet) of gas to Egypt gas exporter in the For example, Qatar moved fast meant that Petronet had to buy Lng producers Rasgas and Qatar-
over three years from the Tamar past decade, Qatar is now solely to switch tankers from Europe to Lng from Rasgas at $12 to $13 per gas to sell into each others mar-
site off its Mediterranean coast. focused on defending its market asia, where Lng rates jumped in million British thermal units, the kets.
US player noble Energy and its share and securing new clients. 2011 after Japan closed down its new contract means a price of $6 to They also enable Qatar to supply
israeli partner Delek group have an oversupplied market means nuclear power stations following $7 per million Btu, indias Petro- clients in politically sensitive
signed four separate letters of in- it is not prepared to defend its the Fukushima disaster. leum Minister Dharmendra Prad- countries such as Egypt, where
tent to export gas from the Tamar crown by ending a 2005 ban that it has also established a pres- han said at the signing. relations have soured with Qatar
and the Leviathan offshore fields firmly slammed the brakes on any ence in the emerging rival US Petronets revised terms amount in recent years.
to Egypt. further development of the super- market to take advantage of op- to a $1.1 billion transfer of value Qatars spot sales have benefited
They include potential sales to giant north Field. portunities there. from seller to buyer, Credit Suisse from proximity to new markets
the Egyptian Lng plants. Qatar is instead being forced to Qatar has a 70% stake in golden estimated in a separate note. such as neighbouring Dubai and
However, the status of gas ex- renegotiate once-lucrative long- Pass Products, a venture with Kuwait.
ports to Egypt is uncertain after term contracts and resort to trad- ExxonMobil that is seeking regu- Hagling for terms Qatars The Qataris are also now poach-
Egypt froze talks on potential ing houses to sell spot cargoes in latory approval to export from main Lng customers, such as Jap- ing regional customers from
deals last month. its quest to fend off australian and Texas. anese and South Korean power rivals through incentives.
Egypt was angered at the award US rivals. The US supermajor is Qatars generation companies, are now This was the case in January
by an international arbitration The tiny state, which produces main partner in the production haggling for better terms follow- with Pakistan, which backed out of
panel of $1.8 billion to the israel 77 million tonnes per annum of and marketing of Lng from the ing Petronets revision. a nearly $1 billion deal with Shell.
Electric Corporation for damages Lng, has a distinctive edge over north Field. With mounting pressure to Pakistan was to buy 60 Lng car-
from the cut-off of Egyptian gas competition because of the inte- Falling gas prices have piled pres- offer better terms to its long-term goes from the supermajor after
supplies following the revolution. grated nature of its gas export sure on Qatar to revise long-term customers, Qatar has moved to Shell submitted the lowest price
at the same time, Cyprus has projects and low production costs. Lng contracts linked to oil prices. compensate for falling revenues in a tender finalised late last year.
just approved the purchase by Bg Control over the upstream Petronet Lng, indias biggest gas by stepping up spot cargoes and Before officially awarding the
of a major stake in noble Energys segment, liquefaction trains, importer, signed a revised contract adding new regional buyers. cargoes, Pakistani officials man-
aphrodite gas discovery off the transportation, ports and import in December with Rasgas to im- in a break from the past, it is aged to clinch a more favourable
islands south coast. terminals, enable Qatar to quickly port gas at a significantly lower now using trading houses such as deal with Qatargas.
47075.22_29LNG_Upstream_Full_Feb.indd 1 22/01/2016 12:25
36      
focus
  
LNG   29January2016

FLNG

Despite price
collapse,
projects
are ready
to roll

Three huge vessels are now under construction in South Korea, while
Coral, Browse, Scarborough and Abadi are waiting in the wings
RuSSell SeARAnCke
Wellington

The large-scale floating liquefied rently under construction in South 2018 at the Rotan field off Sabah. FLNG2 is designed for 1.5 million side have stated their objectives for
natural gas segment has been hit Korea Shells Prelude, Petronas Prelude will be capable of process- tpa. Coral and Browse, but whether
by the collapse in the LNG price FLNG1 and Petronas FLNG2. ing 3.6 million tonnes per annum The next crop of large-scale they meet those goals remains to
and market over-supply but, once Prelude should be operational in of LNG, 1.3 million tpa of conden- projects are enis Coral FLNG in be seen.
conditions improve, there are a Australia in 2017, Petronas FLNG1 sate and 400,000 tpa of liquefied Mozambique, Woodsides Browse eni had targeted a final invest-
number of new projects ready to is on schedule for start up this year petroleum gas. in Australia, exxonMobils Scar- ment decision for Coral last year,
proceed. at the Kanowit field off Bintulu, Petronas FLNG1 will have LNG borough in Australia and Inpexs and production start-up at the end
Three large FLNG vessels are cur- while Petronas FLNG2 is aiming for capacity of 1.2 million tpa, while Abadi in Indonesia. eni and Wood- of 2019. however, the Italian major

Operators eyeing smaller-scale developments


AS large floating liquefied natural gas de- flaring. Oslo-based Golar last year secured the middle of this year. At full production, ment decision later this year. The Nor-
velopments in Australia and South-east two contracts for its GoFLNG concept, in Gandria will have a capacity of 2.2 million wegian company has also teamed up with
Asia start to take shape, operators and tech- Cameroon and equatorial Guinea, and is tpa of LNG. Keppel Shipyard in Singapore Bechtel for pre-FeeD work for operator
nology suppliers are also looking at smaller- chasing a project for a third FLNG conver- will carry out the conversion of all three of Steelhead LNG at the Canadian Malahat
scale FLNG projects in a wide range of mar- sion with possible delivery in 2018. Golars FLNG units. project on Vancouver Island, which would
kets, writes Beate Schjolberg. The Cameroon agreement with state- hoegh LNG has so far focused on North liquefy and export gas from onshore fields
Players such as Golar LNG, excelerate and owned SNh and Perenco, Africas first of its America, where it hopes to land two in British Columbia.
hoegh LNG are all pursuing smaller float- kind, was approved in September and is projects currently under planning. Located on Malahat First Nation land, the
ing LNG projects, and though energy mar- scheduled for start-up in the second quarter Rather than going for production from 6.6 million tpa project has to undergo envi-
ket prices make the outlook uncertain, they of 2017. offshore fields, hoegh LNG is concentrating ronmental assessments and other reviews
are confident that the market for FLNG The Golar hilli FLNG vessel will tap the on barge-based solutions that are moored before a final investment decision can be
projects will grow in the years ahead. near-shore Kribi fields, producing at a rate quayside or close to shore. made, currently planned for mid-2017.
While only a few contracts have yet been of 1.2 million tonnes per annum of LNG for In the US, the Delfin LNG project is on excelerate energy is also actively pursu-
signed, the companies point to more than about eight years. track to become the first FLNG development ing FLNG opportunities with its floating
20 potential projects in West Africa, Latin In equatorial Guinea, Golar LNG last year in the country, located at a deep-water port liquefaction, storage and offloading solu-
America, North America and the eastern signed a preliminary 20-year tolling agree- facility 80 kilometres off Louisiana to tion, named FLSO.
Mediterranean, and to a lesser degree in ment with Ophir energy and GePetrol for liquefy gas from the Delfin Offshore Pipe- The vessel is designed to be used both as
east Africa and Asia. use of the Gandria vessel at the Fortuna line. an offshore production vessel and as an
The prospects comprise both stranded project in the deep-water Block R from the hoegh LNG signed a front-end-engineer- alternative to onshore facilities, with ca-
gas fields, liquefaction of gas from onshore first half of 2019. ing and design contract with Bechtel for pacity ranging from 1 million to 4 million
fields for export, and projects to reduce gas A final investment decision is planned for Delfin last year, and expects a final invest- tpa of LNG.
29 January 2016
focus LNG 37

Floating LNG offers the greatest


Leviathan: Shells Prelude
should be operational in
2017
opportunities to the industry
Photo: SHELL
Floating lng is seen as one of delivery. this Flng solution,
the greatest opportunities for the which comes with iHi Marines
lng industry going forward, as flexibility and self-supporting prismatic iMo
its can offer decreased costs and type B tank, has a maximum
more flexibility than land-based cost benefits achievable production capacity of
liquefaction, according to DnV 2 million tpa.
gl. Mix of newbuilds and lng is an area of core value for
Samsung Heavy industries and Japans JgC, which dates back to
Daewoo Shipbuilding & Marine conversions the 1960s when it was first in-
Engineering are constructing volved with Brunei lng.
three newbuild Flng units for AMANDA BATTERSBY
JgC has developed sets of pre-
Shell and Petronas, with the FEED documents for a standard-
South Korean yards working in Singapore ised, modular design for small
consortia with engineering and and mid-scale Flng of either
construction players. 1 million tpa or 2 million tpa ca-
However, many floating pro- ing together two lng tankers. pacity.
duction, storage and offloading this twin hull concept allows the vessels are respectively in-
specialists such as BW offshore, adequate space for the process tended to be deployed on fields of
Modec and Bumi armada have facilities with the necessary more than 1 tcf of gas for a 20-
their own Flng solutions, as does space between sections of equip- year term.
Singapores Keppel Shipyard. ment to satisfy safety require- JCg is basing both its Flng so-
Keppel has significant floater ments, while providing suffi- lutions on air Products liquefac-
conversion experience, including cient lng storage capacity, says tion technology.
for lng floating storage and re- SBM on its website. industry-wide standardisation
gasification units, but none of SBM, together with linde En- of equipment and design the
these FPSo contractors has yet gineering, has performed generic design one, build many ap-
landed an Flng job. pre-FEED work for a range of po- proach needs to be a priority in
Bumi armada is focusing its tential reservoir compositions the lng industry, says DnV gl
Flng efforts on units with pro- and environmental conditions, oil & gas global gas segment di-
duction capacities of between which can be optimised for spe- rector Martin layfield.
1 million and 2.5 million tonnes cific fields. More collaboration needs to
per annum. Keppel has its own proprietary come to the fore. this and pricing
the Malaysian contractor is liquefaction technology, PrenEx, is a big challenge, says layfield,
eyeing the full Flng value chain that the company says offers a who notes that liquefaction costs
from pre-front end engineering simple, safe and reliable alter- have trebled since 2000.
and design through to operations native to other nitrogen expan- industry cannot afford to
and maintenance using a lease sion processes and that can be waste the chance that this [oil
and operate business model. used for both Flng and land- price] crisis affords.
Bumi armada has newbuild based facilities. it is the time to address costs,
both spread-moored and turret- the contractors Flng solu- and industry needs to get their
moored and conversion Flng tions have liquefaction capacity arms around this.
concepts on offer, and has also of between 500,000 and 3 million golar lng and Schlumberger
developed a hybrid lng floating tpa, with storage capacity rang- signed a memorandum of under-
storage and regasification barge ing from 125,000 to 250,000 cubic standing in January to co-operate
(FSRB) concept. metres. on the global development of
this FSRB comes with a shorter Keppel is currently carrying stranded, greenfield and brown-
lead time than even an FSRU con- out the worlds first Flng conver- field gas reserves.
version, according to Bumi ar- sion. the Moss-type lng carrier, the duo aims to deliver low-
mada, which notes a single barge Hilli, is being converted into an cost lng production solutions
can accommodate up to 500 mil- Flng unit for golar lng that will that will enable the accelerated
lion cubic feet per day of gas. be deployed off Cameroon. exploitation of proven gas re-
SBM offshore has its sights Keppel has been lined up to serves.
mainly on mid-scale Flng convert two more lng carriers US contractor Schlumberger
projects of between 1.5 million into Flng solutions for golar, for will be providing the capital, up-
and 2 million tpa, which the con- which it is waiting for notice to stream development knowledge
tractor says is suitable for more proceed, and the client has initi- and resources, while golar will
than 700 stranded gas fields with ated talks for a potential fourth contribute its Flng assets and
reserves of between 500 million such unit. technology.
and 2 trillion cubic feet of gas. Japans Modec and compatriot the first project that will avail
has not yet awarded an engineer- project picked up some momen- SBM is looking to convert lng toyo Engineering have developed itself of this set-up, that the pro-
ing procurement and construction tum a couple of years ago, but is carriers into Flng solutions in the liBro Flng concept, based on ponents say will both reduce risk
contract for the Flng vessel, al- now on hold awaiting an improve- much the same way as has been lithium bromide absorption re- and secure financing for gas de-
though it has a preferred supplier ment in economic conditions. achieved for oil FPSos, which frigeration, that is claimed to of- velopments, is expected to be an-
in the Reef consortium comprising the Flng concept for Scarbor- should translate into lower costs fer an economic solution for mon- nounced within two months.
technip, JgC Corporation and ough is colossal one vessel with and a shorter timeframe com- etising remote stranded gas Cowen group analysts see this
Samsung Heavy industries. processing capacity of between pared to newbuilds. reserves. MoU as a vote of confidence for
the Coral Flng vessel is expect- 6 million tpa and 7 million tpa. With such a conversion, the Modec says the shipyard- Flng technology and its com-
ed to have a liquefaction capacity the recent renewal of the Scar- process facilities along with the friendly design of the liBro Flng petitiveness in the current price
of about 2.5 million tpa, and could borough retention lease indicated storage and crew living quarters concept, using a converted stand- environment at a time when the
be as high as 3 million tpa. government acceptance of a final are located on deck. this novel ard bulk carrier rather than a market is losing confidence in
Woodside, meanwhile, is target- investment decision in late 2020. topside layout is achieved by join- purpose-built hull, enables early glng.
ing a final investment decision in inpexs abadi project in indone-
the second half of this year for sia has also been put back while
Browse, but there is a majority the company and joint venture
view in the market that the opera- partner Shell negotiate with the
tor and its joint venture partners indonesian government on most
will not sanction this year, given aspects of the development.
all the commercial challenges. last September, inpex con-
the Browse concept involves firmed its intent to dramatically
three Flng vessels designed to upsize the Flng vessel from 2.5
produce between 3.5 million tpa million tpa to 7.5 million tpa.
and 4 million tpa and based on the a revised plan of development
same design as Shells Prelude ves- was submitted, but inpex has not
sel. provided any project schedule up-
ExxonMobils Scarborough dates.
FLNG FPSO Water Intake Systems Ooading packages
The FLNG concept for Scarborough EPC SURF packages
Barduct Buoyancy modules Crossing sleeper
is colossal one vessel with
processing capacity of between 6
million tpa and 7 million tpa.
38       
focus
 
LNG   29January2016

floating storage and regasification

Contracts: the FSRU Independence in Klaipeda, Lithuania Photo: HoegH lng

FSRU market on the upswing


Global fleet of floating storage and regasification units
reaches 23, with another 35 projects in the works
Beate SChjoLBeRG
oslo

T he market for floating


storage and regasification
units has surged in recent
years thanks to rising
supply and falling prices for lique-
fied natural gas at a time when
many countries are looking to add
destination. The lower invest-
ment requirement and higher
flexibility means that more coun-
tries can afford to enter the LNG
market, and most of the existing
and planned FSRUs are located in
countries that have not previous-
tract in sub-Saharan Africa
awarded to Golar LNG in Novem-
ber for a project with West African
Gas in Ghana.
Both Golar and the other major
players expect more African
projects to follow as LNG becomes
Most of the existing vessels have
a regasification capacity of be-
tween 400 million and 800 mil-
lion cubic feet of gas per day, mak-
ing them smaller than the average
onshore facility.
The cost varies from about $80
more natural gas to their energy ly imported LNG. affordable for a larger number of million for a converted LNG tank-
mix. Most of these have no plans to countries. er to around $300 million for a
From being a non-existent mar- build traditional onshore termi- LNG is available in large vol- purpose-made newbuild, well be-
ket less than a decade ago, the glo- nals and will rely solely on FSRUs umes and at very competitive low the $1 billion-plus investment
bal fleet of FSRUs counted 23 ves- for import, according to figures price levels, and will drive up de- for an onshore terminal.
sels last year, including awarded from the International Gas Union. mand for LNG and for import ter- The current fleet is a mix of
contracts. minals. Today this picture is even custom-built FSRUs and converted
Another 35 projects are in the Distribution The use is also dif- stronger than it has been this far, LNG carriers. Converted units can
pipeline, mainly in Latin Ameri- ferent rather than sending gas Volumes: hoegh LNG chief Hoegh LNG chief executive be delivered faster and may trade
ca, the Middle East and Asia, ac- into a national pipeline distribu- executive Sveinung Stohle Sveinung Stohle said at the com- as LNG carriers in between jobs,
cording to major player Hoegh tion system, many of the new Photo: sigbjorn sandsmark panys most recent quarterly pres- making them flexible for shorter-
LNG. FSRU import projects are ear- entation. term contracts, but they must
FSRUs differ from traditional marked for electricity production year contracts with a combined head to yards for periodic surveys
onshore import facilities in a or industrial use near the import capacity of 1.1 billion cubic feet of Providers US-based Excelerate every five years.
number of ways they are small- site. gas per day, or 9 million tonnes Energy and Norwegian players Newbuild FSRU units have a
er, faster and easier to install, and Some units are also hired on per annum of LNG, boosting its Hoegh LNG and Golar LNG are the longer construction time, but are
can be removed again at any shorter contracts to meet season- gas supply for power production main providers of FSRU units glo- generally able to stay docked for
time. al or temporary gas-supply defi- amid a national energy shortage. bally, with between seven and the duration of their contract,
The importer pays the FSRU pro- cits. The country has decided to take nine units each. whether it is for five, 10 or 20
vider on a time-charter basis, thus A case in point is Egypt, where on a third FSRU unit within the BW Gas and Exmar also partici- years.
reducing its own investments to domestic distributor Egas over the coming year. pate with two and one unit, re- Regardless of vessel type, the
suitable port facilities and pipe- course of six months last year in- The African market is also com- spectively, including uncommit- lead times remain shorter than for
lines to bring the gas on to its final stalled two FSRU vessels on five- ing along, with the first FSRU con- ted vessels under construction. the larger onshore terminals.

You might also like