Professional Documents
Culture Documents
REVISION HISTORY
Rev. CONTRACTOR: MAK Status of
No. Date Revision History ENGINEER Approval
Prepared Reviewed Approved
First Submission
following award of
0 2016 Contract
CONTENTS
1.0 Scope
2.0 Purpose
3.0 Responsibilities
4.0 References
5.0 Safety
6.0 Procedures
1.1 This method of statement covers the placing of bituminous pavement areas
shown on approved drawings.
2.0 Purpose
2.1 This method statement defines the responsibilities and describes the activities
and procedures to be implemented for the placing of bituminous pavement for
the Construction, Completion and Maintenance of Roads, Bridges, Storm
Water Drainage, Sewers and Other Services for Roads Connecting Sabah al
Ahmad and Khiran New Towns -RA239 Project to comply with the contract
drawings and specification.
3.0 Responsibilities
3.1 The Site Engineer (SE) will ensure that the site preparation activities are
conducted according to the approved Method Statement, and HSE plan.
3.1.1 Ensure all necessary approvals and work permits are obtained prior to
start the work.
3.1.2 Convey all technical data to road foreman and to ensure that the
foreman understood the activities to be executed.
3.1.3 Arrange & ensure the required manpower to execute the work.
3.1.4 Ensure safe working procedures are followed in accordance with the
site safety plan.
3.1.5 Prepare the necessary Request for Inspection (RFI's) to arrange the
consultant Engineer for inspections.
3.1.6 Organize the work in a safe manner to ensure that safety and protective
equipment are properly utilized.
3.2 The Material Engineer (ME) will ensure that the materials being used are in
accordance with the Project Specifications and approved Material Submittals.
He will be in charged with the field laboratory and will undertake the
necessary tests as required for the project with the assistance from Laboratory
Technicians.
4.0 References
4.1 Specifications:
4.1.1 Project Drawings and Specifications.
4.1.2 MPW General Specifications
4.2 Drawings : Document III Volume 3
4.3 BOQ : Bill No. 4
5.0 Safety
The Site Engineer and Road Foreman, in coordination with the Safety Officer,
shall be ensuring compliance with all safety requirements during the
implementation of this work which shall include, but not limited to the
following:
8.0 Procedures
CONTENTS
2.0 Definitions
3.0 References
4.0 Subcontractors
5.0 Materials
7.0 Safety
9.0 Procedure
10.0 Responsibilities
11.0 Attachments
1. Scope:
1.1 This Method Statement describes the procedures to be followed in the placing of the
following asphalt concrete courses:
Bituminous Base Course
Bituminous Binder Course
Bituminous Surface Course
2. Definitions:
3. Reference
4. Subcontractors:
4.1 None
5. Materials:
5.2 Bitumen
Aggregates, bitumen and mix design will be submitted for approval as per clause 331.21
8. Prior Activities:
8.1 Submit mix design and aggregates for Engineers approval as per clause of the
specifications. The job mix shall be made for the Base, Binder and Surface Courses
respectively.
8.6 Trial Area of each pavement material, sampling the permanent works will be laid to the
extent and at locations to be agreed upon with the Engineer as per clause .
8.8 Batching Plant for asphalt production are located in Amghra and another one will be
erected on Site to ensure the required capacity for the Project. All plants will be
calibrated and checked before being put into operation. Regular checks will be
carried out as per clause .
8.9 Bitumen and aggregates shall not be heated to above 150C and 170C
respectively, and the temperature difference between them at the time of mixing
shall not exceed 15C.
9. Placing procedure:
All activities carried out will comply with the Inspection Test Plan which reflects the testing requirements of
the Contract
a) All base and sub-base courses will be cleaned and prepared by removal of
dust and deleterious materials by air jetting or mechanically sweeping or any
other approved means. The cleaned course will be afterwards lightly made wet
Prior to the application of the prime coat.
Note: Enough time will be allowed for the curing of the prime and tack coats
before laying the binder course or the wearing course.
a) Transportation of asphalt concrete from the mixing plant to the pavers will be
via 30 ton tipper trucks designated for this use only. The trucks vehicles will be
treated by oil or water or any other approved means to facilitate the discharge.
Moreover, they will be specially modified to prevent any spills during the
downloading into the paver.
Note: The number of trucks to be used for hauling the asphalt will be sufficient
to avoid any interruption in the paving operation.
b) The flow of delivery will be uniform to assure the best quality of asphalt
finishing.
c) All mixed material will be delivered to the paver in time to permit completion of
spreading and finishing of the mixture during the day working hours. Should
the bituminous material be placed at night, adequate lighting will be provided
and request for approval will be sent to the Engineer.
a) Base course, binder course and wearing course levels will be determined from
the finished pavement surface as shown on the approved shop drawings and
will be submitted for the Engineers approval.
b) The strip width shall not be less than 3 meters. Paver guideline levels will be
set using steel wires stretched and adequately supported to prevent any
sagging on both sides.
9.4 Placing of bituminous material:
c) The material temperature should be more than 120C and will be checked
directly before its discharge according to clause . of the specifications.
e) The material discharge will take place without delay. Rolling shall commence
immediately after placing of asphalt and will stay as close as possible to the
Paver. However, all loose material shall be removed prior to compaction.
f) The paver shall operate at a speed which will give the best results
coordinating with the rate of delivery of material.
g) Initial rolling shall be carried out with the Steel Roller at speeds slow enough
to avoid displacement of asphalt.
i) Rolling shall be longitudinally, beginning at low side towards the high side of
pavement. Adjacent rolls shall be shorter as progressed and finally semi
diagonal steel rolling is applied.
j) The asphalt shall then be rolled with the 25 Ton tire Rollers and shall stop short
of any cracks that might appear.
k) The high powered 35 Ton Pneumatic Tire Rollers shall then be applied to
achieve the required compaction.
l) Final rolling shall be done by the Steel Roller especially at joints and points of
deficiencies.
m) All Rollers shall be equipped with water reservoirs and scrapers to avoid any
breaking of the asphalt surfaces. The tires of the rollers shall be sprayed with
oil/diesel to prevent any fine particles from asphalt getting stuck to the tires.
a) Horizontal Alignment
15mm from Drawings
Rate of deviation not to exceed 1 in 1000
b) Vertical Alignment
10mm for base course
6mm for binder course
6mm for surface course
c) Layer Thickness
5mm for any individual layer
min(10% of combined thickness; 15mm) for combined thickness
d) Smoothness
3mm for surface course
10mm for binder course
10. Responsibilities:
10.1 The CM will coordinate with SE and ensure that the necessary resources to implement
the approved method statement, Job and Activity Hazard Analysis have been allocated
to the task.
10.2 It is the Site Supervisors duty to organize the work in a safe manner to ensure that
safety and protective equipment are being properly utilized. He must also assure the
AHA & JHA are implemented and the method statement procedure is followed and the
ITP applied.
10.3 It is the workers duty to properly wear the protective equipment provided and obey all
safety rules. They must also perform the work as described in the method statement
procedure.
10.4 The SE will ensure that the site preparation activities are conducted according to the
Approved method statement, JHA, AHA and all in-situ tests as required in the ITP are
implemented.
10.5 The ME will ensure that the materials being used are in accordance with the Project
Specifications, the approved method statement and the ITP.
11. Attachments: