Professional Documents
Culture Documents
CLIENT : TRANSCO
Page 1 of 8
CONTRACT No: N-13251
220 kV OHL MODIFICATION WORK AT SHAMKHA
METHOD STATEMENT FOR RECTIFICATION OF TOWER
PLATFORMS
3.0 Terminology :
Ckt : Circuit
3.1 Danger
3.4 Supervision
The control and direction exercised by a Competent Person who is
present at the point of work at all times during the progress of the work.
Page 2 of 8
CONTRACT No: N-13251
220 kV OHL MODIFICATION WORK AT SHAMKHA
METHOD STATEMENT FOR RECTIFICATION OF TOWER
PLATFORMS
Site Engineer:
For ensuring all the activities are undertaken and constructed as per the
drawings, coordinate for necessary work permits, all approved QC
requirements are met by the construction team and ensure that all necessary
resources are available to meet the schedule targets.
Safety Supervisor:
For ensuring all the activities are undertaken and constructed in a safe
manner as per the TRANSCOs approved Method Statement, Risk
Assessment & HSE Manual.
Site Coordinator
For liaisoning with related authorities for obtaining permission for smooth
functioning of project and facilitate site team.
Page 3 of 8
CONTRACT No: N-13251
220 kV OHL MODIFICATION WORK AT SHAMKHA
METHOD STATEMENT FOR RECTIFICATION OF TOWER
PLATFORMS
7.0 Resources:
7.1 Equipment
Dozer
Vibratory roller
Tipper trailers
4 wheeler &6 wheeler trucks
Mobile water tanker
Shovels
Four wheel pick-up & mini-bus
The required platform dimensions shall be checked from profile drawings and
marked.
Additional gatch material shall be put and entire platform surface shall be levelled
by means of shovel and compacted using vibrating roller. Also, area around pile
cap shall be suitably filled up by gatch material and compacted at defined cut-off
level.
Compaction test shall be done at one place for every tower platform.
The final thickness of platform should measure 0.5 meter as per the approved
profile drawing.
Hazards identified:
For the control measures please refer to the task based risk assessment which
is enclosed in Annexure 1.
Standard Personal Protective Equipment will be worn at all time and will include
the following:
1. Safety Helmet
2. High Visibility Jacket
3. Coveralls
4. Safety shoes
5. Safety goggles when required
6. Safety gloves
7. Dust masks when required
8. Ear plugs when required
All drivers and operators will have UAE valid Driving license.
Page 5 of 8
CONTRACT No: N-13251
220 kV OHL MODIFICATION WORK AT SHAMKHA
METHOD STATEMENT FOR RECTIFICATION OF TOWER
PLATFORMS
Tool Box talks will be conducted daily and will include topics of relevant activity
and about health, environment & safety. Documents shall be maintained and
issues discussed shall be recorded.
During site works, KECs Safety Supervisor shall visit the site regularly.
Page 6 of 8
CONTRACT No: N-13251
220 kV OHL MODIFICATION WORK AT SHAMKHA
METHOD STATEMENT FOR RECTIFICATION OF TOWER
PLATFORMS
Note: - Do not handle the casualty if you are not sure/qualified, to avoid further
damage to the injured personnel.
Page 7 of 8
CONTRACT No: N-13251
220 kV OHL MODIFICATION WORK AT SHAMKHA
METHOD STATEMENT FOR RECTIFICATION OF TOWER
PLATFORMS
On Site Equipment:-
Fire Fighting Equipment
Emergency / First Aid Equipment
Emergency Rescue Kit.
D. Emergency Contact Telephone Numbers:-
RELEVANT AUTHORITY
AMBULANCE 998/999
SURESH 050-6137402
Page 8 of 8
.
ANNEXURE: 1- RISK ASSESSMENT Document No.:
TRANSCO Contract No.: N 13251 N13251/PHSEP
Date:09.05.17
ACTIVITIES : RECTIFICATION OF TOWER PLATFORMS
Page No: 1
SN Source of Hazard / Condition that Consequences/ Risk Risk Recommended Control Measures
Hazard/ Aspect develop the Impact Evaluati Level
Activity Hazard on (Risk accepted by applying control measures)
P S (H/M/L)
1 Construction of Vehicle movement Poor Visibility Asset Damage. All drivers should have a valid U.A.E driving license.
Access Road Bad Road condition Personnel injury / fatality.
C 3 M All passengers on board to fasten the seat belts.
and Platforms Poor Vehicle condition Damage to the vehicle Limit the number of passengers to be limited to number of
Blind spots Rollover serviceable seat belts.
Follow the journey management system.
Always engage 4 wheel Drive.
Maintain the tyre pressure as per the requirement.
Mobile phones not to be used while driving.
Night driving is prohibited.
Speed limit in desert should not exceed 80 km/hr.
Always drive with in the speed limit in desert <80 and on
Black top <120.
Flag poles shall be provided in vehicles
All drivers will have mobile phones.
On the roads crossings banks men on either side of road will
be there.
All vehicles and equipments to be fitted with reverse alarm
Severe Weather Poor visibility Injury Work to be stopped at a wind speed above 15 knots.
condition High speed wind Asset Damage
B 4 M In case of poor visibility / sand storm / rain etc job to be
Heavy rain Dehydration stopped.
High temperature A system of convenient interval of work breaks to be
followed for the comfort of the technicians during peak
summer.
Welfare facilities are to be properly available during all along
the period of performing the job.
Ensure shade for adequate rest.
All necessary refreshments are to be provided at the
location & closely supervised by the JP.
Date:09.05.17
ACTIVITIES : RECTIFICATION OF TOWER PLATFORMS
Page No: 2
SN Source of Hazard / Condition that Consequences/ Risk Risk Recommended Control Measures
Hazard/ Aspect develop the Impact Evaluati Level
Activity Hazard on (Risk accepted by applying control measures)
P S (H/M/L)
Gatch Loading / Unloading Vehicle topple in desert or Traffic rules for Fog /low visibility to be followed.
Transportation Poor condition of gatch road D 2 M Short cut not allowed, only approved crossings to be used.
Lifting equipment Injury or property damage Gatch to be properly covered by appropriate cover/ tarpaulin
(Hiab) while being transported.
Over speeding of ROW procedures /checklists developed and distributed by
Vehicles Transco to be followed while making ROW.
Tyre puncture Identify the route and in case of any O/H line crossing
Exceeding vehicle Transco approval to be taken and safety measures such as
load capacity goal post erection to be done on the crossing points
Filling sand, Gatch Poor condition of Property damage While 1st layer of gatch filling, always maintain safe distance
and Levelling & Vehicles Injury / Fatality
D 3 M for the dump truck from existing flow line.
Compaction Incompetent operators Never start compaction until minimum filling thickness has
Incompetent been met as per the specifications.
supervision Depute banks men.
Underground services Obtain Work Permit prior to work commencement.
Proper supervision of the job by JP
ROW procedures/ checklists developed by Transco to be
followed while making ROW
Sufficient thickness of gatch material, minimum 1m or as per
the specification should be maintained.
Date:09.05.17
ACTIVITIES : RECTIFICATION OF TOWER PLATFORMS
Page No: 3
SN Source of Hazard / Condition that Consequences/ Risk Risk Recommended Control Measures
Hazard/ Aspect develop the Impact Evaluati Level
Activity Hazard on (Risk accepted by applying control measures)
P S (H/M/L)
Crossing the Blind spot Fatality/ Injury and asset Ultraviolet sun glasses are to be used to prevent stress on
existing Unsafe driving Damage C 4 H the eyes due to hot weather
tracks/roads Lack of proper
signboards Safety helmet, coverall and safety shoe are mandatory.
All road crossing point to be properly drawn and letter
submitted for road crossing well in advance.
Temporary diversion to be made appropriate sign board,
amxi cones, flashing lights, flagman with reflective jackets
etc to be positioned on the diversions.
Demobilization Loading of Injury/Fatality M Check the access for low bed trailer.
Equipments. Property damage
B 4 Maintain safe distance from flow lines, Power lines or any
Waste disposal and Health infection other facilities.
Site Clearing Depute banks man during loading of equipment over low
bed.
ROW procedures / checklists developed and distributed by
Transco to be followed while making ROW
Identify the route and in case of any O/H line crossing
Transco approval to be taken and safety measures such as
goal post erection to be done on the crossing points.
Date:09.05.17
ACTIVITIES : RECTIFICATION OF TOWER PLATFORMS
Page No: 4
SN Source of Hazard / Condition that Consequences/ Risk Risk Recommended Control Measures
Hazard/ Aspect develop the Impact Evaluati Level
Activity Hazard on (Risk accepted by applying control measures)
P S (H/M/L)
Working / Risk not Electrical shock Personal injury C 3 M Availability of work procedure / instruction at site. Obtain
Crossing near Properly Explosion Fatality, burns, Equipment / work Permit to work as required and follow instruction.
live overhead
lines. identified property damage. Work area should be demarcated using red and white
Incorrect chains/ tapes.
isolation of Provide proper means of equipment, tools, manpower,
conductors. trained / competent personnel to be assigned for the job.
No proper All hazards warnings/signals should be recognized and
2 PPE being obeyed.
used. It is advisable to place notice or play cards giving details of
No proper emergency resuscitation.
lock out tag Procedures in case of electric shock at those locations
out system. where the risk is greater.
Using Proper communication with concerned parties.
inappropriat
e tools.
A.L.N. ACHARYULU
PROJECT MANAGER
(050 621 3208)
ANIL KURNE
SAFETY MANAGER
(050 6152773)
G. SURESH
SITE SUPERVISOR
(050 6137402)
KOUSIK
SURVEYOR
(055 623 4192)
FOREMAN