Professional Documents
Culture Documents
Date: ________________
1.0 BACKGROUND
Local governments confront rising public expectations regarding the delivery of services.
Despite more than two decades of implementation of Republic Act (RA) No. 7160 (Local
Government Code of 1991), local governments still face various challenges in the
exercise of devolved service delivery functions. Foremost among these is the raising of
sufficient funds for local development.
Cognizant of the need to provide further support to the LGUs to enable them to fully
carry out functions devolved to them while at the same time, building their capacity
towards genuine fiscal autonomy, the National Government has scaled up its efforts to
ensure meaningful devolution by providing a Local Government Support Fund (LGSF)
under the FY 2017 General Appropriations Act, Republic Act No. 10924.
2.0 PURPOSE
This Joint Memorandum Circular is being issued to prescribe the general policies and
procedures in the implementation of the ADM program to ensure that all concerned are
able to abide with the prescribed processes and be accountable for the overall
implementation of the Program.
For purposes of this Guidelines, the following terminologies are used and defined as
follows:
3.1 Duly Accredited Civil Society Organizations (CSOs) Refer to CSOs
validated by the DILG thru the Municipal Local Government Operations Officer
(MLGOO) who have previous experience and participation in local planning.
1
3.2 Good Financial Housekeeping (GFH) It is a component of Seal of Good
Local Governance. It is conferred to local government units that obtained an
unqualified or qualified COA Opinion and have complied with the Full Disclosure
Policy.
3.3 Local Government Support Fund (LGSF) Financial subsidy to LGU for the
implementation of priority programs and projects, as provided in the General
Appropriations Act.
3.4 Local Development Council (LDC) The main advisory arm of the local chief
executive in setting the direction and coordinating development efforts in their
respective territorial jurisdictions.
3.6 Notice of Cash Allocation (NCA) Cash authority issued by the DBM to
central, regional and provincial offices and operating units through the
authorized government servicing banks of the MDS, to cover the cash
requirements of the agencies.
3.10 Public Financial Management (PFM) Deals with all aspects of resource
mobilization and expenditure management in government. It is about the way
government mobilizes resources and manages its expenditures to deliver
essential services to its citizens along the areas which generally improve the
lives of citizens.
4.1 Coverage of the Program. The Program covers 1,373 municipalities in Regions
I, II, III, IV-A, IV-B, V, VI, VII, VIII, IX, X, XI, XII, XIII, NCR, CAR and NIR.
4.2.3 The DILG shall consolidate the list of LGUs that have complied with the
conditions for fund release, as referred to 4.2.1 and 4.2.2 hereof.
4.2.4 The DILG shall endorse to DBM the list of LGUs eligible for fund release,
indicating therein the region to which the LGUs belongs, the projects
being funded and the amount per project.
4.2.5 The DBM shall issue the NCA to the pertinent Authorized Government
Servicing Bank (AGSB) and the Advice of NCA Issued (ANCAI) to the
Bureau of Treasury (BTr).
4.2.6 The BTr shall directly download the funds to the LGUs by issuing an
Authority to Debit Account (ADA) to the LGUs Authorized Government
Servicing Bank (AGSB). The BTr shall inform the beneficiary LGUs
through a Notice of Authority to Debit Account Issued (NADAI), copy
furnished the DBM and DILG Regional Offices (ROs) concerned.
4.2.7 Funds for the Municipalities that fail to comply with governance
conditions as of 31 March 2017 shall be released to and implemented by
the Provincial Governments, provided that the Provincial Government
complied with the aforementioned governance conditions.
4.2.8 DILG shall provide the compliant provinces with the list of municipalities
and their respective projects, including their corresponding allocation.
Accordingly, the DILG shall officially inform the concerned non-compliant
municipalities that their projects will be implemented by the Provincial
Government.
4.2.9 In cases where both Municipal and Provincial Governments fail to comply
with the foregoing Governance Conditions, funds for the LGUs shall no
longer be released. Accordingly, the DILG shall officially inform the
ineligible Municipalities, where the Provincial Government also fails to
3
comply with the Governance Conditions, that the funds for their projects
shall no longer be released.
4.3.1 The LGU shall record the fund as trust liability wherein it maintains a
separate subsidiary ledger for each project to record each transaction.
4.3.2 Within 15 days after transfer of fund to the Trust Account, LGU shall
inform the DILG-RO that the funds has been recorded as Trust Account
using the Pro-forma Letter as shown in Annex A hereof.
4.3.3 The LGU shall exclusively utilize the fund for the implementation of the
project in accordance with the existing government procurement,
budgeting, accounting and auditing rules and regulations.
4.3.4 The LGU may use the difference between the Approved Budget for the
Contract and Contract Award Price to finance additional work due to
Variation Orders for the same project, subject to item IV of Section 4.4.3
of this Guidelines.
4.3.5 Within six (6) months after project completion and turnover, any savings
shall be returned to the BTr. LGU shall provide copy to DILG-RO and
DBM-RO of the said transaction.
4.3.6 The LGU through the municipal accountant shall cause the remittance of
unobligated funds as of December 31, 2018 to the BTr.
The LGU shall be accountable in the overall implementation of the projects. The
LGU shall ensure that the design, plans, specifications and construction of
projects are in accordance with the National Government standards and within
the range of costs and project duration of similar projects being implemented by
a national government agency in the same locality.
Within two (2) months after receipt of the funds, the LGU shall submit to
DILG the following:
4
a. DED/POW have been prepared in accordance with the
national government standards and approved by the LCE.
LGU may request technical assistance in the preparation of
DED/POW from the DILG
5
consider site stability and susceptibility to landslide
or flooding based on the latest vulnerability, risk
assessment and geo-hazard maps of the DENR.
No center shall be located on a no-build zone. The
evacuation centers shall be turned over to the LGU
concerned which shall be responsible for
maintenance and operation of the centers.
h. Funds are available for the maintenance and insurance where
applicable once the project is completed.
ii. All projects must be included in the Annual Procurement Plan of the
LGU.
iv. The DILG and other entities may be invited to observe particularly
during pre-bid conference and/or bid opening.
vi. In the event of a failed bidding, the LGU shall immediately start the re-
bidding process within five (5) working days after the Head of the
Procuring Entity (HOPE) has approved the BAC Resolution declaring a
failure of bidding, in accordance with the timelines set forth in 2016
Revised IRR of R.A. No. 9184. Within the same period, the LGU shall
submit to DILG-RO a revised procurement schedule indicating the
revised target dates for the bidding.
vii. In the event that the LGU will have to resort to negotiated procurement
after two (2) failed biddings, the negotiation shall commence within five
6
(5) days after the HOPE has approved the resolution declaring a failure
of bidding and shall be completed within thirty (30) days. Within the
same period, the LGU shall submit to DILG-RO a revised procurement
schedule indicating the revised target dates.
viii. The LGU shall submit to the Local Auditor a copy of the contract and
other required supporting documents within five (5) days from the
execution of the contract, in accordance with Section 3.1 of COA
Circular No. 2009-001 dated 12 February 2009.
ii. The LGU shall ensure that project construction shall commence
within seven (7) days after the issuance of the Notice to Proceed
(NTP).
iii. The LGU shall ensure that quality control and assurance are
observed, and that quality tests are conducted and construction
logbook is maintained at the project site, and shall be made
available to DILG during visits and/or as may be requested.
iv. Any variation order shall strictly comply with Annex E (Contract
Implementation Guidelines for the Procurement of Infrastructure
Projects) of the 2016 Revised IRR of R.A. No. 9184, and the
provisions of the Contract. Any variation order and contract time
extension shall be approved by the LCE. If the cost of the
variation order exceeds the approved allocation for the project,
the LGU shall provide the required additional funds. The LGU
shall inform the DILG-RO of any approved variation order and
contract time extension, and shall ensure that all related
documents are readily available during monitoring by DILG
personnel and/or as may be requested.
v. In case of delay in the implementation of the project, the LGU
shall perform the following actions:
a. Negative slippage of 5%
7
By Administration submit justification on the
cause of delay and catch-up plan, supported by
adequate resources such as materials,
workforce and equipment
vi. In case the Contractor fails to complete the work within the
specified contract duration and any approved time extension, the
LGU shall impose liquidated damages in accordance with Annex
E of the 2016 Revised IRR of R.A 9184.
i. Within a month after receipt of the fund, the LGU shall install the
Community billboards within the premises of the municipal hall in
accordance with the specifications prescribed in Annex D hereof.
ii. Upon mobilization, the LGU shall ensure the installation of the Project
signboard/s at each project location in accordance with COA Circular
No. 2013-004 dated 30 January 2013 and regular updating thereof.
iii. The LGU shall post in their respective website within thirty (30)
calendars days from entering into Contract with the winning
contractor/bidder, the following information per project:
8
a. Project title and detailed description, including the nature and
location
iv. The LGU shall also post in their respective website within thirty (30)
calendars days from the issuance of certificate of project completion
the following:
Any additional fund requirement that may result due to the change/
modification in the project shall be borne by the LGU.
DILG Monitoring
4.5.1 During project monitoring, the DILG shall observe the LGUs compliance
with the following, among others:
a. Implementation timelines
9
c. Availability of appropriate equipment on site, in accordance
with the Equipment Schedule and manpower
4.5.2 DILG shall conduct site visit and spot check during project
implementation.
The DILG, thru channel, shall immediately advise the LGU of any noted
deviation and non-conformity during implementation and recommend
corrective actions.
4.5.3 A feedback mechanism shall be set up by the DILG to address the issues
and concerns in the implementation of projects.
MDC Monitoring
4.5.5 A third party monitoring scheme shall be established by the DILG. It shall
be conducted in partnership with State Universities and Colleges (SUCs),
and accredited CSOs and Peoples Organizations (POs). It shall be
composed of parties that are external to the implementing units and the
direct beneficiaries of ADM projects.
4.6.1 LGU shall submit status report twice a month to the DILG, through
Municipal Local Government Operations Officer (MLGOO), using the
prescribed template attached as Annex E and in accordance with the
schedule of report submission as Annex F. Copies of the approved
Statement of Work Accomplished (SWA) and Statement of Receipts and
Disbursements (SORD) shall be submitted, if requested.
4.6.2 LGU shall submit to DBM, the Speaker of the House of Representatives,
the President of the Senate of the Philippines, the House Committee of
Appropriation, and the Senate Committee on Finance, either in printed
form or by way of electronic document, quarterly reports on the financial
and physical accomplishment by the project in accordance with Special
Provision No. 2 of the LGSF, FY 2017 GAA, RA No. 10924.
4.6.3 The DILG shall evaluate the submitted reports submitted by the LGU to
check the consistency between the reported and the actual works
10
accomplished. As necessary, the DILG may join inspections with the
LGU to resolve inconsistencies.
4.6.4 The DILG shall post the reports submitted by the LGU to ADM online
portal.
4.6.5 The DILG shall conduct regular site visit and spot check during
construction of the project.
4.6.6 Upon completion of the project, LGU shall submit to the DILG the
following:
The LCE and other local officials concerned shall be responsible and accountable in the
proper disbursement and utilization of the LGSF-ADM for the implementation of eligible
programs and/or projects, including compliance with pertinent provisions of R.A. No.
9184 and its 2016 Revised IRR, as well as budgeting, accounting, and auditing rules
and regulations.
6.0 SANCTIONS. Implementation of projects not in accordance with the provisions of this
Circular may result to:
6.1 LGU disqualification from participating in the succeeding round of ADM Program.
6.2 Appropriate civil, criminal and/or administrative case shall be filed against the
concerned local public official/s for acts or omissions in relation to the
performance of their duties under this Memorandum Circular.
7.0 ISSUES FOR RESOLUTION. Interpretation of the provisions of this Joint Memorandum
Circular, including cases not covered herein, shall be submitted to the DILG for
resolution by the DILG and DBM.
8.0 REPEALING CLAUSE. All provisions of existing issuance that are inconsistent with
this Circular are hereby repealed/ amended accordingly.
9.0 EFFECTIVITY. This Circular shall take effect immediately upon publication in the
Official Gazette or a newspaper of general circulation.
11
12