You are on page 1of 1

TIME SCHEDULE CF3 INNER CHAIN LINK FENCE

May Jun July


ID Task Name Duration start finish
01-May 08-May 16-May 24-May 01-Jun 08-Jun 16-Jun 24-Jun 01-Jul 08-Jul
1 MOBILIZATION 1 week 03-05-17 07-05-17
2 SURVEY WORKS 5 week 08-05-17 15-06-17
3 EXCAVATION POST FOUNATION 5 week 16-05-17 23-06-17
4 POST INSTALLATION 5 week 24-05-17 30-06-17
5 INSTALLATION OF BARBED WIRE 3 week 08-06-17 30-06-17
6 INSTALLATION TENTION WIRE 1 week 24-06-17 30-06-17
7 INSTALLATION OF CHAIN LINK 2 week 25-06-17 07-07-17
8 GATES INSTALLATION 2 week 01-07-17 14-07-17