PROJECT : SETIA SKY VILLE SHOW UNIT AND SALES GALLERY

CADANGAN MENDIRIKAN 1 UNIT RUMAH CONTOH DAN PEJABAT JUALAN SEMENTARA 1 TINGKAT (DI FASA 2 )
UNTUK TEMPOH 3 TAHUN DI ATAS- SEBAHAGIAN LOT 10045 (SEBAHAGIAN LOT LAMA 2708 ), LORONG SLIM,
SEKSYEN 2, BANDAR JELUTONG, DAERAH TIMUR LAUT, PULAU PINANG UNTUK TETUAN KAY PRIDE SDN. BHD.

LIST OF ITEMS FOR CONSIDERATION DURING TENDER STAGE


SUCCESS TENDER CLARIFICATION :

Tender Clarification : Client / Consultant Reply


1 Not included in the additional requirement for certification:-
a. GBI compliance
b. FM compliance
c. EMP compliance
2 Period of honouring certificate - 30 days from valuation date.
3 Claim for material on site - to claim 75% of the material cost without any further retention.
4 SSC do not provide as-built drawings after construction.
5 In the case that no such rates in the contract document for the day work rates, then the contractor must
allow a mark-up of at-least 15% for the day work rate.
6 Prices quoted are exclusive of 6% Goods and Service Tax (GST).
7 Prices quoted for Preliminaries are included of the following:
- Insurance
- Level and Setting Out of the Works
- No Hoarding And Others
- Temporary Water for the Works
- Temporary Electricity Supply
- Security of the Works
- Site Management and Supervision
- Working Hours
- Plant and Equipment
- Cleaning The Works And Handing Over
- Clearing Debris
- Sample and Material Test
- Safety
- Hording By Others
- No CIDB

8 Due to ambiguity on drawing, we quote base on BQ quantity.


9 SSC scope of work inside boundry only.
10 SSC not include the turfing, softscape, hardscape and landscape work.
11 We assume the earth level backfill until soffit of slab, SSC only start the work from soffit of slab.
12 BQ1/8R item 1, Swissma "Mega Rib Profile" change to Astana AS760 Colorbond

13 BQ1/8R item 2, matching flashing 300mm girth" change to 600mm girth

1 of 2
PROJECT : SETIA SKY VILLE SHOW UNIT AND SALES GALLERY

CADANGAN MENDIRIKAN 1 UNIT RUMAH CONTOH DAN PEJABAT JUALAN SEMENTARA 1 TINGKAT (DI FASA 2 )
UNTUK TEMPOH 3 TAHUN DI ATAS- SEBAHAGIAN LOT 10045 (SEBAHAGIAN LOT LAMA 2708 ), LORONG SLIM,
SEKSYEN 2, BANDAR JELUTONG, DAERAH TIMUR LAUT, PULAU PINANG UNTUK TETUAN KAY PRIDE SDN. BHD.

LIST OF ITEMS FOR CONSIDERATION DURING TENDER STAGE


SUCCESS TENDER CLARIFICATION :

Tender Clarification : Client / Consultant Reply


14 BQ1/8R item 4, "change supply install 13.52mm thk tinted green tempered laminated glass with
aluminium sub-frame fixed to structural steel framing (measure separately steel frame) and seal with
X'traseal sealent without capping"

15 BQ1/7 item 1, roof truss purlin thickness from 24mm change to 2.5mm

16 BQ1/9 item 5, the gutter girth is 600mm but in the drawing is 1555mm. We follow BQ (600mm)

17 BQ2/9 Fencing & gates - Drawing did not state the location of fencing wall.
18 Aluminium Door & Window:-
BQ1/12,1/13,1/14 (Door) BQ1/19 & 1/20 (Window) - Aluminium powder coat no warranty.
19 Discrepency between drawing and BQ
Drawing no: KDA-2017-10002-SG-1002 Key Plan - show drywall and solid wall
BQ 1/11 - only solid wall
20 No column & beam details or drawing for steel structure support inside the building.
Please provide details & BQ
21 Roof Truss:
Drawing indicate have fascia board to cover the roof truss but no item in BQ.
Refer to drawing no : KDA-2017-10002-SG-3001 & KDA-2017-10002-SG-3002

2 of 2