Professional Documents
Culture Documents
Basic of Design
The following data are calculated using programme AutoCAD 2000 (with VBA) and AutoCivil 8.5 (module AutoDTM)
Grid spacing used in the calculation - X direction = 5m, Y direction = 5m (Area for each cell = 5x5 = 25m)
Existing Ground Level - highest level = 208m ODL, lowest level = 103m ODL
Proposed Earthwork Level - highest level = 157.5m ODL, lowest level = 104.5mODL
Gradient for Propose Slope- Cut = 1:1.75, Fill = 1:2
A) Earthwork Area
Area with NO Earthwork = 4,075 m2 = 43,862 ft2
Area for FILL = 2,153 m2 = 23,174 ft2
Area for CUT = 47,650 m2 = 512,888 ft2
Total Area = 53,878 m2 = 579,924 ft2
B) Earthwork Volume
Shrinkage Factor = 0.0 % (on FILL earth)
Swelling Factor = 0.0 % (on CUT earth)
Surface Loss = 0.00 m Surface loss at FILL area = 0 m3
Surface loss at CUT area = 0 m3
C) Earthwork Rate
Cut and Fill at same site = 1.50 RM per m3
Access Earthwork = 6.00 RM per m3 (ACCESS CUT)
D) Earthwork COST
Cut and Fill at same site = 2,893 * 1.50 = 4,339.50 RM
Access Earthwork = 981,664 * 6.00 = 5,889,984.00 RM
TOTAL COST = 5,894,323.50 RM
362900848.xls 08/11/2017
Readme - 362900848.xls
For calculation using AutoCivil, the cell (drawn in 3D face) for the above 3 area are in different colors:
- Area with NO earthwork = YELLOW color cell
- Area for FILL = GREEN color cell
- Area with CUT earthwork = RED color cell
To obtain the area, say, for FILL area, peform the following task:
- Select all cells | Click Menu "Tools" | Click "Quick Select"
- In "Quick Select" dialog box | Select Apply to "Current Selection" | Select Object Type "3D face" | Select Properties
"Color" | Select Operater "= Equals" | Select Value "Green" (for FILL area) | Select "Include in new selection set" |
OK
- The number of cell for FILL area (in GREEN color) can be seen in the pull down menu in Properties Dialog Box.
- Area for FILL = The number of cell for FILL area X area of a cell
2) Earthwork Volume
- FILL volume (+ve value)
- CUT volume (-ve value)
2 of 3 08/11/2017
Readme - 362900848.xls
Unless proper compaction can be done during FILLING time, or else the Swelling factor is always bigger than Shrinkage
factor
In most of the case we assume there is no Shringkage factor and Swelling factor, as the differences may be very little (we
have yet to receive any complaint from site on the Earthwork quantity we provide, due to the above 2 factor)
Surface loss - loss of earthwork during earhtwork time is difficult to be estimated. It need the input from the Contractor.
However, we can assume 300mm of surface loss for the top layer of soil, which may consist of plant and material that not
suitable for backfil.
(To be further improved)
It is advisible to liase with the contractor or developer to obtain the exact Rate.
Normally, we can use
Rate of CUT and FILL at same site = RM1.50 per m^3
Rate of access CUT or FILL = RM6.00 per m^3
(To be further improved)
3 of 3 08/11/2017