POINTERS TO REVIEW ON MMUP EXAMINATION Simple Stress S = P / A

where S = unit of stress or strength of material


Statistics P = axial force
Median A = cross sectional area

Engineering Economics Types of Stress


Exact Simple Interest I = Pin Axial Stress
where P = present worth Shearing Stress
i = rate of interest Bearing Stress
n = d/365 for ordinary year Longitudinal Stress
n = d/366 for leap year
Simple Strain
Engineering Mechanics Strain = elongation or change in length / original length
Rectilinear Motion Hooke's Law, s = PL / AE
In Uniform Motion S = Vt where E = modulus of elasticity
where S = is the distance travelled or displacement S = stress
V = is the velocity L = original length
t = is the time
Poisson's Ratio, defined as longitudinal strain over lateral strain
Impulse Momentum Theorem
m (Vf - Vo ) = F (tf - to) Helical Spring
where Vo = original velocity S = 64PR^3n / Gd^4
m = mass where P = applied load
t = time D = mean diameter of the spring helix
Vf = final velocity n = no. of turns
F = average G = modulus of rigidity
d = diameter of spring wire
Fluid Mechanics / Thermodynamics R =radius
Steady Flow System
m1 = m2 Beam Deflection and Moments
A1V1p1 = A2V2p2 for Simply Supported
where A = cross sectional area
V = velocity Roof Trusses / Space Trusses
p = density
PERT CPM
Pipes in Parallel Critical Path
Q = Q1 + Q2 + Q3 Activity / Work / Duration
where: Q = discharge
Definition of Terms
Strength of Materials QCS
Moments and Reactions Poisson's Ratio
For Fixed Support Dispute
For Internal Pin Force Majure
1. If you were awarded a project, you will start work: c. Chemical Engg
a. One week before the approval of the authorities d. Civil Engg
b. After the approval of the authorities
c. One day before the approval of the authorities 13. Gypsum board at residence and industrial building used except
a. Low cost
2. Project Scope Management: b. Ease of installation
a. Define scope and control scope c. Recyclability
b. Executing scope and verify scope
c. Closing process and Create work breakdown structure 14. Stress defined
d. All of the above a. Strain time force
e. Only A & B b. Mass divide volume
c. Pressure time length
3. Scope Management starts with is: d. None of above
a. To identify the client requirements
b. Meet the team 15. What is the last of estimation for project
c. Review strategic plan a. Estimation
b. Assembly schedule
4. Final as built drawings for what purpose
a. To keep record for later maintenance 16. Which one of the following is suitable in engineering manner? Decision shall
b. To give more work to architect be based on reason than situation .
c. To be used for further renovation a. Quantity Thinking.
b. Logical Thinking.
5. Control department work starts c. Interpersonal Skills.
a. From the beginning of the project d. Honesty.
b. During construction
c. After construction 17. What is QSAS? a. Qatar Sustainability Assessment System

6. Project management is ideally suited except 18. An activity in a project network can be represented by which of the following?
a. Accountability a. Arrow
b. Flexibility b. Line
c. Innovation c. Node
d. Speed d. All of the above
e. Repeatability
19. Before starting work at site, the major factor has to be checked is?
7. A critical path is the ----------------------in the project management: a. Access to site (EFE)
a. longest b. Storage of Water, tools & equipments
b. shortest c. Safety
c. none d. Approval from MMUP / Civil / Defence etc.
e. All of the above
8. The forward pass review of the project management will indicate the following:
a. The earliest start of the task 20. Software programming flow
b. The earliest finish of the task a. Plan, Do, Check, Act
c. Critical path (longest path) b. Plan, Do, Act, Check
d. Only A & B c. Plan, Act, Do, Check
e. All of the above
21. First step of Scope planning starts with
9. The back pass review of the project will indicate the following: a. Budgeting
a. The latest start of the task. b. Current earning estimation
b. The earliest finish of the task. c. Objectives and requirements to satisfy customer
c. The critical path.
d. Only A & C 22. In network which point getting more inward flow
e. All of the above. a. Float
b. Critical path
10. Intersecting point for WBS and OBS c. Slack
a. Cost account d. Merging point
b. Intersect matrix
c. Project matrix 23. What is the least level of WBS
d. None of above a. Deliverable
b. Cost
11. For operation and designed auto mobile factory c. Work package
a. Mechanical Engineer d. Lowest sub deliverable
b. Civil Engineer
c. Chemical Engineer 24. The best place to build an exhibition and convention center (near the Airport?
d. Petroleum Engineer Or in satelliteplace far from Urban? Etc)
25. One situation for cancel project.
12. Which of the following discipline is most suitable for doing a natural gas 26.What is the most sensitive period in the project?
pipeline work? 27. In cohesive soils, what is a standard thickness of each layer of backfilling?
a. Mechanical Engg a. 30cm
b. Petroleum Engg 28. Hard water is a type of water that a. produces soap scum
1- What is the Max Dry density (gm/cm3) and optimized water content for the following chart?
2- Calculate the fill/excavation (CY)
3- What is the advantage of using concordant cable in pre-stressed concrete?
4- What are RC columns execution sequences?
5- Calculate the displacement for truss.
6-What is the slope at section ..(.. EI=constant
7-Normal dry-density of RC concrete mix.
8-What is ABET?
9-Why in two way slab, lifting of corner slab happens from ..?
10-What should be issued first when project starts?
11-Activity is followed by two activates what do you call this activity?
12-10#@10/m to change to 12# how much the new space?
13-What is the last of stage of sewage treatment plant?
14-The road cross section, using to calculate
15-The expression is used in roads engineering followed capacity.
16-When design RC section, whether the concrete at tension side will be neglected or considered?
17-Is any relation between rock density and its content (more or less)?
18-At project time frame what is type of cost estimation being used?
19-Air-Entrained Concrete is used to ( Freeze-Thaw Resistance)
20-The station is 00,.000 with elevation of 178.00 what is the filling required
21-What is the nearest to 100 Yard (1:100, 1: 1000, 1:1500)
22-How many compaction tests are required in 1000m2?

1. What does QCS stand for?


2. What is hydration in concrete?
3. Calculate joint deflection when membrane temperature increases.
4. What does RQD 100% mean?
5. Calculate super elevation in roads.
6. Calculate stopping distance when moving @ speed of 60mi./hr (distance in feet)
7. What is the function of admixtures in concrete?
8. Project scope definition.
9. What is the last stage in WTP process?
10. What do status reports represent?
11. What is the use of dummy activity in diagrams?
12. Calculate the horizontal displacement for a truss.
13. What is the effect of air within poured concrete?
14. Definition of grade (highways).
15. What is the weight of concrete?
16. What is the yield strength of steel?
17. What is the strength of concrete?
18. What is the maximum allowable stress redistribution in RCC beams (%)?
19. How many compaction tests are required in 1000m2?

20. Tensile strength in wood (direction wrt grains).


21. Ethical- should report any wrong doing.
22. Calculate deflection @ a joint.
23. What is the slope of the cost time curve?
24. Calculate future investment.
25. Where is maximum bending stress located/ how is it distributed when
placing a load on the beams C-S (linear/ Parabolic/uniform/ @ top & bottom)