EPC OF WELL PAD D FOR SORIK MARAPI GEOTHERMAL PROJECT

RECOVERY SCHEDULE
Remaining Remaining Mar '17 Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Minimum Most Maximum Task
ID Description Duration Start Finish Cost 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24Duration Likely Duration Existence %
000001 EPC OF WELL PAD D FOR SORIK MA... 140 14/03/17 31/07/17 $0
000002 Kick of Meeting 0 14/03/17 $0 14/03/17
000003 Access Road to SM-D Completion 0 *23/07/17 $0 *23/07/17
000004 Completion of Water Drilling system 0 *10/07/17 $0 *10/07/17
000005 SM-D Well Pad Completion 0 *12/07/17 $0 *12/07/17
000006 Estimated Slope Protection Finish 0 *27/07/17 $0 *27/07/17
000007 ACCESS ROAD (from Public Road to ... 60 25/05/17 23/07/17 $0
000008 Earthworks and subgrade preparation 26 25/05/17 19/06/17 $0
000009Hauling Mud 20 25/05/17 *13/06/17 $0
000010Cutting Soil of Access Road 7 13/06/17 *19/06/17 $0
000011 Surfacing: geotex, subbase and base ... 21 19/06/17 09/07/17 $0
000012Fabricate& Installation Geotextile 12 19/06/17 *30/06/17 $0
000013Install& Compaction Masonry Stone 12 21/06/17 *02/07/17 $0
000014Install& Compaction Agregate A 7 03/07/17 *09/07/17 $0
000015 Drainage Works, Lined channel 23 01/07/17 23/07/17 $0
000016General Excavation 10 01/07/17 *10/07/17 $0
000017Material Arrival 3 01/07/17 *03/07/17 $0
000018Instalation 20 04/07/17 *23/07/17 $0
000019 Concrete box/Manhole 48 26/05/17 12/07/17 $0
000020Fabricate Formwork 3 26/05/17 *28/05/17 $0
000021Fabricate Reinforcement Steel Bar (Tula... 7 29/05/17 *04/06/17 $0
000022Fabricate Box Culvert 16 05/06/17 *20/06/17 $0
000023Curing 5 21/06/17 *25/06/17 $0
000024Moving& Laydown Culvert 3 26/06/17 *28/06/17 $0
000025Installation 6 29/06/17 *04/07/17 $0
000026Structural Backfilling Compacted 5 05/07/17 *09/07/17 $0
000027Place Base Course 3 10/07/17 *12/07/17 $0
000028 Installed retaining wall at access road, ... 27 20/06/17 16/07/17 $0
000029General Excavation 5 20/06/17 *24/06/17 $0
000030Fabricate basket for gabion 7 25/06/17 *01/07/17 $0
000031Installation Gabion Wall 15 02/07/17 *16/07/17 $0
000032 SM-D WELL PAD WORKS 65 21/05/17 24/07/17 $0
000033 Earthworks 53 21/05/17 12/07/17 $0
000034Excavation, Backfilling and Disposing (5... 33 21/05/17 *22/06/17 $0
000035Pad Surfacing to include sub-base and ... 14 19/06/17 *02/07/17 $0
000036Geotextile fabric (50.000 m2 remaining) 33 21/05/17 *22/06/17 $0
000037Rig Foot print foundation, 15 meters x 3... 10 03/07/17 *12/07/17 $0
000038 Drainage Works 15 03/07/17 17/07/17 $0
000039Sub surface perforated pipe drain works 15 03/07/17 *17/07/17 $0
000040Open canal lined with stone masonry 15 03/07/17 *17/07/17 $0
000041Open canal lined with reinforced concrete 15 03/07/17 *17/07/17 $0
000042Pipe culverts along potentail slope failure 10 03/07/17 *12/07/17 $0
000043Concrete collection/manhole box 14 03/07/17 *16/07/17 $0
000044Open canal cascading lined with stone ... 14 03/07/17 *16/07/17 $0
000045 Pond Construction 21 23/06/17 13/07/17 $0
000046Capacity= 2,000m3 Drawing No. 21 23/06/17 *13/07/17 $0
000047Capacity= 3,000m3 Drawing No. 21 23/06/17 *13/07/17 $0
000048 Concrete Works 14 05/07/17 18/07/17 $0
000049Well Cellar (3.4mx3.4mx1.2m), 4 cellars... 14 05/07/17 *18/07/17 $0
000050Cutting Storage (10mx10mx1.2), Drawin... 14 05/07/17 *18/07/17 $0
000051Concrete Pad for cementing area. Drawi... 14 05/07/17 *18/07/17 $0
000052Septic Tank: 2 meters x 6 meters x 1.8 d... 14 05/07/17 *18/07/17 $0
000053 Driller Mini-Camp Area 7 18/07/17 24/07/17 $0
000054Concrete block for containers' base: 250... 7 18/07/17 *24/07/17 $0
000055Concrete walkway, 50mm x 900mm wid... 7 18/07/17 *24/07/17 $0
000056 SLOPE PROTECTION WORKS 68 21/05/17 27/07/17 $0
000057 Approval design Slope Protection 10 21/05/17 *30/05/17 $0
000058 Geotextile fabric for slope protection 33 31/05/17 *02/07/17 $0
000059 Gabion walls for slop protection 30 18/06/17 *17/07/17 $0
000060 Shotcrete for slope protection (area Cut) 10 18/07/17 *27/07/17 $0
000061 WATER DRILLING SYSTEM FOR PAD ... 47 25/05/17 10/07/17 $0
000062 Provision for Victaulic Pipe Laying for W... 47 25/05/17 *10/07/17 $0
000063 Pipeline tapping, pressure test and com... 47 25/05/17 *10/07/17 $0
000064 Cleaning Area, Demobilization and As B... 7 25/07/17 *31/07/17 $0
000065 HANDOVER 0 *31/07/17 $0 *31/07/17