Professional Documents
Culture Documents
Stn,
Ghatkopar (E), Mumbai 400 077. Maharashtra.
Tel: 2501 3661 / 2 / 3. 6575 4002 / 03.
Malde Capacitors Mfg. Co. Fax: (022) 2501 0758 / 3660
maldecapacitor@gmail.com
By proper Distribution of Power Capacitors you can avail the following Financial
Savings:
1. If S.E.B has rebate system for improved PF than one can avail upto 7 % Rebate in
Electricity Bills for improved PF. States like Maharashtra, M.P, Chattisgarh,
Rajasthan, Gujarat, Goa, Haryana, etc have started giving rebate for improved PF.
2. As we know
PF = KW
KVA
By Improving PF, KVA goes down, i.e. reduction in MD (KVA Demand) charges.
3. By proper distribution of capacitors (near to load point) we are eliminating
Magnetizing current near to the load points hence there is a reduction in System
Current, due to which there is a reduction in System Losses (I2R losses) i.e.
Reduction in KWh consumption by about 2.5% to 4% (varies from system to
system)
4. As there is reduction in KWh consumption due to reduction in I2R losses, there will
further reduction in KVAh. The reduction in KVA will be proportional to the %
reduction in KW.
Quite often, one needs to operate his factory on DG set. Hence, Diesel becomes an
important but costly fuel for production of electricity. We can bring this cost down by
the following ways:
1. By reduction in System Losses
2. By reduction in Alternator Losses.
All the above benefits can be obtained only by one option. i.e.
TO SELECT CAPACITORS AS PER INDIVIDUAL LOAD AND TO CONNECT THEM
TO THE OUT GOING / SECONDARY OF MOTOR STARTER.
Advantages:
1. LEADING CURRENT WILL NEVER GO INTO THE ALTERNATOR WINDING.
HENCE NO VOLTAGE BUILT UP, SO NO FEAR OF TRIPPING OF DG SET
OR BURNING OF AUTOMATIC VOLTAGE REGULATOR (AVR)
2. EVEN AFTER POWER TO TRANSFORMER RESUMES A SEPARATE
CAPACITOR FOR THE TRANSFORMER WILL COMPENSATE FOR THE
MAGNETIZING CURRENT OF TRANSFORMER, WHILE WE ARE YET
RUNNING ON DG SET.
2
As metering system is connected at primary side (i.e. H.T. side) of transformer, it will
register transformer losses and the magnetizing current of Transformer. Magnetizing
current of transformer spoils power factor.
Ix Real / Loss Component
Current V
1
P.F = COS1 = BAD
Iy Magnetizing Current
Ix + Iy
Iy Ix
Ix + Iy Iy Ix
I TRANS
To LIGHTING
TRIVECTOMETER ACB/OCB/MCCB DG Set Supply
Main Switch
CT PT
NO LOAD
CONDITION
HT SIDE CHANGE
SFU SFU SFU OVER
TRANSFORMER
1000 KVA SWITCH
Hence, in our example for 1000 KVA transformer, one must connect separate capacitor
of 100 KVAr Cx bank to overcome the magnetizing KVAr (Reactive Power) of the
Transformer.
We recommend breaking these Cx Capacitors in three parts viz Cx160%, Cx225%
and Cx315%. All these capacitors should be connected through separate switch fuse
unit (SFU) as shown in the diagram above. With these you will get seven steps (ie Cx1,
Cx2, Cx3, Cx1+Cx2, Cx1+Cx3, Cx2+Cx3 and Cx1+Cx2+Cx3). See Table on Right Hand Side.
Select this suitable step of capacitor to compensate the No Load Magnetizing Current,
due to leakage flux in air gap in transformer core, by seeing slower counts of RKVAh
units or nearly equal counts of KWh or KVAh units (means good PF). Keep this
capacitor ON for 24 Hrs x 7Days.
3
Ix Ix + Iy 2
Ix
V
Ic Iy IY Iy Ix I TRANS
1
Iy Ic = Capacitor current
Required Capacitor to
Ix improve P.F
The balance capacitor step to be switched ON when your factory load is ON. The
leading current of these capacitors will compensate the inductive current used to
produce magnetic flux which is used in the secondary winding of the transformer to
induce the voltage.
Connecting a separate capacitor for Transformer, as shown above plays a very
important role during the following events:
1. Newly started project, where the transformer is energized and is only loaded with
Lighting load, i.e. production is yet to start.
2. Company having labour unrest / strike.
3. Maintenance/Breakdown Period.
4. Staggering Holiday or Public holidays.
5. When company is running on DG set, but supply to Transformer has resumed.
For all the above events if a separate capacitor for the transformer is not connected
then the company may have to pay for low P.F. penalties, which is registered by the
H.T. meter due to magnetizing current of transformer and lighting loads.
Also, APFC panels cannot sense the low P.F of transformer as the CT of APFC Panel
senses the current signal after the secondary (LT Side) of transformer. So one needs
to connect separate capacitors for transformer.
Table 1: Capacitors required for the following Transformer KVA
KVA of Size of Capacitor Cx1, Cx2 and Cx3 in KVAr Remark
Transformer Cx Cx1 SFU HRC Cx2 SFU HRC Cx3 SFU HRC
KVAr 60% Fuse 25% Fuse 15% Fuse
150 5 3 16A 10A 1 16A 4A 1 16A 4A Connect
200 7.5 4 16A 10A 3 16A 10A 2 16A 6A capacitor
250 10 6 32A 16A 3 16A 10A 1 16A 4A with the
315 12.5 7.5 32A 20A 3 16A 10A 2 16A 6A help of
500 25 15 50A 32A 6 32A 16A 4 16A 10A SFU &
750 35 20 63A 50A 10 32A 25A 5 16A 16A HRC fuse
1000 50 30 100A 80A 15 50A 32A 5 16A 16A at the
1250 75 45 125A 125A 17.5 50A 50A 12.5 32A 32A secondary
1500 100 60 200A 160A 25 63A 63A 15 50A 32A
of
2000 125 75 250A 200A 35 100A 100A 15 50A 32A
ACB/OCB
2500 150 90 250A 250A 40 125A 100A 20 63A 50A
4
Ix
V
1
Ix + Iy P.F = COS1 = Bad
Iy Ix
Iy Ix
Ix + Iy
From above diagram, we can conclude that for a motor, requirement of capacitor is
fixed as magnetizing current, which spoils the power factor, is fixed. Hence for the 100
HP/1440 RPM motor connect 40 KVAr capacitor.
Ix Ix + Iy
2 Ix
Ic Iy IY Iy Ix V
1 I MOTOR
Iy
Ix
Ic = Capacitor current
Required Capacitor to
Ix Ix + Iy Motor Improve P.F
As you may be having a Star Delta starter for the 100 HP motor, connect capacitor as
shown below:
IM
Over Load Trip Relay
Iy
Iy IC
50 KVAr Bank
Individual Power Capacitors.
25 KVAr
12.5 KVAr
10 KVAr
Example: High Consistency Pulping Section in a Kraft Paper Mill
6
6. Conveyor 7.5/1500 NIL
Total Capacitor Required for Individual 197.5 KVAr
Connection
For Transformer 100 KVAr
Total Capacitors Required 297.5 KVAr
Note: Incase you need our suggestion for your unit please send us the following:
Transformer KVA with % Impedance.
All your Motor details like HP, RPM, application, etc.
One line diagram of your factory (if available.)
Photocopy of your past two months electricity bills,
The above information is given upto the best of our knowledge without any guarantee as regards to either mistake or omissions