You are on page 1of 9

Date 14 Juli 2017

Location

Project Engineering Report


PLN Report
No Task Qty Unit

1 Sign Contract
2 Hand Over Land
3 Schedule
Overall Progress
Vendor Scope
MAN
No Task Qty Unit

1 Sign Contract
2 Down Payment
3 Effective Date
4 Document Engineering Approvement
5 LC
6 Fabrication and Assembling
7 Engineering Accessories
Turbo Charger 2 Set
Flexible Coupling on flywhell 2 Set
Engine Drive Lube Oil Pump 2 Set
Engine Driven HT Cooling Water Pump 2 Set
Engine Driver LT Cooling Water Pump 2 Set
Level Switch in Oil sump for high and low alarm 2 Set
Governor (Speed Control) 2 Set
Engine Safety, Control and Monitorng 2 Set
Painting 2 Set
8 Generator Accessory 2 Set
9 GVU (Fuel Gas System)
Shut off Valve
Gas Filter
Pressure Gauge
Gas Regulator
Etc
10 Intake Air System
Expansion Joint for TC Inlet 2 Set
11 Exhause Gas System
Expansion Joint for TC Outlet 2 Set
12 Instrument and Control System
Genset Control Panel with synchro (GCP) 2 Set
13 Instruction and O&M Manual
Shop Test for DG Set
Clearances
Installation
Pre- Com
Test and Commissioning
Vendor Training
Operation and Maintenance Training
Engine Training Cource
Overall Progress
TSP
No Task Qty Unit

1 Fuel Oil System


FO Suction Strainer for unloading pump 2 Set
FO Unloading pump with by pass line 2 Set
FO flow meter for unloading 1 Set
FO Transfer Pump with sunction Strainer 1 Set
Fuel Oil-Water Separator (Purifier) 1 Set
FO Strainer for Forwarding Pump 1 Set
FO Forwarding pump (Supply Pump) 4 Set
FO Duplex filter unit (Supply Pump) 1 Set
FO Safety relief valve (Regulator Valve) 1 Set
DO Cooler 2 Set
FO Drain tank with pump 1 Set
Pilot Oil Supply pump unit 2 Set
Pilot Oil Transfer Pump 2 Set
Pilot Oil Cooler Unit 1 Set
Pilot Oil Auto Filter Unit 1 Set
Pilot Oil Duplex filter unit 1 Set
Pilot Regulating Valve 1 Set
2 Lubricating Oil System
LO Unloading Pump 1 Set
LO Hose, Hose Reet and Receving Pump 1 Set
LO Suction Strainer For Transfer Pump 2 Set
LO Transfer Pump 2 Set
LO Filter for Flow Meter 1 Set
LO Flow Meter for Transfer Pump 1 Set
Electric Prelubricating Pump (400V) 2 Set
LO Cooler 2 Set
LO Auto Filter 2 Set
LO Purifier Unit 2 Set
Used LO Pump, House and cable 1 Set
Oil Mist Eliminator 2 Set
3 Cooling Water System
Cooling water make up pump 2 Set
HTCW Expantion Tank 2 Set
LTCW Expantion Tank 2 Set
HT Cooling Water Radiator 2 Set
LT Cooling Water Radiator 2 Set
LTCW Temp. Control Valve (MOV) 2 Set
HTCW Temp. Control Valve (MOV) 2 Set
Nozzle Cooling Water System 2 Set
Jacket Water Preaheating Unit 2 Set
Cooling Water Pump for cooler 4 Set
4 Compressed Air System
Starting air compressor (Electrical) 2 Set
Starting air receiver for engine starting 1 Set
Starting air receiver for control air 1 Set
Pressure reducingg valve unit 1 Set
Control air dryer and filter unit 2 Set
Enclosed of starting air compressor 1 Set
5 Intake Air System
Intake Air Filter wit silencer 2 Set
Different Pressure Indicator (Manometer) 2 Set
6 Exhause Gas System
Exhause Gas Silencer 2 Set
Rupture Disk 4 Set
7 Water Treatment System
Service Water supply pump 2 Set
Raw Water transfer pump unit 1 Set
Water Treatment Unit 1 Set
Treated Water Tank 1 Set
Fresh Water Supply Pump with flow meter 2 Set
Waste Water tank with pump 1 Set
8 Spare Part and Tools
Standart Sparepart for TSP 1 Set
Standart Tools for TSP 1 Set
9 Engineer
General Layout
Piping and Instrument Diagram (Engineering) 1 Set
Single Line Diagram 1 Set
D/G set generator arrangement Drawing 1 Set
Piping and Instrument Diagram (Basic) 1 Set
Instrument and O&M Manual 1 Set
10 Transportation
Packing and marking of equipment for TESP Scope 1 Set
Ocean Transport (TSP Scope) 1 Set
11 Supervison and Test (Commissioning)
Erection and Installation (TSP Scope) 1 Set
Site Test and Commissioning 1 Set
12 Shop Test
Shop Test for auxillary equipment 1 Set
13 On site
Operating and maintenance Training 1 Set
Overall Progress
ngineering Report

Start Date Finish Date Prog (%) Status Remark

18-Jun-17 18-Jun-17 1 Open


10-Jul-17 0 Open
10-Jul-17 10-Sep-18 0 Open
33%
ndor Scope

Start Date Finish Date Prog (%) Status Remark

100% Open
0% Open
0% Open
0% Open
0% Open Issued By PLN
0% Open
0%
Open
Open
Open
Open
Open
Open
Open
Open
Open
0% Open
0%
Open
Open
Open
Open
Open
0%
Open
0%
Open
0%
Open
0%
Open
Open
Open
Open
Open
Open
Open
Open
8%

Start Date Finish Date Prog (%) Status Remark

0%
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
0%
Open
Open 1
Open 1
Open 1
Open 1
Open 1
Open 1
Open 1
Open 1
1
0%

0%

0%

0%

0%

0%

0%

0%

0%
0%

0%

0%
0.2
Close 1
Open 0
On Going 0.5
Open 0
Open 0
Close 1
On Going 0.5
1

1
3
3
4
11

You might also like