Professional Documents
Culture Documents
Background
Motivation for this research was the incident of
January 30, 2012 at Byron Station NPP which
involved an open-phase condition on the primary of
two SATs.
This research describes a new method for finding
the zero sequence parameters for typical SATs.
The method cuts the costs of prevailing methods,
particularly for on-site measurements.
Initial simulations were promising. Method was
then validated using actual measurements.
3
Background - 2
In the standard IEEE/ANSI method, at least one
measurement must be carried out from the high
voltage side. This measurement is shown in figure as
Z1No
The usual setting for this Zp-0
Z1Ns or Z2Ns
Zs-0
test would be a high
voltage laboratory, Zm-0 Zt-0
Background - 3
Onsite measurements however would require
renting high voltage mobile laboratories at a high
cost.
Our method eliminates the high voltage test, and
replaces it with the low voltage test shown below.
Only a low voltage (230 400 V) three phase supply
is required. primary phase A
opened Ia
Three-phase low
A voltage source
Vab V V Vca
Ib
A
Vbc V
Ic
A
Background - 4
Our test configuration requires application of a three
phase voltage to the secondary under the following
conditions:
1. Secondary neutral is disconnected.
2. Two primary (high voltage) terminals are shorted to the
neutral, with the remaining terminal left open.
This connection creates conditions involving all three
sequence component voltages and currents.
6
Methods
Our method exploits the primary open phase
sequence model.
Two methods were proposed. A simplified
approximate method and an iterative based
exact method.
E1
I1 Zps-1 Zs-1
I2 Zps-2 Zs-2
I0 Zp-0
Zt-0//Zm-0 V2 V1
7
Methods - 2
The simplified method makes use of Ic
Ib and Ic .
Vc
= = = cos1 Vca
2
Vbc V1 V2
Va
2 2
1 = cos( + 30) 2 = cos( 30) Vab
3 3 Vb
0 + 1 + 2 = 0
8
Methods - 3
The exact method includes transformer resistive
components and involves using the six current and voltage
measurements Ia, Ib, Ic, Vab, Vbc and Vca in addition to the
sequence network model to solve for real and imaginary
values of I1, I2, V1 and V2 . From this solution Io is deduced
and used to find the real and imaginary components of
the zero sequence impedance.
Results
Summary of results for a test carried out on a TVA 18 MVA SAT
at a test site in Virginia.
10
Conclusions
The test is expected to be valuable to those
seeking to determine zero sequence
parameters not available on many legacy SAT
units with affordable costs.
Method is extendable to transmission type
transformers authors are developing model.
Field testing has confirmed the high accuracy
offered by the method.
1
AnalysisofOpenPhaseFaultEventsUsing
ETAPUnbalancedLoadFlowModule
PrestonO.CooperIII
TennesseeValleyAuthority
pocooper@tva.gov
2
Background
Multipleeventsacrossthenuclearpower
industry
Existingschemesdidnotprovideadequate
protection
Needforgreaterunderstandingofwhat
happensduringanopenphasefault(OPF)
3
Event
OPFabovetransformer
Magneticcircuits
reconstructmissing
phase
Configurationaffects
lowsideunbalance
4
WhySteadyState?
WorstcaseV1 andV2 shouldnottrip
instantaneousmotorprotection(current)
I2 createsadditionalheatinginmotors
Motorshavethermalmass
5
Methodology
IEQ EquivalentCurrent
I1 PositiveSequenceCurrent
I2 NegativeSequenceCurrent
IFL MotorFullLoadCurrent
ILR MotorLockedRotorCurrent
6
7
8
Results
Greatertransformerloadingyieldsgreater
unbalances
Lessimpedancetogroundyieldsgreater
unbalances
Lackofastabilizingwindingyieldsgreater
unbalances
Twodifferenttransformersinthesamesystem
yieldequalmaximumunbalances
9
ProtectiveDevices
Possible
TransformerPhaseOvercurrent
TransformerNeutralOvercurrent
TransmissionLineNegativeSequence
Discounted
TransformerDifferential
DegradedVoltage
10
Summary
AdditionalheatingduetoV2 andI2 isa
significantconsequenceofanOPF
Transformerconstructioniscrucial
Steadystatecalculationsareviable
Threedimensionalsurfaces
Visualizetheeffectsofanopenphasefault
Validateexistingordevelopnewprotection
1
Outline
Acknowledgment
Introduction
Equivalent 3-Phase Power System Model
Open-Phase Scenarios Studied
Sample of Results
Notable Results & Conclusion
Questions
3
Acknowledgment
Mr. Joel Mathewson,
Mr. Mario Poujol,
Mr. Volodymyr Habovda
Graduated in 2014, UNC Charlotte
Introduction
Equivalent 3-Phase Power System Model
(in EMTP)
Transformer Data/Model
3 winding transformer (i.e. 3x1 phase)
Ratings: 345/6.9/4.16 kV, 40/35/5 MVA
Yg-Yg-Yg connected (primary solidly grounded, resistive ground on
secondary 6.6 ohms, and tertiary 4.0 ohms, 600A)
7
QUESTIONS?
1
AGENDA
Introduction
Open Phase Fault Network
Test Results
Conclusion
Questions
3
INTRODUCTION
Primary open-phase faults on SATs result in voltage
imbalance at the auxiliary equipment level.
Primary to ground zero sequence impedance has a
major role in balancing the secondary voltages
during open phase faults.
This study investigates the impact of voltage
imbalance on the performance of station auxiliaries.
4
TEST RESULTS
The analysis performed to answer:
Is the motor able to accelerate successfully to rated speed
under open-phase conditions?
If yes, what is the acceleration time required?
What is the voltage unbalance ratio V2/V1 during and after
attaining steady state operation?
7
TEST RESULTS
Voltage imbalance was 8.6% at the instant of starting
and 1.2% at steady state conditions
10
V2/V1 (%)
0
0 2 4 6 8 10 12 14 16 18 20
Time (sec)
200
V1 (%)
100
0
0 2 4 6 8 10 12 14 16 18 20
Time (sec)
10
V2 (%)
0
0 2 4 6 8 10 12 14 16 18 20
Time (sec)
8
TEST RESULTS
Voltage imbalance increased the starting time to 17 s
(3 seconds delay).
1000
Ia (%)
500
0
0 2 4 6 8 10 12 14 16 18 20
Time (sec)
500
T (%)
-500
0 2 4 6 8 10 12 14 16 18 20
Time (sec)
500
wr (rad/sec)
-500
0 2 4 6 8 10 12 14 16 18 20
Time (sec)
9
TEST RESULTS
Results for all three transformers under base (actual
data) conditions
SAT 1 SAT 2 SAT 3
Sequoyah Sequoyah J. M. Farley
33 MVA 18 MVA 26 MVA
Start Run. Start. Run. Start. Run.
TEST RESULTS
Results under unified MVA and positive sequence
impedance conditions:
SAT 1 SAT 2 SAT 3
Sequoyah Sequoyah J. M. Farley
33 MVA 18 MVA 26 MVA
Start Run. Start. Run. Start. Run.
TEST RESULTS
Results under base conditions with Two SATs in
Parallel:
SAT 1 SAT 2 SAT 3
Sequoyah Sequoyah J. M. Farley
33 MVA 18 MVA 26 MVA
Start Run. Start. Run. Start. Run.
CONCLUSION
lower values of primary to ground zero sequence
impedance better voltage imbalance better
starting and running performance.
A maximum voltage unbalance (V2/V1) of less than
10% during starting allowed adequate acceleration of
RCP.
Delayed motor acceleration, or possibly failure to
start could be expected if the voltage imbalance goes
beyond 10%.
13
CONCLUSION
Accurate determination of zero sequence
impedances is necessary to assess the response of
substation auxiliaries and accordingly decide on the
appropriate measures in the event of an open phase
fault on the primary SAT level.
1
Observations
Sequence Models are functions of Connected Load
Load Impedance is a function of Motor Speed
Positive Sequence Motor Impedance is different
than Negative Sequence Motor Impedance
Positive Sequence Torque = Accelerating Torque
Negative Sequence Torque = Decelerating Torque
No Zero Sequence Torque
8
Observations
Sequence Voltage and Current are functions of
Connected Load
When Zero Sequence Impedance is High,
Zero Sequence considerations are minimal
When Zero Sequence Impedance is Low,
Negative Sequence considerations are
minimal
9
Observations
High Zero Sequence Impedance
(Zero Sequence considerations are minimal.)
Motors Rotating during open phase conditions:
o Positive sequence torque is reduced
Observations
High Zero Sequence Impedance
(Zero Sequence considerations are minimal.)
Motor Acceleration during open phase conditions:
o Positive sequence torque is reduced
Observations
Low Zero Sequence Impedance
(Negative Sequence considerations are minimal.)
Motors Rotating during open phase conditions:
o Positive sequence torque is reduced
Observations
Low Zero Sequence Impedance
(Negative Sequence considerations are minimal.)
Motor Acceleration during open phase conditions:
o Positive sequence torque is reduced
Observations
Traditional Open Phase Detection Schemes are
applied on a per Motor basis
Non-Nuclear Electrical Systems are designed for
staged load increases
Nuclear Power Generating Station Electrical
Systems are designed for Rapid Step Loading
14
Conclusions
Understanding Zero Sequence Impedance is KEY
Conclusions
Open Phase Watchdog Parameters
Monitor for Negative Sequence Current
Monitor Total Current
Monitor Positive Sequence Phase Angle
Negative Sequence Current, Large Phase Angle (~700),
High Total Current
Motor Acceleration Quick Trip
Negative Sequence Current, Moderate Phase Angle
(~400), Moderate Total Current
Motors Rotating Slow Trip
1
Agenda
Unbalanced System
OPF Study Objective & Requirements
OPF Analysis and Related Indexes
General Element Modeling
Examples
Conclusion
3
Lifetime reduction
5
Unbalance Factors/Indexes
System unbalance is considered as a disturbance
Voltage/Current unbalance factors
Ratio of negative sequence to positive sequence
Ratio of zero sequence to positive sequence
Ratio of maximum deviation from average value
to average value
7
3-Phase Machines
Sequence models
12
Loads
Single-Phase Loads
Different connection types: AB, BC, CA, AN, BN or CN
Three-Phase Loads
Connected in Delta, Wye or Wye-G
Example
Steady State vs. Transient
3-phase Currents
3-phase Voltages
17
Example
Buried Delta & Motor Loading
Scenario Revision Study Case
Scenario 1 Base ULF-100%
Scenario 2 Base ULF-50%
Scenario 3 Buried-Delta ULF-100%
Scenario 4 Buried-Delta ULF-50%
Mtr1 Mtr2
25.00%
20.00%
15.00%
10.00%
5.00%
0.00%
Scenario 1 Scenario 2 Scenario 3 Scenario 4
18
Example
Double Open-Phase Fault
Heavily Loaded Motors
Ground path
Study # Double Open-Phase Fault Study Case
Study 1 B-C open at T1 primary side Summer
Study 2 B-C open at T1 primary side Winter
Study 3 B-C open at T2 primary side Summer
Study 4 B-C open at T2 primary side Winter
Mtr35 Mtr31
Study
V1 L-L V2/V1 V1 L-L V2/V1
(%) (%) (%) (%)
Study 1 34.31 100 33.8 99.97
Study 2 108.3 5.69 107.4 5.62
Study 3 105.8 3.2 70.48 100
Study 4 101.6 0.31 103.5 4.3
19
Conclusion
Data requirement including element connections,
sequence impedance, unbalanced loads & sources