This document contains a daily activity and achievement log for the week of June 26th to July 1st. It details the various tasks completed each day, including site inductions, progress checks, sample presentations, cleaning activities, and documentation of daily photos. The log shows that each day consisted of 11 hours of work from 6:30am to 6:30pm, with an hour lunch break. Recurring daily tasks included pre-start meetings, site inductions, and documentation of progress photos.
This document contains a daily activity and achievement log for the week of June 26th to July 1st. It details the various tasks completed each day, including site inductions, progress checks, sample presentations, cleaning activities, and documentation of daily photos. The log shows that each day consisted of 11 hours of work from 6:30am to 6:30pm, with an hour lunch break. Recurring daily tasks included pre-start meetings, site inductions, and documentation of progress photos.
This document contains a daily activity and achievement log for the week of June 26th to July 1st. It details the various tasks completed each day, including site inductions, progress checks, sample presentations, cleaning activities, and documentation of daily photos. The log shows that each day consisted of 11 hours of work from 6:30am to 6:30pm, with an hour lunch break. Recurring daily tasks included pre-start meetings, site inductions, and documentation of progress photos.
DATE ACTIVITY / ACHIEVEMENT Time Time Period Hours
Take notes in the pre-start meeting, i.e. what tasks are
going on today. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Go around the site updating all the emergency contacts list. i.e. from basement 3 to level 5/6 on all 4 buildings. Site walk with Tim (Senior Site Engineer) to check that all Monday the spitters are in place on all the balconies. Mark-up GA 6:30am 6:30pm 1hr 11 hrs 26/6/17 drawings of where all spitters are located. Revised the Residential Operations and Maintenance Manual that we would be handing over the individual apartment owners. Walk around the site with Shane Tozer to update Zutec Progress on all apartments. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
Take notes in the pre-start meeting, i.e. what tasks are
going on today. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Clean the roof of building C for consultant and client inspection. (removing all the rubbish/ scaffolding/ Tuesday temporary power boxes/ sweeping the dirt/ washing 6:30am 6:30pm 1hr 11 hrs 27/6/17 down the surface with a hose) Site walk with Tim (Senior Site Engineer) to check that Arch Systems have installed either subsill/subheaders, subframes or windows for each apartment (ONGOING PROGRESS). Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels. Take notes in the pre-start meeting, i.e. what tasks are going on today. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Site walk with the foreman Tom, using an app called Zutec to check and update statuses of each and every apartment (total 130 apartments). Check contracts with Kris Hocking to see if Wednesday 6:30am 6:30pm 1hr 11 hrs subcontractors have agreed or made any variations to 28/6/17 the agreed work. Used aconex field to notify subcontractors of incomplete works and defects. Presented samples to the architect, which are the following: robe hooks for apartments, towel rails and toilet roll holder. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
Take notes in the pre-start meeting, i.e. what tasks are
going on today. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Confirm that the missing spitters are completed. Thursday 6:30am 6:30pm 1hr 11 hrs Clean Eastern Boundary and organise crane lift for the 29/6/17 2m bin. Practice fire alarm drill and as a safety measurement, I performed a building sweep for building D. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
Take notes in the pre-start meeting, i.e. what tasks are
going on today. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Presented samples to the client for formal signoff and construction approval for the following items: robe hooks Friday for apartments, towel rails and toilet roll holder. 6:30am 6:30pm 1hr 11 hrs 30/6/17 After the executed contracts are agreed upon and signed every page, make an electronic copy and send out the hard copy to the subcontractor. Check above entry doors for fire and hydraulic ratings. Make sure that the fire and hydraulic items are caulked. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Organise a clean-up of Building D with two zenith labourers. Saturday 6:30am 2:30pm 1hr 7 hrs Sit-down with Tim and talk about personal progress, how 1/7/17 I am going, what am I learning, am I enjoying the cadetship. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
Take notes in the pre-start meeting, i.e. what tasks are
going on today. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Site walk with Tim (Senior Site Engineer) to check that Arch Systems have installed either subsill/subheaders, subframes or windows for each apartment (ONGOING PROGRESS). Monday 6:30am 6:30pm 1hr 11 hrs 3/7/17 Ensure all balcony spitters are installed with the PVC pipework. Stationary order for the project team (pens/folders/laminating paper). Follow up with Telstra and Optus regarding the relocation of the pits situated in the carriageway. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
BUILTSAFE TRAINING DAY 1
Topics include: - Safety in the workplace Tuesday 7:30am 5:30pm 1hr 9 hrs - Responsibilities by PCBU/Principal contractor 4/7/17 - Examples of poor safety - Safety Measures - LTIs/MTIs - Lag indicators/lead indicators
Take notes in the pre-start meeting, i.e. what tasks are
going on today. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Wednesday 6:30am 6:30pm 1hr 11 hrs 5/7/17 Presented samples to the architect, which are the following: paint samples for exterior and interior finishes, marble stone bench tops, carpet samples for entrance matting. Call and email subcontractors regarding, training agendas, key registers, O&M manual for the residential/commercial/Woolworths handover. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
Take notes in the pre-start meeting, i.e. what tasks are
going on today. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Going around the site and updating the Site Emergency Assembly Plan on every nurse call from basement 3 to Thursday level 5/6 on all 4 buildings. 6:30am 6:30pm 1hr 11 hrs 6/7/17 Key register review with the Nicholas Moldrich for update and progress follow up. Head contract Warranties with Kris to explain and chase from subcontractors. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
Take notes in the pre-start meeting, i.e. what tasks are
going on today. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Presented samples to the client for formal signoff and construction approval for the following items: paint samples for exterior and interior finishes, marble stone bench tops, carpet samples for entrance matting. Scan in the signed sample submission documents with Friday 6:30am 6:30pm 1hr 11 hrs pictures of items. Transmit them to the specific trades via 7/7/17 Aconex to allow them to gather the materials and place orders for the required products. Emailing Gerry Law from Ausiron to organise the B1 driveway sample for architect sign off. Follow up with subcontractors for the Woolworths handover requirements as the handover date is coming up very soon. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
Completed site inductions to inform new subcontractors
of the project information, safety measures, emergency procedures and amenities. Saturday Check with Harry Wurcker that the storage cages 6:30am 2:30pm 1hr 7 hrs 8/7/17 (provided by Modern Welding) are ordered in and following the critical dates as promised. Ensuring that Anthony from Polyseal completes waterproof works for the planter boxes. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
Take notes in the pre-start meeting, i.e. what tasks are
going on today. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Calling Cameron Morrall from Kirk Interiors to organise Monday sample for the timber skirting. 6:30am 6:30pm 1hr 11 hrs 10/7/17 Calling Robert Fiszman from Cronulla Carpets to organise sample for timber flooring. Organise the Handover for the Woolworths Retail section as handover is on the 18th of July. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
Take notes in the pre-start meeting, i.e. what tasks are
going on today. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Clean the roof of building B for consultant and client inspection. (removing all the rubbish/ scaffolding/ Tuesday temporary power boxes/ sweeping the dirt/washing down 6:30am 6:30pm 1hr 11 hrs 11/7/17 the surface with a hose) Site walk with Tim (Senior Site Engineer) to check that Arch Systems have installed either subsill/subheaders, subframes or windows for each apartment (ONGOING PROGRESS). Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
Take notes in the pre-start meeting, i.e. what tasks are
going on today. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Presented samples to the architect, which are the following: timber flooring, timber skirting, B1 driveway Wednesday screen, toilet partition. 6:30am 6:30pm 1hr 11 hrs 12/7/17 Organise with Joel for Mckenzie Group to inspect waterproofing. Organise key collection for Key register with Pedro (Project Manager from EDP). Talk to Kristoffer Hocking about requirements for the Optus/Telstra pit relocation, regarding road plates, traffic management. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
FIRST AID TRAINING DAY
Thursday 8am 5pm 1hr 8 hrs - Learnt about open wounds /allergies /poisons 13/7/17 /breaks /CPR /bandaging
Take notes in the pre-start meeting, i.e. what tasks are
going on today. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Presented samples to the client for formal signoff and construction approval for the following items: timber flooring, timber skirting, B1 driveway screen, toilet partition. Scan in the signed sample submission documents with Friday pictures of items. Transmit them to the specific trades via 6:30am 6:30pm 1hr 11 hrs Aconex to allow them to gather the materials and place 14/7/17 orders for the required products. Calling Tom Johnston from Inten for Handover requirements for all the hydraulic services. Calling David Adamson for As-Builts drawings for fire services. Calling Josh Binnie for the Architectural As-Built Structural drawings. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
Completed site inductions to inform new subcontractors
of the project information, safety measures, emergency procedures and amenities. Labouring: cleaning all rooms on Building B for floor prep / clean all rooms with the Preston decks as they are being removed this coming week / take all appliances (dishwasher/over/cooktop/rangehood) to level 1 in Saturday 6:30am 4:30pm 1hr 9 hrs Building A & B. 15/7/17 Assist in the first aid deliveries for the amenities. Building sweep to check that no person is left behind on the site. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
Take notes in the pre-start meeting, i.e. what tasks are
going on today. Monday Completed site inductions to inform new subcontractors 6:30am 6:30pm 1hr 11 hrs 17/7/17 of the project information, safety measures, emergency procedures and amenities. Take the appliances (dishwasher/over/cooktop/rangehood) to level 1 on Buildings C & D. Took out the Operations and maintenance manuals for each item. In addition, removed the loose fittings on the appliances so they dont get stolen. Russell (Built Construction Worker) rolled his ankle on a piece of gyprock in the basement. Took him the Ryde Hospital for x-rays and then drove him home. Returned to work to complete paper work. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
BUILTSAFE TRAINING DAY 2
Topics included: Tuesday - WHS Management System What is it and why 7:30am 5:30pm 1hr 9 hrs 18/7/17 do we need one? - Key processes covered by Builts WHS Management System (Built.Safe) - Participant Assessment & Feedback
Take notes in the pre-start meeting, i.e. what tasks are
going on today. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Presented samples to the architect, which are the following: exhaust louvres, exhaust screens, bathroom mirror, junior WC (& cistern), and glass balustrades. Handing out notices to nearby shops and residents for Wednesday 6:30am 6:30pm 1hr 11 hrs the decommissioning of our tower crane. 19/7/17 Spotting a construction worker as they are performing core drilling for pipework for the tenancies. Drilled 6 65mm holes and 3 125mm holes over 4 tenancies. Moved excess of appliances from sample storage room to some apartments and the others to the storage cages on a different level. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
Take notes in the pre-start meeting, i.e. what tasks are
going on today. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Thursday 6:30am 6:30pm 1hr 11 hrs 20/7/17 Site walk with Tim (Senior Site Engineer) to check that Arch Systems have installed either subsill/subheaders, subframes or windows for each apartment (ONGOING PROGRESS). Site complaint from neighbouring shop owner due to subbies acting careless with rubbish. Address the issue by talking to the project manager and site manager. Talk to subbies through a toolbox talk for a warning. Block access to all 4 roofs as fence panels have been removed. Organised a SWMS and sign on sheet with the site manager John Peacock for any access. All access will require permits such as working at heights and must have a harness. Placed signs up where all roof hatches are, top levels of stair cores and on the rooftop entrance. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
Take notes in the pre-start meeting, i.e. what tasks are
going on today. Completed site inductions to inform new subcontractors of the project information, safety measures, emergency procedures and amenities. Presented samples to the client for formal signoff and construction approval for the following items: exhaust Friday louvres, exhaust screens, bathroom mirror, junior WC (& 6:30am 6:30pm 1hr 11 hrs 21/7/17 cistern), and glass balustrades. Scan in the signed sample submission documents with pictures of items. Transmit them to the specific trades via Aconex to allow them to gather the materials and place orders for the required products. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.
Completed site inductions to inform new subcontractors
of the project information, safety measures, emergency procedures and amenities. Crane removal of TC1, 36hr operations where we have Saturday 6:30am 4:30pm 1hr 9 hrs closed of Hannah Street. Organising with Tim and Shane 22/7/17 for traffic controls and removal of fencing. Take daily site photos for every room in every apartment (bedroom/kitchen/bathroom/general), podium levels, 3 basement levels and retail levels.