You are on page 1of 19

KONTRAK NO.

9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI


MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.

INSITU CONCRETE

Provision of Concrete (Supply Only)

3.201 Designed mix, Grade C20 cement to BS12,


20mm aggregate, minimum cement content m
3
225.00 190.00 210.00 201.40 270.00 262.00 224.65 310.00 312.50
3
225 kg/m .

3.202 Designed mix, Grade C25 cement to BS 12,


20mm aggregate, minimum cement content m3 230.00 199.00 220.00 211.10 280.00 268.00 235.65 310.00 312.50
250 kg/m3.

3.203 Designed mix, Grade C30 cement to BS 12,


20mm aggregate, minimum cement content m3 270.00 210.00 233.00 222.10 290.00 279.00 248.05 310.00 350.00
300 kg/m3.

3.204 Designed mix, Grade C35A cement to BS 12,


20mm aggregate, minimum cement content m3 290.00 236.00 294.00 246.00 320.00 301.00 304.55 310.00 412.50
350 kg/m3.

B3.2-1
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.

Page Total Carried to Summary of Sub-Bill No. 3.2

B3.2-2
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.

PLACING OF CONCRETE (Laying Only)

Mass Concrete

3.201 50mm thick concrete blinding (Grade C20). m


3
50.00 100.00 50.00 85.00 40.00 44.00 35.00 310.00 100.00

3.202 Mass concrete for valve support (Grade C25). m


3
50.00 62.00 50.00 96.80 40.00 44.00 35.00 310.00 125.00

Reinforced Concrete (Grade C25)

3.203 Base slab of valve chambers, thickness


300mm. m3 50.00 62.00 50.00 85.00 40.00 44.00
35.00 310.00 125.00

3.204 To concrete plinth support. m3 50.00 62.00 50.00 85.00 40.00 44.00 35.00 310.00 125.00

3.205 For wall of valve chambers, thickness 300mm. m3 50.00 62.00 50.00 85.00 40.00 44.00 35.00 310.00 125.00

3.206 For apron and ground slab. m3 50.00 62.00 50.00 85.00 40.00 44.00 35.00 310.00 125.00

Reinforced Concrete Grade C30

3.207 For pile cap. m3 50.00 62.00 50.00 79.10 40.00 44.00 35.00 310.00 125.00

3.208 For tank columns. m3 50.00 62.00 60.00 79.10 50.00 154.00 35.00 310.00 125.00

3.209 For ground beams. m


3
50.00 62.00 50.00 79.10 40.00 66.00 35.00 310.00 125.00

3.210 For intermediate beams. m3 50.00 62.00 60.00 79.10 50.00 132.00 35.00 310.00 125.00

3.211 For staircase, landing platform and beams. m3 50.00 62.00 65.00 96.80 50.00 132.00 35.00 310.00 125.00

B3.2-3
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.

Page Total Carried to Summary of Sub-Bill No. 3.2

B3.2-4
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.

Reinforced Concrete (Grade C35A)

3.201 For tank slab. m3 50.00 62.00 65.00 100.40 50.00 154.00 35.00 310.00 562.50

3.202 For tappered wall of tank. m


3
50.00 62.00 65.00 112.20 50.00 154.00 35.00 310.00 562.50

3.203 For tank beam bottom side of tank. m


3
50.00 62.00 65.00 112.20 50.00 154.00 35.00 310.00 562.50

3.204 For tank roof. m


3
50.00 62.00 70.00 100.40 50.00 154.00 35.00 310.00 562.50

3.205 For walkway. m3 50.00 62.00 70.00 100.40 50.00 154.00 35.00 310.00 562.50

3.206 For lantern roof and lantern column. m3 50.00 62.00 70.00 124.10 50.00 154.00 35.00 310.00 562.50

3.207 For walkway cantilever beam. m3 50.00 62.00 70.00 124.10 50.00 154.00 35.00 310.00 562.50

B3.2-5
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.

Page Total Carried to Summary of Sub-Bill No. 3.2

B3.2-6
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.

CONCRETE ANCILLARIES

Formwork - Fair Finish

All formwork shall be of wrought tounged and


grooved boards or playwood or metal panels.
The rates for all formwork shall include for
propping, struting, bracing, falsework, fillers,
rebates, boxing out and/or casting in pipes,
volts fittings, etc.

3.201 Pilecaps for columns. m2 45.00 65.00 52.00 77.30 45.00 85.00 50.00 34.00 75.00

3.202 Ground beams. m2 45.00 65.00 52.00 77.30 45.00 85.00 50.00 34.00 75.00

3.203 Intermediate beams. m2 45.00 65.00 52.00 77.30 48.00 100.00 50.00 34.00 75.00

3.204 Beams underside tank level. m


2
45.00 65.00 60.00 77.30 48.00 100.00 50.00 34.00 87.50

3.205 Column and stump. m2 45.00 65.00 52.00 77.30 50.00 100.00 50.00 34.00 87.50

3.206 External of reservoir wall. m2 45.00 65.00 60.00 77.30 52.00 100.00 50.00 34.00 87.50

3.207 Internal of reservoir wall. m2 45.00 65.00 60.00 77.30 52.00 100.00 50.00 34.00 87.50

3.208 Reservoir slab. m2 45.00 65.00 65.00 77.30 55.00 100.00 50.00 34.00 87.50

3.209 Roof tank. m2 45.00 65.00 65.00 77.30 55.00 100.00 50.00 34.00 87.50

3.210 R.C. staircase, intermediate landing platforms


and beams. m2 45.00 65.00 75.00 77.30 55.00 90.00
50.00 34.00 87.50

3.211 R.C. landing platform and support beam. m


2
45.00 65.00 75.00 77.30 55.00 100.00 50.00 34.00 87.50

3.212 Walkway around the tank. m2 45.00 65.00 75.00 77.30 55.00 100.00 50.00 34.00 87.50

B3.2-7
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.

Page Total Carried to Summary of Sub-Bill No. 3.2

B3.2-8
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.

3.201 Lantern and lantern column. m


2
45.00 65.00 75.00 77.30 60.00 90.00 50.00 34.00 87.50

3.202 Form small void for 300mm DN scour pipe


No. 150.00 250.00 150.00 236.90 150.00
opening, depth not exceeding 0.5m. 250.00 250.00 125.00

3.203 Form large void for 300mm & 400mm DN


outlet and outlet pipe opening, depth not No. 180.00 300.00 150.00 236.90 300.00 500.00
exceeding 0.5m. 250.00 500.00 125.00

3.204 Form large void for 300mm DN inlet pipe


opening, depth not exceeding 0.5m.
No. 150.00 300.00 150.00 236.90 300.00
250.00 250.00 250.00

3.205 Form large void for 400mm DN overflow pipe


opening , depth not exceeding 0.5m.
No. 180.00 300.00 150.00 236.90 300.00
300.00 300.00 375.00

3.206 Form large void for 1000mm x 1000mm


access opening at platform, depth not No. 270.00 500.00 300.00 355.40 500.00
exceeding 0.5m. 500.00 800.00 500.00

3.207 Form large void for 1200mm x 1200mm


lantern opening, depth not exceeding 0.5m.
No. 290.00 600.00 300.00 355.40 500.00
500.00 1,000.00 625.00

B3.2-9
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.

Page Total Carried to Summary of Sub-Bill No. 3.2

B3.2-10
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.

Reinforcement

Mild Steel to BS 4449

3.201 Nominal size 10mm and below. tonne 3,000.00 2,800.00 3,250.00 3,775.80 3,400.00 4,950.00 3,350.00 2,000.00 5,000.00

High Yield Steel to BS 4449

3.202 Nominal size 12mm and below. tonne 3,300.00 2,800.00 3,250.00 3,775.80 3,400.00 4,950.00 3,350.00 2,000.00 4,375.00

3.203 Nominal size 16mm and above. tonne 3,700.00 2,800.00 3,100.00 3,628.60 3,400.00 4,950.00 3,350.00 2,000.00 4,375.00

3.204 BRC A10 (BS 4483 or M.S 145) m2 60.00 25.70 28.00 21.40 36.00 17.00 25.00 28.00 31.25

Structural Joints

3.205 250mm wide eyeleted PVC waterstop without


central bulb between wall and base. m 60.00 81.00 60.00 106.60 50.00 99.00
50.00 60.00 100.00

3.206 250mm wide eyeleted PVC waterstop without


central bulb at wall.
m 60.00 81.00 70.00 106.60 50.00 99.00
50.00 60.00 100.00

3.207 250mm wide eyeleted PVC waterstop with


central bulb at base.
m 60.00 81.00 60.00 106.60 60.00 99.00
50.00 60.00 100.00

3.208 Surface joint, 2 layers of slip membrane of


width 0.30m.
m 70.00 50.00 80.00 29.60 45.00 66.00
50.00 6.00 50.00

B3.2-11
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.

Page Total Carried to Summary of Sub-Bill No. 3.2

3.201 Surface joint, seal 25mm x 25mm pliastic 99


joint sealing compound or equivalent for m 70.00 30.00 55.00 35.50 45.00 44.00 50.00 20.00 50.00
construction joint as shown on the drawing.

PRECAST CONCRETE

3.202 1350mm long x 150mm width x 75mm thk PC


cover slab for overflow/scour chambers. No. 45.00 23.00 40.00 106.60 150.00 55.00 1,200.00 80.00 125.00

MISCELLANEOUS METALWORK

B3.2-12
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.
3.203 Galvanised mild steel handrail of 50mm
diameter tubular section of 3.2mm thickness
and 1000mm high with stands spaced at m 150.00 133.00 170.00 177.70 180.00 154.00 50.00 500.00 262.50
1500mm apart complete with fixing
accessories as shown in drawing.

3.204 Stainless steel handrail of 50mm diameter


tubular section of 3.2mm thickness and
1000mm high with stands spaced at 1500mm m 250.00 328.00 220.00 236.90 400.00 528.00 50.00 500.00 750.00
apart complete with fixing accessories inside
the tank as shown in drawing.

3.205 Stainless steel ladder 2.2m high, stringer


50mm x 13mm thick 450mm apart, rungs
20mm dia. at 300mm centre complete with No. 3,500.00 1,553.00 3,500.00 3,079.70 5,000.00 3,500.00 1,200.00 6,250.00
fixing accessories inside the tank.

B3.2-13
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.

Page Total Carried to Summary of Sub-Bill No. 3.2

3.201 65mm x 65mm x 13mm thick stainless steel


angle section pipe bracket with fixing
accessories inside the tank as shown in No. 250.00 1,093.00 380.00 420.50 150.00 110.00 250.00 500.00 250.00
drawing.

3.202 Safety grating 1100mm square stainless steel


grating for outlet/auxiliary sump.
No. 1,200.00 914.00 1,350.00 1,396.50 1,500.00 1,320.00 150.00 1,000.00 2,500.00

3.203 Safety grating 1000mm square stainless steel


grating for scour sump.
No. 1,000.00 788.00 1,350.00 1,396.50 1,400.00 150.00 1,250.00 1,250.00

3.204 Plate flooring, stainless steel cover with frame


and handle and fixing accessories complete for No. 2,300.00 5,175.00 2,700.00 1,396.50 1,500.00 150.00 300.00 1,875.00
1000 x 1000mm opening.

3.205 Galvanised mild steel step iron. No. 60.00 35.00 35.00 40.30 60.00 55.00 150.00 25.00 87.50

3.206 65mm x 65mm x 13mm thick hotdipped


galvanised m.s angle section pipe bracket with
fixing accessories outside the tank as shown in No. 200.00 351.00 300.00 260.60 100.00 55.00 50.00 80.00 100.00
drawing.

PAINTING

B3.2-14
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.
3.207 Supply and paint exposed exterior surface of
reservoir column, staircase and etc. with one 2
m 15.00 10.00 12.50 11.80 20.00 15.00 25.00 50.00 25.00
coat of primer and two coats of arclyic paints.

3.208 Supply and paint surfaces in contact with


water with two coats of approved water 2
m 22.00 4.00 40.00 16.60 30.00 25.00 25.00 50.00 37.50
proofing agent.

3.209 Supply and paint non-toxic chemical resistant 2


paint for internal roof tank. m 17.00 10.00 27.00 23.70 36.00 20.00 35.00 50.00 43.75

3.210 To paint LAP logo, reservoir informations on


the reservoir, as per LAP standard.
No. 2,000.00 8,000.00 5,000.00 4,738.00 4,000.00 5,000.00 2,000.00 2,500.00

B3.2-15
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.
Page Total Carried to Summary of Sub-Bill No. 3.2

MISCELLANEOUS

3.201 Reservoir water tightness test complete with Lump


report. 7,000.00 2,500.00
Sum

3.202 Clean and disinfect tank as specified. Lump


3,000.00 1,250.00
Sum

3.203 Supply and install complete with paint


ventilation window in aluminium frame with
mosquito proof gauge and stainless steel mesh No. 900.00 300.00 500.00 237.00 500.00 400.00 1,000.00 1,500.00 625.00
fabric complete with fixing accessories.

3.204 To supply and install new reservoir


information board accordance to LAP No. 1,000.00 2,000.00 2,000.00 600.00 5,000.00 1,250.00
standard.

B3.2-16
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.

Page Total Carried to Summary of Sub-Bill No. 3.2

B3.2-17
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.

SUMMARY OF SUB-BILL NO. 3.2

B3.2-1

B3.2-2

B3.2-3

B3.2-4

B3.2-5

B3.2-6

B3.2-7

B3.2-8

B3.2-9

B3.2-18
KONTRAK NO. 9: MEMBINA DAN MENYIAPKAN SATU (1) BUAH TANGKI
MENARA KONKRIT BERKAPASITI 2.27ML DAN KERJA-KERJA
BERKAITAN DI JALAN SAW AH CHOY, TAIPING

BILL NO. 3 - 2.27 ML RESERVOIR


SUB-BILL NO. 3.2 - RESERVOIR WORKS
(ALL QUANTITIES ARE PROVISIONAL)
D:\Contoh BQ\[Lampiran E - Jadual A.xls]Bill3.2 ENGINEER'S ESTIMATE P 1/8 P 2/8 P 3/8 P 4/8 P 5/8 P 6/8 P 7/8 P 8/8
ITEM DESCRIPTION UNITS RATE RATE RATE RATE RATE RATE RATE RATE RATE
NO.

Total of Sub-Bill No. 3.2 Carried to Grand Summary

B3.2-19