You are on page 1of 8

ENERGYCON 2014 May 13-16, 2014 Dubrovnik, Croatia

Dynamic Behavior Analysis of Distributed


Generation in an Off-Grid Network with Power
System Simulator for Engineering (PSS/E)
Konstantina Mentesidi1, Student Member IEEE, Monica Aguado 1, 2, Member IEEE
1
Electrical and Electronic Engineering Department, Public University of Navarra, Spain
1
mentesidi.74525@e.unavarra.es
2
Grid Integration Department, National Renewable Energy Centre (CENER)
Ciudad de la Innovacion 7, 31621 Sarriguren-Spain
2
maguado@cener.com

Abstract The integration of distributed generation Undoubtedly, embedded generation aims to minimize power
technologies into distribution networks creates a number of losses as it is preferably allocated near the demand side,
technical issues. In order to analyze a grid and examine the whereas nearby node voltages are improved with the reactive
impacts of distributed power penetration, considerations such as power compensation. Voltage and reactive power are linked to
the dynamic behavior of powers systems that entails transient
a chicken-and-egg situation: Reactive power intake induces
stability analysis, grid capacity and limits characterization need
to be taken into account. Besides, this kind of study is very voltage dips in the system with generating plants or capacitor
important to ensure the networks secure operation under fault banks take part in this compensation. However, when the R/X
incidents. Although, in the current paper, Steady State and ratios of the system branches are high, the capability of
Dynamic Analysis configurations are proposed in order to reducing the losses is rather low and the loss effect is also
determine the allocation, maximum capacity of embedded depended on the penetration rate. With the integration of
generation that may be inhabited within a real island power dispersed generation in the grid is necessary to estimate the
system, emphasis is paid on the Dynamic Analysis configurations. expected disturbances beginning with those in the point of
In this way, it is possible to check the off-grid systems behaviour common coupling (PCC) due to a particular DG installation
under normal operation and against several disturbances onto
[2], [3].
the grid. Geothermal plants using basic machine model such as
synchronous generator, exciter and governor and Wind farms In addition, the question of power quality and DG is not
employing Doubly-fed Induction Generator (DFIG) technology outspoken. On the one hand dispersed generation unit can
were chosen throughout this research work. The adequate positively affect the power quality. For instance, embedded
stability margin of the system was investigated upon the fault generation can prove to have a positive effect on the voltage
ride through capability and frequency response of the network profile, especially on rather low voltage levels depending on
elements whereas among the most critical perturbations was a the penetration level [4], [5]. What is worthy to mention is
three phase fault application at the connection point of the wind that embedded plants extensively occupy rotating machines,
farm. Moreover, two different exciter models (IEET1 & EXST1)
with induction and synchronous generators increasing the
were chosen to perform open-circuit setpoint step tests and
record their field voltage and terminal voltage responses after fault level of the distribution system.
tuning application. PSSE software simulation tool of Siemens In order to analyse a power grid from an electrical point of
PTI will be utilized throughout this work. view, examine its stability and define the potential integration
of distributed generation into the grid, static and dynamic
Keywords: Dynamic Analysis; Distributed Generation; LV-grid; simulations need to be carried out [6]. Stability considerations
PSSE. can be divided into two case studies: the steady state stability
and dynamic stability analyses.
I. INTRODUCTION Steady-state analysis involves the calculation of power
There is no any universally approved definition of what flows on the network lines, transformers and the voltage
constitutes the embedded generation. In general speaking, all profiles of system bus bars. This study is very important for
the reviews seem to converge at least to the small-scale the planning and design of the connection of distributed
generation statement and that distributed energy resources generation to the transmission and distribution grid. N-1
(DERs) are ordinarily applied to the distribution system analysis is also essential in order to ensure the security and
voltages of 230/415 V up to 145 kV [1]. Heavy concern is reliability of power supply [7], [8]. Short circuit calculations
raised upon the effects that the connection of distributed introduce the proper selection of high voltage equipment and
generation (DG) to the low voltage (LV) networks 230/400 V protection relays.
may induce. On the other hand, a transient event occurs undesirably and
But which are the technical considerations for the instantly in a power system and can either be an oscillatory or
connection of dispersed technology into a power system? impulsive disturbance [7]. For instance, branches and bus

978-1-4799-2449-3/14/$31.00 2014 IEEE 1042


ENERGYCON 2014 May 13-16, 2014 Dubrovnik, Croatia

faults, line, loads and generators tripping may induce stepped down transformers. Moreover, it concentrates the
frequency, rotor angle as well as voltage oscillations and can highest load demanding on the 30 kV distribution network
lead to the failure of the distribution system where the system. The MV distribution network includes four 30/10 kV
embedded generation is planned to be connected to or even substations.
can cause damage to the power electronics equipment.
Therefore, a transient stability study is necessary to C. Network Branches
investigate the power system response to disturbances and The transmission branches in total thirteen, among which
check over its fault ride through capability to see if the the twelve are overhead and one is subterranean line, are all of
network elements have adequate stability margin [8]-[10]. them at different lengths. The 60 kV network is designated
The objective of the present study is to propose a method with conductors type of Cu 185 & 95 mm2. Distribution
for evaluating the potential areas in a practical off-grid power branches (72 in number of various lengths and types) up to 10
system, suitable for the introduction of distributed generation kV comprise a rather complex low voltage network thus their
into the network. Emphasis will be paid on the transient data wont be provided as is not the goal of the current study.
stability analysis of the system with the subsequent TABLE I
introduction of embedded generation units by analysing the POWER SOURCE PERCENTAGES, YEAR 2009
machine states namely; exciter response test, electrical,
mechanical, reactive power outputs, terminal voltage and so Power Installed Energy Power Plants
on after a three-phase fault incident at the respective Thermal 73.9% 59.49%
Geothermal 22.3% 36.59%
connection point. Therefore, in the current research, steady
Hydro 3.8% 3.92%
state and dynamic simulations are employed in an example
Total 132.694 (MW) 442 (GWh)
autonomous power grid that is a real distribution network.
PSS/E (version 31.0) [11] is the software tool that will be
utilized throughout this work. TABLE II
LOAD CONFIGURATION, YEAR 2009

Voltage nodes Pmax (Pmin) Qmax (Qmin)


II. STUDY CASE-DESCRIPTION OF THE ELECTRICAL SYSTEM (kV) MW MVAr
A. Power Plants 10 43.38 (22.46) 16.88 (8.43)
30 50.87 (41.05) 15.56 (10.96)
The power generation of this off-grid system consists of 1
central fossil fuel power station, of 2 geothermal power plants
and of 7 hydraulic power stations. Their general data are III. METHODOLOGY & THE PSS/E PLATFORM FOR POWER
presented in Table I, whereas in Table II represents the total SYSTEM ANALYSIS
maximum and minimum values of the active and reactive
parts of load demand at the different voltage nodes on a
characteristic summer day. The hydro total potential amounts The Siemens PTI PSS/E simulator is a software tool that
for 3.8% of the whole power capacity, thus is not taken into allows power flow, short circuit and dynamic modelling in an
account in the current work. integrated environment. The program is more than 30 years in
The transmission and distribution system consists of a commercial use and may solve problems of large and small
medium voltage (MV) Transmission Network at 60 kV and a scale. It is generally an acceptable instrument in the area of
low voltage (LV) Distribution Network with voltage levels of integration into the power networks [12].
30 and 10 kV. The system comprises of 1000 buses, however A. Driving Scenarios
it will be simplified due to convergence issues by
In the current study there were employed different
accumulating the feeders in the distribution substations.
scenarios regarding to the generation capacity, to the
Appendix illustrates the single line MV/LV network
renewable energy engagement and load demanding. The
scheme of the islanded power system with all the transmission
above scenarios were examined under two temporal time
branches connecting the power plants to the substation nodes
frames, one actual, of 2009 and one future time based on 2015.
and only some of the distribution branches are also
The electricity generation plan includes possible renewable
represented.
resource at the off-grid power system, like a plan to expand
In addition, node 1 CTCL-FPP (Appendix) of 60 kV was
geothermal and wind farms up to the year of 2015.
selected as the reference bus, the so-called slack or swing
Therefore, it was presumed a wind power installed potential
generator.
of 14 MW by 2015.
B. Substations Concluding we could loosely summarize the different
The MV Transport Network includes five 60 kV schemes to the ones beneath:
substations MV / LV (Appendix). These are stepped down Scenario 1, year 2009 base case
from 60 to 30 and/or 10 kV. The main networks substation is Scenario 2, year 2015 with additional geothermal
the SEFO since it is the only connected to the three systems power
power plants and to the distribution network through its three

978-1-4799-2449-3/14/$31.00 2014 IEEE 1043


ENERGYCON 2014 May 13-16, 2014 Dubrovnik, Croatia

Scenario 3, year 2015 with wind w energy and Each individual wind turbinne generates at 690 V and the
geothermal power. wind turbine generators (WT TGs) are connected to the
Table III illustrates the case summaryy results from the distribution MV bus bars of 300 kV and 60 kV by dedicated
power flow computations for the first two sccenarios. lines through their 0.69/30 and 0.69/60 kV step-up
transformers respectively. Thee wind generators aggregated
TABLE III operate for the 80% of their installed
i capacity. Power flow
POWER FLOW SUMMARY FOR MACHINE AND
D LOAD DATA
modelling data for the wind gennerators are shown in Table IV.
Active & Reactive Scenarrios TABL
LE IV
Power MW/MVAr 1 2 WIND TURBINE GE
ENERATOR DATA
Pthermal(Q) 74.8(22.3) 59.2(22.3)
Pgeothermal (Q) 20.7(8.5) 45.5(14.2) Symbol Values
Pdemand(Q) 94.3(32.4) 102.9(35) Qmax(Qmin) 0.65(--0.65) MVAr
Plosses(Q) 0.8(7.2) 1.1(8.9) Pmax(Pmin) 2(00.1) MW
Zsource j00.8 pu
B. Secure operation under critical contingeencies Mbase 2.1 MVA
The steady state and dynamic response off the studied power
system for the aforementioned scenarios is i evaluated by its In the current study three--phase symmetrical faults are
secure operation under both N and N-1 criteeria. (N-1) criterion calculated for the transmissionn and distribution substations
means that the system must withstand on itss own a loss of any nodes of the system rated at vooltages of 60, 30 and 10 kV for
single element. That means that all the liine flows must be all the Scenario cases. Short cirrcuit power calculation is based
below their limits not only for a given norm mal operating state, on (1).
but also when any of the lines is disconnecteed.
One of the biggest challenges in the cuurrent work was to = 3 I V LL S (1)
maintain the dynamic security not only att normal operating cc cc
state, but also following credible conttingencies, such as Where Scc is the three-phasee short-circuit power, Icc is the
short circuits, tripping a transmission line, and loss of a large short-circuit phase current in am
mps, and VLL is the line to line
unit that are presented in Section V. voltage in volts. Fig. 1 & 2 illlustrate the reactive losses and
According to the prerequisites for saafe operation, the the fault current values at the addition buses respectively as
voltage profile of the transmission and diistribution network resulted from the load flow simulations, including wind
and the transformer and non-transformer branches current energy in the power system. The parenthesis denotes the
loadings should follow the criteria beneath: voltage level in kV.
5% of the nominal voltage value (0.95-1.05 pu) and
10% of the nominal voltage for N-1 criteriion 9.4
80% is set as the maximum deffault value for the
Reactive Power Losses

branches loadings to be checked against their


t power ratings 9.2 Qlosses=8.9 MVAr
in the run time options. 9
(MVAr)

C. Systematic steps for DG penetration 8.8


Short circuit calculations define the pootential distributed 8.6
capacity that can be introduced into the grrid. Principally, the
main objective of such analysis is to checck the short circuit 8.4
power at every substation in order to evaaluate the available 8.2
4 11 13 27 30 31 33 35 44 45
space in terms of capacity to penetrate dispersed generation (60) (60) (30) (60) (30) (30) (30) (60) (30) (30)
units.
Scenario 2 8.9 8.9 8.9 8.9 8.9 8.9 8.9 8.9 8.9 8.9
These DG units are normally penetrated into the buses with
the highest short circuit capacity to induce the minor impacts Scenario 3 8.9 9.3 9 8.8 9.3 8.6 8.3 8.7 8.8 9
on the systems stability. In the current paper,
p two rules of Fig. 1. Reactive power losses wiith different DG nodal allocation
thumb were examined as where to addd the distributed
generation. Bus 35 (60 kV) seems to bee the most suitable among the
The former was to introduce these units u at the lower addition transmission node, wiith power losses minimised to
voltage buses and the latter to try to add wiind energy to buses 1.0 MW + 8.7 MVAr (Fig.1) and a a 206 A (Fig.2) increase in
with denominator the higher short circuitt capacity and the the 3-phase fault current. Inn addition, implementing the
high load demanding and at the meanw while obtaining the contingency analysis for this node,
n the results are smoother
minimum possible power losses. One moore criterion to be for a loss of one of its transporrt lines 60 /30 kV compared to
considered is that the wind potential to bee penetrated cannot the other buses.
surpass the 5% of the short circuit capacityy at the connection For the same reasons, among the distribution nodes the
point node (Spanish low voltage electrical regulations). most suitable to connect the winnd generators is bus 31 (30 kV).
Here, the short circuit current inncreases by 239 A (Fig. 2) and

978-1-4799-2449-3/14/$31.00 2014 IEEE 1044


ENERGYCON 2014 May 13-16, 2014 Dubrovnik, Croatia

power losses are minimised to 1.1MW + 8.6MVAr (Fig.1). details, the WT3 generic model [11] comprises of the modules
This could be abbreviated to the fact that wind generators as follows:
added via transformers 0.69/30 kV to that node are behaved as WT3G: generator/converter module
swing generators to balance apparent power throughout the WT3E: electrical control module
system. WT3T: mechanical control module
WT3P: pitch control module

5200
I (A)
4400

3600

2800

2000

1200
4 11 13 27 30 31 33 35 44 45
(60) (60) (30) (60) (30) (30) (30) (60) (30) (30)
Scenario 2 Scenario 3 Fig. 3. PSS/E DFIG Generic Model [11]

Fig. 2. Fault currents (A) at the addition buses, Scenarios 2 & 3

V. RESULTS AND DISCUSSIONS


IV. MODELING FOR TRANSIENT STABILITY ANALYSIS
A. Open-Circuit Set point Step Test
The dynamic data in PSS/E consists of parameter info for In this research, there were performed open circuit set point
generators, turbines, exciters, governors etc. The version 31 step tests for two exciter models namely, EXST and IEET1 to
provides with a dynamic model library for a DFIG variable identify the exciter that is not well-tuned. Throughout this
speed wind turbine. The most prevalent disturbance in order to simulation, each generator being tested is initialized to unity
check against the WTGs model response subjected to grid terminal voltage on open circuit. Furthermore, a simple step
disturbances is a 3-phase symmetrical fault on the change of 5% (typically from 0.01 to 0.05) is applied to the
interconnection bus. voltage regulator references and the resulting responses of
Throughout this work, it is considered that conventional field voltage and generator terminal voltage are observed. The
generators can offer primary regulation whereas the wind step magnitude should not exceed the 10% since the objective
generators cannot. In all the simulations the speed controller of this test is to examine small disturbance behavior.
value of conventional generators is adjusted, thus they can The excitation system IEET1 at bus 1-CTCL (swing bus) is
give 1.5% of their power potential if it is necessary. very oscillatory for KF=0.02 compared to EXST model for the
Moreover, dynamic modelling of conventional generators same synchronous machine (Fig.4). The typical tuning gain
concerns the definition of the standard generator model, the parameters of a rate feedback type excitation system are TF
AVR modeling (voltage regulation) and the governor model and, more particular KF. Fig. 4 to 6 illustrate the effects of
(speed control). According to the different generator types, exciter tuning on the field voltage and generator terminal
within the current study were chosen the appropriate models voltages for the different excitation systems. A value of
that are included in the PSS/E library: KF=0.08 pu is observed to yield an acceptable open circuit
Thermal power plants (for steam and/or gas response. IEET1 and EXST models are indicated as 1 and 2
turbines): GENROU round rotor generator, IEEG1 (IEEE- respectively in the following graphs.
1981) governor model, EXST1 (IEEE-1981) and IEET1 Fig. 7 depicts the blocks of the EXST excitation system in
(IEEE-1968) excitation model. PSS/E. The variable limiter has minimum and maximum
DFIG: In order to model this kind of technology is values of VTVRMIN-KCIFD and VTVRMAX-KCIFD respectively.
utilized the WT3 model of PSS/E that occupies doubly fed This limiter is operated as input of the generator terminal
induction generator. This technology allows inertia and speed voltage (VT) and filed current (IFD) including a constant
control, because the blades are decoupled from the generator, parameter KC.
whereas is connected to the grid via an AC/DC/AC converter From Fig. 4 & 5, it can be seen that the EFD voltage
. response for the EXST exciter model is very exact during the
The schematic figure (Fig. 3) below shows the interaction step signal being applied to the exciter set point and the final
among the generic control modules in a wind turbine. In more steady state profile has a good convergence characteristic.

978-1-4799-2449-3/14/$31.00 2014 IEEE 1045


ENERGYCON 2014 May 13-16, 2014 Dubrovnik, Croatia

B. Testing the DFIG into the Off-Grid network


In order to test the wind turbines riding through capability
over perturbations, a bolted 3-phase symmetrical fault was
applied on the distribution connection point of the wind farm,
1 bus 31 (SEVF, Appendix) rated at 30 kV. The fault is applied
one second after the initiation of the simulation lasting for 200
milliseconds. This time corresponds to 9 cycles for the 50 Hz
system and the total simulation time was defined at 20 s.
2
Fig. 8 represents that during the fault on the 30 kV
interconnection point, the voltage at addition bus drops to zero,
whereas the terminal voltage of the wind turbine bus
depresses by almost 90% reaching the value of 0.1 pu. It was
expected that the voltage reduction in the WT terminal bus
Fig. 4. Field voltages for IEET1 & EXST exciter models
would follow the same pattern as for the faulted node;
however the minimum terminal value for the former is higher.
After fault, at 1.2 seconds, both sites gradually recover to 1 pu.
2 The 90% voltage depression can be attributed to the fact that
the wind turbine generators are directly connected to the
1 faulted bus via transformers and are not stood off from it.
1

2
ETERM WF

VOLT SEVF
Fig. 5. Effect of exciter tuning for IEET1 & EXST excitation models

ETERM Fig. 8. Voltage response for WTG terminal & 30 kV Wind Farm busbar after
a 3-phase fault incident.

Fig. 9 shows the mechanical, pitch angle, and electrical


EFIELD outputs of the wind turbine generators during the short circuit
occurrence. Examining the active power response, is
observed that during the fault, the rotor speed increases giving
a negative slip and starts to accelerate. Actually, there is a
difference among the electrical and mechanical power, where
the former tends to be zero (decrease). Mechanical power at
the beginning remains the same and after the fault starts to
oscillate causing mechanical stress in the drive train system.
The pitch module responds by altering the blade pitch angle
(increases) during the fault in order to reduce the mechanical
Fig. 6. Field and terminal voltage responses for IEET1 exciter model
power. Both, electrical and mechanical outputs are reduced
during the fault event and their oscillations last about 5 s,
where the generator tries to restore its pre-fault value.
The wind farm generates active power immediately after
the fault incident and helps to keep it in operation during the
fault sequence.
Frequency increases (Fig. 10) during the fault time as rotor
speed increases to minimize the drive-train loads due to
mechanical stress. Oscillations last up to 5 seconds where both
Fig. 7. EXST exciter model in PSS/E [11]
locations restore their initial value. In addition, variations in

978-1-4799-2449-3/14/$31.00 2014 IEEE 1046


ENERGYCON 2014 May 13-16, 2014 Dubrovnik, Croatia

frequency figures do not overpass the 0.2 Hz with the C. Loss of one large power unit (CTCL-FPP swing bus, 60
minimum value being at 49.8 Hz. kV)
The figures beneath (Fig.111-13) illustrate the system
correspondence after such a losss. The variations in frequency
(Fig.11) at the transmission suubstation nodes during transit
oscillations are lower than 0.2225 Hz, whereas the established
frequency in 20 seconds reacches approximately the value
49.9 Hz. Voltages (Fig.12) during
d the perturbation time
remain over the 98% of the noominal value (0.9875 pu) and
after that period of time reccover to a new steady state
condition. It was truly accepted that the remaining
conventional and dispersed maachines need to increase their
output to compensate for the looss of a generator unit. Fig. 13
shows these active power outpuuts of the remaining generation
units during the fault occurrencee.

Fig. 11. Frequency deviation at the transmission substation nodes after a


slack generator loss

VOLT [SEFO 60 kV]

Fig. 9. Transient responses of the WTGs durinng the fault incident

VOLT [SEPD1 60 kV]]

WT Terminal Node

Fig. 12. Voltage deviation at the transpport substations after a slack generator
loss
WF Connection Nodee

D. Loss of the transmission linee CTCL-SEFO rated at 60


As it can be easily seen froom Fig. 14, the voltage drops
Fig. 10. Frequency deviation at the wind farm (W
WF) connection node & slightly for all the substation noodes with the highest dip being
WT terminal noticed at the terminal bus of thet tripped line, SEFO rated at
60 kV.

978-1-4799-2449-3/14/$31.00 2014 IEEE 1047


ENERGYCON 2014 May 13-16, 2014 Dubrovnik, Croatia

FREQ [SEPD1 60 kV]


P [BUS 95 (10 kV)]

P [BUS 96 (11 kV)]


FREQ [SEPD1 60 kV]

Fig. 15. Frequency disturbance at the transport substations after a


Fig. 13. Power outputs of the generation units in operation during the fault transmission line loss
incident
Focus was concentrated upon wind power and geothermal
Nevertheless, in all cases the reductions do not fall under installations. To achieve this objective it was necessary to
impermissible values (2%). Fig. 15 depicts the frequency accomplish load flow, contingencies (N-1), short circuit and
deviation at the transport substation nodes during the fault dynamic analyses. PSS/E version 31.0 software tool and its
incident. It fluctuates with peaks below zero during the line wind turbine model WT3 are used for simulations throughout
tripping and a new steady-state is also obtained under zero this work. Moreover, the effect of tuning and open-circuit
value, shortly after 9 seconds. The frequency drops, because a testing of two different excitation model systems was
generator is lost and the others will supply to share the load. investigated.
The remaining generators governor speeds will decrease due There were defined three case Scenarios to check the
to lower droop contribution and set a new steady frequency systems voltage and frequency stability with the addition of
below its nominal figure established at 49.999 Hz. The 25.77 and 14 MW of geothermal and wind power respectively.
biggest frequency oscillation belongs to SEPD1 60 kV Wind power inclusion under specific scattering and
substation bus, but all remain within the permissible limits. connection topology does not affect the electrical system and
reduce the losses. Nevertheless, the impact on power losses is
minimal in all cases as the amount of power added was small
compared to the total system handling capacity.
Short circuit analysis showed that the penetration of wind
power and generally of distributed generation raises the short
VOLT [SEFO 60 kV]
circuit level. Especially, a 3- phase fault implemented at the
connection node of the wind farm increases the current at the
addition bus and to the ones interconnected to it via branches.
Moreover, the wind farm as introduced to this electrical
system remains connected under voltage dips caused during
the fault on the transmission and/or distribution voltage
connection node.
Additional fault incidents were implemented such as the
loss of a swing generator and of an important transmission
line. The results showed that the voltage and frequency
behaviour at the transmission substations does not fall under
impermissible values, while they are soon after the fault
Fig. 14. Voltage responses at the transport substations after a transmission clearing reset to their initial conditions.
line loss

VI. CONCLUSION ACKNOWLEDGMENT


This research work evaluates the potential areas in a The research leading to these results has received funding
practical off-grid power system, suitable for the introduction from the European Union Seventh Framework Programme
of distributed generation into the network from the point of (FP7/2007-2013) under grant agreement n 608593.
view of transient stability analysis.
REFERENCES
[1] G. Pepermans, J. Driesen, et.al., Distributed generation: definition,
benefits and issues, Energy Policy , vol. 33, pp. 787-798, 2005.

978-1-4799-2449-3/14/$31.00 2014 IEEE 1048


ENERGYCON 2014 May 13-16, 2014 Dubrovnik, Croatia

[2] S. Ropenus and K. Skytte, Regulatory revieew and barriers for the [8] N. Hemdan and M. Kurrat, Innfluence of distributed generation on
electricity supply system for distributed generation in EU-15, IEEE different loadability aspects off electric distributions systems, 20th
International Conference on Future Power Systems, 2005, 6 pp.-6. International Conference on Ellectricity Distribution, CIRED, paper
[3] S. Papathanassiou and N. Hatziargyriou, Techhnical requirements for 0255, Prague, 8-11 June 2009.
the connection of dispersed generation to thee grid, Electric Power [9] L. Yazhou, A. Mullane, G. Lighttbody and R. Yacamini, Modelling of
Systems Research 77, 2007, pp. 24-34. the Wind Turbine with a Doubbly Fed Induction Generator for Grid
[4] T. Tuerkucar and D. Gailey, Survey Study off Status and Penetration Integration Studies, IEEE Transsactions on Energy Conversion, vol. 21,
Levels of Distributed Generation (DG) in Europe E and the US), No.1, March 2006.
<http://www.distributedgeneration.gov.uk/docum ments/27_10_2003_06 [10] M. Emranjeet and I. Syed, Sttability Considerations of Distributed
_05_2003_kel_00306-partone.pdf> DTI, Date accessed:
a 19/01/2006. Power Systems with Low Innertia Generators, in International
[5] P. Dondi,, D. Bayoumi, C. Haederli, D. Julian and
a M. Suter, Network Conference on Communication,, Conference & Power (ICCCP07),
integration of distributed power generation, Joournal of Power Sources Muscat, February 19-21, 2007.
106, 2002, pp.1-9. [11] PSS/E-31 Program Operational Manual,
M Siemens Power Technologies
[6] A. Mohamad, N. Hashin, N. Hamzah, N. Ismail and M. Latip, Inc.
Transient Stability Analysis on Sarawaks Grrid using Power System [12] High -Performance Transmissionn Planning Application for the Power
Simulator for Engineering (PSS/E), in IEEE Symposium
Sy on Industrial Industry. Siemens PTI PPS S/E. Availabe at: https://www.pti-
Electronics and Applications, 2011, pp. 521-5266. us.com/pti/software/psse/university/index.htm.
[7] I.D. Margaris et. al., Methods for evaluatingg penetration levels of
wind generation in autonomous systems, in IEEE I Bucharest Power
Tech Conference, June 28th-July 2nd 2009, pp.7.

APPENDIX

Single line MV/LV network representatioon in PSS/E

978-1-4799-2449-3/14/$31.00 2014 IEEE 1049

You might also like