Professional Documents
Culture Documents
OCTOBER, 2012
DOCUMENT NUMBER:
FYP-NG01009296-YOKA1-RA-6068-00003
APPROVAL
Proprietary Information: This document contains proprietary information and may not be partly or wholly reproduced without prior written
permission from Shell Limited
Revision Philosophy
Revisions for review will be issued at R01, with subsequent R02, R03, etc as required.
All revisions approved for issue or design will be issued at A01, with subsequent A02, A03, etc as required.
Documents approved for Construction will be issued at C01, C02, C03, etc as required
Documents or drawings revised as As built will be issued as Z01, Z02 Z03 etc as required
Narrative sections revised from previous approved issues are to be noted in the table below and/or highlighted in the RH
margin (using the appropriate revision status) thus: A02
Previous revision highlighting to be removed at subsequent issues.
Drawings/diagrams revised from previous approved issues are highlighted by 'clouding' the affected areas and by the use of a
triangle containing the revision status.
If a document is cancelled the document will be issued at the next sequential number and suffixed with a X. For example if R02
is the current revision then X03 will be the Cancelled revision
All revisions to this document must be approved by the relevant Technical authority
Revision History
CONTENTS
1.0 SCOPE.4
2.0 PURPOSE...4
5.0 RESPONSIBILITIES..4
6.1 MATERIALS............................................................................................................5
1.0 SCOPE
This procedure is applied to the painting of all piping, structural steel, bends and pipe
fittings, valves, machinery and other steel equipments subjected to corrosion by
atmospheric environment in this project.
This procedure is to be applied in conjunction with other applicable project specification,
procedure, drawing and manufacturers instruction
The method statement shall describe the method of blasting of pipes and painting of pipes,
structural skids, vessels and tanks in accordance with applicable codes and standards for
Forcados Yokri Integrated Completion Project onshore.
2.0 PURPOSE
The purpose of this procedure is to provide requirement and responsibilities for painting
activities which should be followed till the end of this project.
PROJECT SITE: FYIP Onshore Completion Works For Yokri Flow station.
Location where work is to be performed.
5.0. RESPONSIBILITIES
Project Manager
The Project Manager ensures adequate provision of all the resources needed for the
successful execution of the work scope.
He ensures that experienced and skilled persons are involved in the execution of the work
scope. He is responsible for managing HSE for these operations.
QA/QC Engineer
QA/QC Engineer shall be responsible for control and verification of the implementation of
this method statement.
He shall be responsible for all quality control and quality assurance functions.
Site Engineer
He ensures that the job is carried out in a professional manner and on schedule. He
manages and coordinates the resources provided.
Safety Officer
He is responsible for validity and re-validity of Permit-to-Work (PTW) before
commencement of work and makes it readily available on site for sighting of Shell
Representative(s) and NATONY LIMITED QA/ QC team.
He assists the Site Engineer to ensure that all personnel adhere strictly to the safety rules
and regulations.
6.1 MATERIALS
a) PAINTS
All paints and paint materials to be used shall be obtained from manufacturers
approved by SPDC.
All material shall be supplied in the manufacturers original containers, durably and
legibly marked with the description of the contents. This shall include the
specification number, the colour reference number, the method of application for
which it is intended, the batch number, date of manufacture, the shelf-life expiry
date and the manufacturers name or recognized trade mark.
The storage and preparation of paints and other coating materials shall be in
accordance with the manufacturers instructions.
b) ABRASIVES
Abrasives to be used in blast cleaning all pipes, plates etc shall be as specified in
ISO 8504-2. Suitable abrasive are:
- Chilled iron grit or shot .
- Steel and malleable iron grit or shot.
- Non-metallic abrasive (aluminium oxide, copper, slag, garnet, etc).
For height above two (2) meter, erect scaffolds to form platforms for grit blasters. Fill grit
pot with grit via sieve. Connect compressor unit and two blasting guns via hoses to two
grit pots. Put on compressor unit with valves in closed position.
Operators and grit blasters shall kit-up with their safety gears, which includes blasting
aprons, coveralls, safety boots, hand gloves, ear muff and eye goggles, prior to blasting
operation.
Note:
Dead manhandle to be connected along with blasting hose to the blaster for safely
operation.
After grit blasting of pipes, and structures they shall be primed with the appropriate primer
within 4 hours of abrasive cleaner application.
The paint shall be applied in accordance with the manufacturers product data sheet,
which shall include the mix ratio, the method of application, the use of thinners and over
coating times.
Areas with inadequate coating thickness shall be thoroughly cleaned, and if necessary,
abraded, and additional compatible coats shall be applied until they meet the required film
thickness.
Painting shall not be performed when the temperature of the surface is less than 3 oC
above the dew point of the surrounding air or when the relative humidity of the air is
greater than 85% unless local conditions dictate otherwise and SPDC is in agreement.
If condensation, rain, dust or other foreign materials contaminate the surface of a paint
coating, which is not dry to the touch, the paint shall be removed, the surface re-cleaned
and fresh paint applied in accordance to DEP 30.48.00.31.
g) At site, painting of all pipe spools, vessels and skids shall commence after the completion
of all installation works.
h) The recommended coating system shall be as per DEP 30.48.00.31-GEN, jan09 table 7
for new structures made of carbon steel and table 12 for maintenance coating system.
i) Spray painters shall be fully kitted with their safety gears, which include nose masks,
protective clothing, safety boots, hand gloves and eye goggles prior to painting operation.
Note:
All surfaces shall be cleaned and dried before application of paint.
Wet film thickness shall be determined using wet comb, while dry film thickness shall be
determined using Electrometer.
6.4.3 ADHESION
The adhesion of the primer to the steel substrate and the inter coat adhesion of the
subsequent coat(s) after curing shall be determined by the application of either a cross-
cut test in accordance with ISO 2409 or a pull-off test in accordance with ISO 4624.
Prior to final acceptance of the paintwork, an inspection shall be made and Natony
Limited and SPDC shall both be represented and they shall sign an agreed inspection
report. A sample of this inspection report is attached to this document.
PROJECT: LOCATION:
CLIENT: DATE OF WORK:
ITEM DESCRIPTION:
MATERIAL CONDITION:
EQUIPMENT / TOOLS USED:
INSTRUMENT USED:
WEATHER CONDITION:
PAINTING PERIOD:
SURFACE CONDITION:
CONDITION AFTER SURFACE PREPARATION:
PAINT APPLICATION TECHNIQUE (S):
TYPE OF QUALITY CONTROL CHECKS:
1. WFT 3. SURFACE CONTAMINATION
2. DFT 4. ADHESION
RESULT / COMMENT:
DATE: __________
DATE : __________