Professional Documents
Culture Documents
On Appeal from the United States District Court for the District of Columbia
(Richard J. Leon, District Judge)
________________________
BRIAN E. FROSH
Attorney General of Maryland
ERIC D. MILLER ALBERT M. FERLO JULIE SWEENEY
Perkins Coie LLP Perkins Coie LLP Assistant Attorney General
1201 Third Avenue 700 Thirteenth Street, Maryland Transit Administration
Suite 4900 NW Suite 600 6 St. Paul Street, Suite 1200
Seattle, WA 98101-3099 Washington, D.C. 20005 Baltimore, Maryland 21202
Telephone: 206.359.3773 Telephone: 202.654.6200 Telephone: 410.767.3844
Facsimile: 206.359.4773 Facsimile: 202.654.6211 Facsimile: 410.333.2584
emiller@perkinscoie.com aferlo@perkinscoie.com jsweeney@mta.maryland.gov
Attorneys for State of Maryland
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 2 of 72
court and are appellees in Case Nos. 17-5132, 17-5161, and 17-5174 and cross-
appellants in 17-5175.
Transportation, the United States Fish and Wildlife Service, and the United States
Department of the Interior were defendants in the district court and are appellants
The State of Maryland was the defendant-intervenor in the district court and
The amici curiae in the district court proceeding were Prince Georges
i
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 3 of 72
35), Order dated August 3, 2016 (JA 436-37), Opinion dated November 22, 2016
(JA 661-71), Order dated November 22, 2016 (JA 672-73), Opinion dated May 22,
2017 (JA 818-29), Order dated May 22, 2017 (JA 830), Final Judgment dated May
30, 2017 (JA 836-37), and Opinion dated June 9, 2017 (JA 929-52) issued by
Judge Richard J. Leon in the United States District Court for the District of
14-1471 (D.D.C.).
5161 and 17-5174, and Plaintiffs appeal, Case No. 17-5175 with this case.
1
JA refers to the Joint Appendix filed with this Court on August 18, 2017.
ii
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 4 of 72
TABLE OF CONTENTS
Page
GLOSSARY.............................................................................................................ix
iii
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 5 of 72
TABLE OF CONTENTS
(continued)
Page
iv
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 6 of 72
TABLE OF AUTHORITIES
PAGE(S)
CASES
Alaska Wilderness Recreation & Tourism v. Morrison,
67 F.3d 723 (9th Cir. 1995) ................................................................................26
*Allied-Signal, Inc. v. U.S. Nuclear Regulatory Commn,
988 F.2d 146 (D.C. Cir. 1993) ................................................................32, 33, 39
Apache Corp. v. F.E.R.C.,
627 F.3d 1220 (D.C. Cir. 2010) ..........................................................................33
Black Warrior Riverkeeper, Inc. v. U.S. Army Corps of Engineers,
781 F.3d 1271 (11th Cir. 2015) ..........................................................................33
California Communities Against Toxics v. E.P.A.,
688 F.3d 989 (9th Cir. 2012) ..............................................................................40
v
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 7 of 72
TABLE OF AUTHORITIES
(continued)
PAGE(S)
vi
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 8 of 72
TABLE OF AUTHORITIES
(continued)
PAGE(S)
Simpson v. Young,
854 F.2d 1429 (D.C. Cir. 1988) ..........................................................................30
STATUTES
5 U.S.C. 706(2)(A)................................................................................................19
16 U.S.C. 703 - 712 ............................................................................................10
vii
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 9 of 72
TABLE OF AUTHORITIES
(continued)
PAGE(S)
RULES
Fed. R. Civ. P. 59(e).........................................................................11, 17, 36, 37, 40
REGULATIONS
23 C.F.R. 771.130 .................................................................................................31
viii
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 10 of 72
GLOSSARY
EIS Environmental Impact Statement
ix
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 11 of 72
JURISDICTIONAL STATEMENT
The district court had jurisdiction under 28 U.S.C. 1331 and issued a final
judgment disposing of all claims on May 30, 2017. (JA 836.) The State of
Maryland filed a timely notice of appeal on May 30, 2017. (JA 838.) This Court
accordance with law, and not arbitrarily and capriciously, when it concluded that a
issues was not required by the National Environmental Policy Act and the agencys
implementing regulations?
2. If the Court affirms the district court on issue 1 above, did the district
court abuse its discretion when it vacated the Federal Transit Administrations
Record of Decision?
will provide fast and reliable east-west transit service in and between Montgomery
and Prince Georges counties in Maryland. (JA 1027.) The Project is being
1
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 12 of 72
With 21 stations, the Purple Line will greatly improve public transit connections
campus at College Park, and New Carrollton. (JA 1206-07.) Four of the Purple
state, local, and regional transportation and land use plans, including the
carried out by Montgomery County in the 1970s, when the County first adopted a
master plan calling for a transit line connecting Bethesda to Silver Spring via the
Georgetown Branch a freight rail corridor then still in active use for carrying coal
trains to Georgetown in Washington, D.C. (JA 1206.) Over the next several
decades, the County refined its plans. Eventually, after the corridor ceased to be
used for freight rail traffic, the County purchased the Georgetown Branch right-of-
2
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 13 of 72
local, regional, and statewide studies, the Project evolved into a proposal to
develop a new east-west transit line between Bethesda in Montgomery County and
In parallel with the NEPA process, Maryland applied to FTA for a grant under
FTAs New Starts program for capital investment grants, 49 U.S.C. 5309(d).
notice announcing its intent to prepare an EIS for this proposed high capacity
transit project. (JA 1074.) The notice identified the Projects several goals,
2
Since acquiring the Georgetown Branch right-of-way in the mid-1990s,
Montgomery County has allowed the right-of-way to be used on an interim basis as
a recreational trail while awaiting construction of the transitway and a permanent
recreational trail. (JA 1070-71.)
3
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 14 of 72
the Metrorail radial lines, as well as to other rail or bus services in Montgomery
alternatives for detailed analysis. (JA 1235.) These included an alternative that
constructing a new busway largely separate from lanes carrying automobile traffic
(the Bus Rapid Transit Alternatives); and three alternatives that involved
building a new light rail transit line, also largely separate from existing traffic lanes
(the Light Rail Alternatives). Id. The three Bus Rapid Transit Alternatives and
the three Light Rail Alternatives each involved three distinct levels of investment:
Low, Medium, and High. 3 (JA 1235-36.) The Bus Rapid Transit and Light Rail
Alternatives generally followed similar routes and had essentially the same
3
A higher investment level corresponded to more construction of new
structures to separate the transitway from road traffic, which in turn corresponded
to higher speeds for transit vehicles. (JA 1235-36.)
4
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 15 of 72
footprint and number of stations, except that one of the Bus Rapid Transit
alternatives in depth, weighing their relative costs, impacts, and benefits. (JA
1233.) They conducted hundreds of public meetings across the 16-mile corridor.
(JA 1212.) After more than five years of study, they released an Alternatives
Analysis/Draft EIS (Draft EIS) in September 2008. (JA 1213, 1077-90.) The
Draft EIS presented all eight alternatives in an equivalent level of detail and did
not express a preference among them. (JA 1084-86.) The Agencies accepted
comments on the Draft EIS for 90 days twice the length of time required by
regulation and held four public hearings. (JA 1208, 1213.) The Agencies
considered more than 3,300 comments on the Draft EIS. (JA 1208, 1213, 1486.)
and comment on every EIS, gave the Draft EIS its highest rating: LO-1, which
means a lack of objection to the project and that the document itself is complete.
(JA 1558.1.) The agency also noted that [e]nvironmental impacts of each
process, conducted concurrently with the NEPA process, requires the project
5
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 16 of 72
5309(d)(2)(A)(i); see also 49 C.F.R. 611.105. After the comment period for
the Draft EIS closed, Maryland identified a Light Rail Alternative as its Locally
several factors as the basis for adopting a Light Rail Alternative rather than a Bus
accommodate long-term growth, and light rails greater consistency with the land
Maryland also noted that the other alternatives No Action and the Transportation
System Management Alternatives were not selected because they would not
granted approval for Maryland to advance its Locally Preferred Alternative into the
4
The statute that defines the required steps in the New Starts process 49
U.S.C. 5309 was amended on July 6, 2012, by enactment of the Moving Ahead
for Progress in the 21st Century Act (MAP-21), Pub. L. No. 112-141 (July 6,
2012). Prior to MAP-21, the required steps were preliminary engineering and
final design. As redefined by MAP-21, the required steps are project
development and engineering. See 49 U.S.C. 5309(d)(2)(A); see also 78 Fed.
Reg. 1992 (Jan. 9, 2013) (FTAs final rule implementing MAP-21 changes to the
New Starts project development process).
6
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 17 of 72
The Final EIS. In August 2013, after an additional five years of analysis
and public outreach, FTA issued the Final EIS. (JA 1205.) The Final EIS
EIS. (JA 1231.) The Final EIS also included updated transit ridership forecasts for
the Purple Line. These forecasts were developed in accordance with FTAs
rigorous standards for ridership forecasts used both in NEPA and in New Starts
that nearly three quarters (73%) of Purple Line trips in 2040 would not include
transfers to or from Metro. (JA 1270.) In addition, the Final EIS summarized and
responded to the 3,300 comments addressing the Draft EIS. (JA 1208, 1486.)
Although not a requirement, FTA invited comments on the Final EIS and received
nearly 1,000 additional comments. (JA 1059-60.) None of those comments raised
an issue concerning the effect of Metrorail ridership or safety issues on the Purple
Line.
The Record of Decision. On March 19, 2014, FTA issued its Record of
Decision, explaining its rationale for approving the Purple Line as a light rail
project. (JA 1027-58.) The Record of Decision included FTAs responses to all
substantive comments on the Final EIS. (JA 1059-60.) On March 31, 2014, FTA
7
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 18 of 72
published a notice in the Federal Register announcing that the Record of Decision
was a final agency action for purposes of judicial review. 79 Fed. Reg.
18,113. That notice initiated a 150-day statute of limitations period, which ended
2119, 2166, 2375.) With input from MTA, FTA systematically reviewed and
FTA in June 2014, asserting that a supplemental EIS was needed to evaluate new
the Hays Spring amphipod in the vicinity of the Purple Line. (JA 2088-109.)
The Agencies met with Plaintiffs and consulted with the U.S. Fish and Wildlife
Service. (JA 2111.) Maryland engaged an expert on the subject to review and
investigate Plaintiffs claims and provide his expert opinion. (JA 2113.) After
considering this information, the Service confirmed that the Hays Spring
amphipod was not present in the vicinity of the project and that the Project would
have no effect on that species. (JA 2112.) Based on that determination, FTA
8
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 19 of 72
concluded, in May 2015, that a supplemental EIS was not needed on this issue.
(JA 2118.)
letter to FTA in July 2015, asserting that a supplemental EIS was needed to address
various cost-saving changes made to the design of the project. (JA 2119-34.) To
assist FTA, Maryland prepared a detailed report describing each specific design
change that Maryland had adopted as part of its effort to minimize project costs
and explaining why the design changes would not cause any significant change in
determined that those cost-saving changes did not require a supplemental EIS. (JA
2164-65.)
submitted to FTA a third letter, repeating the previous arguments about amphipods
and design changes, and also introducing a host of new arguments on a variety of
topics. (JA 2166-74.) The letter included several declarations from purported
experts challenging the Agencies ridership forecasts and questioning the funding
plan for the Purple Line. (JA 2175-83, 2196-201, 2202-07.) This letter also
asserted, with little explanation or evidence, that newly emerging problems on the
prepare a supplemental EIS for the Purple Line. (JA 2167-68.) MTA submitted to
9
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 20 of 72
FTA a written response addressing each issue raised by Plaintiffs. (JA 2221-57.)
In January 2016, after considering Plaintiffs letter and Marylands response, FTA
again determined that a supplemental EIS was not required to address any of the
FTAs Record of Decision. (JA 428.) Over the course of the next year and a half,
Plaintiffs filed an amended complaint and then two supplemental complaints. (JA
complaints expanded the scope of the lawsuit to include challenges to FTAs three
supplemental EIS.
In early 2016, the parties filed cross-motions for summary judgment. (JA
262-77, 278-90.) In late July 2016, while those motions were pending, Maryland
and FTA announced that the Full Funding Grant Agreement for the Project would
be executed on August 8, 2016. (JA 801 at 25.) The execution of a Full Funding
5
The complaint also included claims against FTA under the Endangered
Species Act, 16 U.S.C. 1531 - 1541, and the Migratory Bird Treaty Act, 16
U.S.C. 703 - 712, and included additional claims against the U.S. Fish and
Wildlife Service under the Endangered Species Act. The district court ruled
against the Plaintiffs on all of those claims. (JA 836-37, 929-52.)
10
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 21 of 72
Grant Agreement marks the culmination of FTAs New Starts grant application
process.6
On August 3, 2016, days before the grant agreement was to be signed, the
addressing a single issue raised by Plaintiffs and reserving judgment on all other
issues raised in the cross-motions for summary judgment. (JA 427-35, 436-37.)
The court found that FTA had erred in January 2016 when FTA determined that a
supplemental EIS was not required to assess the potential for recent Metrorail
ridership declines and safety issues to affect ridership on the Purple Line, and it
ordered FTA to prepare a supplemental EIS on the Metrorail issue. (JA 427-35,
436-37.) In its August 3 Order, the court also vacated FTAs Record of Decision,
without finding any flaw in the Record of Decision itself. (JA 435.)
On August 23, 2016, the Agencies filed motions to alter or amend the
district courts August 3 Order. (JA 453-73, 483-86.) They asked the court to (1)
allow FTA to decide in the first instance whether any new information concerning
the Metrorail system required preparation of a supplemental EIS and (2) reinstate
the Record of Decision while that additional analysis was prepared. In support of
6
The State has requested a New Starts grant of $900 million. (JA 800-01 at
23.) This amount is less than half of the approximately $2.4 billion needed for
construction of the Purple Line. (Id. 26.)
11
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 22 of 72
addressing future Metrorail ridership scenarios and their potential effects on Purple
37 (Allen).) With its reply memorandum, FTA submitted another expert witness
(Garliauskas).)
granting in part and denying in part the Agencies motions to alter or amend the
judgment. (JA 661-73.) The district court modified its previous order to allow
FTA to make its own assessment of the need for a supplemental EIS (JA 672-73),
but denied the request to reinstate the Record of Decision. (JA 670-71.)
Order, MTA worked with FTA to assess the potential effects of Metrorail ridership
and safety issues on the Purple Line. This work occurred over the next several
2016, Maryland submitted a 35-page report to FTA analyzing Metrorail safety and
12
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 23 of 72
ridership issues in relation to the Purple Line (November 2016 Report). (JA
the full range of possible declines in Metrorail ridership, ranging from a near-term
ceased to exist (Scenario 5). (JA 2359-60.) The purpose of Scenario 5 was to
take uncertainties about future Metrorail ridership entirely out of the assessment of
MTAs November 2016 Report examined how each of the five scenarios
would affect the environmental impacts analysis in the Final EIS, the Purple Lines
ability to meet the Purpose and Need for the Project identified in the Final EIS, and
the basis for selection of a Light Rail Alternative as the States Locally Preferred
Alternative. (JA 2362-72.) MTAs November 2016 Report explained that even
extreme and unrealistic assumptions about future Metrorail ridership did not
option as its Locally Preferred Alternative. (JA 2373.) The report concluded that
the recent Metrorail ridership and safety issues do not constitute the type of new
would require preparation of a supplemental EIS under the criteria set forth in
13
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 24 of 72
to FTA a fourth letter, identifying several old and some new issues and asserting
EIS on the Metrorail issue. (JA 2375, 377-80.) Attached to this letter were 287
pages of documents, ranging from news articles to blog posts. (JA 2381-87.) The
attachments to the letter also referenced the three declarations that Plaintiffs had
previously submitted to the district court in September 2016, which MTA and FTA
had considered and responded to in the litigation. (JA 2381.) Plaintiffs letter did
not expand upon the content of the three declarations nor did it explain why they
December 7, 2016, MTA submitted to FTA a response addressing the issues raised
issued a determination finding that the Metrorail ridership and safety issues did not
November 2016 Report, Plaintiffs fourth letter and attachments, and MTAs
response to that letter. (JA 2420.) FTAs December 2016 Determination reviewed
the five scenarios analyzed in MTAs November 2016 Report and concluded that
all three elements of the Projects Purpose and Need would be met under the first
14
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 25 of 72
four scenarios, in which Metrorail ridership declines to varying degrees but the
unlikely fifth scenario, in which Metrorail transfers to and from Metrorail and the
Purple Line would fall to zero, FTA found that the Purple Line would remain the
alternative that would best meet the Projects overall Purpose and Need because
renewed motions for summary judgment in the district court. (JA 697-723, 724-
51.) These motions urged the district court to uphold FTAs December 2016
Determination and to issue a final decision on all of the issues reserved in the
courts August 3 Order. The Agencies also asked the court to reinstate FTAs
On May 22, 2017, the district court issued a memorandum opinion (May 22
ridership and safety issues. 7 (JA 818-29.) Noting FTAs finding that the Purple
Line will meet its established purposes, no matter what happens to WMATA
Metrorail, the court stated without further explanation that this is a curious
7
On May 12, 2017, Maryland petitioned this Court for a writ of mandamus
to direct the district court to enter a final appealable judgment. When the district
court issued its May 22, 2017 Order, Maryland voluntarily dismissed its Petition.
15
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 26 of 72
conclusion. (JA 825.) The court did not identify any specific flaw in that aspect
of FTAs analysis, nor did the court acknowledge or delve into the detailed
analysis that FTA provided to the court. Rather, the court set aside FTAs decision
based on the courts finding that the agency had not specifically responded to the
three declarations referenced by Plaintiffs in their November 2016 letter. (JA 822.)
The court acknowledged that FTA was not obligated to defer to the substantive
2016), for the proposition that an agency may not disregard materials that were
included in the administrative record on remand, and it concluded that [t]he facts
here could not be more similar. (JA 827-28.) The district court did not address
On May 30, 2017, the district court issued what it described as a final and
all remaining issues in the case and noted that an opinion would follow. (JA 836-
37.) On the same date, Maryland filed a notice of appeal. (JA 838.)
all issues in the case other than the issue decided in its May 22 Opinion. (JA 929-
16
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 27 of 72
52.) In the June 9 Opinion, the district court rejected each of Plaintiffs challenges
Plaintiffs later filed a motion to alter the judgment pursuant to Rule 59(e),
asking the court to clarify what issues it had decided in its June 9 Opinion. (JA
1014.) Plaintiffs then filed a motion to enforce the judgment, asking the district
court to order FTA to provide details on how it was complying with the order to
prepare a supplemental EIS. (JA 1023.) On July 31, 2017, the district court denied
On July 19, 2017, this Court granted Marylands emergency motion for a
stay pending appeal. By doing so, this Court reinstated FTAs Record of Decision.
SUMMARY OF ARGUMENT
The administrative record amply confirms that FTA acted lawfully in
December 2016 when it concluded, based on expert analysis, that it did not need to
supplement its Final EIS for the Purple Line to evaluate the effects of hypothetical
future declines in Metrorail ridership. FTAs decision that it did not need to
prepare a supplemental EIS was reasonable and made in accordance with its
regulations and relevant case law. A supplemental EIS is needed only when new
an agencys decision. FTAs detailed analysis found that even an extreme decline
17
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 28 of 72
in the number of Metrorail riders using the Purple Line, down to zero, would not
result in new or different environmental impacts that it had not fully considered.
FTAs analysis also showed that even if few or no Metrorail riders used the Purple
Line, the selected light rail option was still the most effective alternative to achieve
the three elements of the Projects Purpose and Need. FTA went beyond what was
Plaintiffs.
Even if the district courts decision to require a supplemental EIS were valid,
under this Courts precedent it is inappropriate for the district court to order
agency decision where, as here, the disruption resulting from vacatur is substantial
and there is reason to believe that, if given the opportunity, the agency will be able
December 2016 Determination on the Metrorail issue did not provide a basis for
ARGUMENT
18
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 29 of 72
beyond those evaluated in the Final EIS and thus did not warrant preparation of a
ridership would affect the Purple Lines ability to meet its Purpose and Need or
change the basis for selecting a Light Rail Alternative. FTA concluded that the
fate of Metrorail ridership, whatever it might be, would not require a supplemental
EIS for the Project. The district courts May 22 Opinion requiring FTA to prepare
a supplemental EIS on the Metrorail ridership and safety issues ignored both
was not arbitrary and capricious, and the district court erred in setting it aside.
will set aside agency action only when it is arbitrary, capricious, an abuse of
19
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 30 of 72
whether the agency has adequately considered and disclosed the environmental
impact of its actions. Del. Riverkeeper v. FERC, 753 F.3d 1304, 1313 (D.C. Cir.
2014). The Court applies a rule of reason to an agencys NEPA analysis and
deficiency no matter how minor. Myersville Citizens for a Rural Cmty., Inc. v.
FERC, 783 F.3d 1301, 1322 (D.C. Cir. 2015) (quoting Nevada v. Dept of Energy,
impacts of their decisions and that the public is provided an opportunity to have
input into those decisions. Robertson v. Methow Valley Citizens Council, 490 U.S.
332, 349 (1989). To effectuate these purposes, NEPA calls for an agency to
major federal actions. Id.; 42 U.S.C. 4332. Having prepared an EIS, an agency
is not required to supplement it every time new information comes to light after
the EIS is finalized. Marsh v. Or. Nat. Res. Council, 490 U.S. 360, 373 (1989).
seriously different picture of the environmental landscape. Natl Comm. for the
New River, Inc. v. FERC, 373 F.3d 1323, 1330 (D.C. Cir. 2004) (citing City of
20
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 31 of 72
Olmsted Falls, OH v. FAA, 292 F.3d 261, 274 (D.C. Cir. 2002)) (emphasis in
original). As the Supreme Court has explained, a contrary rule would render
find the new information outdated by the time a decision is made. Marsh, 490
U.S. at 373.
environmental concerns and bearing on the proposed action or its impacts would
taking into account information provided by Plaintiffs, FTA conducted its own
regulations. (JA 2420.) FTA concluded that any changes in ridership that might
result from a reduction in transfers to and from the Metrorail system would not
found that a reduction in Metrorail ridership would not alter the physical impacts
21
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 32 of 72
of the Project, which would have the same footprint regardless of the number of
riders using it. (JA 2423-24.) FTA also found that even the most drastic reduction
in Metrorail ridership would not alter the operational impacts of the Project in any
material way, because the frequency of service would not be reduced. (JA 2424.)
In fact, FTA concluded that the environmental impacts from the Project would be
less significant, not greater, if the frequency of service were reduced as a result of a
FTA appropriately relied upon the informed opinions of its own experts
levels would not significantly change the environmental impacts of the Project. An
upheld unless a plaintiff can show that it is arbitrary and capricious. Marsh, 490
U.S. at 376-78; Natl Comm. for the New River, 373 F.3d at 1330. Plaintiffs have
D. FTA Reasonably Concluded That the Project Would Still Meet its
Purpose and Need Even if Metrorail Transfers to the Purple Line
Declined.
FTA also reasonably concluded that any declines in Metrorail ridership
would not affect the ability of the Purple Line to achieve its Purpose and Need, and
22
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 33 of 72
would not undermine FTAs rationale for approving the Purple Line as a light rail
project.
The Final EIS identified three Purpose and Need elements for the Project:
In its December 2016 Determination, FTA found that the first and third
elements of the Purpose and Need do not depend on Metrorail and would be
achieved by the Purple Line regardless of the Metrorail ridership and safety issues.
(JA 2425.) In other words, even if Metrorail ridership were to continue to decline,
the Project would still improve east-west transit, connect communities along the
corridor, and connect major activity centers in and between Bethesda, Silver
FTA then explained that the second element of the Purpose and Need
of the Metrorail system. (JA 2426.) Rail travel between certain suburban
Maryland Metrorail stations requires lengthy trips into and out of Washington,
23
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 34 of 72
D.C. Id. FTA found that under the first four scenarios evaluated in MTAs
November 2016 Report, in which Metrorail transfers to the Purple Line decline to
various degrees but the Metrorail system remains operating, the Purple Line would
remain an attractive alternative to those lengthy trips and would thus meet the
second element of the Projects Purpose and Need. Id. FTA further observed that,
only under the highly unlikely fifth scenario, in which transfers between the
Purple Line and Metrorail fall to zero, would the Project not necessarily meet the
connection to Metrorail element of the Purpose and Need. Id. FTA noted,
The district court did not refer to or discuss the agencys rationale for
reaching its conclusion, and instead simply commented that it was curious that
the agency had found that the Purpose and Need would still be met no matter
courts criticism is ill-founded, because FTAs rationale for its conclusion was
specific and well-supported. Nothing in the district courts decision provides any
24
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 35 of 72
basis for finding FTAs decision on this issue to be arbitrary and capricious. The
court should have deferred to FTAs expert analysis of highly technical issues
FAA, 550 F.3d 1168, 1172 (D.C. Cir. 2008) (an extreme degree of deference is due
within the agencys area of expertise, courts generally defer to the informed
discretion of the responsible federal agencies. Davis v. Latschar, 202 F.3d 359,
369 (D.C. Cir. 2000) (citations omitted); Coalition on Sensible Transportation, Inc.
v. Dole, 826 F.2d 60, 66, 67 (D.C. Cir. 1987) ([T]echnical disputes of [this] sort
[are] most fit for expert administrative resolution and judicial deference).
objective of the Project when it decided that a supplemental EIS was not required
considered and discussed the effect of a decline in Metrorail ridership on the three
elements of the Projects Purpose and Need, and concluded that except in the
the Project still would meet all elements of the Purpose and Need. And even for
25
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 36 of 72
basis for finding that the Project remained the best alternative to meet the overall
As a result, this is not a case like Alaska Wilderness Recreation & Tourism
v. Morrison, 67 F.3d 723 (9th Cir. 1995), in which the court required a
hypothetical cancellation of a contract that formed the entire basis for eliminating
the . . . contract, which opened for consideration alternatives which could not be
freely reviewed when the . . . contract was in force, is an event requiring serious
against all three elements of the Purpose and Need and concluded that the light rail
option was the alternative that best met these elements. (JA 1231-66.) FTA
transfers to the Purple Line would not change this conclusion or result in
environmental impacts that were not fully considered in the Final EIS. Unlike the
26
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 37 of 72
fanciful assumption that Metrorail will cease to function. But NEPA is grounded
the project and feasible alternatives); Vermont Yankee Nuclear Power Co. v.
NRDC, 435 U.S. 519, 551 (1978) (NEPA alternatives are governed by a rule of
the Capital Beltway, demolishing the 14th Street Bridge, or eliminating Metrobus
service. No legitimate purpose under NEPA could be served by requiring FTA and
Maryland to spend taxpayer dollars evaluating in a supplemental EIS how the need
for the Purple Line would change based on such an improbable and unforeseeable
event.
law.
27
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 38 of 72
First, in its December 2016 Determination, which was filed with the court
(JA 674), FTA specifically stated that it considered and reviewed additional
EIS was required on the Metrorail issue. Moreover, FTA considered MTAs
point response to every substantive issue raised in the body of Plaintiffs letter.
(JA 2411-19.) FTA did not respond separately to each item attached to or
Dombeck, 222 F.3d 552, 560 (9th Cir. 2000) (Agency does not need to seek public
Second, the record as a whole makes clear that MTAs and FTAs entire
28
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 39 of 72
(JA 494-640.) To the extent that the declarations addressed the issue of Metrorail
ridership, they contended that a recent decline in Metrorail ridership could be more
long-lasting and severe than was assumed in an August 2016 declaration from
MTAs ridership expert, Greg Benz. (JA 2297-99, 2303-07, 2319-22.) After
receiving Plaintiffs declarations, MTA worked with FTA to develop the five
Purple Line. Thus, far from ignoring Plaintiffs declarations, the Agencies
developed the five scenarios in MTAs November 2016 Report specifically to take
into account the declarants hypotheses that there could be severe, long-term
passenger forecasts for the Purple Line and their personal preferences for a
was warranted on the Metrorail ridership issue. See Covad Commcns, Co. v.
F.C.C., 450 F.3d 528, 550 (D.C. Cir. 2006) (The failure to respond to comments
29
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 40 of 72
is significant only insofar as it demonstrates that the agencys decision was not
Clark, 741 F.2d 401, 409 (D.C. Cir. 1984)); Pub. Citizen, Inc. v. F.A.A., 988 F.2d
186, 197 (D.C. Cir. 1993) (requirement to respond to comments is not particularly
demanding); Simpson v. Young, 854 F.2d 1429, 1435 (D.C. Cir. 1988) ([t]he
agency need only state the main reasons for its decision and indicate it has
In finding fault with FTAs December 2016 Determination, the district court
incorrectly relied on PEER, 827 F.3d 1077, where this Court determined that the
U.S. Fish and Wildlife Service erred in not considering information submitted by
plaintiffs when the agency reconsidered a decision under the Endangered Species
Act. PEER is inapposite, however, because unlike the agency in PEER, FTA did
not disregard the declarations, but expressly reviewed and considered the
Equally misplaced was the district courts reliance on Gerber v. Norton, 294
F.3d 173 (D.C. Cir. 2002), and Getty v. Federal Savings and Loan Insurance
Corp., 805 F.2d 1050 (D.C. Cir. 1986). Both cases address an agencys failure to
district court never found, nor does the record show, that FTA failed to consider a
relevant factor. In fact, as discussed above, FTA assessed each of the factors
30
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 41 of 72
In sum, FTA fulfilled its obligation to take a sufficiently hard look at the
Metrorail ridership and related maintenance and safety issues. Theodore Roosevelt
Conservation Pship v. Salazar, 616 F.3d 497, 510 (D.C. Cir. 2010). FTA
reasonably concluded that no supplemental EIS was required because the new
information about the Metrorail ridership and safety issues (1) would not result in
significant environmental impacts that FTA had not previously considered, (2) did
not undermine FTAs conclusion that the Project meets the Projects Purpose and
Need, and (3) did not undermine FTAs basis for approving Marylands choice of
Light Rail as the Locally Preferred Alternative. In keeping with the highly
849 F.3d at 1082, this Court should defer to FTAs reasonable conclusion that a
supplemental EIS was not required because the information did not constitute a
was presented in the Final EIS. Natl Comm. for the New River, 373 F.3d at 1330.
31
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 42 of 72
with applicable law in considering and rejecting the need for Plaintiffs requested
erroneous, the district court abused its discretion when it vacated the Record of
Decision and refused to reconsider the vacatur. The district court failed to apply
Services v. Department of Health and Human Services, 435 F.3d 326, 330 (D.C.
Cir. 2006).
(D.C. Cir. 1993), this Court established the standard for deciding whether to vacate
32
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 43 of 72
an agency order found to be invalid. The Court held that vacatur is not an
whether to vacate depends on the seriousness of the orders deficiencies (and thus
the extent of doubt whether the agency chose correctly) and the disruptive
(citation omitted). Where there is a serious possibility that the [agency] will be
able to substantiate its decision on remand, this Court has declined to vacate an
agencys decision. Id.; see also Apache Corp. v. F.E.R.C., 627 F.3d 1220, 1223
(D.C. Cir. 2010). As recently as this month, this Court reaffirmed the continuing
Grp., LLP v. Sec. & Exch. Commn, __ F.3d __, No. 16-1061, 2017 WL 3389269,
at *6 (D.C. Cir. Aug. 8, 2017); see id. at *8 (citing Allied-Signal); id. (deeming
vacatur inappropriate because the SEC may be able to approve the Plan once
again, after conducting a proper analysis on remand, and unwinding the Plan in
that exist at a particular time. See Black Warrior Riverkeeper, Inc. v. U.S. Army
Corps of Engineers, 781 F.3d 1271, 1289 (11th Cir. 2015) (declining to vacate
33
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 44 of 72
agency decision at this time); Maryland Native Plant Socy v. U.S. Army Corps
court stated that [w]hile a temporary halt in the project is not ideal, it would make
little sense and cause even more disruption if defendants were to proceed with the
project while the [supplemental EIS] was being completed, only to subsequently
determine that another alternative is preferable. (JA 435.) The court pointed to
no evidence supporting its finding that keeping the Record of Decision in effect
would cause even more disruption than would result from vacating it, and the
court reached that conclusion without first asking the parties to address the likely
consequences of vacatur. Id. Nevertheless, even if there had been some support
In the same order, the district court decided to reserve judgment on all
(JA 428.) Those reserved claims included challenges to the Final EIS. Thus, at
the time the district court vacated the Record of Decision, it had not yet ruled on
the claims that directly challenged the adequacy of the Final EIS upon which the
34
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 45 of 72
illegal. Here, however, the August 3 Order (JA 436-37) vacated a decision that the
district court had not found to be inadequate or illegal: FTAs March 2014 Record
of Decision.
EIS are two separate decisions, each subject to review in its own right. In 23
action distinct from the agencys Record of Decision and subject to its own
statute of limitations. Courts have also recognized this distinction. See Jersey
Heights Neighborhood Assn. v. Glendening, 174 F.3d 180 (4th Cir. 1999) (the
the NEPA analysis prepared for that initial approval are separate decisions, each
with its own statute of limitations); RB Jai Alai, LLC v. Secretary of the Florida
subsequent decisions not to prepare a supplemental EIS because they were separate
decisions).
35
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 46 of 72
Here, the only NEPA violation found by the district court in its August 3
Order was that FTA had erred in its January 2016 decision not to prepare a
supplemental EIS. At no time did the district court find a flaw in the Final EIS or
Record of Decision, and, in fact, the court later found them both to be valid. As a
result, the district court erred by vacating the Record of Decision when concluding
that there was a flaw in FTAs wholly distinct January 2016 decision not to prepare
a supplemental EIS. EarthReports, Inc. v. F.E.R.C., 828 F.3d 949, 959 (D.C. Cir.
2016) ([T]he courts review is limited to the administrative record before the
district court to reconsider its order vacating the Record of Decision and outlined
the disruptive consequences that would flow from maintaining that order. (JA 453,
457-59, 467-72.)8 Maryland noted that the Project was being developed through a
8
The district court never asked for separate briefing to address remedy.
Maryland, in its supplemental summary judgment brief, asked the court for an
opportunity to address the cascading consequences that would flow from a
decision to vacate the Record of Decision. (JA 318.) However, the district court
36
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 47 of 72
public-private partnership contract under which the private partner was responsible
for financing, developing, designing, and constructing the Purple Line, and for
operating and maintaining the Purple Line for 30 years.9 For example, the
schedule developed by the private partner was extremely complex, with almost
6,000 discrete activities that will need to be coordinated and sequenced over the
six-year design and construction period. (JA 446 at 29.) Any delay in that type
schedule, resulting in further delay and cost. This delay would result in substantial
increased costs due to the complexity and scope of the work planned to occur on a
project of this magnitude and to the intricate and timed financial investments and
commitments of the private participants and local, state, and federal governments.
(Id. at 30-32.)
Notwithstanding the significant harm to Maryland and the public from the
vacatur, the district court refused to amend its order vacating the Record of
Decision. Instead, the court noted that the disruptive consequences factor of the
Allied-Signal test compelled the decision to deny the request to reinstate the
Record of Decision. (JA 670.) The court further stated that Maryland had
issued its August 3 Order vacating the Record of Decision without further briefing
on the issue.
9
The consequences of delay are fully explained in the Declaration of
Charles Lattuca, submitted to the district court by Maryland as part of the Rule
59(e) motion. (JA 439, 448-52 at 41-60.)
37
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 48 of 72
that vacatur ensures that the project will proceed only with the benefit of a fully
fleshed out consideration of the issues required by NEPA. (JA 670-71.) But
under Allied-Signal and other cases addressing the vacatur issue, the disruptive
change that would result from vacating the agency decision only to later reinstate
it once the agency had provided an adequate explanation for its actions in other
International Union, United Mine Workers of America v. Fed. Mine Safety and
The district court erred in two ways. First, the court misunderstood the
would occur through implementation of the Project if the Record of Decision were
kept in place, rather than on the disruptive consequences flowing from vacatur of
the Record of Decision, which had been in place for over two years by the time of
the courts order. Second, by failing to re-weigh those consequences in light of the
the district court, in effect, issued a preliminary injunction without making any of
38
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 49 of 72
August 3 Order, it relied on its finding that FTAs January 2016 decision not to
Courts August 3 Order, FTA, with MTAs assistance, prepared a new analysis of
the Metrorail ridership issue. After considering this new analysis, FTA determined
again that a supplemental EIS was not warranted. (JA 674-85.) Both MTA and
FTA asked the Court to lift its order vacating the Record of Decision based on
consequences of vacatur had increased. (JA 697-723, 724-51.) After the court
again concluded in its May 2017 Opinion that FTA needed to prepare a
supplemental EIS, the court failed to mention the Allied-Signal factors or consider
The court erred when it failed to reevaluate the vacatur remedy at that time.
151. The order to be vacated is the order that has been found to have
deficiencies, not any other related order. The district courts May 22 Opinion
reviewed and rejected FTAs December 2016 Determination not the March 2014
39
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 50 of 72
Record of Decision or the January 2016 determination. Indeed, the court found
only a single flaw in the December 2016 Determination: a failure to address three
analysis prepared by Maryland to support its August 2016 Rule 59(e) motion. The
district court also failed to weigh the seriousness of that single flaw in the
the district court erred by refusing to reconsider the appropriateness of the order
vacating the March 2014 Record of Decision, when the only NEPA error found by
supplemental EIS.10 In addition, the district court again erred in failing to reweigh
California Communities Against Toxics v. E.P.A., 688 F.3d 989, 993-994 (9th Cir.
2012) (declining to vacate an EPA rule where [s]topping construction [on a power
10
The district court further abused its discretion by failing to reconsider
vacatur after its May 30 Order upholding the FEIS and the Record of Decision on
all other grounds.
40
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 51 of 72
vacatur is introduced, even though the Corps may eventually be able to articulate
sustainable reasons for its decision). Given that the only flaw found by the
clear that the disruptive consequences of an interim change to the status of the
CONCLUSION
For the foregoing reasons, this Court should reverse that portion of the final
statement and should reverse the district courts order vacating FTAs March 2014
Record of Decision.
41
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 52 of 72
BRIAN E. FROSH
Attorney General of Maryland
JULIE SWEENEY
Assistant Attorney General
Maryland Transit Administration
6 St. Paul Street, Suite 1200
Baltimore, MD 21202-1614
Telephone: 410.767.3844
Email: JSweeney@mta.maryland.gov
ERIC D. MILLER
Perkins Coie LLP
1201 Third Avenue, Suite 4900
Seattle, WA 98101-3099
Telephone: 206.359.3773
Facsimile: 206.359.4773
Email: emiller@perkinscoie.com
42
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 53 of 72
TABLE OF CONTENTS
Addendum Page
ADDENDUM 1
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 55 of 72
ADDENDUM 2
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 56 of 72
(D) Any detailed statement required under subparagraph (C) after January 1, 1970,
for any major Federal action funded under a program of grants to States shall not
be deemed to be legally insufficient solely by reason of having been prepared by a
State agency or official, if:
(i) the State agency or official has statewide jurisdiction and has the
responsibility for such action,
(ii) the responsible Federal official furnishes guidance and participates in such
preparation,
(iii) the responsible Federal official independently evaluates such statement
prior to its approval and adoption, and
(iv) after January 1, 1976, the responsible Federal official provides early
notification to, and solicits the views of, any other State or any Federal land
management entity of any action or any alternative thereto which may have
significant impacts upon such State or affected Federal land management entity
and, if there is any disagreement on such impacts, prepares a written assessment
of such impacts and views for incorporation into such detailed statement.
The procedures in this subparagraph shall not relieve the Federal official of his
responsibilities for the scope, objectivity, and content of the entire statement or of
any other responsibility under this chapter; and further, this subparagraph does not
affect the legal sufficiency of statements prepared by State agencies with less than
statewide jurisdiction.
(E) study, develop, and describe appropriate alternatives to recommended courses
of action in any proposal which involves unresolved conflicts concerning
alternative uses of available resources;
(F) recognize the worldwide and long-range character of environmental problems
and, where consistent with the foreign policy of the United States, lend appropriate
support to initiatives, resolutions, and programs designed to maximize international
cooperation in anticipating and preventing a decline in the quality of mankinds
world environment;
(G) make available to States, counties, municipalities, institutions, and individuals,
advice and information useful in restoring, maintaining, and enhancing the quality
of the environment;
(H) initiate and utilize ecological information in the planning and development of
resource-oriented projects; and
(I) assist the Council on Environmental Quality established by subchapter II of this
chapter.
ADDENDUM 3
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 57 of 72
ADDENDUM 4
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 58 of 72
ADDENDUM 5
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 59 of 72
(a)
(1) The provisions of this regulation and the CEQ regulation apply to actions
where the Administration exercises sufficient control to condition the permit or
project approval. Actions taken by the applicant which do not require Federal
approvals, such as preparation of a regional transportation plan are not subject to
this regulation.
(2) This regulation does not apply to, or alter approvals by the Administration
made prior to the effective date of this regulation.
(3) Environmental documents accepted or prepared after the effective date of this
regulation shall be developed in accordance with this regulation.
(b) It shall be the responsibility of the applicant, in cooperation with the
Administration to implement those mitigation measures stated as commitments in
the environmental documents prepared pursuant to this regulation. The FHWA will
assure that this is accomplished as a part of its program management
responsibilities that include reviews of designs, plans, specifications, and estimates
(PS&E), and construction inspections. The FTA will assure implementation of
committed mitigation measures through incorporation by reference in the grant
agreement, followed by reviews of designs and construction inspections.
(c) The following roles and responsibilities apply during the environmental review
process:
(1) The lead agencies are responsible for managing the environmental review
process and the preparation of the appropriate environmental review documents.
(2) Any applicant that is a State or local governmental entity that is, or is
expected to be, a direct recipient of funds under title 23, U.S. Code, or chapter 53
of title 49 U.S. Code, for the action shall serve as a joint lead agency with the
Administration in accordance with 23 U.S.C. 139, and may prepare
environmental review documents if the Administration furnishes guidance and
independently evaluates the documents.
(3) The Administration may invite other Federal, State, local, or federally-
recognized Indian tribal governmental units to serve as joint lead agencies in
accordance with the CEQ regulation. If the applicant is serving as a joint lead
agency under 23 U.S.C. 139(c)(3), then the Administration and the applicant will
decide jointly which other agencies to invite to serve as joint lead agencies.
ADDENDUM 6
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 60 of 72
(4) When the applicant seeks an Administration action other than the approval of
funds, the role of the applicant will be determined by the Administration in
accordance with the CEQ regulation and 23 U.S.C. 139.
(5) Regardless of its role under paragraphs (c)(2) through (c)(4) of this section, a
public agency that has statewide jurisdiction (for example, a State highway
agency or a State department of transportation) or a local unit of government
acting through a statewide agency, that meets the requirements of section
102(2)(D) of NEPA, may prepare the EIS and other environmental review
documents with the Administration furnishing guidance, participating in the
preparation, and independently evaluating the document. All FHWA applicants
qualify under this paragraph.
(6) The role of a project sponsor that is a private institution or firm is limited to
providing technical studies and commenting on environmental review
documents.
(d) When entering into Federal-aid project agreements pursuant to 23 U.S.C. 106,
it shall be the responsibility of the State highway agency to ensure that the project
is constructed in accordance with and incorporates all committed environmental
impact mitigation measures listed in approved environmental review documents
unless the State requests and receives written FHWA approval to modify or delete
such mitigation features.
ADDENDUM 7
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 61 of 72
(a)
(1) Early coordination with appropriate agencies and the public aids in
determining the type of environmental review documents an action requires, the
scope of the document, the level of analysis, and related environmental
requirements. This involves the exchange of information from the inception of a
proposal for action to preparation of the environmental review documents.
Applicants intending to apply for funds should notify the Administration at the
time that a project concept is identified. When requested, the Administration will
advise the applicant, insofar as possible, of the probable class of action and
related environmental laws and requirements and of the need for specific studies
and findings which would normally be developed concurrently with the
environmental review documents.
(2) The information and results produced by, or in support of, the transportation
planning process may be incorporated into environmental review documents in
accordance with 40 CFR 1502.21, and 23 CFR 450.212(b) or 450.318(b). In
addition, planning products may be adopted and used in accordance with 23 CFR
450.212(d) or 450.318(e), which implement 23 U.S.C. 168.
(b) The Administration will identify the probable class of action as soon as
sufficient information is available to identify the probable impacts of the action.
(c) When both the FHWA and FTA are involved in the development of a project,
or when the FHWA or FTA acts as a joint lead agency with another Federal
agency, a mutually acceptable process will be established on a case-by-case basis.
(d) During the early coordination process, the lead agencies may request other
agencies having an interest in the action to participate, and must invite such
agencies if the action is subject to the project development procedures in 23 U.S.C.
139. Agencies with special expertise may be invited to become cooperating
agencies. Agencies with jurisdiction by law must be requested to become
cooperating agencies.
The FHWA and FTA have developed guidance on 23 U.S.C. Section 139 titled
SAFETEA-LU Environmental Review Process: Final Guidance, November 15,
2006, and available at http://www.fhwa.dot.gov or in hard copy upon request.
(e) Other States, and Federal land management entities, that may be significantly
affected by the action or by any of the alternatives shall be notified early and their
views solicited by the applicant in cooperation with the Administration. The
ADDENDUM 8
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 62 of 72
ADDENDUM 9
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 63 of 72
ADDENDUM 10
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 64 of 72
ADDENDUM 11
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 65 of 72
ADDENDUM 12
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 66 of 72
ADDENDUM 13
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 67 of 72
ADDENDUM 14
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 68 of 72
ADDENDUM 15
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 69 of 72
boat service, and fixed-guideway facilities for buses (such as bus rapid transit) and
other high occupancy vehicles. A new fixed guideway means a newly-constructed
fixed guideway in a corridor or alignment where no such guideway exists.
FTA means the Federal Transit Administration.
Full funding grant agreement means a contract that defines the scope of a New
Starts project, the amount of New Starts funds that will be contributed, and other
terms and conditions.
Horizon year means a year roughly 10 years or 20 years in the future, at the option
of the project sponsor. Horizon years are based on available socioeconomic
forecasts from metropolitan planning organizations, which are generally prepared
in five year increments such as for the years 2020, 2025, 2030, and 2035.
Locally preferred alternative means an alternative evaluated through the local
planning process, adopted as the desired alternative by the appropriate State and/or
local agencies and official boards through a public process and identified as the
preferred alternative in the NEPA process.
Long-range transportation plan means a financially constrained long-range plan,
developed pursuant to 23 CFR Part 450, that includes sufficient financial
information for demonstrating that projects can be implemented using committed,
available, or reasonably available revenue sources, with reasonable assurance that
the Federally supported transportation system is being adequately operated and
maintained. For metropolitan planning areas, this would be the metropolitan
transportation plan and for other areas, this would be the long-range statewide
transportation plan. In areas classified by the Environmental Protection Agency as
nonattainment or maintenance of air quality standards, the long-range
transportation plan must have been found by DOT to be in conformity with the
applicable State Implementation Plan.
Major capital transit investment means any project that involves the construction
of a new fixed guideway, extension of an existing fixed guideway, or a corridor-
based bus rapid transit system for use by public transit vehicles.
NEPA process means those procedures necessary to meet the requirements of the
National Environmental Policy Act of 1969 (NEPA), as amended, at 23 CFR Part
771; the NEPA process is completed when the project receives a categorical
exclusion, a Finding of No Significant Impact (FONSI) or a Record of Decision
(ROD).
New Starts means a new fixed guideway project, or a project that is an extension to
an existing fixed guideway, that has a total capital cost of $250,000,000 or more or
ADDENDUM 16
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 70 of 72
for which the project sponsor is requesting $75,000,000 or more in New Starts
funding.
New Starts funds mean funds granted by FTA for a New Starts project pursuant to
49 U.S.C. 5309(d).
No-build alternative means an alternative that includes only the current
transportation system as well as the transportation investments committed in the
Transportation Improvement Plan (TIP) (when the horizon year is 10 years in the
future) or the fiscally constrained long-range transportation plan (when the horizon
year is 20 years in the future) required by 23 CFR Part 450.
Secretary means the Secretary of Transportation.
Small Starts means a new fixed guideway project, a project that is an extension to
an existing fixed guideway, or a corridor-based bus rapid transit system project,
with a total capital cost of less than $250,000,000 and for which the project
sponsor is requesting less than $75,000,000 in Small Starts funding.
Small Starts funds mean funds granted by FTA for a Small Starts project pursuant
to 49 U.S.C. 5309(h).
Small Starts project development is a phase in the Small Starts process during
which the scope of the proposed project is finalized; estimates of project costs,
benefits and impacts are refined; NEPA requirements are completed; project
management plans and fleet management plans are further developed; and the
project sponsors obtains commitment of all non-Small Starts funding. It also
includes (but is not limited to) the preparation of final construction plans
(including construction management plans), detailed specifications, construction
cost estimates, and bid documents.
ADDENDUM 17
USCA Case #17-5132 Document #1689447 Filed: 08/18/2017 Page 71 of 72
CERTIFICATE OF COMPLIANCE
I hereby certify that this brief complies with the type-volume limitation of
word-processing system used to prepare this brief, the brief contains 9604 words,
excluding the parts of the brief exempted by Fed. R. App. P. 32(a)(7)(B)(iii), and
complies with the type style requirements of Fed. R. App. P. 32(a)(6), because it
New Roman).
CERTIFICATE OF SERVICE
I hereby certify that on August 18, 2017, a copy of the foregoing document