PROPOSED MASTER SCHEDULE FOR A BLOCK OF 7-STOREY INDUSTRIAL BUILDING WITH BASEMENT CAR PARKS AND ANCILLARY FACILITIES

AT 2 KUNG CHONG ROAD

ID TaskTask Name Duration Start Finish Q2 '17 Q3 '17 Q4 '17 Q1 '18 Q2 '18 Q3 '18
Mode Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18
0 2 Kung Chong Road-v13-27072017 326 Mon 10-04-17 Mon
days 09-07-18
1 Contract Commencement 1 day Mon 10-04-17 Mon 10-04-17
175 Aluminium Works Material Submission, Shop Drawing 143 Tue 13-06-17 Thu 28-12-17
Submission Including PE Submission, Mock-Up Submittal, & days
Manufacturing Schedules
176 Glass Curtain Wall System (External Facades) 143 daysTue 13-06-17 Thu 28-12-17
177 Submission of Samples, Test Reports 15 days Tue 13-06-17 Mon 03-07-17
178 Review & Approval of Samples, Test Reports 5 days Tue 04-07-17 Mon 10-07-17
179 Submission of Shop Drawings Including Structural Calculation 25 days Tue 11-07-17 Mon 14-08-17
180 Review & Approval of Shop Drawings Including Structural Calculation
10 days Tue 15-08-17 Mon 28-08-17
181 Submission of Structural Calculation to Authority for Approval 5 days Tue 29-08-17 Mon 04-09-17
182 Review & Approval of Structural Calculation from Authority 20 days Tue 05-09-17 Mon 02-10-17
183 Mock-Up Submittal Including Mock-Up Testing 20 days Tue 29-08-17 Mon 25-09-17
184 Review & Approval of Mock-Up Submittal 5 days Tue 26-09-17 Mon 02-10-17
185 Procurement & Fabrication of Approved Specified System (1st 17 batch)
days Tue 03-10-17 Wed 25-10-17
187 Procurement & Fabrication of Approved Specified System (3rd 17 batch)
days Thu 16-11-17 Fri 08-12-17
190 Delivery to Project Site for 3nd batch 14 days Mon 11-12-17 Thu 28-12-17
204 Horizontal Aluminium Composite Cladding System (Size Varies) 138 daysTue 13-06-17 Thu 21-12-17
205 Submission of Samples, Test Reports 15 days Tue 13-06-17 Mon 03-07-17
206 Review & Approval of Samples, Test Reports 5 days Tue 04-07-17 Mon 10-07-17
207 Submission of Shop Drawings Including Structural Calculation 25 days Tue 11-07-17 Mon 14-08-17
208 Review & Approval of Shop Drawings Including Structural Calculation
10 days Tue 15-08-17 Mon 28-08-17
209 Submission of Structural Calculation to Authority for Approval 5 days Tue 29-08-17 Mon 04-09-17
210 Review & Approval of Structural Calculation from Authority 20 days Tue 05-09-17 Mon 02-10-17
211 Mock-Up Submittal Including Mock-Up Testing 20 days Tue 29-08-17 Mon 25-09-17
212 Review & Approval of Mock-Up Submittal 5 days Tue 26-09-17 Mon 02-10-17
213 Procurement & Fabrication of Approved Specified System (1st 17 batch)
days Tue 03-10-17 Wed 25-10-17
214 Procurement & Fabrication of Approved Specified System (2nd17 batch)
days Thu 09-11-17 Fri 01-12-17
216 Delivery to Project Site for 2nd batch 14 days Mon 04-12-17 Thu 21-12-17
262 (Item Under PC Sum) Architectural Material Submission & Shop 170 Tue 09-05-17 Mon 01-01-18
Drawing Submission days
275 Submission of Samples: Lift Installation System (P.C Sum: S$840,000.00)
12 days Tue 16-05-17 Wed 31-05-17
276 Review & Approval of Submitted Samples: Lift Installation 5 days Thu 01-06-17 Wed 07-06-17
System (P.C Sum: S$840,000.00)
277 Submission of Shop Drawings Based on Submitted Samples: Lift 12 days Thu 08-06-17 Fri 23-06-17
Installation System
278 Review & Approval of Shop Drawings: Lift Installation System 5 days Mon 26-06-17 Fri 30-06-17
287 M&E Material Submission, Shop Drawing Submission & 134 Tue 09-05-17 Fri 10-11-17
Combined Service Drawings days
302 Submission of Catalogue, Test Reports, Calculations: ACMV System
9 days Tue 06-06-17 Fri 16-06-17

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: 2 Kung Chong Road-v1
Milestone Inactive Summary Start-only Critical
Date: Fri 28-07-17
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 1
PROPOSED MASTER SCHEDULE FOR A BLOCK OF 7-STOREY INDUSTRIAL BUILDING WITH BASEMENT CAR PARKS AND ANCILLARY FACILITIES AT 2 KUNG CHONG ROAD

ID TaskTask Name Duration Start Finish Q2 '17 Q3 '17 Q4 '17 Q1 '18 Q2 '18 Q3 '18
Mode Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18
303 Review & Approval of Catalogue, Test Reports, Calculations : 8 days Mon 19-06-17 Wed 28-06-17
ACMV System
304 Submission of Samples: ACMV System 10 days Thu 29-06-17 Wed 12-07-17
305 Review & Approval of Samples: ACMV System 6 days Thu 13-07-17 Thu 20-07-17
306 Submission of Shop Drawings (Basement Level): ACMV System7 days Fri 21-07-17 Mon 31-07-17
307 Review & Approval of Shop Drawings (Basement Level): ACMV6System
days Tue 01-08-17 Tue 08-08-17
344 Submission of Co-ordinated Services Drawings & Structural 12 days Wed 09-08-17 Thu 24-08-17
Penetration Drawings (For Basement Only)
345 Review & Approval of Co-ordinated Services Drawings & 6 days Fri 25-08-17 Fri 01-09-17
Structural Penetration Drawings (For Basement Only)
352 Sub-Structure Works 156 daysThu 27-04-17 Thu 30-11-17
353 Soil Invesigation Works- 2 Bore Hole 9 days Thu 27-04-17 Tue 09-05-17
354 Ultimate Load Test 1 Works 5 days Wed 10-05-17 Tue 16-05-17
355 Dismantling of Kentledge System & Mobilization to Site 12 days Wed 17-05-17 Thu 01-06-17
356 Bored Piling Works to Gd Line 1-8 & A-G 26 days Fri 02-06-17 Fri 07-07-17
357 Bored Piling Works to Gd Line 1' & A' (Along Boundary Line) 20 days Mon 10-07-17 Fri 04-08-17

358 Working Load Test Including PDA Test 20 days Mon 07-08-17 Fri 01-09-17
363 Excavation Works 25 days Mon 04-09-17 Fri 06-10-17
364 ERSS Works: Soldier Piling Works (Localised Pit) - 2nd 15 days Mon 18-09-17 Fri 06-10-17
Mobilization
365 RC Works for Pile Caps, Slab - Basement 1 from Gd Line A-F, 1-8 39 days Mon 09-10-17 Thu 30-11-17
368 Super-Structure Works 112 daysFri 20-10-17 Mon 26-03-18
369 RC Works for Beam , Slab - 1st Storey from Gd Line A-F, 1-8 11 days Fri 01-12-17 Fri 15-12-17
372 RC Works for Columns & Staircase Walls- 1st Storey 9 days Tue 12-12-17 Fri 22-12-17
373 RC Works for Beam , Slab - 2nd Storey 12 days Tue 19-12-17 Wed 03-01-18
374 RC Works for Columns & Staircase Walls - 2nd Storey 9 days Tue 26-12-17 Fri 05-01-18
375 RC Works for Beam , Slab - 3rd Storey 12 days Tue 02-01-18 Wed 17-01-18
376 RC Works for Columns & Staircase Walls - 3rd Storey 10 days Fri 12-01-18 Thu 25-01-18
377 RC Works for Beam , Slab - 4th Storey 12 days Wed 24-01-18 Thu 08-02-18
378 RC Works for Columns & Staircase Walls - 4th Storey 9 days Wed 31-01-18 Mon 12-02-18
379 RC Works for Beam , Slab - 5th Storey 12 days Wed 07-02-18 Thu 22-02-18
380 RC Works for Columns & Staircase Walls - 5th Storey 9 days Wed 14-02-18 Mon 26-02-18
381 RC Works for Beam , Slab - 6th Storey 12 days Wed 21-02-18 Thu 08-03-18
382 RC Works for Columns & Staircase Walls - 6th Storey 8 days Wed 28-02-18 Fri 09-03-18
383 RC Works for Beam , Slab - Roof & Upper Roof Storey 12 days Wed 07-03-18 Thu 22-03-18
384 RC Works for Columns & Staircase Walls - Roof & Upper Roof Storey
8 days Thu 15-03-18 Mon 26-03-18
386 Architectural Works & M&E Works 142 daysWed 08-11-17 Fri 25-05-18
444 6th Storey 46 days Fri 23-03-18 Fri 25-05-18
445 Walls 15 days Fri 23-03-18 Thu 12-04-18
447 Floor Finishes 18 days Fri 06-04-18 Tue 01-05-18
452 M&E Final Fix 18 days Wed 02-05-18 Fri 25-05-18

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: 2 Kung Chong Road-v1
Milestone Inactive Summary Start-only Critical
Date: Fri 28-07-17
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 2
PROPOSED MASTER SCHEDULE FOR A BLOCK OF 7-STOREY INDUSTRIAL BUILDING WITH BASEMENT CAR PARKS AND ANCILLARY FACILITIES AT 2 KUNG CHONG ROAD

ID TaskTask Name Duration Start Finish Q2 '17 Q3 '17 Q4 '17 Q1 '18 Q2 '18 Q3 '18
Mode Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18
453 Roof Storey 44 days Tue 27-03-18 Fri 25-05-18
454 Walls 18 days Tue 27-03-18 Thu 19-04-18
457 Wall Finishes 11 days Tue 10-04-18 Tue 24-04-18
460 M&E 2nd Fix 11 days Tue 17-04-18 Tue 01-05-18
461 M&E Final Fix 18 days Wed 02-05-18 Fri 25-05-18
462 Identation & Off-Site Fabrication of Lifts 114 daysMon 03-07-17 Thu 07-12-17
463 Handover of Lift Shafts to NSC ( To be completed 8 months from 0 days Thu 07-12-17 Thu 07-12-17 07-12
commencement date)
464 Lift Installation Include Testing & Commisioning 86 days Fri 08-12-17 Fri 06-04-18
465 Aluminium Works On-Site Installation Schedules 69 days Thu 09-11-17 Tue 13-02-18
468 Glass Curtain Wall System (External Facades) - 3rd batch 33 days Fri 29-12-17 Tue 13-02-18
472 Horizontal Aluminium Composite Cladding System (Size Varies) - 38 days Fri 22-12-17 Tue 13-02-18
2nd batch
478 1st Level External Works Include Boundary Wall & Entrance 35 days Mon 09-04-18 Fri 25-05-18
Culverts, etc
484 Application of TOP Inspection 24 days Mon 28-05-18 Thu 28-06-18
485 Obtain TOP & Handover of Building to Client 7 days Fri 29-06-18 Mon 09-07-18

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: 2 Kung Chong Road-v1
Milestone Inactive Summary Start-only Critical
Date: Fri 28-07-17
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress