SAUDI ARAMCO ID/PID FORM REV 1 - 010109 REV 6 31-Mar-12

SATIP No. APPROVED DATE DISCIPLINE:


SAUDI ARAMCO TYPICAL INSPECTION PLAN
A/C Split Systems-Direct Expansion (DX) Type SATIP-K-001-11 30-Apr-13 HVAC
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

1.1 Not applicable

2.0 MATERIAL RECEIVING

SAIC- SAIC- Saudi Aramco shall be notified for inspection of every


2.1 Air Cooled Condenser
K-4037 K-4037 H W Condensers

See See
2.2 AHU See SATIP-K-001-02 Air Handling Unit
Remarks Remarks
SAIC- SAIC- Saudi Aramco shall be notified for inspection of every
2.3 Fan Coil Receiving Inspection
K-4038 K-4038 H W Fan Coils

Air Cooled Condenser SAIC- SAIC-


2.4
Handling, Storage and Preservation K-4037 K-4037 W S Weekly Inspection by Contractor QA/QC

Fan Coil SAIC- SAIC-


2.5
Handling, Storage and Preservation K-4038 K-4038 W S Weekly Inspection by Contractor QA/QC

See See
2.6 Refrigerant Piping See SATIP-K-001-07 Refrigerant Piping
Remarks Remarks
HVAC System Electrical, See See
2.7 See SATIP-P-104-08 HVAC Equipment
Instrumentation and Control Remarks Remarks
3.0 INSTALLATION
Essential Operating Facilities HVAC SAIC- SAIC-
3.1
requirements K-4006 K-4006 H W

Pressurized Building HVAC SAIC- SAIC-


3.2
Requirements K-4044 K-4044 H W

Communication Facilities HVAC SAIC- SAIC-


3.3
Requirements K-4045 K-4045 H W

SAIC- SAIC-
3.4 Battery Room HVAC Requirements
K-4046 K-4046 H W
Air Cooled Condenser SAIC- SAIC- Saudi Aramco shall be notified for Installation
3.5
Inspection K-4039 K-4039 H W Inspection of every air Cooled Condensers
AHU See See
3.6 See SATIP-K-001-02 Air Handling Unit
Inspection Remarks Remarks

Page 1 of 3
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 REV 6 31-Mar-12
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
A/C Split Systems-Direct Expansion (DX) Type SATIP-K-001-11 30-Apr-13 HVAC
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Fan Coil SAIC- SAIC- Saudi Aramco shall be notified on start of this activity
3.7
Inspection K-4040 K-4040 H W for each building / zone

Air Moving / Cooling Equipment


SAIC- SAIC- Saudi Aramco shall be notified on this activity for every
3.8 Duct / Pipe Connection
K-4003 K-4003 I W system
Inspection

See See
3.9 Metal duct See SATIP-K-001-03 HVAC Metal Duct System
Remarks Remarks

Condensate Drain Lay-out SAIC- SAIC- Saudi Aramco shall be notified on start of this activity
3.10
Inspection K-4007 K-4007 I W for each building / zone / Area

Thermoplastic piping
See See
3.11 (Used for condensate Drain Lines & as See SATIP-S-070-03 Thermoplastic and RTR piping
Remarks Remarks
required)
See See
3.12 Refrigerant Piping (Copper) See SATIP-K-001-07 Refrigerant Piping
Remarks Remarks

See SATIP-J-100-01 Flow Instrumentation


SATIP-J-200-01 Pressure Instrumentation
See See
3.13 Instrumentation SATIP-J-300-01 Level Instrumentation
Remarks Remarks
SATIP-J-400-01 Temperature Instrumentation
and as applicable

HVAC System Electrical, See See


3.14 See SATIP-P-104-08 HVAC Equipment
Instrumentation and Control Remarks Remarks

4.0 PRE-COMMISSIONING

System Testing, Adjusting and See See See SATIP-K-001-012 Testing, Adjusting and
4.1
Balancing (TAB) Remarks Remarks Balancing of the HVAC System

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may
1 adjust the levels of Saudi Aramco participation based upon the Contractors performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.

Page 2 of 3
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 REV 6 31-Mar-12
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
A/C Split Systems-Direct Expansion (DX) Type SATIP-K-001-11 30-Apr-13 HVAC
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4 attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QA/ QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 3 of 3