Offshore World - Track Record
Track Record

Our Fleet Brunei Shell Petroleum

- Offshore Construction Vessels Pipeline Restoration Project

- Offshore Support Vessels SKID Field Development Project

- Fleet List Download Mampak Field Development Project


CPLQ Jacket Installation
Industry Outlook
Replacement of Main Oil Line

Platform Abandonment Project


Bugan Field Development Project

Location: Offshore Brunei

Period: 2007-Ongoing

Vessels: Da Li Hao, Swiber Conquest, Swiber Glorious, Swiber


Victorious, Aziz

WD: 40-60 meters

Pipeline Restoration Project (2007-2008)

Installation of 18 pipelines 6" OD to 12" OD varying from 1km to 15km long with a total of 43km including 36 stalk-on
risers, multiple pipeline crossings and riser clamps in water depths varying from 20m to 48m

Mampak Field Development Project (2007-2008)

Installation of Mampak well head platform & Magpie module with 1,500 t deck
Installation of 3 pipelines 8" OD to 12" OD with a total of 28km including 6 stalk-on risers and a subsea cable 6.5km
long

Replacement of Main Oil Line (2009)

Installation of 80km of 24" main oil trunkline from shore to 40m water depth including y-piece and 50m spool tie-ins

Bugan Field Development Project (2009)

Installation of Bugan well head platform with 2 pipelines, 4 stalk-on risers and 1 subsea cable

SKID Field Development Project (2010)

Installation of SKID well head platform with 3 pipelines, 6 risers and 1 subsea cable

CPLQ Jacket Installation (2010)

Installation of 8 legged jacket for new LQ

Platform Abandonment Project (2010)

Abandonment of 6 platforms and their disposal

Client: Brunei Shell Petroleum

http://www.swiber.com/offshore-world-track-record.html 1/9
21/08/2017 Offshore World - Track Record :: Swiber Limited
Project: Transportation & Installation of Offshore facilities for Major
Project

Location: Brunei

Period: FY2010-2011

WD: 50 meters

Work Scope:

Decommissioning of 4 platforms 1 x 16 x 14 km
Installation of 1500 MT, 8 leg Champion 7 LQ 1 x 16 x 14 km
jacket including transportation
1 x 12 x 9.6 km
T&I of 1200 MT 4 leg jacket
Cable T&I 1 x 16 x 14 km
T&I of topside - 700 MT approx.
Pipelines - T&I including tie-in, Riser. Crossings
for span correction & pre-commissioning

Client: Petronas Carigali

Project: Puteri Field Development

Location: Offshore Malaysia

Period: 2007 - 2008

Vessel: Da Li Hao

WD: 61 meters

Work Scope:
Transportation and installation of 900 MT jacket, 1,300 MT deck and
2 x 8" x 13 km pipelines in 61 meters water depth

Installation of 8 subsea spools and manifold connecting new facilities


to existing FPSO system

Client: Petronas Carigali

Project: Abu Cluster Project

Location: Offshore West Malaysia

Period: 2006-2007

Vessel: Da Li Hao, Swiber Conquest

WD: 61 meters

Work Scope:
Installation of 6 and 8 (2km each) pipelines by rentis method in 61m
water depth

Transportation & installation of 1,200T Jacket using submersible


method

Transportation and installation of a 2,200 MT deck

Transportation and installation of 6-point mooring system for Abu


FSO

Tow and Hook-Up of Abu FSO and installation of mid-water arch

Installation of flexible risers

Client: Kodeco Energy Ltd

Project: Offshore EPCI Services for West Madura and Poleng


Fields (KE-32, KE-38 and PPP)

Location: Offshore East Java, Indonesia

Period: 2007-2008

Vessel: Da Li Hao, Swiber Conquest

http://www.swiber.com/offshore-world-track-record.html 2/9
21/08/2017 Offshore World - Track Record :: Swiber Limited

WD: 55 meters

Work Scope:

Installation of Sub-sea Pipelines (water depth: 5m to 55m)

16 x 22km KE38 Platform to Platform

12 x 7km KE32 Platform to Tie-in point


16 x 48km PPP to Gresik

Pipeline installation using Swiber Conquest

Platform Installation (water depth: 55m)

Installation of 2 x 250MT wellhead platforms (KE- 32 & KE38)


Installation of PPP process platform (1,300MT deck & 1,000MT
jacket)

Platform installation using the Da Li Hao

Client: Talisman Energy

Project: Block PM 3 Commercial Arrangement Area Northern field


Development Project
Search Engine
Location: Malaysia
ABOUT SWIBER INTEGRATED SOLUTIONS INVESTORS MEDIA HUB CAREERS CONTACT US SITEMAP
Period: 2008

Vessel: Da Li Hao

WD: 60 meters

Work Scope:

Installation Works for Decks, Pipelines and Installation of 24 x 30km pipeline


Spools
Installation of tie-in spools
Installation of wellhead riser platform BO-C
(1550MT) and riser platform BO-D (2,040 MT)

Client: ConocoPhillips Indonesia

Project: North Belut Field Development

Location: Natuna Sea, Indonesia

Period: 2008-2009

Vessel: Da Li Hao, Swiber Conquest, Swiber Victorious

WD: 96 meters

Work Scope:

Installation of WHP-D and WHP-C wellhead Installation of 16 dia, 37km gas pipeline
platforms with jackets weighing 1,800 MT each between NBCPP and Kerisi PLEM
and the decks weighing 2,200 MT each
Installation of 22 dia, 10km multiphase pipeline
Installation of CPP jacket weighing 5,600 MT between NBCPP and WHP-C
using launch method using newly
18 Subsea Tie-ins in 100m water depth with
commissioned launch barge SLB-1
spools as long as 52m long.
Installation of 10 dia, 37km liquid pipeline
between NBCPP and Kerisi PLEM

Client: Murphy Oil Malaysia

Project: Murphy Block SK309 & SK311 development

Location: Malaysia

Period: 2008-2009

Vessel: Swiber Conquest

WD: 35 meters

Work Scope:
Installation of 2 ea. 24 OD trunklines 36km each from shore to
GORA platform

http://www.swiber.com/offshore-world-track-record.html 3/9
21/08/2017 Offshore World - Track Record :: Swiber Limited
Beach pull including shore approach works involving coffer dam
installation, Lucker winch set up and pulling pipe to shore
Installation of 20 OD x 4km pipeline
Installation of 4 infield pipelines 6 and 8 OD total of 31km

Pre-commissioning of pipelines

Client: MOGE

Project: Yadana Yangon Domestic Gas Oil Pipeline

Location: Myanmar

Period: 2009-2010

Vessel: Swiber Conquest, Swiber Concorde, and Aziz

WD: 2 - 60 meters

Work Scope:
Installation of 150km of 24 pipeline

Riser spool installation at Yadana Platform using SAT diving including


installation of 50-70m long spools
2 x above water tie-ins in 28m and 6m water depth
1km Beach Pull using Concorde in 4.5m water depth

Pre-trenching & back-filling for 6km from land fall point. Used IDN
dredger for pre-trench
Pre-commissioning of 150km line including drying to -10C

Client: British Gas India

Project: HYDRA - PK & SWP Project

Location: Panna Field, Offshore India

Period: 2008-2009

Vessel: Swiber Supporter

WD: 39 - 59 meters

Work Scope:

Engineering, Procurement, Construction/fabrication, Transportation, Installation & Pre-Commissioning of:

PK Platform, a new 6-slot wellhead platform, 2 x 4.5 gas lift pipelines (PPA-SWP & PPA-PK)
jacket 700 MT - Deck 350 MT and 4 x 1.25 chemical injection lines, piggy
backed on main pipeline (two each on PPA-
SWP (South West Panna) Platform, a new 6-
SWP & PPA-PK)
slot wellhead platform, jacket 700 MT - Deck
350 MT Installation of risers at PPA and tie-ins at PPA,
PK and SWP
1 x 12 x 5.5 km (PK-PPA) and 1 x 14 x 12.1
km (SWP-PPA) production pipeline

Client: British Gas India

Project: Panna Gas Lift Project

Location: Panna Field, Offshore India

Period: 2008-2009

Vessel: Swiber Conquest, Swiber Supporter

WD: 42 - 47 meters

Work Scope:

Offshore-Fabrication, Transportation and Installation of 6"x 6.8 km gas lift line pipes, Riser & Tie-in Works

Client: British Gas India

Project: British Gas Pipeline Project

http://www.swiber.com/offshore-world-track-record.html 4/9
21/08/2017 Offshore World - Track Record :: Swiber Limited
Location: India

Period: FY2010-2011

Vessel: PJW -3000, Swiber Supporter

WD: 39 - 59 meters

Work Scope:

Engineering, Procurement, Construction/ Fabrication with modification,


Transportation, Installation & Pre-commissioning of:

SWP (South West Panna) Platform modification from 6 slots


wellhead platform to 9 slots to renamed as PL Platform with jacket
800MT - deck 350MT;
One 14x 7.5km (PL-PPA) pipeline;

Two 4 gas lift pipelines (PL-PPA) and four 1 1/4 chemical


injection pipelines (PPA-PL), piggy backed on main pipeline

Client: Vietsovpetro (VSP)

Project: Dai-Hung Structural Installation Project

Location: Vietnam

Period: FY2011

Vessel: Magnificent

Work Scope:
Upend & installation of 4000 MT Jacket

Installation of 8 skirt pile & drive up to 85m penetration below sea


bed, maintain jacket levels within tolerance
Removable of 4 buoyancy tanks
Installation of 2 boat landings

Installation 1 x 1250 MT topside


Installation 1 helideck
Installation 1 flare boom

Hook-up, Touch up painting, & pre- commissioning

Client: ONGC

Project: B-193 Field Development Project

Location: Offshore Mumbai, India

Period: 2010-2011

Vessel: Magnificent

WD: 60 - 75 meters

Work Scope:

EPCIC for 5 new wellhead platforms Transportation and Installation


Detailed Engineering (by Consortium partner- Deck weights ranging from 1200 MT to 1320
Sime Darby) MT each
Procurement and Fabrication (by Consortium Jacket weights ranging from 1340 MT to 1454
partner- Sime Darby) MT each

Client: ONGC

Project: MHNRD II Pipeline Project

Location: India

Period: 2011

Vessel: Swiber Conquest, Swiber Supporter, Swiber Atlantis

WD: 60 meters

Work Scope:

http://www.swiber.com/offshore-world-track-record.html 5/9
21/08/2017 Offshore World - Track Record :: Swiber Limited
Engineering, procurement, transportation and installation of several
pipelines and platform modifications

Laying of approx. 75.0km submarine pipeline in 14 segments for well


fluid, gas lift, and water injection pipelines
Topside modification of 10 no. of existing well platforms (LA, NB, N1,
NV, N6, NR, NW, NP, LC and WI-4) and associated modifications on
NQP, NQG, proposed platform MNP and MNW process platforms

Client: ONGC

Project: North Tapti Gas Field Development

Location: Western Offshore India

Period: 2010-2011

Vessel: PJW3000

WD: 25 meters

Work Scope:

EPCIC for new wellhead platforms and connected pipeline to existing process platform on North Tapti Gas Field
Development

EPCIC for 2 new wellhead platforms and 2 Procurement and Coating of Linepipe (by
pipelines Swiber)
Detailed Engineering (by Aker) Transportation and Installation (by Swiber)
Procurement and Fabrication (by Consortium Jackets 536 MT each, Decks 840 MT each
partner - Lamprell)

Client: Santos (Sampang) Pty. Ltd.

Project: Wortel Field Development

Location: Indonesia

Period: FY2011-2012

WD: 42 meters

Work Scope:

Santos Wortel Jacket, Topside & Pipeline Installation Project


3 leg Jacket(Piled Structure), 175 t deck, Oyong WHP modification Work, 10" x 9.6 km P/L)

Client: CNOOC/COOEC - China

Project: LF13-2 Pipeline Replacement Project

Location: CHINA

Period: FY2011

WD: 150- 160 meters

Work Scope:

Pipe in Pipe Installation of 11.50 KM (12"/16" ) Pipeline Installation

Client: ONGC

Project: B193 Process Platform

Location: India

Period: FY2011-2012

Vessels: PJW3000 & Swiber Conquest, Holmen Pacific & Holmen


Atlantic

WD: 75 meters

Work Scope:

http://www.swiber.com/offshore-world-track-record.html 6/9
21/08/2017 Offshore World - Track Record :: Swiber Limited
Design, engineering, procurement, fabrication, transportation,
installation and commissioning of major platforms.

CPP jacket 6,400 MT, Deck 13,500 MT,

LQ Jacket 4,600 MT, Deck 7,200 MT

Client: ONGC

Project: Subsea Pipeline for B193 Project

Location: India

Period: FY2011-2012

Vessels: Swiber Conquest & Swiber Concorde

WD: 60 meters

Work Scope:

EPCI (engineering, procurement, construction and installation) of seven segments of pipelines ranging from 8" to
16" over a total length of 116.5km.
Also in the scope are modification works for the BCP-B platform and tie-in with ICP Heera trunkline, laying of 24.5
km subsea composite cable from B-22A to B-193A, laying of 8" x 2.744 km length of subsea flexible pipeline, tie-
in of 16" rigid pipeline from B-22 to B-193A with pre-installed riser at B-193A jacket.

Client: Brunei Shell Petroleum

Project: Inspection, Repair, and Maintenance Contract

Location: Brunei

Period: 2010-2014

Work Scope:
Saturation Diving System Supply of equipment and personnel for
BSP for ERM work in its offshore facilities

Client: Brunei Shell Petroleum

Project: Cable Replacement Project

Location: Brunei

Period: FY2011-2012

Work Scope:
7 Cables Installation, J-tube , Riser Installation

Work Scope: Receiving & transportation of cables, Installation of


clamps, I/J tubes & crossings etc.

Client: Brunei Shell Petroleum

Project: Brunei Shell - CPNQ-07

Location: Brunei

Period: FY2011-2012

WD: 50 meters

Work Scope:
Transportation and Installation of New Champion 7 Living Quarters
(CPNQ-07).
Jacket Weight - 1500 MT

Deck Weight -700 MT

Client: Pearl Oil/MEINDO

http://www.swiber.com/offshore-world-track-record.html 7/9
21/08/2017 Offshore World - Track Record :: Swiber Limited
Project: Ruby Field Development Project

Location: Indonesia

Period: FY2011-2012

WD: 0-90 meters

Work Scope:
Installation of 305KM , 14" pipeline including beach pull & Onshore
preparation & laying.

Client: ConocoPhillips Indonesia

Project: Bawal Field Development

Location: Indonesia

Period: FY2011-2012

WD: 90 meters

Work Scope:

Phase 1: Phase 2:

Installation of 7.35 km umbilical from Hang Installation of 34 km umbilical from SDU2 to


Tuah platform to SDU 2 UTA
Installation of 8" x 800 m flexible pipeline from Installation of tie-in spools and pre- commission
T8 well to Manifold works
Topside modification works Topside modification works

Client: ESSAR/ONGC

Project: D-1 Field Development Project

Location: India

Period: FY2011-12

WD: 85 meters

Work Scope:
Installation of 3 WH Jackets (1996 MT, 2230 MT & 2335 MT), 3 WH
Platform Decks (2030 MT, 2 x 2033 MT) and one bridge (300 MT) in
D-1 Field Development Project.

Client: PTTEPI

Project: Zawtika Offshore Pipeline Installation

Location: Myanmar

Period: FY2011 - FY2013

WD: 160 meters

Work Scope:

Installation of 28" x 230 km gas export pipelines sized for 600 MMSCFD, connecting between ZPQ process
platform, though Block M10 to landfall close to Mawgyi village, nearby existing Yadana and Yetagun lines and
about 3-4 km south of Daminseik village

Client: PVC-MS

Project: Block 16-1 Te Giac Trang Field Development Project

Location: Vietnam

Period: FY2012

Water Depth: 40 - 50 m

Work Scope:
Transportation and installation of H4 Topsides (2320 MT)

http://www.swiber.com/offshore-world-track-record.html 8/9
21/08/2017 Offshore World - Track Record :: Swiber Limited

Client: Total E&P Indonesie

Project: Sisi Nubi Phase 2B & Peciko Phase 7B Development


Project

Location: East Kalimantan, Indonesia

Period: Q2/Q3 2013

Value: US$77M

Water 40 - 70 meters
Depth:

Work Scope:

Transportation & Installation of new facilities including:

WPS2 Quadripod Jacket Structure (1400 MT) WPN3 Platform Integrated Topsides (900 MT)
WPS2 Platform integrated topsides (1350 MT) SWP-J Tripod Jacket Structure (750 MT)
WPN3 Tripod Jacket structure (820 MT) SWP-J Platform integrated Topsides (840 MT)

Client: Total E&P Myanmar

Project: TEPM Yadana Subsidence Project (YSP)

Location: Myanmar

Period: FY2012-FY2013

Water Depth: 45 m

Work Scope:

Transportation and installation of FP2, QP2 and Ancilliary structures:

MCP N-W Module (150 MT) QP2 Jacket (1986 MT)


MCP S-W Module (31 MT) QP2 Boat Landing (132 MT)
MCP-FP2 Bridge (350 MT) Main Support Frame-2 (1615 MT)
FP2 Tripod Jacket (600 MT) PP-QP2 Bridge (260 MT)
PP N-W Module (35 MT) QP2 Module (2036 MT)

Client: PEMEX Exploration and Production

Project: Dos Bocas Line 5 Project

Location: Gulf of Mexico

Period: Q1 2012 - Q1 2013

Vessels: Swiber Concorde and Aziz

WD: 26.2 meters

Work Scope:
Procurement and Construction of 36" x 77 Km. of Coastal Linking
Platform to TMDB (Line 5 ) Offshore Pipeline including HDD shore
approach and onshore tie-in