Item No. Description of Works Unit Quantity Unit Rate Amount Remarks
Civil works
1 Site Preparation of Surface dressing works. Sqm. 206.50 5.06 1,044.89
2 Excavation for foundation, drain, pipeline etc. in
boulder mixed soils, disposal ( up to 10m lead Cum. 69.87 416.94 29,131.60
and 1.5m lift).
3 Back filling of footing. Cum. 50.08 127.00 6,360.16
4 Stone soling works in the foundation and flooring
and levelling including haulage distance up to 30 Cum. 16.88 3,790.00 63,975.20
m.
5 Sand filling work below stone soling in rooms
Cum. 5.69 1,771.00 10,076.99
floor
6 Cement Concrete (P.C.C.) works of Foundation
in (1:4:8 ratio ) of Concrete including supply of Cum. 6.75 7,813.27 52,739.57
material and haulage distance up to 30 m.
7 Rubble masonry works including supply of hard
stone blocks, preparing cement mortar and
Cum. 67.89 8,863.00 601,709.07
const. of wall upto 5 m. high ( haulage distance
up to 30 m. ) in 1:4 ratio.
8 Cement Concrete works of super structures,
deck, slab, beams in (1:1.5:3 ratio ) of Concrete
Cum. 47.01 12,606.88 592,649.43
including supply of material and haulage
distance up to 30 m.
9 Cutting, binding, placing in position as shown in
the drawings and banding wire of reinforcement
Kg. 10228.65 109.26 1,117,582.51
steel bars for R.C.C. works including haulage
distance of 30m.
10 Making wooden forms including selection of
materal, measuring,cutting,fixing,nailing as per Sqm. 418.47 504.83 211,256.21
specified drawings and hauling upto 30m. and
11 placing
Brick & removal
( Chimny with all
Bhatta) complete
masonry works.
works including
supply of Bricks, preparing cement mortar and
Cum. 48.83 11,755.00 573,996.65
const. of wall upto 5 m. high ( haulage distance
up to 30 m. ) in 1:4 ratio.
12 12.5mm thick Cement sand plaster works on wall
Sqm. 647.96 272.37 176,484.87
surface in 1:4 ratio.
13 12.5mm thick Cement sand plaster works of
Sqm. 138.63 315.04 43,674.00
Ceiling in 1:4 ratio.
14 Two Coat Washable Distemper painting works
on New surface upto satisfaction of site Engineer Sqm. 527.31 97.30 51,307.26
all complete.
15 Two Coat Weather coat painting works on New
surface upto satisfaction of site Engineer all Sqm. 308.91 140.02 43,253.58
complete.
16 Making and fittings of sal wood frame Door &
Windows (Frame size 100x75mm) all complete. Cum. 0.41 218,789.80 89,703.82
Item No. Description of Works Unit Quantity Unit Rate Amount Remarks
18 Making and fittings of 12mm. thick plywood
Panelled shutter in 38mm. sal wood frame with
Sqm. 7.74 8,318.08 64,381.94
Hinge, Tower bolt, locking set, handle and screw
& nail all complete.
19 Making and fittings of Aluminium sheet One
sides in 38mm. sal wood frame with Hinge,
Sqm. 5.16 6,832.53 35,255.85
Tower bolt, locking set, handle and screw & nail
all complete.
20 Making and fittings of Aluminium double pannel
sliding window with fly mesh shutter frame Sqm. 28.74 4,788.00 137,607.12
section (88x38x1.30)mm and 5mm thick glass.
21 Making and fixing 24 gauge mosquito proof wire
mesh and Diamad wire mesh door shutter in
Sqm. 6.02 5,225.59 31,458.05
38mm thick sal wood frame. ( shutter size =
1.092 x 2.05m.).
22 Making 4.5mm x 20mm. Iron grill
(100mmx100mm size) & fixing including clining Sqm. 3.84 2,314.00 8,885.76
by sand paper, applying paint etc. complet.
23 Two coat Readymade enamel or plastic
Sqm. 76.60 138.74 10,627.48
emulsion painting works upto satisfaction of site
24 Engineer
20mm all complete
thick Cement works.
sand plastreing works of
Sqm. 216.70 318.90 69,105.63
Floor plaster works in 1:6 ratio.
25 3mm thick fine cement rubbing ( punning )
Sqm. 216.70 207.00 44,856.90
works.
26 Skirting work in inter wall surface and external
wall surfaces (12.5mm thick Cement sand Sqm. 38.91 325.06 12,648.08
plastreing works in 1:2 ratio.)
27 Two coat Enamel paint on skirting surfaces Sqm. 38.91 138.74 5,398.37
28 Providing & laying porcelain glazed/Non Glazed
tile in (1:4)cement mortar at Bathrooms with
Sqm. 34.34 1,448.75 49,750.08
proper line & level as per specification & site
incharge instruction
4,204,738.87
Sanitary Works
29 Supply and Erection at Kitchen Sink Complete
set with Sink cock (24"x18"x8") size all Set. 1.00 7,571.60 7,571.60
complete.
30 Supply and Erection at One pice COMODE with
low level cistern complet set and all complet Set. 2.00 12,667.82 25,335.64
works.
31 Supply and Erection at 20" size Orissa Pan with
low level cistern complet set and all complet Set. 1.00 11,361.79 11,361.79
works.
32 Supply and Erection at Wash Basin Complete
set (16"x20") ISI mark with Cock all complete Set. 3.00 6664.25 19,992.75
set.
33 Supply and Erection at Looking mirror (18"x12"
Set. 6,297.09
size). 3.00 2099.03
34 4" dia Rose Shower ,revolving type Set. 3.00 1075.53 3,226.59
35 Supply and Erection at Soap dish (steel) 4"x6" Set. 3.00 453.38 1,360.14
Item No. Description of Works Unit Quantity Unit Rate Amount Remarks
36 Supply and Erection at Tower rod (steel) 16" Set. 3.00 932.65 2,797.95
37 Supply and Erection at Telephonic shower with
Set. 5,623.50
1.5 m flexible tube 2.00 2811.75
38 15mm,Two way angle cock Set. 2.00 1547.61 3,095.22
39 Supply and Erection at C.P. Bibcock 15mm dia
Set. 3.00 1,979.43
long neck type with wall flange 659.81
40 Supply and Erection at 1000 Lit. PVC Water tank
1
With Tank Nipple /2" & 1"( NS ISO Premium ) No. 1.00 18,946.25 18,946.25
208,692.05
Electricfication works
Item No. Description of Works Unit Quantity Unit Rate Amount Remarks
50 Concealed point Wiring medium Light Circuit
(6m.-10m.) while new house, According to
drawing, placing HDP pipe while concreting and Point 15.00 464.00 6,960.00
fixing its switch board via ceiling rose box; all
complete.
51 Concealed point Wiring Long Light Circuit (11m.-
15m.) while new house, According to drawing,
placing HDP pipe while concreting and fixing its Point 4.00 4399.00 17,596.00
switch board via ceiling rose box; all complete.