You are on page 1of 3

Advantages and Disadvantages of

Timber is said to be renewable because, in order to


Timber Frame Construction
replace it, another tree is planted. Provided that a similar tree is
planted for every one that is felled, the supply is infinite. This is
in stark contrast to bricks, blocks and concrete, all of which rely Advantages of Timber Frame Construction
on the extraction of raw materials from the earth, which
ultimately will run out. Timber has many environmental benefits not found in
other building materials. The level of carbon dioxide (CO2) in
Apart from the ability of trees to absorb and store the air is increasing significantly as a direct result of our
CO itself, they also need less CO2-producing activities, such as
2
lifestyle and mankinds industrial activities and is a major cause
industrial processes, to be created. To make steel for example, of the greenhouse effect which in turn leads directly to global
raw materials have to be mined, transported and then combined warming. Trees will lock away CO2 in their wood, which is
together in factories also producing waste. By contrast, there is retained throughout the existence of the timber. The use of
almost no waste in timber production even sawdust is used for timber as a building material encourages the growth and
chipboard or paper production. expansion of the forests that provide the supply, which absorb
CO2 and therefore help to reduce the level of global warming.
Timber has proved to be a strong and durable
material. If built well timber frames buildings will last for
hundreds of years. Quick Erection Times

The timber frame structure of a typical 2 storey


The exercise of building in timber requires more precision
semi-detached house (Generic House Type 2, Appendix 5)
and planning than a brick and block property. For economy, the can be constructed in approximately 1 week. Quick
elements of a timber frame are carefully designed and calculated erection times can allow the work of other trades to
proceed earlier in the construction programmed. Quick
to use as little material as possible for the strength required. As a erection times are offset by additional period required to
result, it is not straightforward to alter or extend the frame of an facilitate the tendering, longer detail design lead in times
existing house and demolition of walls should not be undertaken and manufacture of the timber frame. These factors
reduce the overall benefits of reduction in construction
without seeking structural advice. time on site in context of the overall development
process.
If anything substantial is to be fixed to a timber stud wall, The TFHC assessed the construction programmed
implications for House Type 2 of the Generic House Type
such as a heavy bookshelf, the fixings must be made into the
models in Appendix 5 and concluded that when
frame, not the plasterboard wall covering alone which will not be benchmarked against other forms of construction the
able to support the load. overall development times where broadly similar.
The TFHCs assessment on the overall saving of
time on site is based on an overview of the generic house
types in Appendix 5 and subsequently reviewed with
timber frame manufacturers and further benchmarked
against other forms of construction for housing. The Environmental Sustainability
above times are indicative and may vary based on
project-specific issues such as: The majority of structural timber used in Ireland
comes from managed forests and is a renewable and
Number of residential units in the scheme sustainable material. The growing of timber benefits the
Mix of units (detached, semi-detached, terraced) environment, and its harvesting, production and transport
Phasing of development are seen to produce less CO2 than other construction
Availability of resources
materials such as concrete and steel. The environmental
Regional industrial relations issues
benefits of timber frame construction are reduced when
Capacity at particular points within respective
timber is imported from sources outside non local and
supply industries
requiring substantial fuel consumption in transportation. Most
of the solid structural timber used in Ireland is sourced in
Reduced Site Labour
Scandinavia and North America.
The timber frame erection crew for the typical two
storey semi-detached house will consist of three Potential Problems with Timber Frame
carpenters and one crane operator. Construction

Design

Reduced Risk There are some residual reservations about timber


frame among architects, engineers, builders, administrative
Commercial institutions and lenders view construction bodies, financial institutions and insurance companies as well
risk as a critical factor in the overall approval of schemes and as with end users.
reflect this in different financing arrangements. The TFHC Perceived problems with timber frame construction in the
believe that construction risk is linked to the period of time housing market from both the end users and local authorities
set aside for construction. The longer the period, the greater would include a perceived greater risk of fire, issues of sound
the risk in terms of industrial relations issues, inclement attenuation in a timber structure and the impact such a
weather, and availability of resources and consequently it is structure might have on the security of the end user.
our view that the benefit in terms of time saving on site
manifests itself as a saving in construction risk. Procurement and Detail Design

Quality
A timber frame solution is at a disadvantage in a
Industrialised prefabrication of engineered products is procurement process where a prescriptive design and
believed by the TFHC to provide consistent quality assurance specification is tendered which is specific to a masonry
when compared to works on sited. Buying prefabricated cavity wall construction. Acceptance of a comparable
building systems, e.g. bathroom pods, kitchen units,
timber frame solution, which would require review, takes
architectural pre-cast concrete panels, etc. is seen by
builders, developers and design professionals as a means of time to prepare. The time allowed may be insufficient or
achieving expected quality. The timber frame manufacturers unavailable in the current tender process.
interviewed during the course of this study all had well
organised quality control procedures in place and the Deficiency in On-Site Quality
research by the TFHC has shown that most of the defects
occurring in timber frame construction in Ireland were site Familiarisation with the timber frame construction
related methods is often lacking in both the construction crew
and any architects or site managers who should be
ensuring on-site quality is achieved. Training courses are works and other adjoining construction such as chimneys,
run by manufacturing companies or the timber industry rising walls and block construction. As a result, these
to ensure that there is an acceptable level of know-how. works need to be set out with a high degree of accuracy.
Problems arise on a site if agreed tolerance between the
Critical Setting Out of Ground Works required dimensions and the built dimensions are not
followed.
Timber frames are designed and manufactured to
tight tolerance and require accurate setting out of ground

You might also like