X Cavities resulting from gouging or grinding operations to remove attachment welds to the shell shall be 653/
examined by magnetic particle or liquid penetrant methods. 12.1.2.2
X Completed welds attaching nozzle neck to shell, and reinforcing plate to shell and to nozzle neck, shall be 653/
examined by the magnetic particle or liquid penetrant methods. 12.1.2.3
The welds of permanent attachments (not including shell-to-bottom welds) and, areas where temporary 653/
X attachments are removed and the remaining weld projections have been removed, shall be examined 12.1.4.2
visually.
W:\06 Projects\6547 VOPAK TK D 2151\QC Documents\TO JOSE FOR SUBMIT\ITP Data\QF-120 Field Inspection checklist API-650-653 VOPAK D-2151 tk Page 1 of 6
Project Number: 6548 Superintendent:
REMOVE OLD 5th RING and INSTALL NEW 5th RING SHELL PLATEs and Wind Girder & its Support
Pads and Supports
X Receive and Release 5th Ring shell plate Material.
X Remove old 5th RING and Wind Girder and prepare weld preps for new plates
X Install and Weld in accordance with the specified Drawing and WPS.
Visually Inspect and RT/UT the weld seams. Record on Form TARSCO-QA-01VT and Vendor's RT/UT 9.4 /
X
Form. Record the welder on the Welder Map Drawing. Record RT/UT Locations on the NDE Map. 7.3.3
X Install the Wind Girder and Weld in accordance with the specified Drawing and WPS.
Visually Inspect the weld seams. Record on Form TARSCO-QA-01VT Form. Record the welder on the 9.4 /
X 7.3.3
Welder Map Drawing.
X Visually Inspect the weld seams. Record on Form TARSCO-QA-01VT Form. Record the welder on the
Install Drawing.
X Visually Inspect the weld seams. Record on Form TARSCO-QA-01VT Form. Record the welder on the
Install Drawing.
FOAM CHAMBERS
X Receive and Release Foam Chamber Material.
X Install and Weld and Bolt, as specified, in accordance with the specified Drawing and WPS.
X Visually Inspect the weld seams. Record on Form TARSCO-QA-01VT Form. Record the welder on the
Install Drawing.
W:\06 Projects\6547 VOPAK TK D 2151\QC Documents\TO JOSE FOR SUBMIT\ITP Data\QF-120 Field Inspection checklist API-650-653 VOPAK D-2151 tk Page 2 of 6
Project Number: 6548 Superintendent:
DIFFUSERS
X Receive and Release Diffusers Material.
X Provide and install diffusers to replace the existing one in accordance with the specified Drawing and WPS.
X Visually Inspect and Record on Form TARSCO-QA-01VT. Record the welder on the Install Drawing.
HANDRAIL
X Receive and Release Handrail Material.
X Install handrail in accordance with the specified Drawing and WPS.
X Visually Inspect and Record on Form TARSCO-QA-01VT. Record the welder on the Install Drawing.
W:\06 Projects\6547 VOPAK TK D 2151\QC Documents\TO JOSE FOR SUBMIT\ITP Data\QF-120 Field Inspection checklist API-650-653 VOPAK D-2151 tk Page 3 of 6
Project Number: 6548 Superintendent:
X Visually and VB Inspect and Record on Form TARSCO-QA-01VT and -04VB. Record the welder on the
Deck Plate Welder Map Drawing.
REMOVE AND INSTALL EFR PONTOON DECK, COVER RING and COVER PLATES
X Receive and Release Plate Material.
X Install Plates in accordance with the specified Drawing and WPS.
X Visually Inspect and Record on Form TARSCO-QA-01VT. Record the welder on the Install Drawing.
W:\06 Projects\6547 VOPAK TK D 2151\QC Documents\TO JOSE FOR SUBMIT\ITP Data\QF-120 Field Inspection checklist API-650-653 VOPAK D-2151 tk Page 4 of 6
Project Number: 6548 Superintendent:
W:\06 Projects\6547 VOPAK TK D 2151\QC Documents\TO JOSE FOR SUBMIT\ITP Data\QF-120 Field Inspection checklist API-650-653 VOPAK D-2151 tk Page 5 of 6
Project Number: 6548 Superintendent:
W:\06 Projects\6547 VOPAK TK D 2151\QC Documents\TO JOSE FOR SUBMIT\ITP Data\QF-120 Field Inspection checklist API-650-653 VOPAK D-2151 tk Page 6 of 6